Dry Run #3 East Los Angeles High School #1 Scheduler: Karo Topchyan

Activity ID Activity Name Original Early Start Early Total


Finish Float 2010 2011 2012
Duration Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
Reno Competition - E.L.A.H.S. #1 578 25-May-10 17-Aug-12 0 17-Aug-12, Reno C

General Conditions 578 25-May-10 17-Aug-12 0 17-Aug-12, Genera

HPCC00010 Contract Award/Notice to Proceed #1 0 25-May-10 0Contract Award/Notice to Proceed #1


HPCC00020 Mobilization 20 25-May-10 22-Jun-10 0 Mobilization
HPCC00170 Notice to Proceed #2 0 19-Aug-10 0 Notice to Proceed #2
HPCC00110 Elevators DA Submittal 90 20-Aug-10 29-Dec-10 97 Elevators DA Submittal
HPCC00180 Start Mass Excavation Project 0 26-Oct-10 -42 Start Mass Excavation Project
HPCC00160 Elevators Delivery & Fab 70 30-Dec-10 06-Apr-11 97 Elevators Delivery & Fab
HPCC00030 Building #1 Struct. Steel Fab. 80 05-Jan-11 26-Apr-11 -1 Building #1 Struct. Steel Fab.
HPCC00070 Curtain Wall DA Submittal 90 19-Jan-11 25-May-11 0 Curtain Wall DA Submittal
HPCC00080 Fire Protection DA Submittal 90 07-Mar-11 08-Jul-11 230 Fire Protection DA Submittal
HPCC00040 Building #2 Struct. Steel Fab. 85 14-Mar-11 08-Jul-11 0 Building #2 Struct. Steel Fab.
HPCC00120 Curtain Wall Deli very & Fab 60 25-May-11 17-Aug-11 -43 Curtain Wall Deli very & Fab
HPCC00050 Building #3 Struct. Steel Fab. 75 11-Jul-11 21-Oct-11 37 Building #3 Struct. Steel Fab.
HPCC00130 Fire Protection Delivery & Fab 60 11-Jul-11 30-Sep-11 230 Fire Protection Delivery & Fab
HPCC00060 Building #4 Struct. Steel Fab. 85 25-Jul-11 18-Nov-11 0 Building #4 Struct. Steel Fab.
HPCC00090 Basketball Backstops DA Submittal 90 01-Aug-11 02-Dec-11 8 Basketball Backstops DA Submittal
HPCC00100 Telescoping Bleachers DA Submittal 90 03-Aug-11 07-Dec-11 1 Telescoping Bleachers DA Submittal
HPCC00200 Project Ready For Power Service 0 29-Nov-11 188 Project Ready For Power Service
HPCC00150 Telescoping Bleachers Delivery & Fab 120 08-Dec-11 23-May-12 0 Telescoping Bleachers Delivery
HPCC00140 Basketball Backstops Delivery & Fab 115 14-Dec-11 23-May-12 0 Basketball Backstops Delivery
HPCC00190 Start Fire Alarm Testing 0 07-Jun-12 51 Start Fire Alarm Testing
HPCC00220 Academic Areas Substantially Complete 0 08-Aug-12 0 Academic Areas Sub
HPCC00230 Inspection Completion 0 08-Aug-12 0 Inspection Completio
HPCC00240 Project Final Completion 0 17-Aug-12 0 Project Final Comp

Sitework 285 23-Jun-10 02-Aug-11 273 02-Aug-11, Sitework

HPCC01020 SWPPP Implementati on 4 23-Jun-10 28-Jun-10 554 SWPPP Implementati on


HPCC01100 Demo Existing Bldgs 14 19-Aug-10 08-Sep-10 -42 Demo Existing Bldgs
HPCC01110 Demo Existing Warehous e 10 19-Aug-10 01-Sep-10 -42 Demo Existing Warehous e
HPCC01120 Demo/Strip AC Pavement 10 25-Aug-10 08-Sep-10 -42 Demo/Strip AC Pavement
HPCC01030 Rough Grade Stakes 2 09-Sep-10 10-Sep-10 -42 Rough Grade Stakes
HPCC01040 Rough Grade Site 10 13-Sep-10 24-Sep-10 -42 Rough Grade Site
HPCC01050 Over-Excavate/Re-compaction Bldg#1 15 27-Sep-10 15-Oct-10 -42 Over-Excavate/Re-compaction Bldg#1
HPCC01090 Temporary Shoring 22 27-Sep-10 26-Oct-10 470 Temporary Shoring
HPCC01060 Over-Excavate/Re-compaction Bldg#2 15 28-Jan-11 17-Feb-11 0 Over-Excavate/Re-compaction Bldg#2
HPCC01080 Over-Excavate/Re-compaction Bldg#4 15 03-Jun-11 23-Jun-11 0 Over-Excavate/Re-compaction Bldg#4

