Professional Documents
Culture Documents
Brigadoon Repairs
HB Southern Builders LLC proposes to replace rotted T-111 siding and paint to match existing and remove and
replace concrete sidewalks.
Scope of Work:
Front Entrance
Replace concrete sidewalk SF 6.00
Building 3 Breezways
Remove and replace soffit with 1/2" cdx plywood and paint to match existing SF 8.00
Remove and replace T-111 siding and paint to match existing SF 132.00
Seal concrete cracks on stairwell landing to prevent water intrusion with NP1 sealant LF 30.00
Building 4 Breezways
Remove and replace T-111 siding and paint to match existing SF 132.00
Seal concrete cracks on stairwell landing to prevent water intrusion with NP1 sealant LF 20.00
Clean up:
HB Southern will maintain debris removal throughout the day with a complete pickup of all debris at the end of each
work day.
Completion Schedule:
HB Southern will complete the project within 7 calendar days from start of construction.
**HB Southern cannot be responsible for delays caused by weather.
Exclusions:
Any work not described in the attached scope of work
Lead Paint or Asbestos Surveys or Abatement
Warranty:
1 year for all materials and workmanship
Thanks for the opportunity to bid this project. We look forward to working with you in the very near future.
Please fax a signed copy to (210) 579-1925 so we can schedule a start date.