You are on page 1of 5

DEPARTMENT OF PUBLIC WORKS & HIGHWAYS

Contract ID No.: 015OB0148


Contract Name: Construction of Four (4) Storey Eight (8) Classroom School Building at Sto. Nino National High School, Marikina City
Location of the Contract: Marikina City

BILL OF QUANTITIES
No. ________
Part No. ______________
ITEM
NO.

I.

II.

DESCRIPTION

Part Description: ________________


UNIT

QUANTITY

Earthworks
a) Excavation

m3

478.40

b) Backfill

m3

368.00

c) Earthfill

m3

73.60

d) Gravelfill

m3

18.40

a) F'c=4,000 Psi (27.6 Mpa)

m3

331.57

b) Lean Concrete

m3

11.45

a) Grade 60

kgs.

34,541.60

b) Grade 40

kgs.

23,470.49

a) CHB Wall

m2

636.00

b) Plastering

m2

2,198.00

c) Concrete Topping

m2

608.00

Concrete Works

c) Rebars

III.

Masonry Works

UNIT PRICE
AMOUNT
(Pesos)
(Pesos)
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:

SUB-TOTAL

DEPARTMENT OF PUBLIC WORKS & HIGHWAYS


Contract ID No.: 015OB0148
Contract Name: Construction of Four (4) Storey Eight (8) Classroom School Building at Sto. Nino National High School, Marikina City
Location of the Contract: Marikina City

BILL OF QUANTITIES
No. ________
Part No. ______________
ITEM
NO.

DESCRIPTION

Part Description: ________________


UNIT

QUANTITY

IV.

Roof Framing Works

m2

234.00

V.

Tinning Works

m2

234.00

VI.

Covered Pathwalk/Media Agua

m2

89.60

VII.

Fabricated Materials
a) Door

m2

53.28

b) Windows

m2

74.88

c) Jambs

bf

1,874.67

d) Hardwares

job

1.00

Storm Drainage

job

1.00

IX.

Railings

lm

64.00

X.

Grill Works

m2

588.44

XI.

Carpentry Works
m2

234.00

VIII.

a) Ceiling Works

UNIT PRICE
AMOUNT
(Pesos)
(Pesos)
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:

SUB-TOTAL

DEPARTMENT OF PUBLIC WORKS & HIGHWAYS


Contract ID No.: 015OB0148
Contract Name: Construction of Four (4) Storey Eight (8) Classroom School Building at Sto. Nino National High School, Marikina City
Location of the Contract: Marikina City

BILL OF QUANTITIES
No. ________
Part No. ______________
ITEM
NO.

DESCRIPTION

Part Description: ________________


UNIT

QUANTITY

b) Blackboard

set

8.00

XII.

Emergency Exit

set

1.00

XIII.

Electrical Works

job

1.00

XIV.

Painting Works

m2

9,361.00

XV.

Billboard

job

1.00

UNIT PRICE
AMOUNT
(Pesos)
(Pesos)
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:
In Words: Pesos: __________________ In Words: Pesos: __________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
__________________________________________________________________
In Figures:
In Figures:

SUB-TOTAL
GRAND-TOTAL
AMOUNT IN WORDS: ____________________________________________________________________________________
___________________________________________________________________________
Date: _____________________

Submitted By:

Calendar Days: 210 CD


Name & Signature of Bidder's Representative

Position
Name of Firm

Address

DEPARTMENT OF PUBLIC WORKS & HIGHWAYS


Contract ID No.: 015OB0148
Contract Name: Construction of Four (4) Storey Eight (8) Classroom School Building at Sto. Nino National High School, Marikina City
Location of the Contract: Marikina City

SUMMARY OF BID PRICE


(All Parts of Bill Quantities)
Contract ID:
Part No.

Part Description

Total Amount

TOTAL AMOUNT
TOTAL AMOUNT IN WORDS:

Name: _____________________________________________________________________________________
Signed: _____________________________________________________________________________________

in the capacity as: _______________________

Date: _________________________________

Duly authorized to sign the Bid for and/or in behalf of: ___________________________________________________________________________________

DEPARTMENT OF PUBLIC WORKS & HIGHWAYS


Contract ID No.: 015OB0148
Contract Name: Construction of Four (4) Storey Eight (8) Classroom School Building at Sto. Nino National High School, Marikina City
Location of the Contract: Marikina City

MINIMUM EQUIPMENT REQUIRED


DESCRIPTION
Backhoe with Breaker
Bagger Mixer
Concrete Vibrator
Welding Machine
Plate Compactor
Bar Cutter
Service Vehicle
Handtools

NUMBER
1
2
2
2
2
2
1
40

OWNED

*Minimum Testing and Equipment Materials in accordance with D.O. # 86 series of 1990*

* SHOW PROOF OF OWNERSHIP.

THE LEASED EQUIPMENT SHALL BE LISTED


IN DETAIL TO INCLUDE THE BRAND, SERIAL NO.,
CAPACITY, AND PRESENT LOCATIONS,

LEASED