Last name: First Name: ID Number: Email: Barkley Robert 312115245 rbar3387@uni.sydney.edu.au

Unit code: ___FINC2011___ Unit name: ___________Corporate Finance 1________________ Tutors name (if applicable):_____Vycke Wu________ Tutorial day/time: ____Tuesday 3 pm____ Full assessment title: _________________Cicero mines Assignment______________________ Word count of assessment:___________________2403__________________________________ Due date:__24__/__10____/___12__ Time & date submitted:___11___ _24__/__10_/_12___

Academic Honesty All forms of plagiarism and unauthorised collusion are regarded as academic dishonesty by the University, resulting in penalties including failure of the unit of study and possible disciplinary action. If you are in doubt about academic honesty, please consult with the unit coordinator. Declaration Tick each box I have completed the online academic honesty module (if applicable)
I have read and understood the University of Sydney Student Plagiarism: Coursework Policy and Procedure, which is published by the University online at http://www.usyd.edu.au/senate/policies/Plagiarism.pdf;

I understand that failure to comply with the above can lead to the University commencing proceedings against me
for potential student misconduct under Chapter 8 of the University of Sydney By-Law 1999 (as amended).

I certify that this work is substantially my own, and where any part of this work is not my own, I have indicated as
such by acknowledging the source of that part or those parts of the work.

The assessment has not been submitted previously for assessment in another unit The assessment conforms to the requirements in the Unit of Study Outline. I have retained a duplicate copy of the assessment
The Faculty may reproduce this assignment, provide a copy to another member of faculty, and/or communicate a copy of this assignment to a plagiarism checking service (which may then retain a copy of the assignment on its database for the purpose of future plagiarism checking).

Please type name in place of signature. Robert Barkley ____________________ By filling out and using this cover sheet, you approve of the information contained. Filling out and then using this coversheet as part of an electronic submission operates in the same way as if you had physically signed a paper copy of the cover sheet.

Cicero Mines Investment Analysis


Part 1: Project Evaluation When making capital budgeting decisions, there are various techniques that can be utilised. Ross et al. (2008) describes that the predominant capital budgeting methods used as being the Net Present value (NPV) method, the Internal Rate of Return (IRR) method, the Payback method, and the Accounting Rate of Return (ARR) method. Conversely, Brealey, Myers and Allen (2011) proposes that the NPV and IRR methods are considered prestige compared to the ARR and the Payback Methods, as they take into account the time value of money. Thus, the following project evaluation will focus on using the NPV and IRR methods. NPV Method: The Net Present Value method discounts future cash flows of a project in attempt to discover the value of a project in present terms, considering the time value of money. Multiplying the tax rate by the incremental taxable profit, where incremental taxable profit is found by misusing expenses and depreciation from annual revenues, provides the NPV. NPV of Machine A: The tax paid is calculated as the tax rate x the incremental taxable profit as follows: Year Annual Revenues Salvage Value Less Annual Depreciation Less Annual Operating expenses Incremental Taxable Profit Annual Tax at 30% Net Profit after Tax (35,000) (152,000) 113,000 33,900 79,100 1-5 300,000 6 300,000 10,000 (35,000) (152,000) 123,000 36,900 86,100

Cash flows for the following years are calculated as follows: Year Machine Cost Installation cost Working Capital Incremental Taxable Profit Salvage Value Plus Depreciation Free Cash Flow before Tax Less Tax Free Cash Flow (290,000) (290,000) 35,000 148,000 33,900 114,100 0 (200,000) (10,000) (80,000) 113,000 80,000 123,000 10,000 35,000 158,000 36,900 121,100 1-5 6


Analysis and explanation: Initially, the machine and installation costs and working capital symbolise the negative cash flows in year 0 Working capital is then assumed to be recovered as a positive cash flow in year 6, recognising the completion of the project Sunk costs such as the cost of market analysis are ignored Taxation reduces the free cash flow generated by either machine Since depreciation is not a cash flow, it is required to be added back to the incremental taxable profit due to it being initially subtracted from revenue when calculating annual tax It should be noted that the 10% loan offered by a salesman for Machine A is not significant in determining the value generated by the chosen machine.

