You are on page 1of 71

CONSTRUCTION OF A NEW BRIDGE

ACROSS THE RIVER NILE AT JINJA

ABUTMENT A1
STRUCTURAL OUTLINE
SHEET - 1
UVCO/1407/JNJ/PY/

This drawing is indicative only at this stage for the purpose


of tendering and subject to revision and finalization at a later
stage.
This drawing is copyright and remains the property of
Utracon Overseas Pte., Ltd and must not be used/ retained
or copied without written permission.

CONSTRUCTION OF A NEW BRIDGE


ACROSS THE RIVER NILE AT JINJA

ABUTMENT A1
STRUCTURAL OUTLINE
SHEET - 2
UVCO/1407/JNJ/PY/

This drawing is indicative only at this stage for the purpose


of tendering and subject to revision and finalization at a later
stage.
This drawing is copyright and remains the property of
Utracon Overseas Pte., Ltd and must not be used/ retained
or copied without written permission.

CONSTRUCTION OF A NEW BRIDGE


ACROSS THE RIVER NILE AT JINJA

ABUTMENT A1
APPROACH SLAB
UVCO/1407/JNJ/PY/

This drawing is indicative only at this stage for the purpose


of tendering and subject to revision and finalization at a later
stage.
This drawing is copyright and remains the property of
Utracon Overseas Pte., Ltd and must not be used/ retained
or copied without written permission.

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
0

RONALD

NISHIO AKIYAMA 04/08/15

REV

ESTABLISHED

CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT A1
STRUCTURAL OUTLINE
SHEET - 1
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
0

RONALD

NISHIO AKIYAMA 04/08/15

REV

ESTABLISHED

CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT A1
STRUCTURAL OUTLINE
SHEET - 2
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
0

RONALD

NISHIO AKIYAMA 04/08/15

REV

ESTABLISHED

CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT A1
BEARING DETAILS
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
0

RONALD

NISHIO AKIYAMA 04/08/15

REV

ESTABLISHED

CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT A1
BEARING REINFORCEMENT
DETAILS
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
0

RONALD

NISHIO AKIYAMA 04/08/15

REV

ESTABLISHED

CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT A1
APPROACH SLAB
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

CONSTRUCTION OF A NEW BRIDGE


ACROSS THE RIVER NILE AT JINJA

ABUTMENT A2
PRESTRESSING DETAILS @ GRID A2
UOUG-15401-W-A2-PT-0001

This drawing is indicative only at this stage for the purpose


of tendering and subject to revision and finalization at a later
stage.
This drawing is copyright and remains the property of
Utracon Overseas Pte., Ltd and must not be used/ retained
or copied without written permission.

CONSTRUCTION OF A NEW BRIDGE


ACROSS THE RIVER NILE AT JINJA

ABUTMENT A2
PRESTRESSING DETAILS @ GRID Y75
UOUG-15401-W-A2-PT-0002

This drawing is indicative only at this stage for the purpose


of tendering and subject to revision and finalization at a later
stage.
This drawing is copyright and remains the property of
Utracon Overseas Pte., Ltd and must not be used/ retained
or copied without written permission.

CONSTRUCTION OF A NEW BRIDGE


ACROSS THE RIVER NILE AT JINJA

ABUTMENT A2
PRESTRESSING DETAILS @ GRID Y76
UOUG-15401-W-A2-PT-0003

This drawing is indicative only at this stage for the purpose


of tendering and subject to revision and finalization at a later
stage.
This drawing is copyright and remains the property of
Utracon Overseas Pte., Ltd and must not be used/ retained
or copied without written permission.

CONSTRUCTION OF A NEW BRIDGE


ACROSS THE RIVER NILE AT JINJA

ABUTMENT A2
PRESTRESSING DETAILS @ GRID Y77
UOUG-15401-W-A2-PT-0004

This drawing is indicative only at this stage for the purpose


of tendering and subject to revision and finalization at a later
stage.
This drawing is copyright and remains the property of
Utracon Overseas Pte., Ltd and must not be used/ retained
or copied without written permission.

CONSTRUCTION OF A NEW BRIDGE


ACROSS THE RIVER NILE AT JINJA

ABUTMENT A2
PRESTRESSING DETAILS @ GRID Y78
UOUG-15401-W-A2-PT-0005

This drawing is indicative only at this stage for the purpose


of tendering and subject to revision and finalization at a later
stage.
This drawing is copyright and remains the property of
Utracon Overseas Pte., Ltd and must not be used/ retained
or copied without written permission.