HPCC01140 Demo Bldgs past Utah St. 10 04-Jul-11 15-Jul-11 187 Demo Bldgs past Utah St.
HPCC01070 Over-Excavate/Re-compaction Bldg#3 15 12-Jul-11 02-Aug-11 0 Over-Excavate/Re-compaction Bldg#3
HPCC01130 Site Punchlist 0 02-Aug-11 273 Site Punchlist

Actual Work Critical Remaining Work Summary Page 1 of 9 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Dry Run #3 East Los Angeles High School #1 Scheduler: Karo Topchyan
Activity ID Activity Name Original Early Start Early Total
Finish Float 2010 2011 2012
Duration Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
B-Permit Off-Site Utilities 193 14-Jul-11 10-Apr-12 93 10-Apr-12, B-Permit Off-Site U tilities

HPCC02030 Off-Site Improvements 193 14-Jul-11 10-Apr-12 93 Off-Site Improvements


HPCC02010 60" Storm Drain 98 18-Jul-11 30-Nov-11 187 60" Storm Drain

HPCC02020 Off-Site Inspection Complete 0 10-Apr-12 93 Off-Site Inspection Complete

Building #1 338 18-Oct-10 06-Feb-12 139 06-Feb-12, Building #1

General Conditions 0 30-Jan-12 30-Jan-12 144 30-Jan-12, General Conditions


HPCC10010 Inspection Complete Bldg #1 0 30-Jan-12 144 Inspection Complete Bldg #1
HPCC10020 Energize Equipment Bldg #1 0 30-Jan-12 144 Energize Equipment Bldg #1
Below 1st Floor 128 18-Oct-10 18-Apr-11 -1 18-Apr-11, Below 1st Floor
HPCC11010 Sub. Parking Struct. Excavation 6 18-Oct-10 25-Oct-10 -42 Sub. Parking Struct. Excavation
HPCC11080 Install Moisture Barrier 4 26-Oct-10 29-Oct-10 -1 Install Moisture Barrier
HPCC11020 UG Sewer Main 6 01-Nov-10 08-Nov-10 -1 UG Sewer Main
HPCC11030 UG Storm Main 6 01-Nov-10 08-Nov-10 -1 UG Storm Main
HPCC11040 UG Water Main 6 01-Nov-10 08-Nov-10 -1 UG Water Main
HPCC11050 UG Fire Main/Devices 6 09-Nov-10 16-Nov-10 -1 UG Fire Main/Devices
HPCC11060 UG Electrical/Trans 6 17-Nov-10 24-Nov-10 -1 UG Electrical/Trans
HPCC11070 Excavate Elevator Pittslab 3 29-Nov-10 01-Dec-10 -1 Excavate Elevator Pittslab
HPCC11090 Form/Rebar/Pour Elevator Pittslab 4 02-Dec-10 07-Dec-10 -1 Form/Rebar/Pour Elevator Pittslab
HPCC11100 Form/Rebar/Pour Footings 11 08-Dec-10 22-Dec-10 -1 Form/Rebar/Pour Footings
HPCC11190 Cure Elevator Pittslab 20 08-Dec-10 05-Jan-11 19 Cure Elevator Pittslab
HPCC11110 Form/Rebar/Pour Parking Struct. Walls 11 17-Dec-10 03-Jan-11 -1 Form/Rebar/Pour Parking Struct. Walls
HPCC11120 Cure Footings/Walls 20 04-Jan-11 31-Jan-11 -1 Cure Footings/Walls
HPCC11200 Strip Elevator Pittslab 2 06-Jan-11 07-Jan-11 19 Strip Elevator Pittslab
HPCC11130 Strip Footings/Wall s 4 01-Feb-11 04-Feb-11 -1 Strip Footings/Wall s
HPCC11140 Install Steel Columns 12 07-Feb-11 22-Feb-11 -1 Install Steel Columns
HPCC11150 Build Stairwells 7 23-Feb-11 03-Mar-11 -1 Build Stairwells
HPCC11160 Form/Rebar/Pour Sub. Parking Slab 12 04-Mar-11 21-Mar-11 -1 Form/Rebar/Pour Sub. Parking Slab
HPCC11210 Cure Sub. Parking Slab 21 15-Mar-11 12-Apr-11 -1 Cure Sub. Parking Slab
HPCC11170 Strip Slabs 3 13-Apr-11 15-Apr-11 -1 Strip Slabs
HPCC11180 Post Tension Slabs 1 18-Apr-11 18-Apr-11 -1 Post Tension Slabs
First Floor 177 19-Apr-11 21-Dec-11 172 21-Dec-11, First Floor
HPCC12030 Install Concrete Metal Decking 5 19-Apr-11 25-Apr-11 344 Install Concrete Metal Decking
HPCC12040 MEP Stubouts 3 19-Apr-11 21-Apr-11 -1 MEP Stubouts
HPCC12010 Start Steel Erection Bldg #1 0 26-Apr-11 0 Start Steel Erection Bldg #1
HPCC12050 Erect Structural Steel 12 26-Apr-11 11-May-11 0 Erect Structural Steel
HPCC12060 Plumb/Line Structural Steel 3 10-May-11 12-May-11 0 Plumb/Line Structural Steel
HPCC12070 Weld/Bol t Structural Steel 7 13-May-11 23-May-11 0 Weld/Bol t Structural Steel
HPCC12080 Pour Concrete Decks 3 24-May-11 26-May-11 -23 Pour Concrete Decks
HPCC12090 Cure Concrete Decks 21 27-May-11 24-Jun-11 -23 Cure Concrete Decks
HPCC12100 Exterior Wall Framing 14 27-Jun-11 14-Jul-11 -23 Exterior Wall Framing

