Huawei DBS3900
Commissioning Procedure
(V1.2)
Scope
The scope of this document is to give a detail procedure for the commissioning of the
Huawei DBS3900 base station. The document will provide the required tools, contacts
and procedures to be followed.
Document Revision
Version Author Reviewer Date Approver Change Log
Draft S Perkins 02/11/2009 Initial Draft
V1.0 Pan Fei 04/20/2009 V1.0
V1.1 Pan Fei 04/27/2009 V1.1
V1.2 Pan Fei 05/15/2009 V1.2
1. Tools List
Tools Sub Contractor Huawei
Compass X
Digital Camera X
GPS Navigation (Optional) X
Laptop X
Mobile Phone (For X
communication)
Test Data Card X
Test Mobile Phone and SIM X
USB Flash Memory Stick X
UTP Network Cable X
Vehicle X
Multi meter X
2. Site Awareness
There are a number of site in Canada that are in remote location that require
situational awareness therefore when travelling to and from remote site locations it is
important that the engineer is equipped for travel to remote sites
Engineers must also be aware that Tower work takes precedent over any other site
work; therefore if tower work is in progress then the tower crew is in control of the site.
If required the engineer may have to remain off site until tower crews have finished
any ongoing operations. If tower work is in progress then hard hats are required to be
worn onsite.
3. Commissioning Process
The commissioning process for the Huawei DBS3900 will follow the flow shown below.
The following section will provide a breakdown of the activities required for successful
commissioning of the base station.
4. NTP Report
The NTP report is a report that details which sites have received “Notice to Proceed”
(NTP) from the customer. This report then provides the basis for scheduling activities
for commissioning preparation and commissioning activities. From this report a
forecasting schedule will then be produced to initiate the site configuration data to be
prepared and the scheduling of engineers to attend site for commissioning.
The details of this process are not covered in this document and is only included for
informational purposes.
5. Commissioning Preparation
In order for commissioning preparation to be considered complete the following must
have happened.
Make sure that each USB stick is only kept with 3 files above dedicatedly for one
NodeB, it’s better to label the USB stick with the site Name before commissioning to
avoid the USB sticks mixing if more than 1 site will be integrated for one team.
• All employees must have a hard hat, hard hat must be worn at all times
when a tower crew is on site
• Upon entry into the site one person must immediately call the security control
center and report what site you have entered, provide your name and you are
from Huawei, report site name and site number, report what your work order is
to be on site.
• The security control center phone number, site name and site ID is posted
on the wall beside the phone
• If there is a site book you must log into the book.
• When you are last person in the site you must call security control and sign out
from the site before leaving.
• You must take care and ensure that the lights are turned off, the shelter door is
locked and properly closed, shut the gate and close the gate lock.
Once the audit checks have been completed and no major issues have been found
then commissioning can commence. If any major issues are found then the issue
must be recorded and escalated to Huawei Regional PM and Huawei RNC Engineer
DBS3900 automatically reads the related software and data configuration file under
the fixed directory structure from the USB stick and verifies their names and formats:
NodeBsoftware: \\NodeB\Software\Software.csp
BootROM: \\NodeB\Software\Firmware.csp
Data configuration file: \\NodeB\Configuration\NodeBCfg.xml
1. Connect the USB Memory stick provided by Huawei to the USB port on the
BBU3900 (do not use the test port). If the USB Memory stick is detected
correctly the following should happen within 20 seconds: the LED on the USB
disk is blinking; the RUN LED on the WMPT is blinking quickly (On for 1s, OFF
for 1s) about 2 seconds, ALM LED on WMPT is “ON” since the hardware is
different with the default scripts; CPRI LED on WBBPb are “OFF”.
ALM LED
“ON” WMPT
USB LED remains solidly “ON”. It will take about 10 minutes to activate the
software.
4. The DBS3900 will carry out a reset after the software and the data
configuration has been activated. During this process the LED on the USB will
transition from ON->OFF->Blinking; the RUN LED on WMPT transitions:
ON->OFF->Blinking (ON for 0.125s, OFF for 0.125s); RUN LED on the 2
WBBPb will blink respectively; CPRI LED on WBBPb will flash once “RED”
and then become “Green”. The full reset will take about 5 minutes.
5. After the reset is complete, DBS3900 runs normally, the status should now be:
LED on USB is “OFF”; RUN LED on WMPT blinks (ON for 1s, OFF for 1s);
ALM LED on WMPT stays “OFF” (If there are no alarms); RUN LED on
WBBPb blinks (ON for 1s, OFF for 1s);CPRI LED on WBBPb stays “GREEN”
Note: WMPT always blinks slowly (ON for 1s, OFF for 1s) in 30 seconds, please plug
it again.
