DOC. NO.: GREENERGY POWER (I) PVT LTD VER.

: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 1 of
DPR POWER PROJECT 58

GREENERGY POWER (I) PVT Ltd

Project of 5 Mega Watt

By Crystalline Technology
In
Kadiri, ananthpur dist.
andhrapradesh

Owned by-
“sahil energy “
hyderabad
India.
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 2 of
DPR POWER PROJECT 58

REV. NO.: P0 PPD BY: CHKD BY: APPD BY:


DATE 09/12/2009 PSS VJS UKS

SECTION NO. DESCRIPTION PAGE NO.

A. EXECUTIVE SUMMARY 5

B. PROJECT AT A GLANCE 6

SECTION – 1 INTRODUCTION TO THE PROJECT 8

INTRODUCTION 9

GENERATION OF ELECTRICITY & IMPORTANCE OF 9


RENEWABALE ENERGY

SOURCES OF GREENHOUSE GASES 9

GREEN HOUSE GAS CONCENTRATION TRENDS

ATMOSPHERIC LIFETIME & GLOBAL WARMING


POTENTIAL (GWP) FOR SOME GREEN HOUSE GASES

WORLD ENERGY SCENARIO

BACKGROUND OF THE PROJECT

BARRIERS IN DEVELOPMENT OF THE PROJECT

BENEFITS OF GRID CONNECT SOLAR ENERGY

CHOICE OF TECHNOLOGY

SECTION – 2 PROJECT DESCRIPTION


DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 3 of
DPR POWER PROJECT 58

INTRODUCTION

BRIEF DETAILS OF PROJECT AREA

LOCATION MAP OF JALGAON IN MAHARASHTRA

SITE METEROLOGICAL DATA

SECTION – 3 DEMAND ANALYSIS AND JUSTIFICATION OF THE


PROJECT

INTRODUCTION

SOLAR POWER POTENTIAL IN INDIA

SOLAR RADIATION OF INDIA

SOLAR ENERGY POTENTIAL IN MAHARASHTRA

THE CURRENT POWER SCENARIO OF MAHARASHTRA

POWER SUPPLY POSITION IN THE STATE

NEED FOR THE PROJECT

SECTION – 4 TECHNICAL FEATURES & EQUIPMENT OF THE PLANT

BASIC SYSTEM DESCRIPTION

OPERATION PHILOSOPHY

POWER GENERATION SCHEME

DESCRIPTION OF MAIN PLANT EQUIPMENT

DESCRIPTION OF POWER EVACUATION SYSTEM AND


INTERFACING WITH GRID

SECTION – 5 POWER PLANT CONFIGURATION AND SPECIFICATIONS


OF MAIN PLANT EQUIPMENT

SELECTION OF UNITS

SPECIFICATIONS OF MAIN PLANT

SECTION – 6 OPERATION AND MAINTENANCE

OPERATION AND MAINTENANCE PHIOLOSOPHY

ORGANIZATION STRUCTURE

SECTION – 7 SWOT ANALYSIS

SECTION – 8 PLANT LAYOUT & CIVIL ENGINEERING ASPECTS

INTRODUCTION

PLANT LAYOUT
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 4 of
DPR POWER PROJECT 58

MAIN PLANT AND EQUIPMENT LAYOUT

STRUCTURAL WORKS

SECTION – 9 PROJECT IMPLEMENTATION

IMPLEMENTATION CONCEPT

PROJECT SCHEDULE

SECTION – 10 ESTIMATED PROJECT COST

BASIS OF COST ESTIMATION

ESTIMATED COST OF PROJECT

SECTION – 11 ESTIMATED POWER GENERATION COST

COST OF POWER GENERATION

ESTIMATED COST OF POWER GENERATION

SECTION – 12 ENCLOSURES

ANNEXURE

ANNEXURE 1 THE PROMOTIONAL POLICIES OF MNRE FOR SOLAR


POWER GENERATION

ANNEXURE 2 PROJECT SCHEDULE

DRAWINGS

TEE-167-GA-101 PLOT PLAN

TEE-167-GA-102 GENERAL ARRANGEMENT: CONTROL ROOM

TEE-167-GA-501 KEY SINGLE LINE DIAGRAM / P0


DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 5 of
DPR POWER PROJECT 58

(A) EXECUTIVE SUMMARY

The Electricity Act, 2003, paves way for an innovative approach to solve our
country’s power problems. It has paved the way for a competitive environment;
open access to existing transmission and distribution network to transmit electricity
across regions; de-licensing of generation, captive power and dedicative
transmission lines; licensing of distribution and supply companies and the
restructuring of State Electricity Boards

The Ministry of Power have a mandate to promote cogeneration and renewable


sources for Power generation under Nodal agencies and hence it will play a major
role in mainstreaming renewable energy sector. The advantage or renewable
resources includes their capacity to produce energy without producing carbon-
based warming and polluting agents into the atmosphere. The financial cost of its
applications is not always cheap but if the environmental costs of using fossil are
accounted for, renewable energy wins hands-down. There are also indirect savings
on health and its costs as there are no harmful emissions.

In the above backdrop, Sahil Energy Pvt. Ltd., has decided to set up a 5MW Solar
Power Plant. This Detailed Project Report (DPR) brings out all technical details and
overall costs justifying the selection of the project. The total power generation is
envisaged to be 5MW from Solar Photovoltaic Cell. It is a very important document
that is required for Environmental Impact Assessment (EIA) studies, fixation of tariff,
finalizing Power Purchase Agreement (PPA) and also for submission to Financial
Institutions for obtaining project funding. The total project cost is expected to be
Rs85 Crores and the average cost of generation is expected to be Rs.12.86 /kWh.

(B) PROJECT AT A GLANCE

1.0 GENERAL

1.1 The Project 5MW Solar PV Grid Connected Power


Project

1.2 Owner SAHIL ENERGY

1.3 Location of Plant ANANTAPUR DIST.

1.4 Location Kadiri

1.5 Distance from District Headquarter


DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 6 of
DPR POWER PROJECT 58

1.6 Access by Road Chennai Mumbai National highway

1.7 Access by Rail Kadiri Railway station

1.8 Access by Air Satya Sai Airport Anantpura

1.9 Telecommunications Telecommunication facility available

1.10 Land It is proposed to install 5MW on the land,


admeasuring about ………… Acre, which
is already demarcated

1.11 Land Characteristics Barren Land


Non Agricultural Land

1.12 The Geographical location of the 13'-40' and 15'-15' Northern Latitude and 76'-50'
and 78'-30' Eastern Longitude
project site

1.13 Irradiation details considered Kadiri, Anantpur(Dist.)

1.14 Type of Module Mounting Structure Fixed Structures, Earth Mounted

1.15 Type of PV Modules Considered for Crystalline


the offer

1.16 Proposed Capacity 5 MWp

1.17 Capacity of each PV Module 200 Wp

1.18 Invertors Capacity 100 KVA x 50 Nos.

1.19 Projected Energy Production per year 8.3 MU(Assured)

1.20 Total Project Cost Rs 80. CR


DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 7 of
DPR POWER PROJECT 58

SECTION - 1

INTRODUCTION TO THE PROJECT


DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 8 of
DPR POWER PROJECT 58

1.0 INTRODUCTION

World Economic growth is driven by energy, whether in the form of finite resources
such as coal, oil and gas or in renewable forms such as hydroelectric, wind, solar
and biomass or its converted form. This energy generation and consumption
strengthens the nation’s industries, vehicles, homes and offices. It also has
significant impact on the quality of the country’s air, water, land and forest
resources. For future growth to be both rapid and sustainable, it needs to be as
resource efficient and environmentally benign as possible.

