You are on page 1of 20

Revision No: First Issue

Date of Issue:
DOCUMENT RELEASE AUTHORIZATION
Prepared by

: ____________________________

Reviewed & Approved By : ____________________________

This document is a property of GPT Infraprojects Limited and is not to be


reproduced, copied, handed over to a third party or used for any purpose other
than that for which it has been loaned.

I.

History of Revisions
Revisio
n No.
R0

II.

Revision
Date

Chapter / Clause No. &


Text affected

Reason for
Revision
First Issue

Document Distribution
Sr.N
o.
1
2
3
4
5
6

Issued to

No. of
Seats

Submitt
ed

INDEX
CHAPTER
1. PURPOSE
2. SCOPE
3. DEFINITIONS
4. CROSS REFERENCES
5. CONSTRUCTION PROCEDURE
5.1
5.2
5.3

PAGE NO.
5
5
5
5
6

Materials for Foundation Works


Concrete Mix for Foundation
Plants and Equipments for Well Foundation Work

6. CONSTRUCTION METHODOLOGY FOR WELL FOUNDATION


6.1
6.2
6.3
6.4
6.5
6.6
6.7

Setting out
Island, Cofferdam & Barge Operation
Cutting Edge
Well Curb
Well Steining and Sinking
Plugging of Well and Well Cap
Time Cycle

7. INSPECTION & TESTING


8. OHS & ENVIRONMENT MANAGEMENT PLAN
9. ATTACHMENTS
10.
DISTRIBUTION

19
19
21
21

11.

RECORDS

21

1. PURPOSE:
The purpose of this document is to provide detail construction
methodology, resources deployment, and safety & environment
system/procedures to be adopted by GPT and its sub-contractors during
execution of well foundation in connection with construction of Major Bridge
over Yamuna River at Kalpi (1275/2)

2.SCOPE:
The scope of this methodology covers the following activities:

Preliminary works
Selection, testing and acceptance of materials and mixes for
permanent works
Deployment of plants, equipments and machinery etc.
Construction methodology for well foundation.
Quality Assurance and Quality Control during construction work and
post installation checks, tests etc.
Construction Methodology for Well Foundation in water ( Caissons,
details will be submitted separately)

Physical Scope of work is as follows:


For dimension details of well please ref drg no: AA/1626/KALPI-SUB/WC &
CE/02/R2.

3.DEFINITIONS:
The words like Contract, Contractor, Engineer (Synonymous to Engineers
Representative), Drawing, Employer, Government, Works, Worksite used in
this methodology considered shall be considered to have the meaning as
understood from the definitions of these terms given in the General
conditions of the contract.

4.CROSS REFERENCE:

The methodology shall be read in conjunction with the following documents:

RVNL Technical Specification.


IRS codes (Concrete Bridge Code etc.)
MORTH - Specification for Well Foundation.
BIS/ASTM/BS standards/ codes referred elsewhere in this
methodology.
Good for Construction Drawing for Kalpi Yamuna Rail Bridge.

5.CONSTRUCTION PROCEDURE:
5.1

Materials for Foundation Works:


The following materials shall be used for the activity:

5.1.1 Cement:
The cement is Ordinary Portland Cement of 43 grade & Portland
Pozzolona Cement conforming to IS 8112 & IS 1489 codes
respectively and shall meet all physical and chemical requirements
as specified in RVNL spec, MORTH spec & Contract Spec.
5.1.2 Coarse & Fine Aggregate:
Coarse & Fine aggregate conforming to IS 383 shall be used.
Gradation of combined aggregates of different sizes (Coarse
Aggregate only) shall be in accordance with IS 383.
Various mechanical properties of coarse aggregates and properties
of fine aggregate are to be conformed to IS 2386 Series and the
tests shall be conducted as per relevant test codes as described in
RVNL spec, Contract Spec.
5.1.3 Water:
Portable water shall be used for concreting and shall be
conforming to RVNL Spec.
5.1.4 Reinforcement Steel:
Reinforcement steel for works shall be Fe 500D grade and
conforming to IS 1786, only TMT bars to be used.
5.1.5 Concrete Admixture:
Admixture to be used shall be conforming to IS 9103 and prior
approval from Engineer shall be obtained for the use of Admixture.