Actual Work Critical Remaining Work Summary Page 2 of 9 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Dry Run #3 East Los Angeles High School #1 Scheduler: Karo Topchyan
Activity ID Activity Name Original Early Start Early Total
Finish Float 2010 2011 2012
Duration Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
HPCC12110 Seal Concrete Decks 5 15-Jul-11 21-Jul-11 19 Seal Concrete Decks
HPCC12120 Install Bldg #1 Curtain Wall s 7 17-Aug-11 26-Aug-11 0 Install Bldg #1 Curtain Wall s
HPCC12250 Structure Complete Bldg #1 0 22-Aug-11 -23 Structure Complete Bldg #1
HPCC12130 Rough MEP Admin/Lunch Shelter 4 26-Aug-11 01-Sep-11 0 Rough MEP Admin/Lunch Shelter
HPCC12140 Install Elevators 7 01-Sep-11 12-Sep-11 36 Install Elevators
HPCC12150 Install/Layout Interior Walls 14 01-Sep-11 21-Sep-11 0 Install/Layout Interior Walls
HPCC12160 Install Food Service MEP 4 21-Sep-11 27-Sep-11 25 Install Food Service MEP
HPCC12170 Start Interior Drywall Bldg #1 0 21-Sep-11 0 Start Interior Drywall Bldg #1
HPCC12180 Install Insulation 14 21-Sep-11 11-Oct-11 0 Install Insulation
HPCC12260 Install Drywall 15 11-Oct-11 01-Nov-11 0 Install Drywall
HPCC12190 Tape/Finish Drywall 14 01-Nov-11 21-Nov-11 0 Tape/Finish Drywall
HPCC12200 Install Doors & Hardware 10 21-Nov-11 05-Dec-11 0 Install Doors & Hardware
HPCC12240 Restrooms Fixtures/Finishes 7 21-Nov-11 30-Nov-11 0 Restrooms Fixtures/Finishes
HPCC12220 Interior Drywall Complete Bldg #1 0 30-Nov-11 0 Interior Drywall Complete Bldg #1
HPCC12210 Install Windows 12 05-Dec-11 21-Dec-11 0 Install Windows
HPCC12230 Food Service/Finish Carpentry 5 05-Dec-11 12-Dec-11 179 Food Service/Finish Carpentry
Roof 35 15-Jul-11 01-Sep-11 251 01-Sep-11, Roof
HPCC13010 Install Roof Curbs 8 15-Jul-11 26-Jul-11 -23 Install Roof Curbs
HPCC13020 Install Roof Metal Decking/Rigid Insulation 10 27-Jul-11 09-Aug-11 -23 Install Roof Metal Decking/Rigid Insulation
HPCC13030 Install Roofing Membrane 9 10-Aug-11 22-Aug-11 -23 Install Roofing Membrane
HPCC13040 Finish Roofing Mechanical 4 23-Aug-11 26-Aug-11 251 Finish Roofing Mechanical
HPCC13050 Finish Build-Up Roof w/Cap Sheet & Reflective Coating
4 29-Aug-11 01-Sep-11 251 Finish Build-Up Roof w/Cap Sheet & Reflective Coating
North Elevation 33 21-Dec-11 06-Feb-12 139 06-Feb-12, North Elevation
HPCC14010 Start Exterior Plaster Bldg #1 0 21-Dec-11 0 Start Exterior Plaster Bldg #1
HPCC14020 Install Exterior Doors & Hardware 4 21-Dec-11 27-Dec-11 168 Install Exterior Doors & Hardware
HPCC14030 Install Overhead Roll-up Door 1 21-Dec-11 22-Dec-11 171 Install Overhead Roll-up Door
HPCC14040 Exterior Plaster Scratch Coat 10 21-Dec-11 04-Jan-12 139 Exterior Plaster Scratch Coat
HPCC14050 Exterior Plaster Brown Coat & Cure 14 04-Jan-12 24-Jan-12 139 Exterior Plaster Brown Coat & Cure
HPCC14060 Exterior Plaster Finish Coat 7 24-Jan-12 02-Feb-12 139 Exterior Plaster Finish Coat
HPCC14310 Install Painted Metal Sunshade Panel 2 02-Feb-12 06-Feb-12 139 Install Painted Metal Sunshade Panel
West Elevation 28 21-Dec-11 30-Jan-12 144 30-Jan-12, West El evation
HPCC15010 Install Exterior Doors & Hardware 1 21-Dec-11 22-Dec-11 171 Install Exterior Doors & Hardware
HPCC15130 Exterior Plaster Scratch Coat 9 21-Dec-11 03-Jan-12 144 Exterior Plaster Scratch Coat
HPCC15140 Exterior Plaster Brown Coat & Cure 14 03-Jan-12 23-Jan-12 144 Exterior Plaster Brown Coat & Cure
HPCC15150 Exterior Plaster Finish Coat 5 23-Jan-12 30-Jan-12 144 Exterior Plaster Finish Coat
HPCC15160 Exterior Plaster Complete Bldg #1 0 30-Jan-12 144 Exterior Plaster Complete Bldg #1