2.0 GENERATION OF ELECTRICITY & IMPORTANCE OF RENEWABLE ENERGY

The growth in installed power generating capacity has not kept pace with the
projected demand. To solve this problem, it is necessary to set up more power
plants and most of these power plants will be either fossil fuel based or hydro
electric units. However, the conventional power stations cause enormous damage
to be environment due to pollution and other side effects.

Renewable energy sources energy source are wonderful options because they are
limitless. These will not be exhausted though fossil fuel will be gradually exhausted
in course of time. Also another great benefit from using renewable energy is that
most of these sources do not pollute the environment; the way burning of fossil fuels
dose.

3.0 SOURCE OF GREENHOUSE GAS

The greenhouse gas emissions (GHG) come primarily from the combustion of fossil
fuels in energy use. Energy use is largely driven by economic growth with short-
term fluctuations in its growth rate created by weather patterns affecting heating and
cooling needs, as well as changes in the fuel used in electricity generation.
The burning of fossil fuels produces around 21.3 billion tones of Carbon Dioxide per
year, but it is estimated that natural processes can only absorb about half of that
amount, so there is a net increase of 10.65 billion tones of atmospheric carbon
dioxide per year. Carbon dioxide is one of the GHG that enhances radioactive
forcing and contributes to global warming, causing the average surface temperature
of the earth to rise. Environment scientists predict that this will cause major adverse
effects, including reduced biodiversity.
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 9 of
DPR POWER PROJECT 58

The electricity sector is unique among industrial sectors in its very large contribution
to emissions associated with nearly all air issues. Electricity generation produces a
large share of nitrogen oxides and sulphur dioxide emissions, which contribute to
smog and acid rain and the formation of fine particulate matter in addition to carbon
dioxide. In addition, this sector has significant impacts on water and habitat and
species. In particular, hydro dams and transmission lines have significant effects on
water and biodiversity

4.0 GREEN HOUSE GAS CONCENTRATION TRENDS

The atmospheric concentration of CO2 has increased by 31% since 1750 and
continues to increase, on average, by 1.5 ppm or 0.4% per year. About 80% of the
anthropogenic emissions of CO2 during the past 20 years is due to fossil fuel
burning and cement production. The rest is due to deforestation. The atmospheric
concentrations of CH4 and N2O have increased by 151% and 17%, respectively,
since 1750. The table given below shows the 20 th Century changes in the Earth’s
atmosphere system for selected GHGs.

TABLE – ATMOSPHERE COCENTRATION OF GHGs IN THE 21ST CENTURY

Atmospheric Pre-Industrial Concentration in Increase in


Indicator Concentration year 2000 Concentration
(1000 – 1750) Level in
Percentage
CO2 280 ppb 368 ppb 31 ± 4%

CH4 700 1750 151 ± 25%

N2O 270 316 17 ± 5%

Tropospheric O3 Increases by 35 ± 15% from 1750, varies with region

HFCs, PFCs, SF6 Increased globally over last 50 years

5.0 ATMOSPERIC LIFETIME & GLOBAL WARMING POTENTIAL (GWP) FOR SOME
GREEN HOUSE GASES

5.1 CARBON DIOXIDE (CO2)

CO2 It has a variable atmospheric lifetime, and cannot be specified precisely.


Recent studies indicate that recovery from a large input of atmospheric CO2 from
burning fossil fuels will result in an effective lifetime of tens of thousands of years.
Carbon dioxide to have a GWP of 1 over all time periods.
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 10 of
DPR POWER PROJECT 58

5.2 METHANE (CH4)

Methane has an atmospheric lifetime of 12+3 years and a GWP of 62 over 20 years,
23 over 100 years and 7 over 500 years. The decrease in GWP at longer timer is
because methane is degraded to water and CO2 by chemical reactions in the
atmosphere.

5.3 NITROUS OXIDE (NOX)

Nitrous Oxide has an atmospheric lifetime of 120 years and a GWP of 296 over 100
years

5.4 CFC 12

CFC – 12 has an atmospheric lifetime of 100 years and a GWP of 106000 over 100
years

5.5 HCFC – 22

HFFC – 22 has an atmospheric lifetime of 121 years and a GWP of 1700 over 100
years

5.6 TETRAFLUOROMETHANE

Tetrafluoromethane has an atmospheric lifetime of 50,000 years and a GWP of


5700 over 100 years

5.7 SULPHUR HEXAFLUORIDE (SF6)

SF6 has an atmospheric lifetime of 3,200 years and a GWP of 22000 over 100
years

6.0 WORLD ENERGY SCENARIO

It was estimated that in 2005, 86% of primary energy production in the world came
from burning fossil fuels, with the remaining non-fossil sources being hydroelectric
6.3%, nuclear 6.0%, and renewable energy sources, i.e. geothermal, solar, wind,
biomass and wastes contributed only 0.9%.

7.0 BACKGROUND OF THE PROJECT

Large multi-megawatt PV plants, approximately to 50 MW, are now in operation in


the world.

Solar Photovoltaic (PV) is known to be an important energy source for developing


countries like India. Its importance is now being reaffirmed even by developed
countries in view of its renewable and environment friendly character. In our country
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 11 of
DPR POWER PROJECT 58

also, optimum utilization of solar energy could not only lead to savings in
conventional energy but also result in many indirect benefits. In India 2MW solar PV
now are commercially operated by independent power producer. But till now solar
technology is expensive compared to other technology and significant financial
assistance from government is needed to the developers and operators of new
plants.

In view of this, the Ministry of New & Renewable Energy Sources has been
promoting electricity generation from Solar PV in Mega-Watt level. These projects
are covered under the Grid Interactive Solar PV Power Generation Projects of
Ministry of New & Renewable Energy Sources, Govt. of India. The Ministry initiated
the programme to establish as a viable and environment friendly electricity
generation option.

8.0 BARRIERS IN DEVELOPMENT OF THE PROJECT

The project has been identified with some barriers as mentioned below:

(a) Higher capital cost – The initial capital investment of the project is so high
compared to other conventional power Project, so per MW cost is high.

(b) Low Capacity Utilization factor – the total unit generation is low compared to
other electricity generation system, because maximum of 6 hours in a day
plant gets the solar light and generates the power.

The project being first of its kind in the state, thee could be more risks and barriers
which might surface as the project progresses and it is difficult to enumerate all at
this stage.

9.0 BENEFITS OF GRID CONNECTED SOLAR PV POWER PLANT

(a) Power from the sun is clean, silent, limitless and free

(b) Photovoltaic process releases no CO2, SO2 or NO2 gases which are normally
associated with burning finite fossil fuel reserves and don’t contribute to global
warming.

(c) Photovoltaics are now a proven technology which is inherently safe as


opposed to other fossil fuel based electricity generating technologies.

(d) No fuel is required for generation, so fuel cost of power generation is zero.

(e) Solar power shall augment the needs of peak power needs

(f) Increase the grid reliability i.e., voltage and frequency


DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 12 of
DPR POWER PROJECT 58

(g) Solar Powered Grid Connect Plants can act as tail end energizers, which in
turn reduces the transmission and distribution losses.

