FIELD FUNCTIONAL TEST REPORT

AIR COOLED CHILLER


Project : : AST 2
Date of Test :
Unit Designation :
Unit Location :
Sty & Area Served :
Unit Make :
Unit Model :
Serial No. :
Control Panel Designation : MCC
:
FIELD MEASUREMENT
No. Description Selected or Specified Site Verification Remarks
Equipment Field Verification
1 Equipment Model / Type
2 Chiller Installation details
3 Control panel installation details
4 Mechanical ventilation details
Control Panel Layout Verification
5 All Indicating Lights Layout
6 All selector switches
7 All panels are accessable.
8
Base Equipment Functional Testing
9 Relevant Valves Status Check
10 Relevant Pumps Status Check
11 Relevant Control panel Status Check
12 DDC panel I/O status Check
13
Intergrated Equipment Functional Testing
14 Generator Interfacing Function Test
15 MV Equipment Interfacing Test
16
17
Miscellaneous
18 -
19
ACCEPTED RE-INSPECTION REQUIRED

ACCEPTED WITH COMMENTS NOT ACCEPTED


REMARKS / COMMENTS

Tested By :
Shinsung (Name & Signature) (Date & Time)

Witnessed By :
Hyundai E&C Co Ltd (Name & Signature) (Date & Time)

Verified & Accepted By :


RTO / PowerQ (Name & Signature) (Date & Time)

Page 1 ACCS
FIELD TEST REPORT
Vibration Measurement Test
Project : :
Date of Test :
Unit Designation :
Unit Location :
Sty & Area Served :
Unit Make :
Unit Model :
Serial No. :

FIELD MEASUREMENT
Selected or
No. Description Specified
Field Measurement Remarks

Electrical Characteristics
1 Volt/ Phase/ Freq. (V/ ø/ Hz)
2 Motor Rated Power (kW)
3 Motor Full Load Amp (A)
4 Motor Type/ RPM
5 Starting Current (A)
6 Running Current (A)
7 Thermal Overload Range (A)
8 Thermal Overload Setting (A)
Mechanical Characteristics
9 Water Flow Rate (l/s)
10 Discharge Pressure (PSI)
11 Suction Pressure (PSI)
12 Water IN Temp. (oC)
o
13 Water OUT Temp. ( C)

ACCEPTED RE-INSPECTION REQUIRED

ACCEPTED WITH COMMENTS NOT ACCEPTED

REMARKS / COMMENTS

Tested By :
Shinsung (Name & Signature) (Date & Time)

Witnessed By :
Hyundai E&C Co Ltd (Name & Signature) (Date & Time)

Verified & Accepted By :


RTO / PowerQ (Name & Signature) (Date & Time)

Page 2 Vib
FIELD TEST REPORT
Pump
Project : :
Date of Test :
Unit Designation :
Unit Location :
Sty & Area Served :
Unit Make :
Unit Model :
Serial No. :
Control Panel Designation :

FIELD MEASUREMENT
Selected or
No. Description Specified
Field Measurement Remarks

Electrical Characteristics
1 Volt/ Phase/ Freq. (V/ ø/ Hz)
2 Motor Rated Power (kW)
3 Motor Full Load Amp (A)
4 Motor Type/ RPM
5 Starting Current (A)
6 Running Current (A)
7 Thermal Overload Range (A)
8 Thermal Overload Setting (A)
Mechanical Characteristics
9 Water Flow Rate (l/s)
10 Discharge Pressure (PSI)
11 Suction Pressure (PSI)
12 Water IN Temp. (oC)
o
13 Water OUT Temp. ( C)

ACCEPTED RE-INSPECTION REQUIRED

ACCEPTED WITH COMMENTS NOT ACCEPTED

REMARKS / COMMENTS

Installed & Tested By :


Lead Management E&C Pte Ltd (Name & Signature) (Date & Time)

Witnessed & Accepted By :


Hyundai E&C Co Ltd (Name & Signature) (Date & Time)

Witnessed & Accepted By :