Discount Rate Calculation In order to calculate the Discount Rate, the cash flows are required to be discounted to derive their present value. Since Cicero Mines is 100% equity financed, the discount rate is the shareholders required rate of return. Megginson (2005) explains that investments of a 100% equity financed firm must be sufficient to satisfy the shareholders of the firm. This required rate of return is obtained through the use of the Capital Asset Pricing Model (CAPM), which describes that the cost of equity is equal to the risk free rate within the market plus beta. Its equation is given by: ! !! = !! + ! (!! !! )!!


The model clearly conveys a relationship between the expected return of a stock and its specific risk, which is provided by the risk free rate plus the product of the market risk premium and beta ( ! ). Therefore, when the values given are substituted into the equation, we attain the following discount rate for Cicero Mines: ! !! = 0.07+E(0.12-0.07)x0.06/0.25! = 0.118 = 11.8% Hence, the discount rate applied to the NPV analysis is 11.8%. The NPV of the project is then calculated as the sum of free cash flows generated throughout each year in present values minus the current cost of the project:

!"#!"#!!"# ! = 290,000 +

114,100 114,100 114,100 114,100 114,100 121,100 + + + + + = 185,365.53 1.118 1.118! 1.118! 1.118! 1.118! 1.118!


NPV of Machine B: Annual tax paid with Machine B: Year Annual Revenues Salvage Value Less Annual Depreciation Less Annual Operating expenses Incremental Taxable Profit Annual Tax at 30% Net Profit after Tax (25,800) (95,000) 199,200 59,760 139,440 1-5 320,000 6 320,000 5,000 (25,800) (95,000) 204,200 61,260 142,940

Cash flows for the following years are calculated as follows: Year Machine Cost Installation cost Working Capital Incremental Taxable Profit Salvage Value Plus Depreciation Free Cash Flow before Tax Less Tax Free Cash Flow (328,000) (328,000) 25,800 225,000 67,500 157,500 0 (250,000) (8,000) (70,000) 199,200 70,000 204,200 5,000 25,800 230,000 69,000 161,000 1-9 10

!"#!"#!!"# ! = 328,000 +

157,500 157,500 157,500 161,000 + ++ + = 570,390.52 ! 1.118 1.118 1.118! 1.118!"

Due to a maximisation of total return to shareholders, the project with the higher NPV should be chosen (Brealey, Myers and Allen (2011)). Thus, Cicero Mines should choose Machine B as it has a higher NPV than Machine A. It should be noted that NPV fails to account for the differing useful lives of each machine. According to Brigham and Ehrhardt (1998) the NPV method has the capability of leading to incorrect conclusions when considering two projects with unlike useful lives. To overcome this problem, Brealey, Myers and Allen (2011) propose to convert the present value of each project to an Equivalent Annual Value (EAV). It should be noted that this method relies on the assumption that the project will be replaced with a similar cash flow pattern. Therefore in this situation, we are able to assume that both Machines A and B have the ability to be replaced by another machine at the end of the useful life. The EAV for each machine is calculated as follows: $185,365.53 = EAV!"#!!"# ! =
[!! !!!.!!" !! ] !.!!"

= $44,830.57

$570,390.52 = EAV!"#!!"# ! =

[!! !!!.!!" !!" ] !.!!"


= $100,125.03

Therefore, Machine B appears to be the better option as it has a higher EAV than Machine A. IRR Method Alternate methods of project valuation must to be considered. Brealey, Myers and Allen (2011) describes that the Interest Rate of Return (IRR) is the discount rate at which a projects NPV is equal to zero. Among other considerations, the higher IRR should be chosen when comparing two mutually exclusive projects. Therefore, the IRR of Cicero Mines project options can be calculated as the following: Machine A IRR: 0 = 290,000 + 114,100 114,100 114,100 114,100 114,100 121,100 + + + + + ! ! ! ! (1 + !"" ) (1 + !"" ) (1 + !"" ) (1 + !"" ) (1 + !"" ) (1 + !"" )!

Therefore the IRR of Machine A is approximately 32.08% Machine B IRR: 0 = 328,000 + 157,500 157,500 157,500 161,000 + ++ + ! ! 1 + !"" 1 + !"" (1 + !"" ) (1 + !"" )!"

Therefore the IRR of Machine B is approximately 47.01% Thus, due to the higher internal rate of return (IRR) and NPV, Machine B seems to be the machine most likely to be chosen.