(h) Provides a potential revenue source in a diverse energy portfolio

(i) Assists in meeting renewable portfolio standards goals

(j) Generation of electricity from Solar PV is totally free of Green House Gas
emission.

10.0 CHOICE OF TECHNOLOGY

Proposed power plant converts sunlight directly into electrical energy by Solar PV
Module. It produces DC current.

There are two types of solar power plants, mainly

(a) Stand alone

(b) Grid Connected

In Grid Connected type power plant, Modules supplies DC current to inverter. Then
DC is converted to low voltage AC current. AC power is stepped up by 415 / 11 kV
step up transformer & fed to the grid.

Now a days there are two types of solar cells available in market

(a) Amorphous type


(b) Crystalline type
(c) Thin Film (CIGS/CdTe) type

The efficiency of amorphous is less than crystalline. So, more area is needed to set
up same capacity solar plant with amorphous type cells.

Polycrystalline solar cells are used in proposed solar power plant.


DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 13 of
DPR POWER PROJECT 58

SECTION - 2

PROJECT DESCRIPTION
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 14 of
DPR POWER PROJECT 58

1.0 INTRODUCTION

The proposed 5MWp solar power plant project will generate electricity from non-
conventional sources. The project will use “polycrystalline” technology for the first
time in the state for producing power by solar energy. This project envisages
generation of safe, reliable electricity in an environmentally friendly way.

2.0 BRIEF DETAILS OF PROJECT AREA

Kadiri is a taluka under Anantpura District situate in Andhrapradesh Proposed


Solar Power Plant is situated in Kadari

Land area of power plant : 20Acres

2.1 Geographical coordinates of power plant site:

(a) Latitude : 13'-40' and 15'-15' Northern Latitude

(b) Longitude : 76'-50' and 78'-30' Eastern Longitude

2.2 Land Characteristics : Barren Land


Non Agricultural Land
Open land & has no shadow
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 15 of
DPR POWER PROJECT 58

4.0 SITE METEROLOGICAL DATA

Area 19130 sq. kms.


Latitude 13°-40' and 15°-15' N
Longitude 76°-50' and 78°-30' E
Temperature Max.: 29.1°C; Min: 17.2°C
Average Rainfall 520.4 mm
Population 3639304 (2001 census)
Population Density 190.2 per sq. kms.
Literacy Rate 56.69%

How to Reach

By Air : Anantapur is 354 Km from Hyderabad and 213 Km away from Bangolore Airport.

By Rail : Anantapur railway station is 354 Km from Hyderabad, 288 Km from Tirupati and
213 Km from Bangalore. Several express and local trains are available to/from Anantapur.

By Road : It is 354 kms from Hyderabad, 213 kms from Bangalore. It is connected with most
important cities of the state and also with neighboring states.
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 16 of
DPR POWER PROJECT 58

SECTION - 3

DEMAND ANALYSIS AND JUSTIFICATION OF THE PROJECT


DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 17 of
DPR POWER PROJECT 58

1.0 INTRODUCTION

It is well know fact that electricity is the most essential input for growth and
development of any state. Andhra pradesh is planning to go rapidly in both the
industrial and agricultural sectors and consequently the demand for power is on the
rise. However, despite Andhrapradesh possessing immense potential of power
ranging from Coal to natural gas not taken place on a scale commensurate with the
possibilities. As a result there exists a big gap between conventional and Non-
conventional power generation for power in the State.

2.0 SOLAR POWER POTENTIAL IN INDIA

India is endowed with rich solar energy resource. The average intensity of solar
radiation received in India is 200 MW/km square (megawatt per kilometer square),
but the amount of solar energy produced in India is merely 0.5% compared to other
energy resources till date

India just have 2.12 megawatts of grid-connect solar generation capacity. As part of
the National Solar Mission, the ministry aims to booster the annual photovoltaic
production to at least 1,000 megawatts a year by 2017. With an installed capacity of
123 GW, the country currently faces energy shortage of 8 percent and a peak
demand shortage of 11.6 percent, In order to sustain a growth rate of 8 percent, it is
estimated that the power generation capacity in India would have to increase to 306
GW in the next ten years which is 2.5 times current levels.
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 18 of
DPR POWER PROJECT 58

3.0 SOLAR RADIATION MAP OF INDIA

KADIRI ANANTPURA SOLAR RADIATION DATA

LOCATION ANNUAL SOLAR RADIATION


13°-40' and 15°-15' N LATTITUDE 5.6 KWh/SQ.M
76°-50' and 78°-30' E LONGITUDE
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 19 of
DPR POWER PROJECT 58

4.0 SOLAR ENERGY POTENTIAL IN MAHARASHTRA

Solar power plants are a necessity at places in Andhra Pradesh for providing
electricity to improve the standard of living of the people. Financial constraints in
the public sector and non-remunerative characteristics of economics act as
disincentives to private entrepreneurs.

Till now, no grid connected solar power plant is being setup in AP though some of
projects are already sanctioned. Nodal agency of Energy, NEDCAP has already
announced tariff policies for solar energy as per MNRE rules

The proposed plant may be the first kind of Solar Power Plant in state that
supplies the solar electricity to the grid

4.1 Promotion Policies of MNRE

The promotional policies of MNRE for solar power generation are enclosed in
annexure-1
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 20 of
DPR POWER PROJECT 58

4.3 Clean Development Mechanism (CDM)

Normally grid connected power plants generate electricity by burning fossil fuel,
which results in GHG emissions and other associated emissions like Sox and
NOx. The proposed power plant project activity aims at reducing these GHG
emissions in addition to power generation by installing a 1.0 MW Solar power
generation plant, to supply power to the Grid

(a) Baseline information

Current data from Central Electricity Authority (CEA) for determination


of combined margin for the regional grids are furnished below:

CENTRAL ELECTRICITY AUTHORITY: CO2 BASELINE DATABASE

VERSION 3.0
DATE 15/12/2007
BASELINE ACM 002 /
METHODOLOGY Ver 07

EMISSION FACTORS

WEIGHTED AVERAGE EMISSION RATE ( TCO2 / MWH ) (EXCL. IMPORTS)


2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07

North 0.72 0.73 0.74 0.71 0.71 0.71 0.72

East 1.09 1.06 1.11 1.10 1.08 1.08 1.03

South 0.73 0.75 0.82 0.84 0.78 0.74 0.72

West 0.90 0.92 0.90 0.90 0.92 0.87 0.85

North-East 0.42 0.41 0.40 0.43 0.32 0.33 0.39

India 0.82 0.83 0.85 0.85 0.84 0.82 0.80


DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 21 of
DPR POWER PROJECT 58

SIMPLE OPERATING MARGIN ( TCO2 / MWh )


2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07

North 0.98 0.98 1.00 0.99 0.97 0.99 0.99

East 1.22 1.22 1.20 1.23 1.2 1.16 1.13

South 1.02 1.00 1.01 1.00 1.00 1.01 1.00

West 0.98 1.01 0.98 0.99 1.01 0.99 0.99

North-East 0.74 0.71 0.74 0.74 0.71 0.70 0.69

India 1.02 1.02 1.02 1.03 1.03 1.02 1.01

BUILD MARGIN ( TCO2 / MWh ) (Excl. Imports)


2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07

North 0.53 0.60 0.63

East 0.90 0.97 0.93

South 0.70 0.71 0.71

West 0.77 0.63 0.59

North-East 0.15 0.15 0.23

India 0.69 0.68 0.68

COMBINED MARGIN ( TCO2 / MWh ) (Excl. Imports)


2000-01 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07

North 0.76 0.76 0.77 0.76 0.75 0.80 0.81

East 1.06 1.06 1.05 1.07 1.05 1.06 1.03

South 0.86 0.85 0.86 0.85 0.85 0.86 0.85

West 0.87 0.89 0.88 0.88 0.89 0.81 0.79

North-East 0.44 0.43 0.44 0.44 0.43 0.42 0.46

India 0.86 0.86 0.86 0.86 0.86 0.85 0.85


DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 22 of
DPR POWER PROJECT 58

(b) How CDM Works?