RTO / PowerQ (Name & Signature) (Date & Time)

Page 3 PUMP
FIELD TEST REPORT
Fan Coil Unit
Project : :
Date of Test :
Unit Designation :
Unit Location :
Sty & Area Served :
Unit Make :
Unit Model :
Serial No. :
Control Panel Designation :
FIELD MEASUREMENT
Selected or
No. Description Specified
Field Measurement Remarks
Electrical Characteristics
1 Volt/ Phase/ Freq. (V/ ø/ Hz)
2 Motor Rated Power (kW)
3 Motor Full Load Amp (A)
4 Motor Type/ RPM
5 Starting Current (A)
6 Running Current (A)
7 Thermal Overload Range (A)
8 Thermal Overload Setting (A)
Mechanical Characteristics
9 Supply Air Qty (CMH)
10 Fresh Air Qty (CMH)
12 Off Coil (S/A) Temp. DB/ WB (oC)
13 On Coil (R/A) Temp. DB/ WB (oC)
14 Outside Air Temp. DB/ WB (oC)
15 Water IN/ OUT Temp. (oC)
16 Water Flow Rate (l/s)
17 Static Pressure (kPa)
18 Coil Pressure Drop (kPa)
Miscellaneous
19 Sound Pressure Level (dBA) -
ACCEPTED RE-INSPECTION REQUIRED

ACCEPTED WITH COMMENTS NOT ACCEPTED


REMARKS / COMMENTS

Installed & Tested By :


Lead Management E&C Pte Ltd (Name & Signature) (Date & Time)

Witnessed & Accepted By :


Hyundai E&C Co Ltd (Name & Signature) (Date & Time)

Witnessed & Accepted By :


RTO / PowerQ (Name & Signature) (Date & Time)

Page 4 FCU
FIELD TEST REPORT
Mechanical Ventilation Fan
Project : :
Date of Test :
Unit Designation :
Unit Location :
Sty & Area Served :
Unit Make :
Unit Model :
Serial No. :
Control Panel Designation :

FIELD MEASUREMENT
Selected or
No. Description Specified
Field Measurement Remarks

Electrical Characteristics
1 Volt/ Phase/ Freq. (V/ ø/ Hz)
2 Motor Rated Power (kW)
3 Motor Full Load Amp (A)
4 Fan Type/ RPM
5 Starting Current (A)
6 Running Current (A)
7 Thermal Overload Range (A)
8 Thermal Overload Setting (A)
9 VSD (Hz)
Mechanical Characteristics
1 Static Pressure (kPa)
2 Air Qty (CMH)

ACCEPTED RE-INSPECTION REQUIRED

ACCEPTED WITH COMMENTS NOT ACCEPTED

REMARKS / COMMENTS

Tested By :
Shinsung (Name & Signature) (Date & Time)

Witnessed By :
Hyundai E&C Co Ltd (Name & Signature) (Date & Time)

Verified & Accepted By :


RTO / PowerQ (Name & Signature) (Date & Time)

Page 5 FAN
FIELD TEST REPORT
DX Split Unit / VRV Unit
Project : :
Date of Test :
FAN COIL UNIT
Unit Designation :
Unit Location :
Sty & Area Served :
Unit Make :
Unit Model :
Serial No. :
CONDENSING UNIT
Unit Designation :
Unit Location :
Unit Make :
Unit Model :
Serial No. :
Control Panel Designation :
FIELD MEASUREMENT
Selected or
No. Description Specified
Field Measurement Remarks
Electrical Characteristics
1 Volt/ Phase/ Freq. (V/ ø/ Hz)
2 Compressor Rated Power (kW)
3 Compressor Full Load Amp (A)
5 Starting Current (A)
6 Running Current (A)
Mechanical Characteristics
7 Supply Air Qty (CMH) H/L
8 Outside Air Qty (CMH)
9 FCU Off Coil (S/A) Temp. DB/ WB (oC)
10 FCU On Coil (R/A) Temp. DB/ WB (oC)
11 Outside Air Temp. DB/ WB (oC)
12 Static pressure (Pa)
13 Suction Pressure (PSI)
14 Discharge Pressure (PSI)
ACCEPTED RE-INSPECTION REQUIRED
ACCEPTED WITH COMMENTS NOT ACCEPTED
REMARKS / COMMENTS

