You are on page 1of 1

Fael Khair Program

Daily Site Diary

Contract Number: BD1-0033


Contractor: Mahabub Brothers (Pvt.) Ltd.
Shelter ID:
Shelter Name:
Day of
Work:

Date:
Beginning of the
day
Middle of the day

Weather

End of the day


Remarks
Labour on Site

Working
Idle
Remarks

Plant on Site

Working
Idle
Broken/Remarks

Materials on Site:
Description of work carried out

Labour/Plant

Duration

Visitors:
Other Comments: Problems, time lost due to weather, site instructions &
day-works orders issued etc.

Signed:

Consultants Representative:
Contractors Representative: