Combined Group Company
for Trading & Contracting
W.L.L,
ec sacyr Construccion S.A.
For the period from April 2014 — Dec 2014
SL# TRAINING SUBJECT PARTICIPANTS a
MANDATORY OPTIONAL
1. | HSE POLICY, Construction
OVERVIEW OF PROJECT HSS
PLAN, CLIENT'S WORK SITE SAFETY
REGULATIONS,
Managers, Engineers
‘DATE
SCHEDULE
15 April -30 April
2014
HEAT STRESS & SUMMAR SAFETY. Workers 4
2 | GUIDELINES FOR HEAVY Equipment 20 May -30 May
EQUIPMENTS OPERATIONS operators, 2014
= RISK ASSESSMENT AND Signalmen
CONTROL MEASURES. Excavation
= SIGNAL COMMUNICATIONS. Supervisors
— HEAT STRESS&SUMMER
SAFETY
3. | HSE POLICY, RESPONSIBILITY & General Foremen, ‘Lune ~ 15 June
ACCOUNTABILITY FOR HEALTH Foremen, 2014
AND SAFETY OF EMPLOYEES AT _| Subcontractor’s Staff
WORK.
HEAT STRESS & SUMMER SAFETY
CONFINED SPACE WORK
PROCEDURE TRAINING.
4 | CLIENT'S WORK SITE SAFETY Construction ‘July —15 July
REGULATIONS Managers, Engineers 2014
HEAT STRESS &SUMMER SAFETY |” General Foremen , Equipment 1 August ~ 20
CONFINED SPACE WORK Foremen, Operators ‘August 2013
PROCEDURE Subcontractor’s Staff
5 | BASIC CONCEPTS & THEORIES OF | Engineers, General 15 SEPT - 15 OCT
ACCIDENT PREVENTION. Foremen, Foremen, 2014
GENERAL HAZARDS ON WORK SITE | Subcontractor’s staff
AND PRECAUTIONS TO BE TAKEN ‘All workers.
5 | WORK PERMIT SYSTEM, Engineers, General 15 AUG ~ 30 AUG
Purpose and Procedure
Foremen, Foremen,
Sub contractors’
2014Combined Group Company
for Trading & Contracting JV Sacyr Construccion S.A.
W.LL.
Pree eee eeeere eee staff
6 | HOT WORK SAFETY PROCEDURES Fabrication / Subcontractors 1 SEPT 15 SEPT
mechanical foremen. 2014
Welders and
Fabricators
7 | WORKINSIDE CONFINED SPACES | GeneralForemen, | Skilled pipe fitters / | 1 SEPT-25 OCT
- Deep Excavations Foremen. Labours 2014
- Manholes® Skilled pipe fitters / 1SEPT=25 OCT
~_ Tunnels. Labours 2014
8 | HEAVY EQUIPMENTS EXCAVATION Equipment 25 SEPT - 30 OCT
| OPERATIONS - RISK ASSESSMENT FOREMEN , operators, 2014
i AND CONTROL MEASURES Subcontractors Banksmen
‘9 | MICROTUNNELING ~ RISK Microtunneling | 4 SEPT—15 SEPT
ASSESSMENT subcontractor 2014
personnel
10 | SLURRY GROUT AND ANNULAR Microtunneling | 1SEPT—15 SEPT
SPACE FILLING subcontractor 2014
personnel ae
12. | PRECAST YARD OPERATIONS — Precast Engineer, Steel fixers, 1 NOV-30 NOV
RISK ASSESSMENT AND CONTROL | Foremen and Precast Carpenters 2014
MEASURES. workers
13 | CAUSES OF FIRE AND Engineers, Foremen, 1 DEC = 10 DEC
PRECAUTIONS Subcontractor's staff 2014
All workers 11 DEC— 30 DEC
2014
Note:
1. Concerned Group leaders / Engineers / Manager shall give names of participants to
conduct training on a convenient day within the date schedule given for each training.
2. Mandatory trainings should be attended by the category of participants as shown
above.