An investor from a developed country can invest in, or provide finance for a
project in a developing country that reduces greenhouse gas emissions so that
they are lower than they would have been without the extra investment- i.e.
compared to what would have happened without the CDM under a business as
usual outcome. The investor then gets credits- carbon credits-for the reductions
and can use those credits to meet their Kyoto target. If the CDM works perfectly it
will not result in more or less emission reduction being achieved than were agreed
under the Kyoto protocol, it will simply change the location in which some of the
reductions will happen. For example, a French company needs to reduce its
emissions as part of its contribution to meet France’s emission reduction target
under the Kyoto Protocol. Instead of reducing emissions from its own activities in
France, the company provides funding for the construction of a new biomass plant
in India that would not have been able to go ahead without this investment. This
they argue, prevents the construction of new fossil-fueled plants in India, or
displaces consumption of electricity from existing ones, leading to Global
Environmental Concerns reduction in greenhouse gas emissions in India. The
French investor gets credit for those reductions and can use them to help meet
their reduction target in France.

(c) Significance of CDM

(i) Achieve sustainable development

(ii) Reduce impact on environment

(iii) Additional stream of income through sale of emission reductions

(iv) Contributes for rural development

(v) Reduce pollution levels

(vi) Technology improvement

(vii) Improves Economics of Project

(viii) Helps developed countries to achieve their emission reduction


commitments
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 23 of
DPR POWER PROJECT 58

SECTION - 4

TECHNICAL FEATURE & EQUIPMENTS OF THE PLANT


DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 24 of
DPR POWER PROJECT 58
1.0 BASIC SYSTEM DESCRIPTION

Solar Photovoltaic power generator consists of solar modules in series and


parallel connections, these convert solar radiations into DC electrical power at
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
the pre-determined range of Voltages whenever sufficient solar radiation is
TEE-185- available. The 5MW SOLAR
individual PV GRIDsolar
crystalline CONNECTED
cells are connected SHtogether
Page 25 inof a
DPR POWER PROJECT 58
module (in series connection), which are hermetically sealed to survive in rugged
weather conditions and ensures optimum performance during its ling life

In order to achieve a higher system voltage, modules are installed in a row


arrangement, called a string. A higher system voltage has the advantage of
lesser installation work, higher efficiency of the entire plant and usage of smaller
cross section cables. Calculated no. of strings is connected in parallel by cables
in Junction Boxes. These junction boxes not only act as a junction point but also
monitor each string output which will be fed to the central monitoring and
analysis system. Outputs from many such junction boxes are connected in
parallel in the Main Combiner Box (MCB). This Main Combiner Box output is fed
to the central inverters/Power Control Unit (PCU) to invert solar generated DC
power in to conventional 3 phase AC power.

Central inverter or PCU operate on MPPT (Maximum power point tracking) mode
to ensure maximum output from the solar generators at different ambient
conditions. Central inverters use higher system voltages to reach very high plant
efficiency. Furthermore, installations can be expanded with additions of more
modules without problems.

AC power from inverters will be fed to LV panel which in turn will be stepped up
through transformer. Power at 11kv/22Kv will be transmitted by overhead
transmission line to grid.
2.0 OPERATION PHILOSOPHY

Solar panels mounted in the field generate DC electric power. The DC electric
power generated by the solar panels cannot be fed directly in to the utility grid.
The GCI range of inverters invert the direct current output from the solar array
into grid compliant AC voltage, feeds it in to the utility grid system with proper
protection and control. The grid connected inverter (GCI) range of inverters
comes with built-in transformer that ensures galvanic isolation of the DC side
from the AC network. This is an important requirement for many utilities to permit
connection of solar panels on to the grid. The system automatically starts up in
the morning and begins to export power to the grid, provided there is sufficient
solar energy and the grid voltage, frequency is within the range. If the grid goes
out of range the inverter will be immediately disconnected and reconnected
automatically at a pre determined time after the grid comes back within range.
When the exported power is very negligible for a pre determined time the system
will go into an sleep mode by disconnecting the inverter from the grid.

3.0 POWER GENERATION SCHEME


DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 26 of
DPR POWER PROJECT 58
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 27 of
DPR POWER PROJECT 58

SECTION-5
POWER PLANT CONFIGURATION AND SPECIFICATIONS OF MAIN
PLANT EQUIPMENT
1.0 SELECTION OF UNITS

The capacity of the Proposed Solar Power Plant has been fixed at 1 MWp.x 5Nos.
The principle factors considered for designing and selection of proposed plant are
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
local solar radiations, ambient conditions and electrical load characteristics of
TEE-185-major system namely
5MW SOLAR PV GRID
the array and CONNECTED SHMoreover,
power conditioning unit. Page 28 ofthe
DPR POWER PROJECT 58
proposed plant is situated at remote village location, so maximum use of local
materials available on site for construction and to retain or preserve the original
appearance of the sire and the environment are considered

SR.NO. ITEM
1.0 PV arrays 50 Nos
2.0 Modules in a string 18 Nos
3.0 String in a array 28Nos
4.0 Inverters 50 X 100 KVA
5.0 Transformer 5Nos

2.0 SPECIFICATION OF MAIN PLANT

(A) SOLAR PV MODULE

SR.NO. ITEM
1.0 Output Power-Pmax (Watt) 200 Wp
2.0 Voltage at maximum power-Vmp (Volts) 28.60 V
3.0 Current at maximum power-Imp (Amps) 7.02
4.0 Open circuit voltage – Voc (Volts) 36
5.0 Short circuit current-Ise (Amps) 7.55
6.0 Type of solar PV cell Poly Crystalline
7.0 Dimensions 1619MM x 1002MM
8.0 weight 23.50Kg

(B) SOLAR INVERTER

SR. ITEM
NO.
1.0 Nominal Voltage 230/400 volts three phase, 4
Wire, grid tracking Nominal
voltage can be adjusted by ± 10%
via system stepoints.

