TENDER FILE NO :
PROJECT :
LOCATION :
SUPPLIER :
SUB-CONTRACTOR :
QUOTATION DATE :
Material Cost :
7.00
Labour For Installing PC Capping/ per@m
Lintol
Dimension
Concrete @ 0.10 x 0.25 3.42
Formwork @ 0.61 1.82
Steel bar :
Y12 1.00 x 4 x 0.89 7.81
R6 0.83 x 7 x 0.22 2.82
15.87
Wastage @ 5% 0.79
16.67
Labour cost / m 7.00
Total Cost / m 23.67
Dimension
Concrete @ 0.05 x 0.253 1.71
Formwork @ 0.56 1.67
Steel bar :
Y12 1.00 x 4 x 0.89 7.81
R6 0.62 x 7 x 0.22 2.12
13.31
Wastage @ 5% 0.67
13.98
Labour cost / m 7.00
Total Cost / m 20.98
Dimension
Concrete @ 0.15 x 0.10 2.03
Formwork @ 0.40 1.20
Steel bar :
Y12 1.00 x 4 x 0.89 7.81
R6 0.62 x 7 x 0.22 2.12
13.16
Wastage @ 5% 0.66
13.82
Labour cost / m 7.00
Total Cost / m 20.82