You are on page 1of 24

Project Builder in SAP

Welcome to Dassian International

Is your business project-centric in nature, or do projects rank highly in importance to your


organization? Are you realizing the maximum potential from your SAP investment?
Dassian is an International company with over 3000 customers across 4 continents, founded in
November 2000 and headquartered in Arizona, USA.
Our Focus

Dassian are experts in Program and Contract Management including compliance with US
Government requirements and Cost Accounting Standards. In addition we provide thought
leadership and design for SAP's product roadmap. Our affordable product applications are
available to bridge the known functionality gaps with a low cost support model.
Our people have in-depth industry expertise coupled with a broad and rich SAP knowledge that
has been acquired through many successful project lifecycles. We take a 'why not SAP' approach
which enables our customers to leverage their SAP investment. We have the experience and
track record to help you get the best from your SAP systems.
Please take a moment to look at our capabilities ranging from SAP certified Add-On products
and support through to expert consulting services. You can browse by industry or Dassian
competency. For more detailed information on the value Dassian can bring to your company,
please contact us.
Knowledge Base

To assist our current customers and future customers, Dassian is offering this document as a
knowledge source. Through this document our customers should be better able to make
informed decisions about the appropriate resources, tools, and solutions in regards to the topic
discussed in this paper.
Contact Information
Project Management Solutions

Erik C. Hayes, Partner


Ehayes@dassian.com

Contracts & Billing Solutions

Barb McElnea, Partner


bmcelnea@dassian.com

6900 E. Camelback Rd, Suit 805


Scottsdale, Arizona 85251
www.dassian.com
(480)922-1700

Page 1

Project Builder in SAP

Table of Contents
Overview ................................................................................................................................................. 3
Technical Updates ................................................................................................................................... 3
Project Builder (CJ20N) BPP ..................................................................................................................... 3
Change Project Structure ..................................................................................................................... 3
Open Project.................................................................................................................................... 4
Create WBS Element ........................................................................................................................ 5
Create Network ............................................................................................................................. 11
Create Activities............................................................................................................................. 22
Delete Object...................................................................................... Error! Bookmark not defined.
Modify WBS Hierarchy ........................................................................ Error! Bookmark not defined.
Delete Project ..................................................................................... Error! Bookmark not defined.
Plan Project Components ....................................................................... Error! Bookmark not defined.
Project Builder EV Methods .................................................................... Error! Bookmark not defined.
Project Builder Scheduling ...................................................................... Error! Bookmark not defined.
Project Builder Milestones ...................................................................... Error! Bookmark not defined.
Project Builder Investment Program Measure Assignment...................... Error! Bookmark not defined.
Project Builder Post Confirmations ......................................................... Error! Bookmark not defined.
Project Builder External Procurement Planning....................................... Error! Bookmark not defined.
Project Builder Personnel Assignments ................................................... Error! Bookmark not defined.

Page 2

Project Builder in SAP


Overview
Project Builder is the primary entry point for performing Project Management in SAP. It is a very large
and complex transaction. This document will discuss the functionality and usage of Project Builder
giving the user a head start on working in this tool.

Technical Updates
There are several key OSS Notes which should be applied to SAP to support the use of Project Builder.
Most of the notes are to improve system performance when opening, working, and saving a project in
Project Builder. The simplest method of limiting system performance impacts is to select Display in the
User Settings option of Project Builder. Then only open for change the lowest level you plan on
changing.
OSS Note: 617591 Table Indexes do not exist
This note applies when Project Builder is using Procurement integration by creating Material
Reservations or Purchase Requisitions.

Project Builder (CJ20N) BPP


Change Project Structure
Procedure
1.

Start the transaction using the menu path or transaction code.

Logistics Project System Project

Project Builder

Page 3

Project Builder in SAP

2.

Click

to select the Project to open.

Open Project

3.

As required, complete/review the following fields:


Field Name
Project definition

R/O/C
R

Description
Description of the Project definition.

Page 4

Project Builder in SAP


4.

Click

to open the Project.

Project Builder: Project DA-000995

5.

Click

to expand the Project Structure, if required.

Create WBS Element


6.

Click

7.

Right-click

WBS Element to select this WBS.


to view the options drop down.

Page 5

Project Builder in SAP

8.

Select Create

9.

As required, complete/review the following fields:

WBS element.

Field Name
WBS element

10.

Click

R/O/C
R

Description
Description of the WBS element.
Example:
New WBS Element

to view the WBS Assignments tab.

Project Builder: Project DA-000995

Page 6

Project Builder in SAP

11.

Click

to view the WBS Control tab.

Project Builder: Project DA-000995

Page 7

Project Builder in SAP

12.

Click

to view the WBS User Fields.

Project Builder: Project DA-000995

Page 8

Project Builder in SAP

13.

Click

to save the new WBS Element.

Project Builder

Page 9

Project Builder in SAP

14.

Double-click

to open the Project DA-000995.

Project Builder: Project DA-000995

Page 10

Project Builder in SAP

15.

Click

Create Network
16.

Right-click

to open the selection box on the New WBS Element.

Page 11

Project Builder in SAP

17.

Select Create

18.

As required, complete/review the following fields:

Network.

Field Name
Network

19.

Right-click

R/O/C
R

Description
Description of the Network.
Example:
New Network

to view the drop down list.

Page 12

Project Builder in SAP

20.

Select Create

Copy network.

Copy from...

Page 13

Project Builder in SAP

21.

Click
copy.

to select the Network to

Copy from...

Page 14

Project Builder in SAP

22.

As required, complete/review the following fields:


Field Name
Network

23.

Click

R/O/C
R

Description
Description of the Network.
Example:
100000000580

to select the Network objects that should be copied.

Copy from...

Page 15

Project Builder in SAP

24.

Click

to review and update the Network Parameters.

Copy from...

Page 16

Project Builder in SAP

25.

Click

to copy the Network.

26.

Click

Project Builder: Project DA-000995

Page 17

Project Builder in SAP

27.

As required, complete/review the following fields:


Field Name

28.

R/O/C

Description

Start date

Description of the Start date.


Example:
07/21/2005

Finish date

Description of the Finish date.


Example:
09/06/2005

Click

Project Builder: Project DA-000995

Page 18

Project Builder in SAP

29.

Click

30.

Click

to select the New Network.

to view the Person Responsible valid values.

Number of the responsible person (project manager) (1) 23 Entries Found

Page 19

Project Builder in SAP

31.

As required, complete/review the following fields:


Field Name

R/O/C

Respons.

32.

Double-click

33.

Click

Description
Description of the Respons..
Example:
00000005

to save the Network.

Project Builder

Page 20

Project Builder in SAP

34.

Double-click

to open the Project DA-000995.

Project Builder: Project DA-000995

Page 21

Project Builder in SAP

35.

Click

Create Activities
36.

Right-click

to open the drop down box for the Network.

Page 22

Project Builder in SAP

37.

Select Create

38.

Click

Activity (internal).

There are several options for creating new Activities. The Internal Activity is
shown. External, Costs, and Service Activities can also be created. Rules for creation of
these activities is discussed in detail in BPS5107_CJ20N_FreeFormProject.
to select the new Activity.

Work center (1)

Page 23

Project Builder in SAP

Work center (1) 10 Entries Found

Page 24

You might also like