QUOTATION

FOR
LAND SCAPE HORTICULTURE

KINGDOM HERITAGE MODEL SCHOOL

ALONG AJASEPO ROAD ITALAMU

ILORIN
QUOTATION FOR LAND SCAPE HORTICULTURE
PROJECT: LAND SCAPE HORTICULTUR
Basis Rate and Volume or Soil is determined by numbers of lorry load required
Material cost
MATRIAL QUANTITY PRICE
Top soil 1 load 6,000
Manure 1 load 4,000
Kerbs 1 load 200
Crush granite 1 load 16,000
Cement 1 load 1750
Sharp sand 1 load 5500
Leterite 1 load 5000
Chicken net 1 roll 7000
Pipe Iron 1 length 2000
Bidding wire 1 roll 3500
Water hole 1 roll 5500
Chemical Amino force 1 1000
FLOWERS
Green bush 1 30
Yellow bush 1 30
Desert rose 1 80
Dwalf Ixora 1 80
Single Ixora 1 60

The project is divided into phase of work as follows


Phase 1 = School building
Phase 2 = fencing system
Phase 3 = Car park
Phase 4 = Maintenance
The cost of each phase will be done as follow respectively

PHASE 1
School building
MATERIAL QUANTITY PRICE
Top soil 20 loads 6000 X 20 = 120,000
Manure 4 loads 5000 X 4 = 20,000
Kerps 600 pieces 200 X 600 = 120,000
Flowers:
Green bush 500 stand 30 X 500 = 15,000
Yellow bush 460 stand 30 X 460 = 138,000
Desert rose 30 80 X 30 = 2,400
Dwalf Ixora 30 80 X 30 = 2,400
Cement 10 bags 1750X10 = 17500
Sharp sand 5 loads 5500X5 = 27,500
Crush granite 1 load 16,000X1 = 16,000
Total N334,620
Labour = 20,000
Tools = 1,000
Transport = 2,500
Total N23,500

Total Grand N 358,120

PHASE 2
MATERIALS QUANTITY PRICE
Asoka tree 46 250 X 46 =11,500
Green bush 717 717 X 30 = 21,510
Top soil 12 loads 6000 X12 = 72,000
TOTAL N105,010

Labour = 13,000
Tool = 1,500
Transport = 1,500
Total 16,000
Grand Total N121,010

PHASE 3
Car park
MATERIAL QUANTITY PRICE
Kerbs 1038ps 200 X 1,038 = 207,600
Top soil 9 loads 6000 X9 = 54,000
Flower:
Single Ixora 756ps 60 X 756 = 45,360
Cement 22bags 1750 X 22 = 38,500
Shape/sand 9loads 5500 X9 = 49,500
Grushed/Granite 2 loads 16,000 X 2 = 32,000
Laterite 4 loads 5,000 X 4 = 20,000
Total N446,960
Labour = 22,000
Tool = 1,000
Transport = 2,000
Total N 25,000

Grand Total N471,960


PHASE 4
MAINTEANCE
MATERIAL QUANTITY PRICE
Chicken net 1 roll 7000 X1 = 7000
Pipe (Iron) 20 length 2000 X20 = 40,000
Binding wire 1 roll 3500 X 1 = 3,500
Water hose 1 roll 5,500 X1 = 5500
Chemical Amino force 4 1000X4 = 4000
Total N60000

Labour 4000
Tool 1,000
Transport 1,000
Total 6, 0000

Grand Total 66,000

Over all grand Total = N1017080