SYSTEM: 500 kV Switchyard Sidi-Krir Over Head Transmission line

First First
Equip. Description / Setting Test /Check Test Test Main./ Test
Comm. Service
Manu. Period Steps Remarks
date date Type Equip.
Name Function Values Time
Distance
Relay Seconda
Main I Distance zone settings AREVA 6/2005 ry ISA
Z1 (forward) 0 sec
[ Micom injection
P437 ]

X1= 33 ohm/phase

R1PP= 6 ohm/phase
R1 PG = 34 ohm/phase
Z2 (forward) 0.45 sec

X2= 53.725 ohm/phase

R2PP= 7.5 ohm/phase


R2 PG = 40 ohm/phase
Z3R (backward) 2 sec
X3R= 10.25 ohm/phase
R3RPP= 12 ohm/phase
R3R PG = 55 ohm/phase
Z3 [ forward ] 0.90 sec
X3 = 79.5 ohm/phase
R3PP = 9.5 ohm/phase
R3PG = 50 ohm/phase
Line impedance angle = 86.47 ْ
Angle α1= α2 = α3 = α4 =
86.47ْ
Power swing blocking Operating delay [ op.delay ] 100 msec
Release delay [ Re.dalay ] 200 msec
Operating value = 5 %
In = nominal C.T
Directional Earth Fault IN> = 0.1 In Op. delay = 0.5 s secondary
current
V N.G = 0.05 Vn Re. delay = 10s

Angle α g = -45ْ
IrefN = 0.1 In
Non directional over I> = 1.5 In [ 3000 A
2 sec
current Primary ]
I>> = 4 In [ 6000 A
2 sec
Primary ]

Switch On To Fault
OK
[SOTF]

SYSTEM:500 kV Switchyard Sidi-Krir Over Head Transmission line

1
First First
Equip. Description / Setting Test /Check Test Test Main./
Comm. Service
Manu. Period Test Steps Remarks
date date Type Equip.
Name Function Values Time
Distance
Relay Seconda
Distance zone
Main II AREVA 6/2005 ry ISA
settings Z1 (forward) 0 sec
[ Micom injection
P442 ]

X1= 33 ohm/phase

R1PP= 6 ohm/phase
R1 PG = 34 ohm/phase
Z2 (forward) 0.45 sec

X2= 53.725 ohm/phase

R2PP= 7.5 ohm/phase


R2 PG = 40 ohm/phase
Z3R (backward) 2 sec
X3R= 10.25 ohm/phase
R3RPP= 12 ohm/phase
R3R PG = 55 ohm/phase
Z3 [ forward ] 0.90 sec
X3 = 79.5 ohm/phase
R3PP = 9.5 ohm/phase
R3PG = 50 ohm/phase
Line impedance angle = 86.47 ْ
Angle α1= α2 = α3 = α4 =
86.47ْ
Power swing
Operating delay [ op.delay ] 100 msec
blocking
Release delay [ Re.dalay ] 200 msec
Operating value = 5 %
Directional Earth In = nominal C.T
IN> = 0.1 In Op. delay = 0.5 s
Fault secondary current
V N.G = 0.05 Vn Re. delay = 10s

Angle α g = -45ْ
IrefN = 0.1 In
Non directional over I> = 1.5 In [ 3000 A
2 sec
current Primary ]
I>> = 4 In [ 6000 A
2 sec
Primary ]

Switch On To Fault
OK
[SOTF]

SYSTEM: 500 kV Switchyard Sidi-Krir Over Head Transmission line

2
First First
Equip. Description / Setting Test /Check Test Test
Comm. Service Main./ Test Steps
Manu. Period Remarks
date date Type Equip.
Name Function Values Time
Back-up Directional Earth AREVA Ie> = 0.1 In [200 A Primary ] IEC standard Seconda Freja In = nominal
protection Fault Forward direction torque angle inverse TMS = ry C.T
Micom P126 67G =0ْ 1 injection secondary
current
OVER CURRENT I>1 = 1.2 In [ 2400 A Primary ] 2.3 sec

I>2 = 3 In [6000 A Primary ] 1.3 sec


I>3 =2 In [ 4000 A Primary ] 10 sec
Used only for SOTF

First First
Equip. Description / Setting Test /Check Test Test Main./ Test
Comm. Service
Manu. Period Steps Remarks
date date Type Equip.
Name Function Values Time
Breaker Syuchro -check AREVA Phase angle = 20 ْ Slip time = 0.1 Seconda Freja
failure sec ry
Micom P143 injection
Slip frequency = 0.05 HZ

Diff.voltage = 17.5 kv Phase


voltage
Block voltage = 270 kv Phase
voltage
Live voltage = 160 kv Phase
voltage
Dead voltage = 65 kv Phase
voltage

Breaker failure IN>1 = 0.1 In TC.B. FAIL 1 = 50 ms In = nominal C.T


[ 50BF ] secondary
current
I > = 1.2 In TC.B. FAIL 2 = 200
ms
B.F. reset at 0.1 In

SYSTEM: 500 kV Switchyard Sidi-Krir Over Head Transmission line

3
First First
Equip. Description / Setting Test /Check Test Test Main./ Test
Comm. Service
Manu. Period Steps Remarks
date date Type Equip.
Name Function Values Time
Voltage ARTECHE 500 / 0.1 KV LINE SIDE
transformer TYPE : √3 √3
[ V.T.] UTF-525 200 VA - CL 3P

Current Japan AE 2000/1 A


transformer power 30 VA
[ C.T. ] system 5P20