Dosage of admixture shall be as per manufacturers instructions


and as per workability requirements, which shall be finalized
during design mix and trials.

5.2

Concrete Mix for Foundation

Concrete mix design shall be carried out as per RVNL Specification and
IS 10262 or any other standard accepted mix design guidelines and
grade of concrete to be used shall be as per drawing / specification.
The concrete shall be designed to achieve desired degree of workability
for specific grade of concrete to facilitate concreting operation. Trials
shall be conducted and cubes shall be cast, tested before acceptance of
Design mix.

5.3

Grade
Grade
Grade
Grade
Grade

of
of
of
of
of

Concrete
Concrete
Concrete
Concrete
Concrete

for
for
for
for
for

Well Curb:
Well Steining:
Bottom Plugging:
Top Plug:
Well Cap:

M 35
M 25
M 25
M 25
M 35

Plants & Equipments for Well Foundation work:

The following Plant/Equipment shall be used for execution of Well


Foundation:
Sr.
No.

Plant
Description

Make /
Capacity

No
Require
d
02

Crawler Crane

20 T, TATA

2
3
4

Shell Grab
Diesel generator
Welding M/C

0.5 - 0.9
82.5 KVA

02
01
04

Batching Plant

02

6
7

Transit mixer
Concrete pump

8
9
10

Total station
Auto level M/C
JCB

Schwing
Stetter
TATA
Schwing
Stetter
Leica
Sokia
3D

Remarks

For well sinking &


shifting purpose.
For well excavation
For power supply.
For cutting edge fab,
shuttering/staging etc.
18 cum/hr

04
02

06 cum capacity

01
01
02

For survey
For level work
For handling well

11

Vibrators

Electric

05

excavated soil.
For concreting.

6. CONSTRUCTION METHODOLOGY FOR WELL FOUNDATION

6.1

Setting Out

Necessary reference points shall be fixed, away from the zone of blowups or possible settlements resulting from well sinking operations. Such
reference points shall be connected to the permanent total stations with
the base lines on the banks. Reference points shall be also be fixed to
mark X-X axis (Usually along the traffic direction) and Y-Y axis (Normal to
X-X axis) accurately. A temporary bench mark shall also be established
near to the well, away from the zones of blow-ups and or possible
settlement.
6.2

Island, Cofferdam & Barge Operation

Wells in water (Above 4.0m depth):- The area is more than 4.5m deep
water, formation of protected island by constructing cofferdam
alternative methods shall be adopted. The material to be used for
construction of cofferdam shall be as per design and drawing depending
on the operating water level with tidal effect.
The material shall be either MS steel shell or Steel Sheet pile of required
size fabricated at centralized yard and shall be transported to site by
trailer or truck.
Sand shall be filled into the cofferdam by grab or manually. In plan
dimension there shall be minimum 2m working place in protected island
formation. (For reference please refer annexure drawing for cofferdam
with sheet pile and sheet shell)
Barge Operation
To tackle the well foundation works in water spans, deployment of
flatbed floating barge shall be required to approach for transportation of
materials and machineries to well foundation and as well as to execute
the well sinking works.
The barge shall be designed for operating water level taking into
account for draft requirement and freeboard with anticipated operating

dead load consists of well sinking crane, crew, and dredged muck and
self-load. Well sinking barge shall be feed up with materials and services
to be provided by another barge. Tug boats shall be for movement and
anchoring/mooring of barges. Total 2 sets of well sinking barge with
required number of Tugboats to complete the well sinking works in time.
Please refer schematic drawing of well sinking by Barge.

