‘The following preparatory works are co be carried out
to ensure proper tiling works:
Surface preparation
+ Screeding / rendering if necessary
= Setting out tiling
Workers must be trained and competent for the job.
Supervisors should ensure that the steps are properly
carried out by workers,
‘The surfaces of the substrate should be level/plumb and.
‘rue to design specifications, or toa tolerance of 3 mm
measured by a 2-m straight edge, When the surface
evenness is not enough, seed or render should be applied.
‘The substrate should be sound and stable, and fiee from
any loose substance (e.g. dust, debris or loosely bonded
topping as shown in Figure 4-1) and deleterious
substance (¢g, oil and grease) chat may reduce or inhibit
adhesion of the next layer of material. Any strong acid
or alkali on the surfaces should be neutralised prior to
the application of the next layer of material. The surface
should be cleaned with a broom and then washed using
water jet (see Figure 4-1).
The environmental conditions on site should be
controlled in conformity with the national standards
(e.g. Section 4.2 of SS CP 68). When necessary,
temporaty shelter should be set up to protect the work
from direct sunshine, rain and excessive heat.4.1.2. Different Substrates
Table 4.1 shows derailed requirements on surface preparation for different substrates
Table 4.1 Surface preparation for different substrates
1. Masonry surfaces 1. On-grade or below-grade substrate should be applied
with an effective waterproofing membrane, such as
bituminous-besed liquid membrane.
Dona
2, Rendering required = Waterproofing works should
be inspected before rendering
2, Reinforced concrete surfaces 1. Concrete cure far 28 days, = This time duration is necessary
for the conerete to cure and
to realise most of ite stvinkge
2. For floor ~The surface of the substrate
Brush surface witha stif broom just before concrete should have a roughened
begins to harden to form mechanical key. texture to form mechanical
key to promote good adhesion
Apply @ slurry coat of soreed/ rent
= Slury coat should comp
teement and polymer latex in
mixing ratio of 1:1 By wight,
Apply screed before this slury coat has lost tackness.
Table 4.1 Continues on next page ®
Preparatory Works 49, lis ia (SR ts SR sed Dd fee PG les edsony Aiojesedaig
Table 4.1 (Continued)
pn Sie
3, For wall
Apply a splash coat.
Splash coat should comprise
cement, dry sand and polymer
latex in mixing ratio of 1:11
by weight,
‘Tho protrusion thickness of
spatter-dash should be about
Caution should be taken in
the formworktelaasing agent
used, as many of them tend
to act as a bond break
It level satisfies the conditions specified, tes can be
installed directly by using a suitable bedding material
Otherwise, rendering roquted
3. High
surfaces
ision concrete block
rendering requited.
1. If level eatisfes the level conditions snecified, only
‘suitable primer may be applied before tling. Otherwise,
Fin doubt, manufacturer's
recommendation should be
sought to ensure the
‘compatibility ofthe render rx
with the blocks.
4, Proprietary partion walls 1
substrate,
fellowed,
4.2. LAYING OF SCREED / RENDER
“To decermine the correct levels for the flooring to be
Jaid, the setting of a common reference line (usually
marked at the wall at Im) should be established. This
is to prevent any mismatch in levels such as ceramic
flooring to living room against parquet flooring to
bedrooms (see Figure 4-2)
Prior o application of cement-based materials, very dry
and porous surface should be pre-wetted generously
‘with clean water (see Figure 4-2), and the excess water
on the surface should be cleaned off such that the
ac a saturated-surface-dry* (SSD) condition.
Manufacturers of these boards should certify their
suitability of uses. The boards should be installed in
‘vlet accordance with the manufacturers insteuetions,
‘especialy with spacing and gradi
‘supporting metal studs to ens
foqurernents of the
‘the rigiaity of the
2. The boards may be coated with a suitable primer to
‘adjust moisture absorption before ting. The instruction
‘of the board manufacturers instruction should be stitly
To achieve a good and consistent mortar mix, pre-
packed mortar is preferred over the conventional cement
and sand mortar mix.
For wall, the frst coat of render should be applied in less
than 15 mm, roughened by a wooden trowel to receive
the next one, and allowed to dry for atleast 24 hours.
Subsequent coats should be applied in the same manner
“until the required thickness is achieved. The total thickness
of the render should be limited by 30 mm; otherwise,
sttips of non-oxidising ribbed metal lathing should be
anchored onto the substrate prior to rendering
* Surface saturated dry : The subsurface should be saturated
swith water, but the surface self should be fie of liaering waterFor floor, the screed should be tamped down to remove
any void and finished with a wooden float (see Figure
4.2), The screed mortar is preferred to be polymer latex
fortified. For a screed thicker than 50 mm, a non-
oxidising metal-mesh should be placed in the middle
as reinforcement.
Screed and render should be air cured for at least 7
days, Water mist spray with a hand pump (see Figure
4-2) in the first 2 days is a good quality-enhancing
practice, After curing, a thorough check on the soundness
in adhesion of the screed and render using a metal rod
should be cartied out (see Figure 4-2). Cracks should
also be properly rectified.
The M&E contractor should identify the concealed
services (especially gas pipes) in the wall by marking
their locations on the surface of the render. This serves
as a pre-cautionary measure to prevent any damages to
the concealed services arising from subsequent installation,
works,sylony Asojesedaig
4.3. SETTING OUT TILING
Ic is important to set out tile Hines according to the
approved tiling setting out drawings. Care should be
taken to minimise the number of tiles that need to be
ccut for satisfactory visual effect. Where tile cutting is
necessary, the position of cut tiles should be planned
and marked before laying tiles (see Figure 4-3). Cut
tiles should be placed at les visible corners.
Contractors need to work out in advance the methods
to deal with interruptions to surfaces (such as openings)
Setting out tile lines on screed
Setting out tie lines with services
Icis a good practice to allocate switches and power
points atthe edge of tiles to minimise tiles cutting (see
Figure 4-3)
To avoid any unsightly visual impact, site supervisor
should alert designer that changes in tile sizes made
after completion of mock-up (where tile layout and
pattern were already decided) would affect the desired
positions of services such as switches and power poinss.
Adjusting the originally planned tile layout would lead
to difficulties in accommodating the positions of these
Marking position of
cut tiles before ting
Allocating switches at edge of tiles
Figure 4-3 Setting out tiling for floor