Building #2 275 04-Mar-11 22-Mar-12 106 22-Mar-12, Building #2

General Conditions 0 05-Mar-12 05-Mar-12 119 05-Mar-12, General Conditions


HPCC20010 Inspection Complete Bldg #2 0 05-Mar-12 119 Inspection Complete Bldg #2
HPCC20020 Energize Equipment Bldg #2 0 05-Mar-12 119 Energize Equipment Bldg #2

Actual Work Critical Remaining Work Summary Page 3 of 9 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Dry Run #3 East Los Angeles High School #1 Scheduler: Karo Topchyan
Activity ID Activity Name Original Early Start Early Total
Finish Float 2010 2011 2012
Duration Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
Below 1st Floor 92 04-Mar-11 11-Jul-11 2 11-Jul-11, Below 1s t Floor
HPCC21010 UG Sewer Main 5 04-Mar-11 10-Mar-11 2 UG Sewer Main
HPCC21020 UG Storm Drain 5 11-Mar-11 17-Mar-11 2 UG Storm Drain
HPCC21030 UG Water Main 5 18-Mar-11 24-Mar-11 2 UG Water Main
HPCC21040 UG Fire Main/Devices 5 25-Mar-11 31-Mar-11 2 UG Fire Main/Devices
HPCC21050 UG Electrical/Trans 5 01-Apr-11 07-Apr-11 2 UG Electrical/Trans
HPCC21060 Excavate Elevator Pitts 3 08-Apr-11 12-Apr-11 2 Excavate Elevator Pitts
HPCC21070 Form/Rebar/Pour Pittslab 2 13-Apr-11 14-Apr-11 2 Form/Rebar/Pour Pittslab
HPCC21080 Form/Rebar/Pour Footings 7 15-Apr-11 25-Apr-11 2 Form/Rebar/Pour Footings
HPCC21090 Cure Pitts/Footings 21 26-Apr-11 24-May-11 2 Cure Pitts/Footings
HPCC21100 Strip Pitts/Footings 3 25-May-11 27-May-11 2 Strip Pitts/Footings
HPCC21110 Form/Rebar/Pour SOG 10 30-May-11 10-Jun-11 2 Form/Rebar/Pour SOG
HPCC21120 Cure Slab on Grade 21 13-Jun-11 11-Jul-11 2 Cure Slab on Grade
First Floor 187 06-Jul-11 22-Mar-12 106 22-Mar-12, First Floor
HPCC22020 MEP Stubouts 3 06-Jul-11 08-Jul-11 232 MEP Stubouts
HPCC22030 Erect Structural Steel 12 12-Jul-11 27-Jul-11 0 Erect Structural Steel
HPCC22010 Start Steel Erection Bldg #2 0 12-Jul-11 288 Start Steel Erection Bldg #2
HPCC22040 Plumb/Line Structural Steel 3 28-Jul-11 01-Aug-11 -7 Plumb/Line Structural Steel
HPCC22050 Weld/Bol t Structural Steel 6 02-Aug-11 09-Aug-11 -7 Weld/Bol t Structural Steel
HPCC22060 Exterior Wall Framing 18 10-Aug-11 02-Sep-11 185 Exterior Wall Framing
HPCC22070 Install Bldg #2 Curtain Wall 1st Flr 7 05-Sep-11 13-Sep-11 185 Install Bldg #2 Curtain Wall 1st Flr
HPCC22080 Rough MEP 6 14-Sep-11 21-Sep-11 185 Rough MEP
HPCC22090 Install Elevators 12 22-Sep-11 07-Oct-11 185 Install Elevators
HPCC22100 Install/Layout Interior Walls 18 10-Oct-11 02-Nov-11 185 Install/Layout Interior Walls
HPCC22110 Start Interior Drywall Bldg #2 0 03-Nov-11 185 Start Interior Drywall Bldg #2
HPCC22120 Install Insulation 8 03-Nov-11 14-Nov-11 185 Install Insulation
HPCC22130 Tape/Finish Drywall 7 15-Nov-11 23-Nov-11 185 Tape/Finish Drywall
HPCC22190 Install Ceiling System 14 15-Nov-11 02-Dec-11 185 Install Ceiling System
HPCC22140 Install Doors & Hardware 3 24-Nov-11 28-Nov-11 189 Install Doors & Hardware
HPCC22160 Restroom Fixtures/Finishes 7 24-Nov-11 02-Dec-11 185 Restroom Fixtures/Finishes
HPCC22150 Install Windows 7 24-Nov-11 02-Dec-11 185 Install Windows
HPCC22180 Finish MEP 1st Floor 5 24-Nov-11 30-Nov-11 187 Finish MEP 1st Floor
HPCC22170 Structure Complete Bldg #1 0 22-Mar-12 106 Structure Complete Bldg #1
Second Floor 110 10-Aug-11 10-Jan-12 119 10-Jan-12, Second Floor
HPCC23010 Install Concrete Metal Decking 6 10-Aug-11 17-Aug-11 -7 Install Concrete Metal Decking
HPCC23020 MEP Stubouts 2 18-Aug-11 19-Aug-11 -7 MEP Stubouts
HPCC23030 Pour Concrete Decking 7 22-Aug-11 30-Aug-11 -7 Pour Concrete Decking
HPCC23040 Cure Concrete Decking 21 31-Aug-11 28-Sep-11 -7 Cure Concrete Decking
HPCC23050 Exterior Wall Framing 8 29-Sep-11 10-Oct-11 119 Exterior Wall Framing
HPCC23060 Seal Concrete Deck 5 11-Oct-11 17-Oct-11 119 Seal Concrete Deck