6.3

Cutting Edge
Sr.N
o.
1
2
3
4
5

Description

Location Used

Angles 150 X 150 X 16


Angles 75 X 75 X 8
MS Plate 20 mm
MS Plate 12 mm
MS Plate 10 mm

Outer Tee
Brackets
Cutting Edge Plate
Bent Plate & Stiffeners
Skin Plate

The cutting edge shall be fabricated with mild steel structural sections
and plated of specified grade as per approved drawings. Fabrication of
cutting edge may be carried out at site or at a shop. The cutting edges
shall be fabricated in pieces / segments. During the process of
fabrication and handling / erection suitable temporary supports are to
provided / maintained to render rigidity and to keep shape of the
segments and / or parts thereof. Number of segments shall be decided
prior to start of fabrication depending on easement of handling and
transport. Checks are to be made on dimension and shape of the
segments.
For bending the structural members, V cuts may be made and after
bending such V cuts are to be closed by welding. Joints in the length of
structural sections shall be made with fillet welds with a single cover
plate or as shown in the drawings.
Tools and Plants for Cutting Edge Fabrication:

Rolling machine / Hydraulic Jacks for bending.


Drilling machine.
Electrical welding machine.
Pug cutting machine.
Hand grinding machine / Table mounted wheel grinder.

Fabrication:
Working Platform
The working platform is made up of used plain steel plates welded to
each others over levelled concrete surface at the central fabrication
yard. The fabrication of the cutting edge involved the following steps.
Preparation of back angles:

Layout of cutting edge is marked on working platform.


Angle sections are cut of required length.
A pair of angles shall be placed together back to back and shall be
bent to the required radius by hydraulic press on bending platform
and same shall be checked with curvature template and corrected
if required.

Preparation of MS plates:

The required width and length of the plate as per drawing shall be
marked and cut using pug cutting machine.
Plate shall be bent to the required radius.
The same shall be checked with curvature template and corrected
if required.

Preparation of Brackets:

Layout of Brackets is marked on working platform.


Angle sections are cut of required length.
The angles are welded as per the drawing, the same is to checked
on the layout platform and corrected if required.

Assembly:

The MS plate shall be connected with angle by tack weld and


checked for the required radius. After final checking welding shall
be done as mentioned.

Stiffeners shall be welded in required spacing.


Bent plates shall be welded as per the drawing.
Fabricated pieces of cutting edge segments are to be shifted to
site by truck of trailer.

Prefabricated segments of the cutting edges shall be brought to site


of work and assembled at the well location. Segments of cutting edge
shall be erected on firm & levelled ground or prepared island base at
the predetermined position. Temporary support as required to
facilitate assembly and keeping the entire assembly in true shape
shall be provided. Placement of the segments shall be made with the
help of a crane on wooden sleepers placed along the periphery of the
cutting edge.
Dimensions, shape & size, alignment and level shall be checked by
the Engineer and splice plate shall be welded at every joints and final
welding shall be completed.

6.4

Well Curb

The following steps are involved in construction of well curb.


1.
2.
3.
4.
5.
6.

Placement of Cutting Edge.


Fixing of formwork and rebars.
Concreting.
Curing.
Removal of formwork.
Sinking of Well Curb.

Placement of Cutting Edge:

Accurate survey shall be carried out by Total Station for fixing the
well locations.
Permanent reference pillars are to be provided at the four sides i.e.
along and across centre line of bridge.
The ground is levelled by removing the top loose soil and
compacted and rescued levels are recorded jointly with the
Engineers representative.
Centre point of well is marked.
The fabricated cutting edge segments shall be shifted to site by
truck / trailer up to the jetty location the same shall be shifted to
well location by barge.
Wooden sleepers are placed at a interval of 1.50m along the
circumference of the cutting edge.
Cutting Edge is placed over wooden sleepers using crane aligned
and joined with respect to centre lines. After alignment joints are
to be welded.

Level and alignment of cutting edge shall be checked finally using


the established horizontal controls. If required minor rigid bracing
are provided for maintaining proper level.
Dowel bars are welded to Cutting Edge as shown in the drawing.