Tested By :
Shinsung (Name & Signature) (Date & Time)

Witnessed By :
Hyundai E&C Co Ltd (Name & Signature) (Date & Time)

Verified & Accepted By :


RTO / PowerQ (Name & Signature) (Date & Time)

Page 6 DX, VRV


FIELD TEST REPORT
Heat Exchanger
Project : :
Date of Test :
Unit Designation :
Unit Location :
Sty & Area Served :
Unit Make :
Unit Model :
Serial No. :
FIELD MEASUREMENT
Selected or Field
No. Description Specified Measurement
Remarks

Hot Side (Secondary)


o
1 Water IN Temp. ( C)
2 Water OUT Temp. (oC)
3 Water IN Pressure. (kPa)
4 Water OUT Pressure. (kPa)
5 Water Pressure Drop. (kPa)
6 Water Flow Rate (l/s)

Cold Side (Primary)


7 Water IN Temp. (oC) By others
8 Water OUT Temp. (oC) By others
9 Water IN Pressure. (kPa) By others
10 Water OUT Pressure. (kPa) By others
11 Water Pressure Drop. (kPa) By others
12 Water Flow Rate (l/s) By others

Miscellaneous
13 Motorized Valve Operation Check -

ACCEPTED RE-INSPECTION REQUIRED

ACCEPTED WITH COMMENTS NOT ACCEPTED


REMARKS / COMMENTS

Tested By :
Shinsung (Name & Signature) (Date & Time)

Witnessed By :
Hyundai E&C Co Ltd (Name & Signature) (Date & Time)

Verified & Accepted By :


RTO / PowerQ (Name & Signature) (Date & Time)

Page 7 HX
Air Flow Measurement Report
Project : :
Date of Test :
Equipment Designation :
Unit Location :
Sty & Area Served :
FIELD MEASUREMENT
Grille Neck Size (mm) Air Velocity (m/s) / Air volume (CMH) Measured Design
Grille
Grille Type Area (m²) Air Qty
No. Air Qty Air Velocity
H (mm) W (mm) 1 2 3 4 5 6 7 8 AVE (cmh)
(cmh (m/s)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Total 0

Tested By :
ACCEPTED RE-INSPECTION Shinsung (Name & Signature) (Date & Time)
REQUIRED
Witnessed By :
Hyundai E&C Co Ltd (Name & Signature) (Date & Time)
ACCEPTED WITH COMMENTS NOT ACCEPTED
Verified & Accepted By :
RTO / PowerQ (Name & Signature) (Date & Time)

Page 8 Air Flw


W=1300 mm

Rectangular Duct Traverse Report

H=
Project :

70
:

0
Date of Test :
Equipment Designation :
Unit Location :
Sty & Area Served :
FIELD MEASUREMENT

Location Position 1 2 3 4 5 6 7 8 9 10 11 12 13 Total (m/s)

Tested By :
ACCEPTED RE-INSPECTION Shinsung (Name & Signature) (Date & Time)
REQUIRED
Witnessed By :
Hyundai E&C Co Ltd (Name & Signature) (Date & Time)
ACCEPTED WITH COMMENTS NOT ACCEPTED
Verified & Accepted By :
RTO / PowerQ (Name & Signature) (Date & Time)

