Place inspected:Saudi Steel Fabrication Dammam Saudi Arabia Date of inspection 25 / 10 / 2015
Observations
Hazards and consequences
Control measures
Timescale
Hazardous Observation
Steel Fabrication
1.
Insufficient
leadership
and
commitment from the management,
safety culture does not exist, which
can result into accidents and many
other problems, that can ruin the
company in no time.
1-Management
should
lead
with
examples as role model.
2-Set realistic targets and Objectives.
3-To review the output progress Quarterly
as per ILO-OSH 2001.
4. Housekeeping is poor
Housekeeping of the entire fabrication
is very bad/poor. Metal pieces are
laying all around the floor. It can result
in trip and fall of workers may result in
severe injury.
1.Immediately
Within 3 days.
2.Less than a
week.
1. Immediately
Within
24Hours.
1. Immediately
1. Remove all unwanted waste And Other
Scrap.
2. Dispose-off in Allocated metal scrap
Waste Box.
2. Less than a
Week.
INTERNATIONAL GENERAL
CERTIFICATE
(2011 specification)
Candidates observation
sheet
02
of 12
Place inspected:Saudi Steel Fabrication Dammam Saudi Arabia Date of inspection 25 / 10 / 2015
Observations
Control measures
Timescale
1- Less Than a
Week.
1- After every 1
or 2 Hours.
2- Within 24Hours.
3Within
24Hours
4- Within a Day.
Good Practice
Good Practice
INTERNATIONAL GENERAL
CERTIFICATE
(2011 specification)
Candidates observation
sheet
03
of 12
Place inspected:Saudi Steel Fabrication Dammam Saudi Arabia Date of inspection 25 / 10 / 2015
Observations
Control measures
Timescale
1- Immediate
Within 48Hours
1. Immediately
2.
Within
24hours
3.
Within
24hours
4.
Before
starting the work
at
new
location/place.
1.Immediately
2-One-two
weeks
INTERNATIONAL GENERAL
CERTIFICATE
(2011 specification)
Candidates observation
sheet
04
of 12
Place inspected:Saudi Steel Fabrication Dammam Saudi Arabia Date of inspection 25 / 10 / 2015
Observations
Hazards and consequences
12.
Only
two
Fire-Extinguishers
available for entire area.
Extinguishing
agents
would
be
inadequate in result of fire.
Control measures
Timescale
Within 3 days
1-Immediately
2-Within one week
1. Immediately
INTERNATIONAL GENERAL
CERTIFICATE
(2011 specification)
Candidates observation
sheet
05
of 12
INTERNATIONAL GENERAL
CERTIFICATE
(2011 specification)
1. Less than a
week.
2. Immediately
Three days
3.During
the
work is carried
out.
1. Within
Two Weeks
1.Immediately
2.Within
24hours
3.To be
conducted daily.
4.Its Necessary.
5.3 days
6.Once every
Month
Candidates observation
sheet
06 of 12
Place inspected:Saudi Steel Fabrication Dammam Saudi Arabia Date of inspection 25 / 10 / 2015
Observations
Hazards and consequences
Control measures
Immediate and longer term actions
Timescale
Good Practice
INTERNATIONAL GENERAL
CERTIFICATE
(2011 specification)
1. Immediately
2. Immediately
within 2 to 3
days
3. While the
work is carrying
out
1. Immediately
with in 48hours
2. Immediately
With in 48hours
3. Once in a 3Months.
Candidates observation
sheet
07
of 12
Place inspected:Saudi Steel Fabrication Dammam Saudi Arabia Date of inspection 25 / 10 / 2015
Observations
Hazards and consequences
Control measures
Immediate and longer term actions
Timescale
1-Immediately
within 24 hours
2-While Workers
carrying out the
Work.
3- Immediately
Within 24 hours.
1. After every 40
minutes.
2.Immediately
Within 24hours
3.Immediately
within 24hours
4. Once in 3
months.