Formwork and Rebars Fixing:


Inner formwork:

Inner form panels are first cleaned and standard form releasing
agent is applied on the surface.
To make the shutter joints leak proof suitable foam sheets between
shuttering joints and/or masking tape at joints are used to seal the
joints.
Inner formwork shall be erected and all the form panels shall be
joined to form the true shape as per the concrete profile,
horizontal and diagonal supports erected. The erection of inner
formwork shall be as per enabling drawing issued by enabling
dept. The formwork shall be handled by crane.

Fixing of Rebar:

Rebars are cut and shaped at the central rebar yard as per the
approved bar bending schedule and transported to site using
truck/trailer up to the jetty location. The bars shall be transported
to well location by barge.
Adequate number of 75 mm cement concrete cover blocks shall be
placed to maintain cover along the periphery of formwork and also
at the bottom to maintain specified cover.
Outer vertical bond bars shall be welded with angle. All other
reinforcement bars along with any stiffeners / spacers are fixed in
position as per drawing and approved bar bending schedule.
The rebar are checked jointly with Engineers representative.

Fixing of Outer Formwork:

Before fixing of outer formwork entire floor area shall be cleaned.


Form panels shall be fixed as per drawing.
To ensure the leak proof joints, thin foam packing shall be provided
between adjacent shuttering panels. Alternatively masking
adhesive tape shall be applied over the shuttering joints.
Access platform using landing mats are provided for inspection
and concrete purpose.
Coil anchors shall be embedded in concrete, at appropriate
locations for erection of shuttering for the next lift.

Final checking shall be done jointly with Engineers representative.

Concreting:

Concrete shall be done by static concrete pump located on barge.


Concrete shall be transported from the nearest batching plant
through transit mixers and ferried to well location by the barge.
Concrete shall be placed in a continuous pour. Shear key shall be
provided at each lift construction joint.
Adequate illumination arrangement shall be ensured to provide
safe working during night hours to satisfy supervision and safety
requirements.
Preparation of construction joint shall be done by green cutting
(removing the laitance) using hard steel/nylon brushes before the
final setting is over at each joint to receive the succeeding lift of
concrete.

Curing:

Curing shall be done by spraying water on surface covered with


hessian cloth.
Curing can also be done by using approved curing compound.

De-shuttering and Gauge marking:

Outer formwork shall be removed within 24 hours.


Inner formwork shall be removed after 72 hours
Gauge marking shall be done along both axes at four outer face
location of the well by using template.

Sinking of Well Curb:

After removal of inner form panel, gunny bags filled with sand shall
be placed in between wooden sleepers along the periphery at the
bottom of cutting edge.
Grounding of the curb shall be done after removing the inner
forms.
The curb is sunk to the ground level by manual dredging in the
dredge hole. When the dredging is partially complete, the loose

6.5

material is removed from the dredge hole using the plate gran and
is dumped outside the area of well, later this dredged material
shall be disposed to nearby area provided by engineer.
The sinking history would be recorded in the format as provided in
the technical specification (Appendix 1200/I, MoRT&H).
The sinking level is monitored at regular intervals of 500mm.

Well Steining and Sinking:


The steps involved in the Steining are:1.
2.
3.
4.

Inner and outer formwork.


Rebar fixing.
Concreting and curing.
Sinking.

Inner and outer formwork:

Inner and outer formwork is made of 4mm MS Steel plates and


rolled steel sections fabricated for a lift of 2.5m.
3.0 mm thick foam sheet adhesive tape at the location of joints are
used to seal the joints.
Form releasing agent shall be applied on the inner face of the
panels coil anchors/ nuts, which are to be embedded in concrete
for erection of lift are fixed at appropriate locations.
The inner form panels are erected for the subsequent lifts, the
form work is supported on the coil nut arrangement with the
bottom lift concrete. The rebar are fixed in position followed by
fixing of outer formwork. Over the inner formwork, rigid horizontal
supports shall be provide to keep the shutters profile and it shall
be used for platform after placing the landing mats
Final checking of formworks shall be carried by jointly with
Engineers rep.

Rebar fixing:

Re bar are cut and bent at the central rebar yard as per the
approved bar bending schedules and transported from the yard by
truck/ trailer.
Re bars are fixed as per drawing and schedule.
Adequate cement concrete cover blocks shall be provided along
the periphery of the formwork to maintain the cover of rebar.

Concreting and curing:

Placement of concrete shall be done as described for the well curb.


Shear key shall be provided at each construction joints.
The concrete surface shall be cleaned thoroughly and surface
preparation is made to receive the succeeding layer of concrete.
Before casting the last lift of steining it shall be checked and
verified for appropriate steel for false steining, grooves for precast
beams to support false work for well cap.

De - shuttering:
The inner and outer form panels are removed after 12 hours of the
concrete finished time.

Steining Sinking:
Following the de shuttering of steining lift, gauge marking is carried
out at both axes in line with well curb marking and reference height is
marked on the wall surface. The sinking operation would be started
after 16 hrs of concreting for steining.
Sinking of wells shall be carried out by dredge hole method by using
the following steps:
Sinking operation:

The sinking operation involves lowering of the well by dredging in


the dredge hole.
Plate grab shall be used in case of soft strata like sandy silt, soft
clay, dense sand, etc.
In case of hard clay, stiff clay strata heavy-duty chisel shall be
used, followed by dredging using Tyne grab.
Levels and alignment of well shall be checked regularly interval of
1hr of sinking to observe the tilt and shift of the well at closer
intervals if the visual observation demands.
Sinking operation shall be preferably carry out round the clock
under skilled supervision.
Dredged materials shall be disposed off to locations designated by
the Engineer.
The above cycle of well steining and sinking shall be repeated up
to the last lift of the well until well reaches to the founding level.

Precautions during sinking:

When the wells have sunk close to each other and clear distance
between them is not greater than the diameter of wells, sinking
shall be taken up on all wells and they shall be sunk alternately.

Before seasonal floods all wells on which sinking is in progress


shall be to sufficient depths below the designed scour level.

Very deep sump shall not be made below the well curb. The depth
of sump shall not exceed 3.0m below the level of cutting edge
unless otherwise specifically permitted by Engineer.

Dewatering is avoided if sand blows are expected.

Tilts and Shifts:


The wells shall be sunk into earth with in permissible limit of tilt and
shift:The dredging operation shall be carried out uniformly over the dredge
hole area. When the minor tilt and shift occurs the same shall be
corrected by controlled grabbing or partial dredging in the direction
opposite to tilt.
In case of tilt/shift is excessive, following method shall be adopted for
correcting the same.
1. Eccentric Kentledge Loading.
2. Providing Temporary obstacles beneath the cutting edge.
3. Pull the well by winches.
Procedure for monitoring Tilts and shifts:
Tilts and shifts is monitored by:

Checking the levels at fixed gauge mark on both of the opposite


faces along axes of well. Levels are checked from the reference
pillars along the axes established in advance for this purpose. The
difference in level will establish the tilt along the axis. It is
designated as ratio of difference in level to dia of well. Such
checking and recording of tilts and shifts are done at regular
intervals depending upon the rate of sinking but at least once a
day, provided there has been sinking of the well.
The tilt of any well shall not be exceed 1 (horizontal) in 80
(vertical), and the shift at the well base shall not be more than

6.6

150mm in any resultant direction. Measurement for tilt shall be


taken every day are recorded.
Sinking history of well shall be maintained in the format given in
Appendix 1200/I, MORT&H

Plugging of well and well cap:


Following are the details for:1.
2.
3.
4.
5.
6.
7.

False Steining.
Bottom Plug.
Sand Filling.
Intermediate Plug.
Top Plug.
Water Filling.
Well Cap.