Part 2: Tax Rate Change With the introduction of a carbon and mining tax, the company tax is expected to increase to 38% before the project can be implemented. This could impact the decision between Machine A and B, as an increased tax expense will decrease free cash flows of the project, creating a difference in calculated NPVs. Hence, the adjusted cash flows for both Machines A and B are as follows: Machine A: Calculation of income tax for years 1-6: Year Annual Revenues Salvage Value Less Annual Depreciation Less Annual Operating expenses Incremental Taxable Profit Annual Tax at 38% Net Profit after Tax (35,000) (152,000) 113,000 42,940 70,060 1-5 300,000 6 300,000 10,000 (35,000) (152,000) 123,000 46,740 76,260


Annual cash flows for Machine A: Year Free Cash Flow 0 (290,000) 1-5 105,060 6 111,260

Assuming that the discount rate calculated in Part 1 remains the same, the NPV of Machine A is $147,577.25 and the IRR of Machine A is approximately 28.2%

Machine B: Calculation of income tax for years 1-10: Year Annual Revenues Salvage Value Less Annual Depreciation Less Annual Operating expenses Incremental Taxable Profit Annual Tax at 38% Net Profit after Tax (25,800) (95,000) 199,200 75,696 123,504 1-5 320,000 6 320,000 5,000 (25,800) (95,000) 204,200 77,596 126,604

Annual cash flows for Machine B: Year Free Cash Flow 0 (328000) 1-9 149,304 10 152404

Assuming all factors remain the same, the NPV of Machine B is $523,568.57 and the IRR of Machine B is approximately 44.37% If taxes were to increase before the investment decision occurs, the decision should still remain with Machine B, as it provides a higher NPV than Machine A. Furthermore, Machine B delivers a higher IRR than Machine A.

Part 3: Proxy Company Since the values that were used to estimate the required rate of return in Parts 1 and 2 have not been updated for several years, they could prove to be false and as a result distort the true discount rate of return appropriate to Cicero Mines, therefore affecting the analysis of investment. As Cicero Mines is not listed on the ASX, a similar proxy company in the same industry as Cicero Mines and of an equivalent size is required. Since we are told that Cicero Mines is a large mining firm, we can assume that BHP Billiton is a suitable proxy for this analysis.


Brealey, Myers and Allen (2011) announce that in order to determine a companies securities expected return, approximations are required for the current risk free rate, the expected excess returns of the market and beta (! ). The CAPM can then be utilised to determine the rate required by Cicero Mines shareholders, in turn offering a suitable discount rate to calculate the NPV of each machine.

Risk-Free Rate: Brigham and Ehrhardt (1998) define the risk free rate (!! ) as the rate at which a security has no risk to carry. It should be noted that a risk free rate is only a hypothetical term as it is very difficult to achieve. Therefore, securities with low risk rates are frequently used. Government bonds are an example of a security, as the government backs the returns. Nevertheless, Brealey, Myers and Allen (2011) proclaim that interest rate changes influence securities such as bonds, and as a result cannot be risk free. Ten year Australian Treasury Bonds are used as a proxy for the risk free rate, due to this project being of a long-term nature. The rate on these ten-year treasury bonds was 5.55% for the month of October 20121. As such, this rate will be used as a proxy for the risk free rate in the CAPM.

Market Risk Premium: The market risk premium is the second component of the CAPM equation and is conveyed mathematically as ! (!! !! ). According to Brealey, Myers and Allen (2011) this value is attained on the basis of long term historical returns on the market above the risk free rate, with the underlying assumption that the monthly market returns will predict future returns. Historical data suggests that since World War 2, the average market risk premium is 8.6%2, which will be used when calculating the discount rate.

Proxy Beta: Beta is the third and final part of the CAPM and since Cicero Mines is not a publically listed company, beta cannot be directly calculated from its share price data. In order to find beta, Bowman and Bush (2006) declare that the beta of a comparable publically listed company is needed as a proxy. In this situation, the comparable company is BHP Billiton and their levered beta equates to 1.773. Consequently, beta must be unlevered to account for the fact that, unlike Cicero Mines, BHP Billiton is not 100% equity financed and therefore its shareholders have a lower market risk. With BHP Billitons debt to equity ratio being 0.32 4, the following formula allows the unlevered beta to be calculated as follows: !!"#$%$&$' = 1.77 = 1.446 1 + 1 0.3 x0.32


1 2

Risk Free Rate for month of October 2012 www.rba.gov.au/ Historical Data of market risk premium was obtained from www.rcrawford.wordpress.com/ 3 BHP Billiton Beta was obtained from www.au.finance.yahoo.com/ 4 Average Debt to Equity ratios (5 year average) were obtained from www.forbes.com/


