ANALISA HARGA SATUAN

Jenis Pekerjaan
: Lapisan ATB
Satuan Pembayaran : Ton
No.URAIAN KEGIATAN
1
1
2
3
4
5
6
7
8
9
10
11
12
13

2
Mandor
Pekerja
Agregat Kasar
Agregat Halus
Filter
Aspal Curah
Sewa Asphatt Mixing Plant
Sewa Wheel Leader 10-15 HP
Sewa Dump Truck 8-10 m3
Sewa Asphatt Finisher
Sewa Todem Roller
Sewa Tire Roller
Sewa Alat Bantu

SAT.

KOEFFISIEN

Jam
Jam
m3
m3
Kg
Kg
Jam
Jam
Jam
Jam
Jam
Jam
set

0.0613
0.4293
0.7028
0.5341
139.2000
157.0000
0.0613
0.0421
0.5429
0.0767
0.0476
0.0356
1.0000

HARGA SATUAN
( Rp. )
5
8,571.43
4,571.43
175,200.00
173,880.00
1,350.00
7,300.00
3,800,000.00
482,502.02
65,000.00
856,725.00
223,436.00
226,360.00
1,000.00

HARGA SATUAN PEKERJAAN / M3


HARGA SATUAN PEKERJAAN / TON
DIBULATKAN
Jenis Pekerjaan
: Lapisan AC
Satuan Pembayaran : m2
No.URAIAN KEGIATAN
1
1
2
3
4
5
6
7
8
9
10
11
12
13

2
Mandor
Pekerja
Agregat Kasar
Agregat Halus
Filter
Aspal Curah
Sewa Asphatt Mixing Plant
Sewa Wheel Leader 10-15 HP
Sewa Dump Truck 8-10 m3
Sewa Asphatt Finisher
Sewa Todem Roller
Sewa Tire Roller
Sewa Alat Bantu

SAT.

KOEFFISIEN

Jam
Jam
m3
m3
Kg
Kg
Jam
Jam
Jam
Jam
Jam
Jam
set

0.0024
0.0241
0.0336
0.0149
4.8015
6.6150

0.0024
0.0016
0.0385
0.0030
0.0018
0.0025
1.0000

HARGA SATUAN
( Rp. )
5
8,571.43
4,571.43
175,200.00
173,880.00
1,350.00
7,300.00
3,800,000.00
482,502.02
65,000.00
856,725.00
223,436.00
226,360.00
1,000.00

HARGA SATUAN PEKERJAAN


DIBULATKAN

Jenis Pekerjaan
: Pengecatan Marka Jalan dengan Thermoplastic ( teb. 2mm)
Satuan Pembayaran : M2
No.URAIAN KEGIATAN
SAT. KOEFFISIEN HARGA SATUAN
( Rp. )
1
2
3
4
5
1
2
3
4
5
6
7
8

Mandor
Operator
Pengemudi / sopir
Pekerja / buruh tak terampil
Thermoplastic
Glass beed
Cargo truck 5,0 ton
Road marking machine

Jam
Jam
Jam
Jam
kg
kg
jam
jam

0.0140
0.0140
0.0140
0.0275
2.8000
0.5000
0.0500
0.0500

8,571.43
5,000.00
5,000.00
4,571.43
27,000.00
40,000.00
109,814.52
41,600.00

HARGA SATUAN PEKERJAAN


DIBULATKAN
Jenis Pekerjaan
: Lapisan Aspal Pengikat ( Tack Coat)
Satuan Pembayaran : Lt
No.URAIAN KEGIATAN
SAT. KOEFFISIEN
1
1
2
3
4
5
6
7

2
Mandor
Pekerja Terampil
Aspal Curah
Minyak Tanah
Sewa Aspal Spatyer
Sewa Compresor
Sewa Dump Truck 8-10 m3

Jam
Jam
Kg
Ltr
Jam
Jam
Jam

0.0030
0.0201
0.8894
0.2530
0.0030
0.0063
0.0030

HARGA SATUAN
( Rp. )
5
8,571.43
4,571.43
7,300.00
7,000.00
23,000.00
75,000.00
65,000.00

HARGA SATUAN PEKERJAAN


DIBULATKAN

JUMLAH
( Rp. )
6=45
525.43
1,962.51
123,130.56
92,869.31
187,920.00
1,146,100.00
232,940.00
20,313.34
35,288.50
65,710.81
10,635.55
8,058.42
1,000.00
1,926,454.42
844,936.15
844,930.00

JUMLAH
( Rp. )
6=45
20.66
110.17
5,886.72
2,590.81
6,482.03
48,289.50
9,158.00
772.00
2,502.50
2,570.18
402.18
565.90
1,000.00
80,350.65
80,350.00

JUMLAH
( Rp. )
6=45
120.00
70.00
70.00
125.71
75,600.00
20,000.00
5,490.73
2,080.00
103,556.44
103,555.00

JUMLAH
( Rp. )
6=45
25.71
91.89
6,492.62
1,771.00
69.00
472.50
195.00
9,117.72
9,115.00

DAFTAR HARGA SATUAN ALAT & BAHAN


Nama Kegiatan
Nama Pekerjaan
Lokasi

:
:
:

URAIAN

NO.

#REF!
#REF!
#REF!