2.0 Output Frequency 50Hz ± 0.5% inverter to follow grid


frequency up to ±3Hz of the
nominal output frequency during
normal operation

3.0 Continuous rating 100 kw at unity power factor

4.0 Max DC link Voltage Range 800 volts DC


DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 29 of
DPR POWER PROJECT 58
(C) 415V PCC x 125 Nos

SR. NO. ITEM


1.0 TECHNICAL PARAMETERS
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
1.1 System particulars
1.1.1 Rated voltage and phases 415 V, 3 Phase, 4 wire
TEE-185- Frequency
1.1.2 5MW SOLAR PV GRID CONNECTED
50 Hz SH Page 30 of
DPR
1.1.3 System earthing POWER PROJECT 58
Effectively earthed
1.1.4 Maximum system voltage 457 V
1.1.5 One minute power frequency withstand
voltage 2.5 kV
(a) Power circuit 1.5 kV
(b) Control circuit
1.1.6 Continuous current rating of busbars
(a) PCC 2000A
1.1.7 Short circuit withstand
(a) PCC 50 kA/1 sec.
1.1.8 Reference ambient 500C max.
1.1.9 Max temp of busbars at rated current 900C
2.0 CONSTRUCTIONAL REQUIREMENTS

2.1 Sheet steel thickness


2.1.1 Frames 2.5 mm cold rolled
2.1.2 Doors 2.5 mm cold rolled
2.1.3 Covers 2.0 mm cold rolled
2.2 Degree of protection IP 52
2.3 Colour finish shade as per IS: 5 Seven tank process painting with
epoxy based
2.3.1 Interior Glossy white
2.3.2 Exterior Shade 631

2.4 Busbar material All alloy of E 91 E grade. For main


bus bars
- copper for Auxiliary bus bars fully
insulated
2.4.1 Bus bra installation Fully insulated
2.5 Earthin bus.
2.5.1 Material GS
2.5.2 Size
(a) for PCC By bidder
2.6 Clearances in air of live parts 5-50 degrees Celsuis
2.6.1 Phase to Phase 25.4 mm
2.6.2 Phase to earth 19.4 mm
2.7 Single front design All panels
2.8 Draw out / Fixed type design Rate for IP30
2.8.1 PCC-ACB Draw out type
2.8.2 MCCB Fixed / plug in type
2.9 Incoming supply to PCCs Through cables
2.10 Vertical cable alley Minimum 250 mm
2.11 Cable entry Bottom
3.0 INCOMER CIRCUIT BREAKER FOR PCC
3.1 Circuit breaker type Fully draw out type Air circuit
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 31 of
DPR POWER PROJECT 58

(D) TRANSFORMER
SR. ITEM
NO.
1.0 GENERAL
1.1 Application Power Transformer
1.2 Quantity 1 No.
1.3 Installation (Indoor / Outdoor ) Outdoor
1.4 Type (Auto / 2 Winding / 3 Winding) 2 Winding
1.5 Rating 1.6 MVA
1.6 Cooling ONAN
2.0 TEMRATURE RISE
2.1 Ambient temp. maximum 45ْ C
2.2 Temp. Rise of oil by thermometer 50ْ C
2.3 Temp. Rise of winding by resistance method 55ْ C
2.4 Impedance at rated current frequency at 75ْ C 6.25%
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 32 of
DPR POWER PROJECT 58

3.0 TAPPING: Off Load Tap Changer


3.1 Tapping on winding (HV) +5 to -5%
3.2 Total tapping range +10
3.3 Step 2.5% ( 5 taps)
4.0 RATING
4.1 No load voltages (a) HV Winding 11 kV
(b) LV Winding 433 V
4.2 Frequency 50 Hz 433 V
5.0 TERMINAL CONNECTION
5.1 HV Winding Line end XLPE cable (with heat shrink
terminations)
5.2 HV Winding neutral end ----------
5.3 LV Winding Line / N end XLPE cable (with heat shrink
terminations)
5.4 LV Winding neutral bushing Separate Neutral bushing for earth
connection (suitable for 1.1kV
grade)
5.5 Earthing conductor for Transformer body (a) Material -- G.I. strip
(b) Size -- 60 x 12 mm
6.0 SYSTEM DATA
6.1 System voltages (a) HV Nominal / Highest 11/12
kV
(b) LV Nominal / Highest
0.433/0.457 kV

6.2 Fault levels (a) HV (6.6kV) system 40 kA


(b) LV (415V) system 50 kA

6.3 System Neutral Earthing (a) HV (11kV) Earth through


Resistor
(b) LV (415V) Solidly Earth
System

7.0 WINDING
7.1 Material of Winding Copper
7.2 Winding connection & vector group HV (11kV) Delta Dyn 11
LV (433V) Star
7.3 Transformer neutral
Type of Earthing (a) HV – Not applicable
(b) LV – Solidly Earthed
8.0 MISCELLANEOUS
8.1 Wheels (a) Plain / Flanged : Flanged
(b) Unidirectional / Bidirectional :
Bidirectional
8.2 Winding temp. indicator required Yes
8.3 Any special final paint required (Epoxy etc.) Epoxy painting
9.0 Additional features for terminal
connection
9.1 HV cable box: With disconnecting chamber,
phase segregated type, provided
with space heater thermostat
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 33 of
DPR POWER PROJECT 58

9.2 LT cable box


9.3 Separate LV Neutral bushing: Required for earth connection to
earth pit
9.4 Neutral CT after bifurcation 2000/1 A, class PS for 64R,
2000/1 A, CL 5P10, 15 VA for
51NS shall be provided
NOTES:

(1) Transformers shall be provided with necessary accessories

(E) HT CABLES
SR. NO. ITEM
1.0 Voltage Grade 11 kV (UE) grade cables, heavy duty
2.0 Conductor Stranded Aluminium
3.0 Conductor Screen Semi – conducting compound
4.0 Insulation XLPE
5.0 Inner sheath Extruded PVC (Type ST-2)
6.0 Outer sheath Extruded PVC (Type ST-2)
7.0 Armoring Galvanized steel strips for multi-core
cables and non-magnetic Aluminium
wires for single core cables
8.0 Cable Operating Temperature 90ْ C
9.0 Short circuit withstand current 40kA for 1 sec.
capacity
10.0 Short circuit withstand temperature 250ْ C

(F) LT CABLES
SR. NO. ITEM UNIT
1.0 POWER CABLE
1.1 Voltage Grade V/V 1100V for 415V system
1.2 Frequency Hz 50
1.3 Earthing system - Solidly earthed system for 415V system
1.4 Conductor -
1.4.1 Material - Annealed Cu
1.4.2 Max withstand Temp -
(a) Normal condition ْC 90
(b) Short circuit condition ْC 250
1.4.3 Conductor type - Stranded
1.4.4 Grade - H4
1.5 Insulation -
1.5.1 Material - XLPE
1.5.2 Reference standard - IS 7098, Part I and Part II
1.6 Inner Sheath -
1.6.1 Material - FRLS PVC
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 34 of
DPR POWER PROJECT 58

1.6.2 Type - ST2


1.7 Outer Sheath -
1.7.1 Material - FRLS PVC
1.7.2 Type - ST2

(G) EARTHING & LIGHITNG PROTECTION

1.0 CODES & STANDARDS

1.1 The earthing of all outdoor equipment and provision of associated earthing
systems, electrodes and connections shall be in accordance with the
recommendations in the latest IEEE 80/IS 3043.

2.0 DESIGN CRITERIA

2.1 GROUNDING SYSTEM

The grounding design calculation shall conform to ANSI / IEEE Standard 80-
2000.

Earth electrodes shall be provided throughout the plant areas along with the
main earth grid. The number of earth electrodes shall be according to achieve
the total earth grid resistance less than one (1) ohm. Earth electrodes shall be
provided in earth pits. The earth pits shall be of two types namely treated with
test links and untreated. Earth electrodes shall be of heavy duty GI pipes, 40
mm dia and 3 meter long. The main buried grid conductors shall be connected
to all the earth electrodes to form a total earth grid.
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 35 of
DPR POWER PROJECT 58

2.2 GROUNDING MATERIAL

Galvanised steel flats of required size shall be used as per approved design. In
any case the minimum size shall be 75 x 10 mm. GS strip for earthing conductor.
Treated earth pits shall conform to relevant INDIAN Standards. The earth grid shall
be installed specified / approved depth of minimum 600mm.