Connect
2. Set the IP address for laptop. You can log in to the NodeB on the LMT only
when the IP address of the LMT PC is correctly set. For local maintenance on
the LMT, the IP addresses of the LMT PC and the NodeB local maintenance
channel stay within the same network segment. You need set IP Address is
17.21.2.33 and mask is 255.255.0.0 in your laptop.
5. Click Add and Fill the table. The Office name is NODEB, the IP Address is
17.21.2.15 and the NE type is NodeB then click [Close].
6. Input the User Name: admin Password: NodeB. Click the “Login”
7. Once you are logged in successfully you should see the following.
2. The Software Update dialog box is now displayed, select Upgrade BOOTROM
and click [Next].
Note: NodeB Bootrom must be upgraded before upgrading NodeB Software; the
reversed procedure may cause the NodeB breakdown.
1. Select the Maintenance tab and choose Service > Software Management.
Then double-click Software Update, as before.
2. The Software Update dialog box is now displayed, this time select Upgrade
NodeB Software and click [Next]
3. The Upgrade NodeB software dialog box will not be displayed. Select
[Download NodeB Software Package], [Download By Configuration] and
[Activate NodeB Software] and then use the [Browse] button to set the location
of the NodeB Software Package, then click the [Next] button.
After the upgrade the software is complete, system will automatically reset
NodeB, this will take about 5 minutes.
Use the [Browse] button to set the location of the configuration file
(NodeBCfg.xml) and click [Start].
2. Once the progress bar reaches 100% click [Close]. Go to the MML command
window for the NodeB and type the command ‘RST NODEB”. Once the
NodeB has reset the new configuration will take effect. Please wait 5-10
minutes.
Then open the ‘extra command’ file on your hard disk. Excution type is ‘All’
and don’t select the ‘prompt when error occurs.
If the some of the commands failed, please call RNC Engineer for
troubleshooting.
To finalize the commissioning of the NodeB and make it ready for call testing it is
necessary to notify the RNC engineer that the software upgrade and the
commissioning is complete. The RNC engineer will need to unlock the cells and load
the appropriate license keys for the NodeB configuration.
“LST VER”
“LST SOFTWARE”
Pleae make sure the version is V200R010C01B053 and then you can make
callp. If it is not the right version, please do Item 10 Local Commissioning
again.
Log the results of the commands to a file and name it <Site
ID>_<SW_Version.txt>. This file will become part of the site
documentation package.
this will form part of the site documentation to be submitted. Record the Primary
Scrambling Code for each cell in <Site ID>_CallP_Register.xls for Call_P test.
11.7 Troubleshooting
For assistance in troubleshooting any problems that arise during the commissioning
of the NodeB the first point of contact will be the RNC engineer for the area. If the
RNC engineer is not able to provide the necessary support the local engineer will
need to contact Huawei technical support.
Alpha
Gamma
N
Beta
Once the cell orientation has been verified then call testing can begin. ( Telus has
some special sites, which are not defined like this, Huawei will provide a list of these
kind of sites)
Call P testing is to be carried out with co-ordination with the RNC Engineer; there are
3 sections to the Call P process, which are:
After you finish the 1900 call test, please call RNC Engineer to unblock 800 cells
and block 1900 cells, you can make 800 calls and Handover
After you finish the callp, please call RNC Engineer to unblock all cells and tell
them the Callp on site finished.
Record the all of the test results to <Site ID>_Telus_CallP Record after finished
each test.
PS: When you make the PS handover test, please remember to record the
average download speed to ‘Telus_CallP Record’ spreadsheet.
• Mobile to Fix line using 11 digits (Local Site telephone can be used for this
purpose)
• Mobile to Fix line using 10 digits (Local Site telephone can be used for this
purpose)
• Fix line to Mobile using 11 digits (Local Site telephone can be used for this
purpose)
• Fix line to Mobile using 10 digits (Local Site telephone can be used for this
purpose)
13.3 Basic Service Tests and handover test (For you reference)
This section of call tests deals with testing the services on each cell of the Site, one of
each of the following tests is required in order to achieve a pass grade for the cells
(unless know conditions exist to prevent one or more of the tests, details of these
conditions must be detailed in the Call P documentation).
1. Call RNC Engineer to block all 850 cells. Then make Voice call and video call in
each 1900 cell. Make sure the PSC is right in each cell.
2. Make a call and walk around the site, to make sure there is no call drop. And then
reverse to make sure there is no call drop
3. 3. Call RNC Engineer to unblock 850 cells and block all 1900 Cells. Then make
Voice call and video call in each 850 cells. Make sure the PSC is right in each cell.
