Fauquier High School Additional Scope Project Costs

Retain 100/200 wing (1979 section)


Demolish 1963 section, rework 1979 section only to the extent needed to meet Code. Requires small addition for stairs, elevator, restrooms; connects utilities, life safety systems. Maintains existing lighting, heating, cooling, etc. with no hallway or classroom renovations.

Construction costs Other costs - design, professional services, contingency Subtotal 1979 building Add: 1963 section demolition Total project cost with demolition Renovate 300 wing Construction costs Other costs - design, professional services, contingency Total project cost Renovate 700 wing
Cost based on 95% design documents; includes biology lab casework.

745,000 65,625 810,625 520,000 1,330,625

1,400,000 182,000 1,582,000

Construction costs Portion of 500 wing bid as an alternate Other costs - design, professional services, contingency Total project cost Total Additional Expanded Scope Project Funding 100/200, 300, and 700 wing total project costs Less: Available cash funding for demolition Total funding needed

1,200,000 154,000 60,000 1,414,000

4,326,625 (674,906) 3,651,719

Note: Project does not include furniture, fixtures, and equipment.