CONSTRUCTION OF A NEW BRIDGE


ACROSS THE RIVER NILE AT JINJA

ABUTMENT A2
PRESTRESSING DETAILS @ GRID Y79
UOUG-15401-W-A2-PT-0006

This drawing is indicative only at this stage for the purpose


of tendering and subject to revision and finalization at a later
stage.
This drawing is copyright and remains the property of
Utracon Overseas Pte., Ltd and must not be used/ retained
or copied without written permission.

CONSTRUCTION OF A NEW BRIDGE


ACROSS THE RIVER NILE AT JINJA

ABUTMENT A2
PRESTRESSING DETAILS @ GRID Y80
UOUG-15401-W-A2-PT-0007

This drawing is indicative only at this stage for the purpose


of tendering and subject to revision and finalization at a later
stage.
This drawing is copyright and remains the property of
Utracon Overseas Pte., Ltd and must not be used/ retained
or copied without written permission.

CONSTRUCTION OF A NEW BRIDGE


ACROSS THE RIVER NILE AT JINJA

ABUTMENT A2
PRESTRESSING DETAILS @ GRID Y81
UOUG-15401-W-A2-PT-0008

This drawing is indicative only at this stage for the purpose


of tendering and subject to revision and finalization at a later
stage.
This drawing is copyright and remains the property of
Utracon Overseas Pte., Ltd and must not be used/ retained
or copied without written permission.

CONSTRUCTION OF A NEW BRIDGE


ACROSS THE RIVER NILE AT JINJA

ABUTMENT A2
PRESTRESSING DETAILS @ GRID Y82
UOUG-15401-W-A2-PT-0009

This drawing is indicative only at this stage for the purpose


of tendering and subject to revision and finalization at a later
stage.
This drawing is copyright and remains the property of
Utracon Overseas Pte., Ltd and must not be used/ retained
or copied without written permission.

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
0 RONALD
REV

ESTABLISHED

NISHIO AKIYAMA 20/07/15


CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT A2
STRUCTURE PLAN & ELEVATION
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
0 RONALD
REV

ESTABLISHED

NISHIO AKIYAMA 20/07/15


CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT A2
STRUCTURE - TOP PLAN
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
0 RONALD
REV

ESTABLISHED

NISHIO AKIYAMA 20/07/15


CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT A2
SECTIONS @ GRID A2 & Y75
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
0

RONALD

NISHIO AKIYAMA 20/07/15

REV

ESTABLISHED

CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT A2
SECTIONS @ GRID Y76 & Y77
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
0

RONALD

NISHIO AKIYAMA 20/07/15

REV

ESTABLISHED

CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT A2
SECTIONS @ GRID Y78 & Y79
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
0

RONALD

NISHIO AKIYAMA 20/07/15

REV

ESTABLISHED

CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT A2
SECTIONS @ GRID Y80 & Y81
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
0

RONALD

NISHIO AKIYAMA 20/07/15

REV

ESTABLISHED

CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT A2
SECTIONS @ GRID Y82 & A20
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
0

RONALD

NISHIO AKIYAMA 20/07/15

REV

ESTABLISHED

CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT A2
STRUCTURAL STAIR DETAILS
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
0

RONALD

NISHIO AKIYAMA 20/07/15

REV

ESTABLISHED

CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT A2
APPROACH SLAB
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
0

RONALD

NISHIO AKIYAMA 20/07/15

REV

ESTABLISHED

CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT A2
CABLE ANCHORAGE
STRUCTURAL DETAILS
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

MID SLAB BAR R/F PLAN


SCALE

1:150

KEYPLAN
ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
A

VANE

REV

ESTABLISHED

NISHIO AKIYAMA 01/08/15


CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT A2
MIDDLE SLAB REINFORCEMENT
PLAN SHEET 1
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

MIDDLE SLAB BAR R/F PLAN


SCALE

1:150

KEYPLAN
ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
A

VANE

REV

ESTABLISHED

NISHIO AKIYAMA 01/08/15


CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT A2
MIDDLE SLAB REINFORCEMENT
PLAN SHEET 2
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
A

VANE

REV

ESTABLISHED

NISHIO AKIYAMA 01/08/15


CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT A2
STAIR REINFORCEMENT DETAILS
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
A

VANE

REV

ESTABLISHED

NISHIO AKIYAMA 01/08/15


CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT-A2 MIDDLE SLAB


REBAR SCHEDULE
SHEET 1
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
A

VANE

REV

ESTABLISHED

NISHIO AKIYAMA 01/08/15


CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT - A2 MIDDLE SLAB


REBAR SCHEDULE
SHEET 2
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

TOP SLAB R/F PLAN (TOP BARS)


SCALE

CONSTRUCTION OF A NEW BRIDGE


ACROSS THE RIVER NILE AT JINJA

1:150

KEYPLAN

ABUTMENT - A2
TOP SLAB REINFORCEMENT PLAN
(TOP BARS)
UVCO/1407/JNJ/PY/

This drawing is indicative only at this stage for the purpose


of tendering and subject to revision and finalization at a later
stage.
This drawing is copyright and remains the property of
Utracon Overseas Pte., Ltd and must not be used/ retained
or copied without written permission.