Actual Work Critical Remaining Work Summary Page 4 of 9 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Dry Run #3 East Los Angeles High School #1 Scheduler: Karo Topchyan
Activity ID Activity Name Original Early Start Early Total
Finish Float 2010 2011 2012
Duration Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
HPCC23070 Install Bldg #2 Curtain Wall 2nd fl r 4 18-Oct-11 21-Oct-11 119 Install Bldg #2 Curtain Wall 2nd fl r
HPCC23080 Rough MEP 2nd F loor 10 24-Oct-11 04-Nov-11 119 Rough MEP 2nd F loor
HPCC23090 Install/Layout Interior Walls 9 07-Nov-11 17-Nov-11 119 Install/Layout Interior Walls
HPCC23100 Finish MEP 2nd Floor 7 18-Nov-11 28-Nov-11 119 Finish MEP 2nd Floor
HPCC23110 Install Insulation 9 29-Nov-11 09-Dec-11 119 Install Insulation
HPCC23120 Tape/Finish Drywall 7 12-Dec-11 20-Dec-11 119 Tape/Finish Drywall
HPCC23130 Interior Drywall Complete Bldg #2 0 20-Dec-11 119 Interior Drywall Complete Bldg #2
HPCC23140 Restroom Fixtures/Furnishes 5 21-Dec-11 27-Dec-11 119 Restroom Fixtures/Furnishes
HPCC23150 Install Doors & Hardware 3 28-Dec-11 30-Dec-11 119 Install Doors & Hardware
HPCC23160 Install Windows 7 02-Jan-12 10-Jan-12 119 Install Windows
Roof 32 18-Oct-11 30-Nov-11 187 30-Nov-11, Roof
HPCC24020 Install Roof Curbs 7 18-Oct-11 26-Oct-11 187 Install Roof Curbs
HPCC24030 Install Roof Metal Decking/Rigid Insulation 9 27-Oct-11 08-Nov-11 187 Install Roof Metal Decking/Rigid Insulation
HPCC24040 Install Roofing Membrane 8 09-Nov-11 18-Nov-11 187 Install Roofing Membrane
HPCC24050 Finish Roofing Mechanical 4 21-Nov-11 24-Nov-11 187 Finish Roofing Mechanical
HPCC24060 Finish Build-Up Roof w/Cap Sheet & Reflective Coating
4 25-Nov-11 30-Nov-11 187 Finish Build-Up Roof w/Cap Sheet & Reflective Coating
North Elevation 39 11-Jan-12 05-Mar-12 119 05-Mar-12, North Elevation
HPCC25070 Start Exterior Plaster Bldg #2 0 11-Jan-12 119 Start Exterior Plaster Bldg #2
HPCC25080 Install Exterior Doors & Hardware 3 11-Jan-12 13-Jan-12 119 Install Exterior Doors & Hardware
HPCC25090 Install Metal Security Screen 3 16-Jan-12 18-Jan-12 119 Install Metal Security Screen
HPCC25100 Exterior Plaster Scratch Coat 12 19-Jan-12 03-Feb-12 119 Exterior Plaster Scratch Coat
HPCC25110 Exterior Plaster Brown Coat & Cure 14 06-Feb-12 23-Feb-12 119 Exterior Plaster Brown Coat & Cure
HPCC25120 Exterior Plaster Finish Coat 7 24-Feb-12 05-Mar-12 119 Exterior Plaster Finish Coat
West Elevation 39 11-Jan-12 05-Mar-12 119 05-Mar-12, West Elev ation
HPCC26140 Install Exterior Doors & Hardware 3 11-Jan-12 13-Jan-12 119 Install Exterior Doors & Hardware
HPCC26150 Install Wrought Iron Gate 3 16-Jan-12 18-Jan-12 119 Install Wrought Iron Gate
HPCC26160 Exterior Plaster Scratch Coat 12 19-Jan-12 03-Feb-12 119 Exterior Plaster Scratch Coat
HPCC26170 Exterior Plaster Brown Coat 14 06-Feb-12 23-Feb-12 119 Exterior Plaster Brown Coat
HPCC26180 Exterior Plaster Finish Coat 7 24-Feb-12 05-Mar-12 119 Exterior Plaster Finish Coat
HPCC26130 Exterior Plaster Complete Bldg #2 0 05-Mar-12 119 Exterior Plaster Complete Bldg #2