3. Time of trainings shall vary from 45 minutes to 1 hr as per the subject.
Prepared by: HSEManager | Approved by : Project Manage:
Sign: Sign : 1qlo6leet
qi
Date DateRoads and Infrastructure Project in Al Kheesa North and East
ET Tad
Cole te)
Project: [Roads & Infrastructure in Al Kheesa North&East. Phase 1 82. [Date Of Mock Drill: 17-06-2014
Scenario of Drill |
Fire caught on a waste bin Kept outside Hyder Site Office near to Mosque . On suspecting that
the fire will catch on the site office, Emergency siren was raised at site offices. All employees
in site office proceed to Assembly point and Fire wardens extinguished the fire.
Total time taken for the drill
Total 15 minutes from start to end
Stert time
08.00 AM
End timo
08:15 AM
No: of person evacuated
17 employees of M/s Parson and Mis hyder
42 employees of CGC-SACYR JV _(Total ~ 59 employees)
Total persons worked in the Office area
on the day
59 persons
Members involved
Observer of Mock-drill
(Chief Coordinator )
Eng.Rizq Al Zoubi. (Project Manager ~ CGC-SACYR JV)
Emergency actions coordinator
Eng.Enrique Fajardo (HSE Manager)
(Evacuation, Fire & Safety coordinators)
Mr.Muhammd Iqubal&Mr.Loveson (Sr. HSE Officer)
Fire controllers.
Mr.Fernando, Mr.Ashok (HSE Officers) ~
Mr-Michael- CGC-SACYR JV Office
Erpeuenon coarse MrJerin, ,Mr.Sreekumar - Hyder Office
First aider Mr.Jibin (Site Nurse)
Mock Drill Scenario
Massive chemical spillage O | Fire Othere
Electric shock | Medical Emergency | Fait from height o
Time Line
Time Event / Activity
0600 AM Emergency siren raised at Site offices of Hyder and CGC-SACYR JV.
Informed Fire wardens and Site Nurse.
Tania Employees stopped working. Switched off computers, AIC, lights , closed doors of their
office rooms and began to proceed to Emergency Assembly Point.
08:03 AM Fire wardens proceeded to Fire incident site with Fire Extinguishers.
08.04 AM Fire wardens began to extinguish fire.
08:05 AM Site Nurse reached incident site
08.06 AM Evacuation completed. Allemployees including Top Management at Site offices
reached Assembly Point
Head counting of assembled employees startedRoads and Infrastructure Project in Al Kheesa North and East €&
MOCK DRILL REPORT
ty Head counting of assembled employees completed. Conformed all employees reached
Assembly point
08:08 AM Fire wardens completed extinguishing of fire
08.09 AM Site nurse conformed nobody is injured in the incident.
‘08.10 AM-08.12 AM | Fire wardens and Site Nurse reached Assembly point. They informed the fire has been
extinguished and Nobody is injured.
Project Manager Eng.Rizq Al Zoubi declared thal the emergency is over and that
Bee ‘everybody can resume their offices..
08.15 AM All employees resumed their offices /jobs.
Observations :
The scenario was planned and discussed among the involved emergency coordinators.
Alll the participants played their role well.
All employees of Hyder Parson and CGC -SACYR JV participated
the emergency drill.
The fire incident site was attended immediately by fire wardens and the fire was extinguished
using the right type of fire extinguisher in a professional way.
The response time taken by Site nurse to reach the incident site was also appreciable.
Project Director observed and assessed the emergency procedures from time to time and
declared the completion of the emergency after ensuring safe conditions are restored. He
advised everybody to resume their offices.
The drill was good and effective as per the program. However, following lapse was noticed
which need to be improved in the event of emergencies.
As follows:
- Response time taken by some employees to reach the Assembly point was more than
enough,
CORRECTIVE ACTION TO BE TAKEN
1. Awareness will be created among all employees to proceed to Assembly point
immediately on hearing Emergency siren.
Drill controlled by Drill Monitored By Noted By
Position Sr. HSE Officer HSE Manager Project Manager
Name Mr.Muhammed Iqubal Eng.Enrique Fajardo
Signature