BOTTOM SLAB R/F PLAN (BOTTOM BARS)


SCALE

CONSTRUCTION OF A NEW BRIDGE


ACROSS THE RIVER NILE AT JINJA

1:150

ABUTMENT - A2
BOTTOM SLAB REINFORCEMENT PLAN
(BOTTOM BARS)
UVCO/1407/JNJ/PY/

This drawing is indicative only at this stage for the purpose


of tendering and subject to revision and finalization at a later
stage.
This drawing is copyright and remains the property of
Utracon Overseas Pte., Ltd and must not be used/ retained
or copied without written permission.

KEYPLAN

SECTION A
SCALE

1:20

SECTION B
SCALE

CROSS SECTIONAL REBAR ARRANGEMENT

1:20

SCALE

1:150

LONGITUDINAL REBAR ARRANGEMENT


SCALE

1:150

LONGITUDINAL REBAR ARRANGEMENT @ MIDDLE


SCALE

CONSTRUCTION OF A NEW BRIDGE


ACROSS THE RIVER NILE AT JINJA

1:150

ABUTMENT - A2
TOP SLAB REBAR ARRANGEMENT & DETAILS
UVCO/1407/JNJ/PY/

This drawing is indicative only at this stage for the purpose


of tendering and subject to revision and finalization at a later
stage.
This drawing is copyright and remains the property of
Utracon Overseas Pte., Ltd and must not be used/ retained
or copied without written permission.

CONSTRUCTION OF A NEW BRIDGE


ACROSS THE RIVER NILE AT JINJA

ABUTMENT A2 TOP SLAB


REBAR SCHEDULE
SHEET 1
UVCO/1407/JNJ/PY/

This drawing is indicative only at this stage for the purpose


of tendering and subject to revision and finalization at a later
stage.
This drawing is copyright and remains the property of
Utracon Overseas Pte., Ltd and must not be used/ retained
or copied without written permission.

CONSTRUCTION OF A NEW BRIDGE


ACROSS THE RIVER NILE AT JINJA

ABUTMENT A2 TOP SLAB


REBAR SCHEDULE
SHEET 2
UVCO/1407/JNJ/PY/

This drawing is indicative only at this stage for the purpose


of tendering and subject to revision and finalization at a later
stage.
This drawing is copyright and remains the property of
Utracon Overseas Pte., Ltd and must not be used/ retained
or copied without written permission.

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
A

VANE

REV

ESTABLISHED

NISHIO AKIYAMA 01/08/15


CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT - A2 WALLS
REBAR SCHEDULE
SHEET 1
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
A

VANE

REV

ESTABLISHED

NISHIO AKIYAMA 01/08/15


CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT - A2 WALLS
REBAR SCHEDULE
SHEET 2
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
A

VANE

REV

ESTABLISHED

NISHIO AKIYAMA 01/08/15


CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT - A2 WALLS
REBAR SCHEDULE
SHEET 3
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
A

VANE

REV

ESTABLISHED

NISHIO AKIYAMA 01/08/15


CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT - A2 WALLS
REBAR SCHEDULE
SHEET 4
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
A

VANE

REV

ESTABLISHED

NISHIO AKIYAMA 01/08/15


CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT - A2 WALLS
REBAR SCHEDULE
SHEET 5
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
A

VANE

REV

ESTABLISHED

NISHIO AKIYAMA 01/08/15


CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT - A2 WALLS
REBAR SCHEDULE
SHEET 6
WORKING DRAWING

DESCRIPTION

STAT.

SCALE :

FILE NAME:

phase

zone

document

number

ENGINEERING CONSULTANT:

EMPLOYER:

ENGINEERING CONTRACTOR:

DRAWING TITLE:

PROJECT DOCUMENT NUMBER:

company

GOVERNMENT OF UGANDA
NEW BRIDGE ACROSS RIVER
NILE AT JINJA
A

VANE

REV

ESTABLISHED

NISHIO AKIYAMA 01/08/15


CHECKED

APPROVED

DATE

UGANDA NATIONAL ROADS AUTHORITY


PLOT 11, YUSUF LULE ROAD
P O BOX 28487
KAMPALA - UGANDA
Email: executive@unra.go.ug

ABUTMENT - A2 WALLS
REBAR SCHEDULE
SHEET 7
WORKING DRAWING

DESCRIPTION