4. Make a PS download and walk around the site, to make sure there is no call drop.
And then reverse to make sure there is no call drop
• Voice call – to be held for 1 minute and checked for call quality.
• Video Call – to be held for 1 minute and checked for video and voice quality.
• HSPA data test
1. Initiate the internet connection and make sure connection is set up.
2. Login to site http://speedtest.net/, choose the city where the site
located and initiate the download test and upload test.
3. Check the download speed
4. Check the upload speed
3. Click ‘ Set’ on LMT to set the save direction. Just select ‘Save
Successful Reaults’ and save to your folder.
Site Overview Photo //<Site ID>/Site Photo/<Site Provides a visual view of the installed
ID>_Overview.jpg equipment in the rack.
DCDU Audit Checklist //<Site ID>/HW Installation Confirms the audit results carried out
Check/<Site for the DCDU prior to commissioning of
ID>_DCDU_Checklist.doc the site.
DCDU Close Up Photo //<Site ID>/Site Photo/<Site Provides a close up view of the
ID>_DCDU.jpg installed DCDUs, to visually confirm
install.
BBU Audit Checklist //<Site ID>/HW Installation Confirms the audit results carried out
Check/<Site for the BBU prior to commissioning of
ID>_BBU_Checklist.doc the site.
BBU Serial Number //<Site ID>/HW Installation Provide the accurate BBU serial
Check/<Site ID>_BBU number for each sites.
SN_<Serial Number>.txt
BBU Close Up Photo //<Site ID>/Site Photo/<Site Provides a close up view of the
ID>_BBU.jpg installed BBU, to visually confirm install.
Power Cabling (PSU //<Site ID>/Site Photo <Site Provides a close up view of the power
end) ID>_PWR.jpg cabling to the PSU.
Local Cell Status //<Site ID>/Commissioning Provides evidence of Cell Status after
Log/<Site commissioning.
ID>_Localcell_Status.txt
Cell Configuration //<Site ID>/Commissioning Provides the cell configuration after the
Log/<Site ID>_ commissioning of the NodeB
Cells_Config.txt
Alarm Log //<Site ID>/Commissioning Provides a log of all of the full alarm
Log/<Site ID>_Alarms.csv information for the site in CSV format.
Call-p Result //<Site ID>/CallP Provides Call-p results of all the cells
Register/<Site for the site.
ID>_Telus_CallP Record
Commissioning //<Site ID>_Commissioning Include three files: ATP Data
Report Report Sheet_scripted_V3.xls,
BatchMML_Result.txt, Data Scan.txt
//<Site ID>/Configuration/
Each team leader should send out all these request files in 24 hours. after the
commissioning. Please send to Huawei Local PM, Site Technician and RNC
Engineer.
• Intra-Frequency Handover
S111:
1. [RNC engineer] Unblock the 3 cells of each sector.
2. [Site Engineer] Make sure mobile phone camp on the cell of sector Alpha,
originate a voice call to the 2nd mobile phone.
3. [Site Engineer] Hold on the call proceeding and move to the cell of sector Beta
and Gamma sequently in clockwise, then move to cell of sector Alpha.
4. [Site Engineer] Make sure the voice call is clear and without drop.
5. [Site Engineer] Hold on the call, move back to cell of sector Gamma and Beta
sequently in anti-clockwise, finally back to cell of sector Alpha.
6. [Site Engineer] Make sure the voice call is clear and without drop.
7. [Site Engineer] Terminate the call and confirm with RNC engineer for the test
results.
8. [Site Engineer] Record the test results in callp register table.
step5 step3
S222:
1. [RNC engineer] Unblock the 3 cells of F1 (850MHZ) of each sector, block the
other 3 cells of F2 (1900MHZ).
2. [Site Engineer]Follow the step2~8 for S111 handover test.
3. [RNC engineer] Block the 3 cells of F1 (850MHZ) of each sector, unblock the
other 3 cells of F2 (1900MHZ).
2009-05-15 HUAWEI Confidential Page27, Total30
Huawei DBS3900 Commissioning Procedure Security Level:
21. [Site Engineer] Confirm with RNC engineer for the successful handover to
850M cell (Gamma) and move to 1900M cell (Beta) in anti-clockwise.
22. [RNC Engineer] Block 1900M cell (Alpha), unblock 85M cell (Alpha).
23. [Site Engineer] Confirm with RNC engineer for the successful handover to
1900M cell (Beta) and move to 850M cell (Alpha) in anti-clockwise.
24. [Site Engineer] Confirm with RNC engineer for the successful handover to
850M cell (Alpha).
25. [Site Engineer] Terminate the call and confirm with RNC engineer for the test
results.
26. [Site Engineer] Record the test results in Callp register table.