RENCANA ANGGARAN BIAYA


No.

: 009 / RAB - PRK / JKU / XI / 2015

Proyek

: Renovasi Rumah PRK - Jakarta Utara

Tanggal : 20 November 2015

URAIAN PEKERJAAN

NO
I

SPESIFIKASI

HARGA
SATUAN

VOLUME

JUMLAH HARGA

TOTAL

PEKERJAAN PERSIAPAN
1 Mobilisasi Alat & Pekerja

ls

1.00

2,500,000

2 Pembongkaran Dinding Toilet

m2

5.78

85,000

490,875

3 Pembongkaran Kusen

bh

7.00

150,000

1,050,000

m2

13.80

85,000

1,173,000

ls

1.00

1,750,000

1,750,000

4 Pembongkaran Lantai

Toilet Kamar Utama & Kamar Belakang Lt.Atas

5 Pembersihan Area Kerja

2,500,000

6,963,875
II

PEKERJAAN URUGAN
1 Urugan Tanah Area R.tamu,Teras, & R.Keluarga

Tanah Urug ( Tinggi 30 cm )

m3

44.85

275,000

12,333,750
12,333,750

III

PEKERJAAN COR BETON


1 Penambahan Cor 30 cm

( Akses Jalan Ke Rumah / Ramp )

m3

1.98

4,550,000

9,009,000
9,009,000

IV
A.1

PEKERJAAN ARSITEKTUR
Pekerjaan Pasangan Dinding
1 Pasangan Dinding Taman Depan

A.2

m2

1.98

115,000

227,700

2 Plesteran

1ps : 8 psr

Hebel

m2

3.96

44,500

176,220

3 Acian

Portland Cement

m2

3.96

26,500

104,940

Pekerjaan Pasangan Lantai


Lantai Dasar
1 Teras

Keramik 60x60 cm

m2

14.30

235,000

3,360,500

2 Teras Luar

Keramik 40x40 cm

m2

19.80

191,000

3,781,800

3 Garasi

Keramik 60x60 cm

m2

17.60

235,000

4,136,000

4 R.Tamu & R.Keluarga

Keramik 60x60 cm

m2

86.90

235,000

20,421,500

5 Toilet R.Tidur Utama

Keramik 40x40 cm

m2

6.60

191,000

1,260,600

6 Toilet Belakang

Keramik 40x40 cm

m2

4.40

191,000

840,400

1 Toilet R.Tidur Belakang

Keramik 40x40 cm

m2

4.40

191,000

840,400

2 Toilet

Keramik 40x40 cm

m2

3.85

191,000

735,350

m'