2.3 EQUIPMENT EARTHING

The frames of all electrical equipment and structural steel work shall be earthed by
connection to earth grid by branches of same cross sectional area of the earth
grid.

2.4 LIGHTINING PROTECTION SYSTEM

Power plant needs protection against Lighting. The system will be designed as
per IS: 2309 and Indian Electricity Rules.

Vertical air termination of 40mm diameter, 3 M long shall be provided above


highest point of array to provide radius of protection full array.

(H) STRUCTURAL MOUNTING EQUIPMENT

SR. ITEM
NO.

1.0 Type Ground Mounting

2.0 Material MS Galvanized

3.0 Overall dimension As per design

4.0 Coating Hot dip (Galvanized) Minimum of 130


Micron size

5.0 Wind rating 150 km / hr

6.0 Tilt angle 30ْ

7.0 Foundation PCC

8.0 Fixing type SS 304 Fastners


DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 36 of
DPR POWER PROJECT 58

SECTION - 6

OPERATION AND MAINTENANCE


DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 37 of
DPR POWER PROJECT 58

1.0 OPERATION AND MAINTENANCE PHILOSOPHY

The proposed Organization structure for the operation and maintenance (O&M) of
the power plant is presented in the exhibit. In order to ensure a high level of
performance of the power plant, it is proposed to induct experienced O&M
engineers from the very beginning of the project.

1.1 BASIC STRUCTURE OF THE O&M TEAM

The basic structure and the broad functional area within the O&M organization
would be as follows:

The Plant Manager would have the primary responsibility for the O&M of the power
plant. The organization will compromise of four broad functional areas viz.
Operation, Maintenance, Technical and Administration. The basic duties covered
under each of these functional areas would be as follows:

1.1.1 Operation

(a) Operation of main generating equipment, switch yard and other auxiliary
plant.

(b) Except for the Power Station Superintendent all other operating personnel
would work one shift basis.

(c) The day to day operation of the power plant will be controlled by the
Manager who will be assisted by the Control room operators and engineers.

1.1.2 Maintenance

(a) Maintenance of mechanical and electrical plant, control systems, buildings,


roads, drainages and sewage systems etc.

(b) Operation of the plant, planning and scheduling maintenance works and
deciding the requirement of spare parts

(c) The Plant Manager will be assisted by departmental engineers, who take
care of the maintenance aspects of all mechanical, electrical and I&C
requirement
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 38 of
DPR POWER PROJECT 58

(d) Trained technicians will be employed to assist the maintenance group in day
to day maintenance of the plant.

1.1.3 Administration

The main responsibilities of this department will be as follows:

(a) Purchase

(b) Plant Security

(c) Liaison with local labour officers

(d) Stores management

(e) Medical Services

(f) Transport services

1.2 FACILITIES TO BE EXTENDED TO THE EMPLOYEES

The number of employees required for operation of the proposed power plant will be
around 10 numbers. The personnel required for administration and finance &
accounts also will be provided. The following facilities will be provided in the power
plant.

(a) Administration Building and Technical Office

(b) Stores

(c) Time and security offices

(d) First Aid and Fire Fighting Station

(e) Toilets and Changes rooms

1.3 STATION OPERATION PHILOSOPHY

The power generated from this plant is exported to MSEB Grid. Necessary software
and hardware features are required for effective operation and maintenance
management system

Software system manages and provides the information needed to manage daily
operations, improve labour productivity, reduce maintenance costs, and monitor
preventive and predictive maintenance programs

Through more effective scheduled and preventive maintenance, the costs


associated with emergency breakdowns can be greatly reduced. This includes
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 39 of
DPR POWER PROJECT 58

savings from reduced payroll overtime, fewer defective products and reduced down
time losses from disrupted production schedules.

1.4 STATION MAINTENANCE PHILOSOPHY

The based power plant maintenance philosophy is based on the following aspects:

1.4.1 Ordinary Maintenance

Ordinary Maintenance, which covers routine checking and minor refurbishment


activities to be performed according to operation manuals of components /
equipments in operating conditions.

1.4.2 Emergency Maintenance

Emergency Maintenance, which is corrective maintenance to be performed when a


significant failure occurs. To minimize forced outages duration, an effective
Emergency Maintenance must be supported by:

(a) A proper stock of spare parts

(b) Permanent monitoring and diagnostic systems for main components.

1.4.3 Maintenance Plan and Scheduled Maintenance

Scheduled maintenance is carried our according to maintenance plan, which should


be discussed and optimized according to the needs of the customer / client.

The maintenance plan is based on scheduled outages for the following components:

(a) Cleaning of Solar Module

(b) Power Processing System

(c) Switchyard equipment

1.5 MAINTENANCE MANAGEMENT SYSTEM

The maintenance of this plant will be carried out as per the above philosophy. This
system aims at maximizing the availability of the plant, while ensuring minimum
maintenance cost and safety of the plant and personnel.

1.6 SPARE PARTS MANAGEMENT SYSTEM

The primary objective of spare part management system will be to ensure timely
availability of proper spare parts for efficient maintenance of the plant without
excessive build-up of non-moving and slow moving inventory.

The spare parts management system for this project will cover the following areas:
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 40 of
DPR POWER PROJECT 58

(a) Proper codification of all spares and consumables

(b) Spare parts indenting and procurement policy

(c) Ordering of critical mandatory and recommended spares

(d) Judicious fixation of inventory levels and ordering levels for spare parts
based on experience.

(e) Development of more than one source of manufacturer / supplier whenever


practicable.

1.7 AVAILABILITY OF O & M MANUALS

All contracts include provision of at least 6 sets of details O&M manuals, which will
be distributed to all departments concerned well in advance from the commissioning
date of the power plant to avoid problems in preparation of commissioning
documents as well as proper installation and commissioning procedures of various
equipments.

1.8 SPECIAL TOOLS AND TACKLES

All contracts will include the provision for supply of one set of all types of special
tools and tackles, which are required for installation, commissioning and proper
maintenance of plant and equipment.
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 41 of
DPR POWER PROJECT 58

1.9 CHECKLISTS AND PROTOCOL

A detailed checklist for the various equipments, supplemented with the checklist
submitted by the supplier shall be drawn and logged for future reference. This will
also form part of the plant’s base history / datum.

Whenever an equipment in commissioned, the important parameters of that


particular equipment should be observed for a period of eight hours and the
readings shall be logged as per the log sheets. These activities shall be performed
in the presence of the customer / consultant and a protocol shall be signed.

1.10 SAFETY AND PROTECTION

The importance of safety and the protection of personnel and equipment cannot be
overemphasized. The system must be designed to minimize hazards to operation
and maintenance personnel, the public, and equipment. The control subsystem
must be equipped with various fuses, built-in fault detection and protection
algorithms to protect the users, the loads, and the PV system equipment. The
safety of an operator or technician is of the utmost importance. Personnel must be
protected from electric shock by following all available safety practices. Such as
displaying high voltage warning signs wherever necessary. In general, the system
must adhere to the IS Codes and standards dealing with safety issues.

