You are on page 1of 1

Record No.

Inspection Record for


Cable Trays/Ladders
Client:

Subcontractor:

Project No.:

Subcontract P.O. No.:

Project Name:

Designation of trays/ladders:

Additional Information:

Vendor:

Reference Document:

P.O. No.:

Items to inspect

Subcontractor
inspected
initials/date

1.0

Specified material used

2.0

Location, routing, spacing, width

3.0

Vertical runs plumb and parallel

4.0

Cut edges painted

5.0

Assembly correctly bolted up

6.0

Supports, hot-dip galvanized

7.0

Covers on HV cable trays

8.0

Tray and ladder runs adequately supported

9.0

Trays, ladders and supports bonded and earthed

Company
Hold
Point

Remarks

inspected*
initials/date

10.0 As built information recorded on


drawing no. .......................

H - Companys presence is mandatory for all activities in section.

Attachments, No. of pages:

h - Companys presence is mandatory.

Accepted for Subcontractor


Name:

Signature:
Date:

Accepted for Company


Name:

Signature:

Date:

Accepted for Client


Name:

Signature:

Date:

*Company only initials for holdpoint

C:\RB_Forms\RB26E02.DOT\