Professional Documents
Culture Documents
Document Number:
Revision:
DCC I.D.:
Pages: 1 of 13
Uncontrolled if printed
LAYOUT &
LESSON 01 - INTRODUCTION TO PROCESS AREA
PIPING DESIGN
PRELIMINARY PLOT PLAN
COURSE
INPUTS
Document Number Title Status
Note: The latest version of this document is stored in EDM. Any prints of this document are
uncontrolled.
Executive Summary
These design guides have been compiled to assist plant design engineers and designers in the
development of Plot Plans for actual jobs and estimates.
Contents
1. INTRODUCTION................................................................................................................... 5
2. CONTENTS OF A PROPOSED PLOT PLAN ...................................................................... 5
2.1 SCALE......................................................................................................................... 5
2.2 BLOCK MODEL - (Electronic) ................................................................................... 5
2.3 ISSUE .......................................................................................................................... 5
3. PLOT PLAN DEVELOPMENT OF UNIT WITHIN AN EXISTING COMPLEX...................... 6
3.1 GENERAL INFORMATION REQUIRED BY PLANT DESIGN ................................... 6
4. LAYOUT OF PLOT PLAN AREA ......................................................................................... 7
5. FLOW DIAGRAMS ............................................................................................................. 10
6. PREPARATION FOR DEVELOPMENT OF PLOT PLAN.................................................. 12
1. INTRODUCTION
These guides have been compiled to assist the plant design engineer when plot plans
are to be developed either for actual jobs or estimates.
Do not consider that these guides are mandatory or assume that the contents can
influence any requirement laid down by the clients standards and layout procedures.
The clients procedures will always override these design guides, unless a mutual
agreement is obtained.
The important function of these guides is to aid in the preparation of a plot plan in the
quickest time possible.
Enclosed in these guides are some typical approaches on the preparation of plot plans,
these include step by step accounts of how a plant design engineer could approach
and develop a plot plan.
It is impossible to show every kind of unit in a refinery or chemical plant in these design
guides, but however, the enclosures will give basic information to give a plant design
engineer the initiative and confidence to tackle most requirements for plot plan
development.
2.1 SCALE
The scale of the proposed plot plan should be as large as the drawing sheet can
permit, and if necessary two or more drawing sheets may be used providing the match
lines are well defined. Do not risk illegibility, by using too small a scale.
2.3 ISSUE
After reviews have been made on the plot plan and or block model, the plant design
group should issue the proposed plot plan for approval to the client.
The block model is also used as an assistance for obtaining client approvals.
Compressors - size of base plate area and type of compressor i.e. centrifugal or
reciprocating, seal oil/lube oil console floor space.
Details of oily water separator.
Control building data.
Specialist equipment - de-salter, package units, centrifuges, conveyors, boilers,
deaerator, coalescers, dryers, cold boxes, (aluminium exchangers) etc.
Tower bottom tangent line minimum heights from grade. Drum heights from grade
whether to bottom of drum or to the bottom tangent line.
Critical elevation requirements for all equipment.
Relative data sheets on towers and drums, including diameter and Tan to Tan.
Exchanger tube lengths and diameters. Fixed tube-sheets.
Withdrawal of tube bundle requirements. Number of shells for each item.
Parallel or in series. Finned tube exchangers. Kettle or conventional type exchangers.
Vertical or horizontal position.
Rotating equipment floor space requirements.
All of the above basic information influences the plot plan layout.
It is sometimes necessary to consult the Mechanical group regarding air cooler lengths
and widths, as in many cases pipe racks are sized to suit widths and lengths of air
coolers.
Check with clients procedures as to permissible location of air coolers. If they are
placed above pipe racks certain conditions are required and reference to future lesson
3 will be required.
For pump base sizes, it is usual to assume certain pump sizes. The approximate
suction and discharge pipe sizes, if given, will automatically give a design engineer a
feel for the size using his past experience, otherwise reference to future lesson 4 will
be required.
Mechanical group should attempt to pass information to plant design on sizes, but it is
more important to know the type of pump, such as: side and side inlet and outlet,
multistage, reciprocating, centrifugal, vertical, rotary, etc.
Steam driven pumps should also be well defined and the pressure of steam required at
turbine given. This could be important to the design engineer, when considering utility
layout.
Battery limits with their co-ordinates are then defined on the proposed areas as in
Figure 1.
Existing pipe racks should then be added. These are normally found on the site plan,
but if they are not indicated the design engineer should check with Projects to define
incoming and outgoing pipe racks. In Figure 1 the existing pipe racks have been
shown. Any other existing conditions should be shown i.e. buildings etc.
North arrow and prevailing wind direction should be added. The plant boundary fence
and any other miscellaneous information such as an adjacent river should be added to
the plot plan as reference. The plant area should now be well defined with all known
outside conditions.
Finally the plant area should be cleared of all obstructions but should it necessitate
leaving an existing underground line the new plant will be designed with it remaining.
The plot plan is now ready for detailed investigation.
5. FLOW DIAGRAMS
The process flow diagram (Figure 2) should be made available for use in developing
the plot plan.
The first step would be to follow and familiarise the main flow patterns through the unit
with the process engineer and as a result there are several points which should be
taken into account and could affect layout of equipment, these typically would be:
The crude charge from storage to charge pumps GA-101, needs to be close to the
incoming line from battery limit.
Pumps should be located near the respective equipment to avoid excessive pressure
drop in suction lines.
The feed lines to heaters, will need manifold stations which split the line into several
manifolds depending on the number of passes in the heater, so it is recommended that
sufficient room should be allowed around the heater. Refer to Lesson 7
The transfer line from the heaters needs to be kept as short as possible and routed
without pockets. Flexibility should be taken into account at Plot Plan Stage.
Lines to and from strippers DA-102 and DA-103 and flare systems should be kept to a
minimum.
Bottoms line out of DA-101 needs investigation as to flexibility, as the temperature
would be on the high side. Also consider hot and cold conditions of spare pump.
The overhead line from DA-101 should be run without pockets to condenser EC-101,
and kept as direct as possible taking flexibility and growth of the tower into account.
The condensate line from condenser EC-101 to FA-101 again should be run without
pockets.
The off gas line from FA-101 to GB-101 should be kept short and also without pockets.
Many of the above statements will apply to most situations in Process Plant layouts
Figure 2