Some of the important safety criteria are as follows:

(a) Electrical components should be insulated and grounded

(b) All high voltage terminations (> 50 Vdc) should be properly covered and
insulated

(c) All component with elevated temperatures should be insulated against


contact with or exposure to personnel

(d) Structures should be grounded and ground fault relays installed to give
warning of ground faults in the array or other electrical components.
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 42 of
DPR POWER PROJECT 58

2.0 ORGANIZATION STRUCTURE

PLANT MANAGER
2 NO

OPERATION MANAGER MAINTENANCE & ADMINISTRATION


(5 NO.) MANAGER (5 NO.)

ADMIN. STAFF ADMIN. STAFF


( 3NOS. ) (3 NOS. )

CONTROL ROOM TECHNICIAN ELECTRICAL


TECHNICIAN (3 NOS.) TECHNICIAN
(3 NOS. + 2 NO. ) ( 5NO. )

TOTAL O&M STAFF = 29 NOS.


DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 43 of
DPR POWER PROJECT 58

SECTION - 7

SWOT ANALYSIS
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 44 of
DPR POWER PROJECT 58

SWOT ANALYSIS.

Non – Conventional Sources, which are renewable in nature, are termed as the
alternate sources of energy. The Challenges of the present – energy scenario
offer us a window of the opportunity in the form of renewable energy sources.

The Power from the sun is clean , silent , limitless and free. Photovoltaic (PV)
process releases no CO2 , SO2 or NO2 gases which are normally associated
with burning finite fossil fuel reserve and don’t contribute to global warming .
Solar power shall augment the need of peak power needs & increases the grid
reliability I.e , Voltage and frequency. Solar Powered grid connect plants can act
as tail end energizes , which in turn reduces the transmission and distribution
losses.

(a) Geographically India is situated at northern hemisphere near the


Equator. So India gets maximum solar irradiation and there is ample of
scope to produce the power from solar PV. But till now this area is totally
virgin area for producing power.
(b) This is true that solar PV efficiency is very low compared to other power
generation systems , Lots of R&D is going on the improve the efficiency.
Solar PV generates electricity only at day time , So the proposed solar
PV Power plant generates power on an average only about six hours in
day time.
(C) India is potentially one of the largest markets for solar energy in the
world. The estimate4d potential of power generation through solar
photovoltaic system is about 20 MW/Sq.km in India. It is useful for
providing grid quality, reliable power in rural area where the line voltage
is low and insufficient cater to connected load. Recent Government
incentives and policies have been providing the momentum for PV in
India . The Government of India already declared national Action plan on
climate change released in mid 2008, identifies eight critical mission –
one of which is the National Solar Mission.
(d) In comparison to other sources of power generation, the PV solar power
is totally dependent in nature . The capacity utilization factor of such type
of plant is only 19%. Because averagely in the year we get 6 hr sunlight
in a day . Only this particular interval solar plant generates electricity.
In comparison to other conventional power generating units, solar power
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 45 of
DPR POWER PROJECT 58

generating unit has many advantages like.

(a) No fuel is required for power generation.


(b) Operation & Maintenance Manpower required is less.
( c) Plant will be running smoothly for a long period as compared to other
conventional power generation units.
(d) In environmental perspective , solar power plant generates clean energy
and gets maximum clean development mechanism (CDM) benefit as
compared to other conventional power generation units.
Considering all the above points, solar power generating potential is always
ahead of all other conventional power generating units in economical &
Environment point of view.
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 46 of
DPR POWER PROJECT 58

SECTION - 8

PLANT LAYOUT & CIVIL ENGINEERING ASPECTS


DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 47 of
DPR POWER PROJECT 58

1.0 INTRODUCTION.

This layout of the plant and facilities for the proposed solar power plant is largely
dictated by its location, shape and road etc. Involving minimum eviction, the wind
rose pattern, land use pattern of adjoining area and the direction of power
evacuation.
2.0 PLAN LAYOUT

The General plant layout is shown in the general arrangement drawing PE-167 –
GA -101 enclosed.
2.1 Planned site layout area.

The plot selected for the proposed power plant is 18 acers. Only 6.45 acres are
required the proposed power plant including plant roads & other building.
3.0 MAIN PLANT AND EQUIPMENT LAYOUT.
Layout of control Room & Administration Building.
The Control building is envisaged in an area of 200 M2 and administration building
of 100 M2.
3.1 Civil Engineering Aspects.

3.1.1 Structural System.

Power Plant Building will have RCC framed structure, floors & roof & brickwork
cladding.
3.1.2 Loads
(a) Live Loads

The loads listed hereunder are minimum loads for the areas involved.
Special use area s will be designed for higher loads as necessary. Hung
loads will be based on minimum loading equivalents of 100Kgs/Sq .m for
piping and 50Kgs/sq.m electrical, ventilation and air conditioning.

(i) Roofs : 3,750Kgs/Sq.m Plus hung loads


( b) Ground Floor.

(i) Control Rooms : 37,500Kgs/Sq.m

(ii) Offices : 18,750 Kgs/Sq.m Plus hung loads.


(c) Seismic Loading.
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 48 of
DPR POWER PROJECT 58

The lateral forces will be established in accordance with the


recommendations of IS- 893.
3.1.3 Reinforced Concrete Structure.

The following grades of concrete as par IS – 456 will generally be consider for civil
work.
(a) M-20 Structure concrete standard for pavement around
building including that for plinth protection work & non
suspended slabs.
(b) M-25 Structural concrete-standard for other structure.
(c) M-10 Mud mat.
(d) M-7.5 Full concrete.
Reinforcing bars will be as per IS-432(Grade-1) for mild steel and as per IS-1786
for High strength deformed bars.

Non – Suspended ground floor shall consist of the following minimum specification
unless otherwise specified.
(a) 230 mm rubble soling blinded with murrum / sand over thoroughly
compacted earth fill.
(b) 50 mm thick lean concrete (m7.5)over soling
(c ) 150mm thick lean concrete slab of grade M-20 (adequately reinforced)
over lean concrete
(d) Proper slope will be provided for adequate draining of ground floor slab.
(e) All expansion / separation joints in slabs shall be filled with premoulded
joint filler sealed with approved mastic sealing compound.
3.1.4 Architecture.
(a) Architectural Concepts of structure should offer its own identity and be
aesthetically blended to give pleasing appearance . Functional needs of
each building will be maintained but without entailing expensive
architectural treatment.
(b) Walls

Walls shall be 230mm thick except toilet partitions, where same shall be
115 mm thick & 2100 mm tall loft on top.
(c) False Ceiling

Plaster of parts board ceiling fixed to aluminum framework and suspended


from steel / R.C beams shall be provided for all air- conditioned spaces.
The illumination and duct grills in this area shall match the overall
aesthetic.
(d) Roof Drainage Systems.
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 49 of
DPR POWER PROJECT 58

The system will be provided for removal of water from roof surface to avoid
damage to the roof structure of all building and shall consist of the
following :