81.40

25,000

2,035,000

7,250,000

Lantai Atas

A.3

Pekerjaan Plin Lantai


1 Lantai Dasar

A.4

Pekerjaan Pintu Jendela & Aksesoris


Lantai Dasar
1 P1 Pintu R.Tamu

Kusen & Pintu Kayu Kamper Finish Cat Termasuk Aksesoris

bh

1.00

7,250,000

2 P2 Pintu Toilet

PVC

bh

2.00

550,000

1,100,000

2 J1 Jendela Depan

Kusen & Jendela Kayu Kamper Finish Cat Termasuk Aksesoris

bh

3.00

4,650,000

13,950,000

Kusen & Jendela Kayu Kamper Finish Cat Termasuk Aksesoris

bh

4.00

4,650,000

18,600,000

1 Cat Dasar Lt.Dasar

Ex. Dulux

m2

565.90

28,500

16,128,221

2 Cat Dasar Lt.Atas

Ex. Dulux

m2

598.15

28,500

17,047,190

1 Pagar

Ex. Dulux

m2

48.40

39,500

1,911,800

2 Teras & Garasi


3 R.Tamu

Ex. Dulux

m2

87.27

39,500

3,447,323

Ex. Dulux

m2

68.30

39,500

2,698,028

4 R.Keluarga
5 R.Tidur Depan

Ex. Dulux

m2

83.65

39,500

3,304,155

Ex. Dulux

m2

66.57

39,500

2,629,455

6 Toilet
7 R.Tidur

Ex. Dulux

m2

29.39

39,500

1,160,984

Ex. Dulux

m2

66.86

39,500

2,640,891

8 Dapur
9 Gudang

Ex. Dulux

m2

79.53

39,500

3,141,435

Ex. Dulux

m2

27.24

39,500

1,075,822

Ex. Dulux

m2

8.69

39,500

343,255

1 R.Tidur 1
2 R. Kerja

Ex. Dulux

m2

46.57

39,500

1,839,673

Ex. Dulux

m2

46.07

39,500

1,819,686

3 R. Tidur 2

Ex. Dulux

m2

63.66

39,500

2,514,452

4 R. Tidur 3

Ex. Dulux

m2

58.01

39,500

2,291,553

5 R. Santai

Ex. Dulux

m2

155.14

39,500

6,128,188

6 Gudang

Ex. Dulux

m2

25.92

39,500

1,023,682

7 Toilet

Ex. Dulux

m2

21.12

39,500

834,240

8 KM/WC

Ex. Dulux

m2

24.86

39,500

981,970

9 Balkon

Ex. Dulux

m2

95.70

39,500

3,780,150

10 T. Jemur

Ex. Dulux

m2

61.09

39,500

2,413,213

Lantai Atas
1 J1 Jendela R.Kerja
A.5

Pekerjaan Cat Dinding


Pelapis Cat Dasar

Lantai Dasar

10 Toilet Belakang
Lantai Atas

RAB

Page 1

URAIAN PEKERJAAN

NO
A.6

SPESIFIKASI

HARGA
SATUAN

VOLUME

JUMLAH HARGA

TOTAL

Pekerjaan Cat Plafon


Lantai Dasar
1 Teras

Ex. Dulux Ceiling

m2

34.76

42,000

1,459,920

2 R.Tamu

Ex. Dulux Ceiling

m2

29.95

42,000

1,258,026

3 R.Keluarga

Ex. Dulux Ceiling

m2

55.79

42,000

2,343,264

4 R.Tidur Depan

Ex. Dulux Ceiling

m2

27.19

42,000

1,142,064

5 Toilet

Ex. Dulux Ceiling

m2

5.50

42,000

231,000

6 R.Tidur

Ex. Dulux Ceiling

m2

24.97

42,000

1,048,740

7 Dapur

Ex. Dulux Ceiling

m2

24.38

42,000

1,023,792

8 Gudang

Ex. Dulux Ceiling

m2

4.27

42,000

179,256

9 Toilet Belakang

Ex. Dulux Ceiling

m2

8.03

42,000

337,260

1 R. Tidur Samping Kanan

Ex. Dulux Ceiling

m2

14.85

42,000

623,700

2 R. Kerja

Ex. Dulux Ceiling

m2

16.50

42,000

693,000

3 R. Tidur Anak

Ex. Dulux Ceiling

m2

24.75

42,000

1,039,500

4 R. Tidur Anak 1

Ex. Dulux Ceiling

m2

21.45

42,000

900,900

5 R. Santai

Ex. Dulux Ceiling

m2

73.70

42,000

3,095,400

6 GUdang

Ex. Dulux Ceiling

m2

4.95

42,000

207,900

7 Toilet

Ex. Dulux Ceiling

m2

3.30

42,000

138,600

8 KM/WC

Ex. Dulux Ceiling

m2

3.63

42,000

152,460

9 Balkon

Ex. Dulux Ceiling

m2

23.10

42,000

970,200

Penambahan Kolom & Menaikan pagar dorong

ls

1.00

4,500,000

4,500,000

Toto

bh

1.00

3,250,000

3,250,000

Lantai Atas

A.7

Pekerjaan Lain-lain
1 Pagar Dorong Depan

PEKERJAAN SANITARY
1 Closet Duduk Toilet Dapur

CW660NJ/SW660J

182,570,757
TOTAL ANGGARAN PEKERJAAN

210,877,382
10.0%

JASA PELAKSANAAN
TOTAL BIAYA PEKERJAAN
PEMBULATAN
TERBILANG

21,087,738
231,965,120
231,900,000

: Dua Ratus Tiga Puluh Sati Juta Sembilan Ratus Ribu Rupiah