Page 9 Duct Tr
FIELD TEST REPORT
Air Handling Unit / Pre-Cool Air Handling Unit
Project : :
Date of Test :
Unit Designation :
Unit Location :
Sty & Area Served :
Unit Make :
Unit Model :
Serial No. :
Control Panel Designation :
Belt size/ qty :
FIELD MEASUREMENT
Field
No. Description Selected or Specified
Measurement
Remarks
Electrical Characteristics
1 Volt/ Phase/ Freq. (V/ ø/ Hz)
2 Motor Rated Power (kW)
3 Motor Full Load Amp (A)
4 Motor Type/ RPM
5 Starting Current (A)
6 Running Current (A)
7 Thermal Overload Range (A)
8 Thermal Overload Setting (A)
9 VSD (HZ)
Mechanical Characteristics
9 Supply Air Qty (CMH)
10 Outside Air Qty (CMH)
11 Outside Air Temp. DB/ WB (oC)
12 Off Coil (S/A) Temp. DB/ WB (oC)
13 On Coil (R/A) Temp. DB/ WB (oC)
14 Outside Air Temp. DB/ WB (oC)
15 Water IN/ OUT Temp. (oC)
16 Water Flow Rate (l/s)
17 Static Pressure (kPa)
18 Coil Pressure Drop (kPa)
Miscellaneous
19 Smoke Detector Activation Test -
20 Sound Pressure Level (dBA)
ACCEPTED RE-INSPECTION REQUIRED

ACCEPTED WITH COMMENTS NOT ACCEPTED


REMARKS / COMMENTS

Tested By :
Shinsung (Name & Signature) (Date & Time)

Witnessed By :
Hyundai E&C Co Ltd (Name & Signature) (Date & Time)

Verified & Accepted By :


RTO / PowerQ (Name & Signature) (Date & Time)

Page 10 AHU,PAU
Project:
STAIRCASE PRESSURIZATION TEST REPORT
Staircase No. : Fan Designation :

Air Velocity Across Door (m/s) (Criteria : › 1.0 m/s) When All Doors Are Closed
Test
FLOOR Force Required to Open Door (N) Pressure Differentiate Across REMARKS
No. 1 2 3 4 5 6 Average
(Criteria : ‹ 110 N) Door (Pa) (Criteria : › 50 Pa)

Tested By :
ACCEPTED RE-INSPECTION Shinsung (Name & Signature) (Date & Time)
REQUIRED Witnessed By :
ACCEPTED NOT ACCEPTED Hyundai E&C Co Ltd (Name & Signature) (Date & Time)

WITH COMMENTS Verified & Accepted By :


RTO / PowerQ (Name & Signature) (Date & Time)

Page 11 Stair P
Room Temperature Report
Project : :
Date of Test :
Floor :
Unit No. :
Unit Location :
Equipment Designation
Drawing No. :
Time : AM/PM
Design Temperature : WB / DB (Deg C)
: RH (%)
FIELD MEASUREMENT
Measured Temperature
(Deg C) Relativity Humidity
Points No. Remarks
(%)
WB DB

Point 1
Point 2
Point 3
Point 4
Point 5
Point 6
Point 7
Point 8
Point 9
Point 10

ACCEPTED RE-INSPECTION REQUIRED

ACCEPTED WITH COMMENTS NOT ACCEPTED

REMARKS / COMMENTS

Tested By :
Shinsung (Name & Signature) (Date & Time)

Witnessed By :
Hyundai E&C Co Ltd (Name & Signature) (Date & Time)

Verified & Accepted By :


RTO / PowerQ (Name & Signature) (Date & Time)

Page 12 Rm Temp
Water Flow Balancing Test Report
Project :
Date of Test :
Floor :
Unit No. :
Unit Location :
Drawing No. :

FIELD MEASUREMENT
Equipment Valve Model Setting Diffential Flow (l/s) Design Flow
Valve Index Designation Turns Pressure Flow (l/s) Deviation
(kPa) (%)

ACCEPTED RE-INSPECTION REQUIRED

ACCEPTED WITH COMMENTS NOT ACCEPTED

REMARKS / COMMENTS

Tested By :
Shinsung (Name & Signature) (Date & Time)

Witnessed By :
Hyundai E&C Co Ltd (Name & Signature) (Date & Time)

Verified & Accepted By :


RTO / PowerQ (Name & Signature) (Date & Time)