Building #3 240 10-Aug-11 10-Jul-12 28 10-Jul-12, Building #3

General Conditions 0 10-Jul-12 10-Jul-12 28 10-Jul-12, General Cond


HPCC30010 Inspection Complete Bldg #3 0 10-Jul-12 0 Inspection Complete Bld
HPCC30020 Energize Equipment Bldg #3 0 10-Jul-12 28 Energize Equipment Bldg
Below 1st Floor 92 10-Aug-11 15-Dec-11 -6 15-Dec-11, Below 1st Floor
HPCC31140 UG Sewer Main 5 10-Aug-11 16-Aug-11 -6 UG Sewer Main
HPCC31150 UG Storm Drain 5 17-Aug-11 23-Aug-11 -6 UG Storm Drain
HPCC31160 UG Water Main 5 24-Aug-11 30-Aug-11 -6 UG Water Main
HPCC31170 UG Fire Main/Devices 5 31-Aug-11 06-Sep-11 -6 UG Fire Main/Devices
HPCC31180 UG Electrical/Trans 5 07-Sep-11 13-Sep-11 -6 UG Electrical/Trans

Actual Work Critical Remaining Work Summary Page 5 of 9 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Dry Run #3 East Los Angeles High School #1 Scheduler: Karo Topchyan
Activity ID Activity Name Original Early Start Early Total
Finish Float 2010 2011 2012
Duration Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
HPCC31190 Excavate Elevator Pitts 3 14-Sep-11 16-Sep-11 -6 Excavate Elevator Pitts
HPCC31200 Form/Rebar/Pour Pittslab 2 19-Sep-11 20-Sep-11 -6 Form/Rebar/Pour Pittslab
HPCC31210 Form/Rebar/Pour Footings 7 21-Sep-11 29-Sep-11 -6 Form/Rebar/Pour Footings
HPCC31220 Cure Pitts/Footings 21 30-Sep-11 28-Oct-11 -6 Cure Pitts/Footings
HPCC31230 Strip Pitts/Footings 3 31-Oct-11 02-Nov-11 -6 Strip Pitts/Footings
HPCC31240 Form/Rebar/Pour SOG 10 03-Nov-11 16-Nov-11 -6 Form/Rebar/Pour SOG
HPCC31250 Cure Slab on Grade 21 17-Nov-11 15-Dec-11 -6 Cure Slab on Grade
First Floor 136 13-Dec-11 20-Jun-12 42 20-Jun-12, First Floor
HPCC32030 Erect Structural Steel 12 13-Dec-11 29-Dec-11 0 Erect Structural Steel
HPCC32010 Start Steel Erection Bldg #3 0 16-Dec-11 -6 Start Steel Erection Bldg #3
HPCC32020 MEP Stubouts 3 16-Dec-11 20-Dec-11 -6 MEP Stubouts
HPCC32040 Plumb/Line Structural Steel 5 29-Dec-11 05-Jan-12 0 Plumb/Line Structural Steel
HPCC32050 Weld/Bol t Structural Steel 5 05-Jan-12 12-Jan-12 0 Weld/Bol t Structural Steel