False Steining:
False steining is cast wherever required and mentioned as per
drawing.
Bottom plug:
Once the cutting edge has reached the founding level as shown in
the drawing or as decided by the engineer, a sump of required
shape and shape as shown in the drawing or decided by the
Engineer shall be formed. It is desirable to have a good idea of the
shape of the sump either by probing or by sending divers.
After completion soundness test of bottom plug filling inside the
well shall commence after a period of 3 days.
Sand filling:
After the bottom plug and waiting period is over, sand filling shall
be started. Good quality sand shall be filled in dredge hole after 3
days of bottom plug concrete up to required level.
After sand has been filled in the well, water remaining on top of
the sand shall be bailed outers. Top level of sand to be checked
and top plug / intermediate plug of required grade of concrete and
thickness shall be laid as shown in the drawing, and balance work
of well cap shall be taken up.
Intermediate / Top plug:Intermediate / Top plug will be carried out after sand filling as per
drawing.

Water filling:
Water filling in the steining wherever mentioned in the drawing
shall be taken into consideration.

Well Cap Casting:


Well cap reinforcement
Layout for the well cap reinforcement shall be given on top plug
and well steining concrete. Already cut, bent and shifted
reinforcement shall be tied in position as per approved drawings.
Clear cover blocks made from same grade of concrete as that of
well cap shall be tied to reinforcement.
Well cap formwork
The normal streel forms shall be the fixed in position as well cap
outer side forms as per drawing. Supporting arrangement shall be
done as per drawing. Well cap shuttering shall be done as per
shape and size of well where false steining is not there.
Well cap concrete
The concrete mixed at central batching plant shall be delivered
through transit mixers. Concrete shall be placed through Concrete
pumps. Concrete shall be vibrated with high frequency needle
vibrators. It shall be ensured that concreting is done continuously
and completed in a single pour without any cold joint.

Time cycle
A
i)
ii)
iii)
iv)
v)
vi)
vii)
viii
)
ix)
B
C

Well curb casting:


Ground preparation for cutting edge placing
Fabricated cutting edge placing
Cutting Edge Welding
Well curb inside shuttering / staging
Vertical bars fixing welding etc.
Binders / links fixing
Outside shuttering fixing
Checking & Concreting

Duration (days)
1.0
1.0
5.0
2.0
2.0
1.0
2.0
2.0

De - shuttering
Total duration
Well Sinking 1m / day, so 4 m lift
Well Steining Lift 2.5m

1.0
17
4

i)
ii)
iii)
iv)
D
i)
ii)
iii)
iv)
v)
vi)
vii)
viii
)

Reinforcement fixing
Inner and outer shuttering
Checking and concreting
De shuttering & Sinking
Total duration
Bottom Plug, Sand filling, Well cap
Cleaning, checking 7 clearance for bottom
plugging.
Bottom plugging
Sand filling
Top plugging
Reinforcement for well cap
Outer shuttering for well cap
Checking and concreting
De shuttering

2.0
3.0
2.0
2.0
9.0

Total duration

14.0

1.0
1.0
4.0
1.0
3.0
2.0
1.0
1.0

8. INSPECTION & TESTING:


All the Inspection and Testing requirements to be prepared in the form of
inspection and test plans for various activities described under different
clauses of this methodology as per relevant M.O.R.T&H Specifications,
Contract Technical Specification and other Codes/Standards as mentioned
in Reference Chapter by the site Quality Control representative.
These inspection and test plans shall consist of type of inspection and
name of the test to be conducted for product realization, frequency of
testing, acceptance criteria and category for inspection.
Inspection and test plans shall be revised whenever there is any change
in methodology and specifications etc. Various field and laboratory test
formats referred in inspection and test plans shall be mentioned in
respective ITPs for various activities.
Any Non-conformity shall be observed, recorded, corrective/preventive
actions and closing of NCRs shall be as per the established document
procedure described in Project Quality Plan.
Various Documents/Records required to be maintained for the present
segmental methodology shall be listed by project quality plan.

