You are on page 1of 8

System Process Document

Firming Planned Orders

Department
Responsibility/Role
File Name 27636916.doc
Revision
Document Generation Date 15/01/2010 09:50:00
Date Modified 1/15/2010 09:50:00 AM
Last Changed by
Status

Firming Planned Orders


Trigger:

Concept
In this topic, you will firm planned orders.

Required Field(s) Comments

Output - Result(s) Comments

Additional Information

Last changed on: 1/15/2010 09:50:00 AM Page 1


System Process Document
Firming Planned Orders

Procedure

Step Action
1. Begin by navigating to the Supply/Demand page.

Click the Workbench link.

Page 2 Last changed on: 1/15/2010 09:50:00 AM


System Process Document
Firming Planned Orders

Step Action
2. Use the Organizations page to select an instance:organization.

Last changed on: 1/15/2010 09:50:00 AM Page 3


System Process Document
Firming Planned Orders

Step Action
3. Find organization TST:M1 TST:Seattle Manufacturing.

Click the vertical scrollbar.

Step Action
4. Click the TST:M1 TST:Seattle Manufacturing list item.

Page 4 Last changed on: 1/15/2010 09:50:00 AM


System Process Document
Firming Planned Orders

Step Action
5. Click the OK button.

or Press [Alt+O].

Last changed on: 1/15/2010 09:50:00 AM Page 5


System Process Document
Firming Planned Orders

Step Action
6. This instance:organization has an automatic query that shows planned orders.

If there is not a planned order automatic query, you would search for planned
orders.

Step Action
7. Click the Firm option.

Page 6 Last changed on: 1/15/2010 09:50:00 AM


System Process Document
Firming Planned Orders

Step Action
8. Click the Save object.

Last changed on: 1/15/2010 09:50:00 AM Page 7


System Process Document
Firming Planned Orders

Step Action
9. You have successfully firmed a planned order.
End of Procedure.

Page 8 Last changed on: 1/15/2010 09:50:00 AM