TIME TABLE FOR THE PROPOSED COFFEE SHOP

ACTIVITIES
Planning, design, drawings
Permits and clearances
Mobilization/demobilization
Site preparation
Excavation
Formworks and rebars
Concrete foundation
Structural steel
Masonry works
Painting works
Carpentry works
Door and windows
Roofing works
Plumbing works
Electrical works
Exterior finishes
Land scapping

OCTOBER
WEEK 1

WEEK 2

WEEK 3

NOVEMBER
WEEK 4

WEEK 1

WEEK 2

WEEK 3

DECEMBER
WEEK 4

WEEK 1

WEEK 2

WEEK 3

JANUARY
WEEK 4

WEEK 1

WEEK 2

JANUARY
WEEK 3

WEEK 4