Discount Rate and NPV Calculations: When using the CAPM formula, the adjusted discount rate of Cicero Mines is calculated by utilising the data obtained from the proxy company as follows: !! + ! (!! !! )! !! = 0.0555 + 0.086 1.77 = 0.20772 Therefore, this provides a proxy discount rate of 20.8%, which substituted into NPV calculations gives the following values: Machine A !"#!"#$% = $84,538.05 Machine B !"#!"#$! = $315,910.10

As a result, the new proxy rate still conveys Machine B as the preferred investment.

Part 4: Sensitivity Analysis Discussed earlier in Part 3, the beta estimated relies on various assumptions such as, historical returns that will reflect future returns, and the market risk of Cicero Mines is similar to its competitors adjusted for leverage. Conversely, the validity of these assumptions may not be entirely correct considering the recent volatility of financial markets and the lack of information on Cicero Mines, and therefore is likely to influence the investment evaluation. As a result of this, a sensitivity analysis was undertaken in the attempt to determine how different beta values impact Cicero Mines investment choice, with everything else remaining constant. The results are as follows: Change to Beta Adjusted Beta Equivalent Discount Rate 1 0.8 0.6 0.4 0.2 0 -0.2 -0.4 -0.6 -0.8 -1 2.77 2.57 2.37 2.17 1.97 1.77 1.57 1.37 1.17 0.97 0.77 0.29372 0.27652 0.25932 0.24212 0.22492 0.20772 0.19052 0.17332 0.15612 0.13892 0.12172 $17,104.79 $28,880.26 $41,437.32 $54,846.01 $69,184.08 $84,538.05 $101,004.33 $118,690.61 $137,717.36 $158,219.63 $180,349.15 $167,664.77 $192,306.98 $219,160.88 $248,497.13 $280,627.12 $315,910.10 $354,761.79 $397,664.70 $445,180.62 $497,965.75 $556,789.10 $150,559.99 $163,426.72 $177,723.56 $193,651.12 $211,443.04 $231,372.06 $253,757.46 $278,974.09 $307,463.26 $339,746.13 $376,439.95 NPV (A) NPV (B) NPV (B) - (A)


The graphical representation of the NPVs of the projects against the range of betas are as follows:

600000 500000 400000 300000 200000 100000 0 0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 Machine A Machine B

As conveyed in the table and graph above, while both machines NPVs are sensitive to the beta values used in the calculations, it is not likely that it should have any influence on the investment decision. This is due to the fact that the NPV of Machine B is significantly higher than that of Machine A, it should be noted that this is for all beta values used in the sensitivity analysis. Therefore, the correct decision is to choose Machine B as it provides the best outcome in all calculations undertaken throughout this investment analysis.

References: Bowman, R. G., and Bush, S. R., 2006, Using Comparable Companies to Estimate the Betas of Private Companies, Journal of Applied Finance 16(2), 71-81. Brealey, R. A., Myers, S. C and Allen, F. 2011, Principles of Corporate Finance, 10th Ed., McGraw Hill Irwin, New York. Brigham, E and Ehrhardt, M, 1998, Financial management: Theory and Practice, Harcourt College Publishers. Forbes, 2012, Ratios and Returns, Forbes, Sydney, viewed 21 October 2012 http://finapps.forbes.com/finapps/jsp/finance/compinfo/Ratios.jsp?tkr=bhp Megginson, William L, 2005, Introduction to Corporate Finance, South Western College Pub, Cincinnati. RTCrawfords Weblog, 2008, BHP Billiton Ltd, Sydney, viewed 22 October 2012 http://rcrawford.wordpress.com/2008/05/25/bhp-billiton-ltd-bhp-buy-sell-hold-may-24-2008/ Ross, S., Westerfield, R. and Jordan, B. 2008, Corporate Finance Fundamentals, 8th ed., McGraw Hill, New York. Reserve Bank of Australia (RBA), 2012, Capital Market Yields Government Bonds Monthly, RBA, Sydney, viewed 21 October 2012 http://www.rba.gov.au/statistics/tables/#govt_finance Yahoo Finance, 2012, BHP Billiton - Key Statistics, Yahoo, California, viewed 22 October 2012 http://au.finance.yahoo.com