9. OHS & ENVIRONMENT MANGEMENT PLAN:


The OH & Safety and Environmental Management Plan for the project
shall be prepared to meet the various safety and Environmental

Management requirements as mentioned in contract documents and also


as per the established OH& Safety and Environmental Management
Systems and procedures of GPT INFRA PROJECTS LTD.
General Safety Arrangements:

All employees, workmen and labour of GPT INFRA PROJECTS LTD. And
its subcontractor engaged for bridge work shall be wearing proper
P.P.E before entering the site.
Barricading shall be provided to cover the entire length of working
area. The barricading shall be provided as per the approved scheme.
Painting of barricading shall be done with approved colour scheme for
prominent visibility.
All the vehicles engaged for the work shall be fitted with proper
indicator systems.
Reverse light rear view mirror and reverse horn shall be fitted with all
the vehicles.
Break, steering condition, tire pressure shall be checked periodically.
Proper speed limit shall be maintained within the project site.
Driver shall not drive vehicle when he is not fit mentally and
physically.
Proper caution boards, flag boys be placed to caution the vehicle
movement at unloading points.
Trained supervisors shall be deployed at working sites.
Unauthorized persons and visitors shall not be allowed within the
critical area/hard hat area.
Trained Flag Boy and warning systems shall be provided.
Periodic training shall be provided to drivers, helpers, and bank men
and flag boys. Tool box talks shall be carried at frequent intervals by
safety personnel/site in charge.
Proper supervision and proper planning of the activity shall be done.
Proper illumination shall be provided during night work.
Good housekeeping shall always be maintained nearby working area
to prevent any kind of hazards.
Any lifting equipments shall be engaged in work after proper
checking and load testing as per relevant requirement. Periodic
maintenance shall be done for all lifting equipments/devices
deployed at work. Record shall be maintained in prescribed format.

All necessary and required safety measures/precautions during the


execution of job shall be undertaken. It shall be ensured that the
construction materials, equipment and facilities will not cause damage
to existing property or interfere with the operation of the project. All
equipment such as lifting tools tackles, cranes, excavators, dumpers,
Roller and Dozer etc. shall be checked periodically to ensure its safe

working. It shall be complied with all applicable provision of safety


regulations; clean-up program and other measure that is in force at the
site.
It shall be comply with the instruction given by the client safety engineer
or his authorized nominee regarding safety precautions. Protective
measures, clean-up requirements etc.
For all major activities potential risks shall be identified and
eliminated/minimized at planning stage by the project safety officer,
Project Manager and Works Manager. The risk assessment analysis
considers the risk index (risk index guide contains Tasks hazard
identification, risk assessment & risk control measures.) as H-High and
M-medium or moderate and L-low (acceptable/tolerable risk).
The project safety officer will refer to risk index guide for determining
risk index. Activity & associated risk when High or medium is recorded
and suitable measures shall be taken to control the risks. The works
Manager and Line supervisors along with project safety officer shall be
review, high and medium risk activities, in order to reduce level of the
risk.
Corporate occupational health& Safety department shall be informed
about actions taken to contain the risks. H-High and M-medium risk shall
be bought under control by taking suitable measures. Where the
activity/risk is not covered in risk index guide, it is further evaluated and
included in risk index guide by the corporate occupational health &
Safety Department for further references.
The risk management at project level shall be carried out for every new
activity undertaken, where the project is ongoing and the measures
identified for risk control shall be recorded in risk control document by
the project site. New measures may be required in the form of addition
of new work method/precaution/improved safety equipment / additional
occupational health & safety training / safety signs / posters etc.

10. ATTACHMENTS:
Annex 1: Details of Cutting Edge for 19.15 x 9.15 m dia well
curb for Kalpi Yamuna Rail Bridge Project.
Annex 2: Details of Well Steining for 19 x 9 m dia well for
Kalpi Yamuna Rail Bridge Project.
Annex 3: Fabrication details of Inner and Outer formwork for
well curb for Kalpi Yamuna Rail Bridge Project.

Annex 4: Fabrication details of Inner and Outer formwork for


well steining for Kalpi Yamuna Rail Bridge Project.
Annex 5: MORT&H Sinking Details to be used.
11.

DISTRIBUTION:

The document shall be distributed to all concerned users.


12. RECORDS
This segmental methodology shall be retained till project
completion.

You might also like