HPCC32060 Exterior Wall Framing 14 12-Jan-12 01-Feb-12 0 Exterior Wall Framing
HPCC32070 Install Bldg #3 Curtain Wall 6 01-Feb-12 09-Feb-12 67 Install Bldg #3 Curtain Wall
HPCC32080 Rough MEP 5 09-Feb-12 16-Feb-12 67 Rough MEP
HPCC32090 Install Elevators 10 16-Feb-12 01-Mar-12 67 Install Elevators
HPCC32100 Install/Layout Interior Walls 18 01-Mar-12 27-Mar-12 67 Install/Layout Interior Walls
HPCC32110 Start Interior Drywall Bldg #3 0 27-Mar-12 67 Start Interior Drywall Bldg #3
HPCC32120 Install Insulation 10 27-Mar-12 10-Apr-12 67 Install Insulation
HPCC32130 Restroom Fixtures/Finishes 6 10-Apr-12 18-Apr-12 67 Restroom Fixtures/Finishes
HPCC32140 Tape/Finish Drywall 10 18-Apr-12 02-May-12 67 Tape/Finish Drywall
HPCC32150 Install Doors & Hardware 3 02-May-12 07-May-12 67 Install Doors & Hardware
HPCC32180 Finish MEP 1st Floor 7 02-May-12 11-May-12 70 Finish MEP 1st Floor
HPCC32160 Install Windows 7 07-May-12 16-May-12 67 Install Windows
HPCC32170 Structure Complete Bldg #3 0 20-Jun-12 42 Structure Complete Bldg #3
Second Floor 87 01-Feb-12 01-Jun-12 55 01-Jun-12, Second Floor
HPCC33010 Install Concrete Metal Decking 6 01-Feb-12 09-Feb-12 0 Install Concrete Metal Decking
HPCC33020 MEP Stubouts 2 09-Feb-12 13-Feb-12 0 MEP Stubouts
HPCC33030 Pour Concrete Decking 7 13-Feb-12 22-Feb-12 0 Pour Concrete Decking
HPCC33040 Cure Concrete Decking 21 22-Feb-12 22-Mar-12 0 Cure Concrete Decking
HPCC33050 Exterior Wall Framing 8 22-Mar-12 03-Apr-12 0 Exterior Wall Framing
HPCC33060 Install Bldg #3 Curtain Wall 2nd fl r 5 03-Apr-12 10-Apr-12 0 Install Bldg #3 Curtain Wall 2nd fl r
HPCC33070 Rough MEP 4 10-Apr-12 16-Apr-12 0 Rough MEP
HPCC33080 Install/Layout Interior Walls 10 16-Apr-12 30-Apr-12 0 Install/Layout Interior Walls
HPCC33090 Install Insulation 9 30-Apr-12 11-May-12 0 Install Insulation
HPCC33100 Tape/Finish Drywall 7 11-May-12 22-May-12 0 Tape/Finish Drywall
HPCC33110 Restroom Fixtures/Furnishes 5 22-May-12 29-May-12 55 Restroom Fixtures/Furnishes
HPCC33140 Finish MEP 2nd Floor 7 22-May-12 31-May-12 56 Finish MEP 2nd Floor
HPCC33150 Install Windows 7 22-May-12 31-May-12 0 Install Windows

