Jefferson Houston: June 14, 2013

Project Update Next Weeks Work One Week Look Ahead Schedule of Upcoming Construction Activities:
o Received Foundation to Grade Permit on 6/6/13. o Site Mobilization: Continuation of site preparation activities. o Erosion and sediment controls o Construction fencing o Tree protection fencing o Construction entrance o Temporary water lines for construction o Begin grading on the north side in the field. o Possibly begin tree removal

Safety First:
o The Construction Zone shall only be accessed by authorized personnel.