Page 13 Water Bal


FIELD TEST REPORT
Noise Criteria Measurement
Project : :

Date of Test :
Floor :
Unit No. :
Unit Location :
Equipment Designation
Drawing No. :
Time : AM/PM

FIELD MEASUREMENT

Points location as indicate Specified Noise Criteria Measured Noise


Remarks
in drawings (NC Level) Criteria (NC Level)

ACCEPTED RE-INSPECTION REQUIRED

ACCEPTED WITH COMMENTS NOT ACCEPTED

REMARKS / COMMENTS

Tested By :
Shinsung (Name & Signature) (Date & Time)

Witnessed By :
Hyundai E&C Co Ltd (Name & Signature) (Date & Time)

Verified & Accepted By :


RTO / PowerQ (Name & Signature) (Date & Time)

Page 14 NC Pg 1
FIELD TEST REPORT
Noise Criteria Measurement

NC CURVES & TABLE


Octave Band Sound Pressure Level Lp (dB re 2 x 10-5 Pa)

90
85
NC65
80
NC60
75
NC65 NC55
70 NC50
NC60
65 NC45

NC55 NC40
60
NC35
NC50
55 NC30

50 NC45 NC25

45 NC40 NC20

NC15
40 NC35
Measured Point : P
35 NC30 #REF!

30 NC25
25
NC20
20
15 NC15

10
63 125 250 500 1000 2000 4000 8000
Frequency (Hz)

-12
Sound Power Level, dB re10 W Octave Band Centre Frequency
Record (Hz)
Equipment /Area :
no.
63 125 250 500 1000 2000 4000 8000

Measured Point : P 1

Total Average Sound Pressure


Level (dB)

Page 15 NC Pg 2 -21 (2) (T1-P1)


STATUS OF ESSENTIAL SUPPLY FANS UNDER ELECTRICAL POWER SUPPLY FAILURE & FIRE ALARM

Project :
STATUS INDICATION AT
ACTUAL FAN STATUS
ITEM FAN DESIGNATION LOCATION LMCP Supervisory Panel REMARKS
RUN STOP RUN STOP RUN STOP

Tested By :
ACCEPTED RE-INSPECTION Shinsung (Name & (Date & Time)
REQUIRED
Witnessed By :
ACCEPTED NOT ACCEPTED Hyundai E&C Co Ltd (Name & (Date & Time)
WITH COMMENTS Verified & Accepted By :
RTO / PowerQ (Name & (Date & Time)

Page 16 Fans E. Supply


SINGLE AHU CONTROL PANELVISUAL & FUNCTION TEST CHECK LIST
S/No. Description Good No Good Remark

Main Incoming
1 Main incoming circuit breaker CB0 function properly

2 Protection fuse and fuse holder

3 Incoming supply light (Red phase, Yellow phase, Blue phase)

4 Voltmeter c/w selector switch if applicable

AHU operation
1 Earth leakage protection relay

2 Ammeter if applicable

Manual mode
1 Put the selector switch to ‘Manual’ mode

2 Press start pushbutton to start the motor, the run light will lights on.
Press the stop pushbutton, motor will be stop, the stop light will
lights on.

3 Simulate the overload trip, the trip light will lights on, the AHU will
cut off.

Auto mode
1 Put the selector switch to ‘Auto’ mode

2 Simulate the BAS command, the AHU will control by BAS.

3 The “RUN”, “STOP”, “TRIP” status will feedback to BAS.

Smoke detector alarm


1 Simulate the smoke detector alarm, the “SMOKE ALARM” light will
lights on, the AHU will cut off.

Fire alarm
1 Simulate the fire alarm occur, the AHU will cut off.

Panel others
1 Put back the panel drawing inside the drawing pocket.

2 Put back the cover and close the panel door.

Tested By :
Shinsung (Name & Signature) (Date & Time)
Witnessed By :
Hyundai E&C Co Ltd (Name & Signature) (Date & Time)
Verified & Accepted By :
RTO / PowerQ (Name & Signature) (Date & Time)

Page 17 panel test