Although the railway preservation movement was busy, with many organisations reluctantly telling us they had no time to take part in our survey, what has stood out is the amount of major work taking place on what can only be described as headliners of the movement. They are the extension to Broadway on the Gloucestershire Warwickshire Steam Railway and the bridge linking that has taken place recently on the Great Central Railway.

“We are going flat out to ensure that everything is ready for trains to run into Broadway for March 30 and there is still much to do there and the effort will be continuing apace at the site,” GWSR spokesman Ian Crowder told us just before Christmas as the tracklaying was nearing completion and the railway’s closure from Monday, January 1 until Saturday, March 10. “There is a fair bit of work to be done during the ‘closed’ season.

“At Toddington, a turnout will be reinstated at south end at the end of the year that will provide a direct connection once again between the yard and the running line. The turnout was taken out a few years ago. This will significantly improve flexibility at Toddington, especially given the much busier timetable we will be operating during 2018 and provide a second means of access to the yard. In addition, around a quarter of a mile of the running line is being relaid at Toddington.”

Longest steel spans

Further south, significant repair work will be undertaken on the ‘skew’ bridge at Gotherington, which, because of the acute angle of the line over the road beneath, has the longest steel span on the GWSR. The track was due to be lifted at the beginning of January for access to the steel deck to repair damage caused by water ingress at a cost estimated at £122,000.

“We also need to repair the newly-refurbished bridge over the B4632 Station Road/Evesham Road at Broadway,” Ian revealed. “The bridge has been struck a few times by overweight vehicles, one strike being particularly serious with a collision from overweight earthmoving equipment on a low loader. The work entails a road closure of the main B4632 (formerly the A44) road into Broadway from the Evesham direction. Fortunately this work will be paid for by the lorry owner’s insurers and it is expected to cost around £58,000.

“This is, of course, highly topical given that Network Rail recently announced that over the past year it had suffered almost 2000 bridge strikes and that’s just the national network, never mind other bridges carrying roads, footpaths, heritage railways and so on. The subsequent disruption to road and rail traffic is estimated to have cost the taxpayer £23 million over the past year.”

He added: “We are considering ways of protecting the bridge – for example, collision protection beams on

You’re reading a preview, subscribe to read more.

More from Heritage Railway

Heritage Railway2 min read
'Sprinter's' Conversion To Community Hub With £60k Grant Funding
THE Llanelli & Mynydd Mawr Railway will be converting the body from a retired Class 153 'Sprinter' into a new community hub, having successfully applied for two separate grants to provide much of the funding. Set on the site of a former colliery, whi
Heritage Railway5 min read
From Volunteer To General Manager
Opened in 1725, the Tanfield Waggonway was a vital artery in the movement of coal from the collieries of the Durham coal fields to the River Tyne. Carrying the original waggonway over Causey Burn was the Causey Arch, which, when it was constructed du
Heritage Railway2 min read
HSTs Join Line-up As Severn Valley Spring Diesel Festival Grows Further
THE Severn Valley Railway’s May 1619 Spring Diesel Festival had added further guests, with up to 18 different locomotives and units now due in service. Colas Rail has agreed to its Class 43 High Speed Train set being in service during the event. It w