Current Northern line closure programme – 2 February 2010

Weekend closures
Closure Start End
Morden to Tooting Broadway 27-Mar-10 28-Mar-10
Morden to Tooting Broadway 10-Apr-10 11-Apr-10
Kennington to Morden 24-Apr-10 25-Apr-10
Kennington to Morden 08-May-10 09-May-10
Kennington to Morden 22-May-10 23-May-10
Kennington to Morden 12-Jun-10 13-Jun-10
Kennington to Morden 19-Jun-10 20-Jun-10
Kennington to Morden 10-Jul-10 11-Jul-10
Kennington to Morden 24-Jul-10 25-Jul-10
Kennington to Morden 31-Jul-10 01-Aug-10
Kennington to Morden 07-Aug-10 08-Aug-10
Kennington to Morden 28-Aug-10 30-Aug-10
Kennington to Morden 18-Sep-10 19-Sep-10
Kennington to Morden 02-Oct-10 03-Oct-10
Kennington to Morden 23-Oct-10 24-Oct-10
Kennington to Morden 30-Oct-10 31-Oct-10
Kennington to Morden 06-Nov-10 07-Nov-10
Kennington to Morden 20-Nov-10 21-Nov-10
Full line 04-Dec-10 05-Dec-10
Kennington to Morden 11-Dec-10 12-Dec-10
Full line 25-Dec-10 28-Dec-10
Kennington to Morden 01-Jan-11 03-Jan-11
Full line 08-Jan-11 09-Jan-11
Kennington to Morden 15-Jan-11 16-Jan-11
Stockwell to Edgware and High Barnet/Mill Hill East 22-Jan-11 23-Jan-11
Full line 29-Jan-11 30-Jan-11
Full line 05-Feb-11 06-Feb-11
Stockwell to Edgware and High Barnet/Mill Hill East 12-Feb-11 13-Feb-11
Full line 19-Feb-11 20-Feb-11
Stockwell to Edgware and High Barnet/Mill Hill East 26-Feb-11 27-Feb-11
Full line 05-Mar-11 06-Mar-11
Full line 12-Mar-11 13-Mar-11
Stockwell to Edgware and High Barnet/Mill Hill East 19-Mar-11 20-Mar-11
Full line 26-Mar-11 27-Mar-11
Stockwell to Edgware and High Barnet/Mill Hill East 02-Apr-11 03-Apr-11
Full line 09-Apr-11 10-Apr-11
Full line 16-Apr-11 17-Apr-11
Full line 22-Apr-11 25-Apr-11
Full line 30-Apr-11 02-May-11
Stockwell to Edgware and High Barnet/Mill Hill East 07-May-11 08-May-11
Full line 14-May-11 15-May-11
Kennington to Morden 21-May-11 22-May-11
Stockwell to Edgware and High Barnet/Mill Hill East 28-May-11 30-May-11
Full line 04-Jun-11 05-Jun-11
Stockwell to Edgware and High Barnet/Mill Hill East 11-Jun-11 12-Jun-11
Full line 18-Jun-11 19-Jun-11
Full line 25-Jun-11 26-Jun-11
Stockwell to Edgware and High Barnet/Mill Hill East 02-Jul-11 03-Jul-11
Full line 09-Jul-11 10-Jul-11
Stockwell to Edgware and High Barnet/Mill Hill East 16-Jul-11 17-Jul-11
Kennington to Morden 23-Jul-11 24-Jul-11
Full line 30-Jul-11 31-Jul-11
Stockwell to Edgware and High Barnet/Mill Hill East 06-Aug-11 07-Aug-11
Kennington to Morden 13-Aug-11 14-Aug-11
Stockwell to Edgware and High Barnet/Mill Hill East 20-Aug-11 21-Aug-11
Kennington to Morden 27-Aug-11 29-Aug-11
Full line 03-Sep-11 04-Sep-11
Stockwell to Edgware and High Barnet/Mill Hill East 10-Sep-11 11-Sep-11
Kennington to Morden 17-Sep-11 18-Sep-11
Stockwell to Edgware and High Barnet/Mill Hill East 24-Sep-11 25-Sep-11
Full line 01-Oct-11 02-Oct-11
Kennington to Morden 08-Oct-11 09-Oct-11
Kennington to Morden 22-Oct-11 23-Oct-11
Kennington to Morden 05-Nov-11 06-Nov-11
Kennington to Morden 12-Nov-11 13-Nov-11

Extended Engineering Hours (i.e. early closures)


These will commence in July from 2330 Monday to Thursday for 16 months across
the full line north of Stockwell. The service would start to ramp down from around
20:30. Last trains would leave central London around 2230, and replacement buses
used. Early closures on Sundays are also under review.