(i) Roof drain Heads


(ii) Rain Water Down comers.
(iii) Fixtures
(e) Building Finishes
(i) Brick Works- internal 230 mm thick brick wall with 1.6
And external cement sand mortar.
(ii) Half thick brick walls for toilets. 1:4 Cements, sand mortar.
(iii) Control rooms shall have IPS floor finish.
(iv) Roof
All roofs shall be provided with extra heavy duty proofing treatment
comprising of ten courses using four layers of Hessian based bitumen felt
and five layers of bitumen paint finishing with 20 mm thick presses per cast
concrete tiles on 15 mm thick (1:4) cement : sand mortar underbed. Water
proofing treatment shall
be laid over 75 mm thick foam concrete /25mm thick expanded polystyrene
insulation.
(v) Painting
- External masonry surface of all building shall have water proof cement
paint – super snowcem of equivalent.
- Acrylic plastic emulsion paint shall be provided for control room, control
equipment room , computer room. UPS room and air- conditioned area
including entrance lobby.
- All other area shall be provided with cement paint (available for internal
use) and white wash.
4.0 STRUCTURAL WORKS.
4.1 MATERIALS
(a) Structural Steel
( All structure steel for array shall be tested quality and shall conform to IS
a standard with galvanized coating.
)
(b) Electrodes
( Mild steel electrodes shall conform to IS:814. The contractor shall furnish
b to the Engineer a certificate issued by the manufacturer to the effect that
) the electrodes supplied are in accordance with the above specification.
For welding in any particular position , the electrodes used shall be those
recommended by the manufacture for use in that position.
(c) Other Materials
( Other materials used in association with steel work shall comply with the
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 50 of
DPR POWER PROJECT 58

c appropriate Indian standard specification .


)
4.2 Commissioning & erection
All steel structures are assembling and installed at site . It is always consider to
maximum use to local resources for assembling and installation . Form design
concept , it is always consider utilization of local resources to optimized project
cost.
4.3 ROAD WORK
4.3.1 Material
Stone for soling shall be consider for road construction of 2M wide array road.

Stone soiling with black bitumen road shall be consider for 4M wide road
Further details will be done on detail engineering stage .
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 51 of
DPR POWER PROJECT 58

SECTION - 9

PROJECT IMPLEMENTATION
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 52 of
DPR POWER PROJECT 58

1.0 IMPLEMENT CONCEPT


The project is planned to be implemented at the earliest . The most essential
aspect regarding the implementation of this project is to ensure that the project is
completed with in the schedule , spanning 6 months from the placement of
purchase order.
A good planning , scheduling , and monitoring program is imperative to complete
the project on time and without cost overruns.

The project zero date start once the kick- off meeting has taken place and the
advance payment has been received.
1.1 PROJECT IMPLEMETATION STRATEGY.

It is envisaged that the project will have the below mentioned phase of activities .
These phases are not mutually exclusive ; to implement the project on fast track
basis some degree of overlapping is envisaged.
Phase I Project Development
Phase II Finalization of the Equipment and contracts
Phase III Procurement and Construction.
Phase IV Plant Commissioning
1.1.1 Phase I – Project Development

In a power project, development of the project plays an important role. Almost


50% of the work of the work is done if one achieves power purchase agreement
from the respective state utilities. The project development starts with visits to the
region, understanding about the regional conditions, socio economic conditions,
transportation facilities and infrastructure facilities available in the region.

Apart from the above the below listed task will be under project development.
Submission of DPR
Power purchase agreement (PPA)
Expedite central Regulatory Authority clearance
Land acquisition / Mortgage.

During this phase, a project team will be formed during the execution of the
project. The
Engineers from group will be involved from early stages of execution of the
project. This would give them the opportunity to familiarize with the equipment and
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 53 of
DPR POWER PROJECT 58

systems being installed. These personnel should involve with the critical team of
installation and commissioning. After the plant being commissioned, these
engineers and technicians would occupy key positions in the organization
structure for the operation and maintenance of the plant.

The responsibility of the project team shall be:

Planning and programming of all the resources required for project completion.
Inspection of major fabrication items
Organize the construction and commissioning of the plant
Monitoring and controlling the project progress
Execute the project within the planned budget.

1.1.2 Phase II – Finalization of the Equipment and Contracts

In the power plant module and junction boxes are the lead items and the planning
schedule for the project implementation should provide adequate time period for
the acquisition and installation of these equipment. The specifications for major
equipment shall be drawn up at an early stage of the project. Program of design
information, from the equipment suppliers, that satisfies the overall project
schedule shall be drawn up. Since, the project execution calls for closer
coordination among the contractors, consultants and the company, proper
contract co-ordination and monitoring procedures shall be made to plan and the
project progress.

1.1.3 Phase III- Procurement and Construction

The procurement is an important function of the implementation of the project.


Once the purchase order is placed, the project team follows up regularly to ensure
smooth and timely execution of the contract and for obtaining technical
information for the inter package engineering.

When the contracts for the equipment are awarded, detailed programmed in the
form of network are tied up with the supplier to clearly indicate the owner’s
obligations and the suppliers responsibility. And upon placement of the purchase
order, the project team follows up regularly to ensure smooth and timely execution
of the contract and or obtaining technical information for the inter package
engineering. The procurement activity includes review of drawing, expediting,
stage and final pre delivery inspection, supervision of installation and
commissioning.
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 54 of
DPR POWER PROJECT 58

During construction the erection and commissioning phase of all the contracts
proceed simultaneously. Adequate power and water shall be made available for
the construction

1.1.4 Phase IV- Erection and commissioning Phase

The commissioning phase in a project is one where design, manufacturing


erection and quality assurance expertise are put to test. The commissioning team
will be from manufacturer of the equipment, consultant and the company. As
discussed in the earlier section, staff identified to operate the plant will be involved
in the commissioning phase of the project it self. When construction phase is
complete, the check list designed to ensure that the plant has been properly
installed with appropriate safety measures. The commissioning team will follow
the internal operating instruction. The plant shall be subjected to a performance
test.

2.0 PROJECT SCHEDULE

As per ANNEXURE-2
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 55 of
DPR POWER PROJECT 58

SECTION – 10
ESTIMATED PROJECT COST

1.0 BASIS FOR COST ESTIMATION

1.1 The capital cost of the plant has been estimated taking into account the cost of
civil & structure works, transportation, installation, testing, commissioning
charges and contingencies.

1.2 Land cost is not considered as land is already available.

1.3 The cost of material and electrical equipment has been estimated based on
budgetary quotation received previous quotations for other projects and in house
cost data suitable altered.
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 56 of
DPR POWER PROJECT 58

1.4 Excise duty is exempted as per MNRE consideration.

1.5 Packing, forwarding , inland transportation and insurance at the rate of 2.5% for
all equipment and systems including spares have been considered.

1.6 Erection, testing and commissioning charges are considered as 8% of supply


cost for mechanical and electrical equipment.

1.7 3% of the equipment cost has been considered towards cost of initial spares.

1.8 Cost of civil works has been estimated based on data available for similar
projects.

1.9 Power plant life is considered as 25 years.


DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 57 of
DPR POWER PROJECT 58

SECTION – 11
ESTIMATED POWER GENERATION COST
DOC. NO.: GREENERGY POWER (I) PVT LTD VER.: P0
TEE-185- 5MW SOLAR PV GRID CONNECTED SH Page 58 of
DPR POWER PROJECT 58

COST OF POWER GENERATION

1.0 Basis for Generation Cost Estimation

1.1 Debt-Equity Ratio shall be 70:30

1.2 Rate of interest on loan shall be 10.0% p.a.

1.3 Depreciation shall be 10.34% for plant & machinery and 3.34% for Civil work

1.4 The working capital is insurance expenses for one year in advance and one
month requirement of spares and consumables

1.5 Eligibility for working capital loan is 75% of total working capital & interest rate on
the loan is 12% p.a.