Batu pecah mesin 0,5/1 cm

Batu pecah mesin 1/2 cm

Batu pecah mesin 2/3 cm

Batu pecah mesin (3/5 cm) dan (4/6 cm)

SATUAN

HARGA SATUAN

Rp

173,880.00

Rp

175,200.00

Rp

171,240.00

Rp

164,400.00

Rp

131,894.00

Rp

171,240.00

Batu kali pecah 15/20 cm

Batu Pecah 2/3 Cm

Aspal panas AC 60/70 ( termasuk angkutan )

m
kg

Rp

2,832.00

Aspal Curah

kg

Rp

7,300.00

Rp

175,200.00

Agregat Kasar

10

Agregat Halus

173,880.00

Filler

m
kg

Rp

11

Rp

1,350.00

12

Kawat Ikat Beton

kg

Rp

15,350.00

13

Besi Beton Polos

kg

Rp

12,500.00

m
kg

Rp

1,636,000.00

Rp

11,040.00

Rp

114,000.00

14

Kayu Menganti ( Bekesting )

15

Paku

16

Batu Krikil Beton

17

Pasir Pasang

Rp

110,000.00

18

Minyak Tanah

m
lt

Rp

7,000.00

19

Sewa alat bantu ( 1 set @ 3 alat )

Set

Rp

1,000.00

20

Sewa aspal finisher ( min. 3 jam )

jam

Rp

856,725.00

21

Sewa aspal sprayer ( min. 4 jam )

jam

Rp

23,000.00

22

Sewa pneumatic tire roller ( min. 5 jam )

jam

Rp

226,360.00

23

Sewa tandem roller ( min. 5 jam )

jam

Rp

223,436.00

24

Sewa compresor ( min. 5 jam )

jam

Rp

75,000.00

25

Sewa dump truck 5 T ( min. 5 jam )

jam

Rp

65,000.00

26

Sewa dump truck 8-10

jam

Rp

65,000.00

27

Sewa motor grader 125-140 pk ( min. 5 jam )

jam

Rp

270,000.00

28

Sewa truck tanki air ( min. 5 jam )

jam

Rp

70,000.00

29

Sewa walles ( min. 5 jam )

jam

Rp

80,000.00

30

Sewa Aspal Mixing Plant

jam

Rp

3,800,000.00

31

Sewa Vibarator Roller ( min. 5 Jam)

jam

Rp

135,000.00

32

Sewa Generator Set

jam

Rp

235,950.00

33

Sewa Wheel Loader 10-15 HP

jam

Rp

482,502.02

34

Sewa Concrete Mixer 0,5 m3

jam

Rp

50,000.00

35

Biaya gilas perkerasan dengan tebal 15-20 cm

Rp

9,200.00

36

Thermoplastic

Kg

Rp

27,000.00

37

Glass beed

Kg

Rp

40,000.00

38

Road marking machine

Jam

Rp

41,600.00

m
Jam

Rp

29,500.00

39

Gedeg Guling

40

Cargo truck 5,0 ton

Rp

109,814.52

41

Got Talang R.15 ( segmen )

Bh

Rp

19,250.00

42

Got talang R.25 ( segmen )

Bh

Rp

24,050.00

43

Paving Abu-abu Tb. 6 cm ( 4 persegi Pj. )

Bh

Rp

950.00

44

Paving Abu-abu Tb. 8 cm ( 4 persegi Pj. )

Bh

Rp

1,200.00

45

Stoper / Topi Uskup Merah tb. 6 cm

Bh

Rp

4,000.00

46

Stoper / Topi Uskup Merah tb. 8 cm

Bh

Rp

5,000.00

47

Batu Bata

Bh

Rp

300.00

48

Bambu Bongkotan dia. 8-12 cm ; Pj. 2,5 m

Btg

Rp

15,500.00

49

Bambu Ori dia. 10-12 cm ; Pj. 3 m

Btg

Rp

21,600.00

Rp

40,600.00

50

Kastin Trap uk.15.25.40

DAFTAR HARGA SATUAN ALAT & BAHAN


Nama Kegiatan
Nama Pekerjaan
Lokasi

:
:
:

#REF!
#REF!
#REF!

URAIAN

NO.

SATUAN
3

51

Pasir Cor

52

Sement PC ( Portland Cement ) 50 Kg

m
Zak

53

Pasir Urug

54

Tasirtu

55

Sewa Crane 30 T - min 8 jam

HARGA SATUAN
Rp

115,000.00

Rp

56,000.00

Rp

94,400.00

Rp

87,850.00

Rp

150,000.00

m
Jam

DAFTAR HARGA SATUAN UPAH


Nama Kegiatan
Nama Pekerjaan
Lokasi

:
:
:

#REF!
#REF!
#REF!

URAIAN

NO.

SATUAN

HARGA SATUAN

Mandor

Orang Hari

Rp

60,000.00

Pekerja Terampil

Orang Hari

Rp

35,000.00

Pekerja / Buruh Tak Terampil

Orang Hari

Rp

32,000.00

Operator

Orang Hari

Rp

35,000.00

Pembantu Operator

Orang Hari

Rp

32,000.00

Tenaga Pemasak Aspal

Orang Hari

Rp

35,000.00

Sopir

Orang Hari

Rp

35,000.00

Pembantu Sopir

Orang Hari

Rp

32,000.00

Kepala Tukang batu

Orang Hari

Rp

50,000.00

10

Tukang batu

Orang Hari

Rp

40,000.00

11

Kepala Tukang Besi

Orang Hari

Rp

50,000.00

12

Tukang Besi

Orang Hari

Rp

35,000.00

13

Kepala Tukang Kayu

Orang Hari

Rp

50,000.00

14

Tukang kayu

Orang Hari

Rp

40,000.00

15

Masinis

Orang Hari

Rp

40,000.00

16

Pembantu masinis

Orang Hari

Rp

30,000.00