Actual Work Critical Remaining Work Summary Page 6 of 9 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Dry Run #3 East Los Angeles High School #1 Scheduler: Karo Topchyan
Activity ID Activity Name Original Early Start Early Total
Finish Float 2010 2011 2012
Duration Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
HPCC33160 Install Ceiling System 7 22-May-12 31-May-12 37 Install Ceiling System
HPCC33120 Interior Drywall Complete Bldg #3 0 29-May-12 55 Interior Drywall Complete Bldg
HPCC33130 Install Doors & Hardware 3 29-May-12 01-Jun-12 55 Install Doors & Hardware
Roof 19 31-May-12 27-Jun-12 37 27-Jun-12, Roof
HPCC34020 Install Roof Curbs 5 31-May-12 07-Jun-12 37 Install Roof Curbs
HPCC34030 Install Roof Metal Decking/Rigid Insulation 4 07-Jun-12 13-Jun-12 37 Install Roof Metal Decking/R
HPCC34040 Install Roofing Membrane 5 13-Jun-12 20-Jun-12 37 Install Roofing Membrane
HPCC34050 Finish Roofing Mechanical 3 20-Jun-12 25-Jun-12 37 Finish Roofing Mechanical
HPCC34060 Finish Build-Up Roof w/Cap Sheet & Reflective Coating
2 25-Jun-12 27-Jun-12 37 Finish Build-Up Roof w/Ca
North Elevation 28 31-May-12 10-Jul-12 28 10-Jul-12, North Elevatio
HPCC35190 Start Exterior Plaster Bldg #3 0 31-May-12 0 Start Exterior Plaster Bldg #3
HPCC35200 Install Exterior Doors & Hardware 2 31-May-12 04-Jun-12 54 Install Exterior Doors & Hardw
HPCC35210 Install Metal Security Screen 2 31-May-12 04-Jun-12 54 Install Metal Security Screen
HPCC35220 Exterior Plaster Scratch Coat 7 31-May-12 11-Jun-12 28 Exterior Plaster Scratch Coa
HPCC35230 Exterior Plaster Brown Coat 14 11-Jun-12 29-Jun-12 28 Exterior Plaster Brown Coa
HPCC35240 Exterior Plaster Finish Coat 7 29-Jun-12 10-Jul-12 28 Exterior Plaster Finish C
West Elevation 28 31-May-12 10-Jul-12 28 10-Jul-12, West Elevatio
HPCC36260 Install Exterior Doors & Hardware 2 31-May-12 04-Jun-12 54 Install Exterior Doors & Hardw
HPCC36270 Install Kalwall Panels & Painted Corrugated Metal
2 31-May-12 04-Jun-12 54 Install Kalwall Panels & Painte
HPCC36280 Exterior Plaster Scratch Coat 7 31-May-12 11-Jun-12 0 Exterior Plaster Scratch Coa
HPCC36290 Exterior Plaster Brown Coat 14 11-Jun-12 29-Jun-12 0 Exterior Plaster Brown Coa
HPCC36300 Exterior Plaster Finish Coat 7 29-Jun-12 10-Jul-12 0 Exterior Plaster Finish C
HPCC36250 Exterior Plaster Complete Bldg #3 0 10-Jul-12 0 Exterior Plaster Complet

Building #4 235 12-Jul-11 04-Jun-12 54 04-Jun-12, Building #4

General Conditions 0 04-Jun-12 04-Jun-12 54 04-Jun-12, General Condition


HPCC40050 Inspection Complete Bldg #4 0 04-Jun-12 54 Inspection Complete Bldg #4
HPCC40060 Energize Equipment Bldg #4 0 04-Jun-12 54 Energize Equipment Bldg #4
Below 1st Floor 92 12-Jul-11 16-Nov-11 2 16-Nov-11, Below 1st Floor
HPCC41130 UG Sewer Main 5 12-Jul-11 18-Jul-11 2 UG Sewer Main
HPCC41140 UG Storm Drain 5 19-Jul-11 25-Jul-11 2 UG Storm Drain
HPCC41150 UG Water Main 5 26-Jul-11 01-Aug-11 2 UG Water Main
HPCC41160 UG Fire Main/Devices 5 02-Aug-11 08-Aug-11 2 UG Fire Main/Devices
HPCC41170 UG Electrical/Trans 5 09-Aug-11 15-Aug-11 2 UG Electrical/Trans
HPCC41180 Excavate Elevator Pitts 3 16-Aug-11 18-Aug-11 2 Excavate Elevator Pitts
HPCC41190 Form/Rebar/Pour Pittslab 2 19-Aug-11 22-Aug-11 2 Form/Rebar/Pour Pittslab
HPCC41200 Form/Rebar/Pour Footings 7 23-Aug-11 31-Aug-11 2 Form/Rebar/Pour Footings
HPCC41210 Cure Pitts/Footings 21 01-Sep-11 29-Sep-11 2 Cure Pitts/Footings
HPCC41220 Strip Pitts/Footings 3 30-Sep-11 04-Oct-11 2 Strip Pitts/Footings
HPCC41230 Form/Rebar/Pour SOG 10 05-Oct-11 18-Oct-11 2 Form/Rebar/Pour SOG
HPCC41240 Cure Slab on Grade 21 19-Oct-11 16-Nov-11 2 Cure Slab on Grade

Actual Work Critical Remaining Work Summary Page 7 of 9 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Dry Run #3 East Los Angeles High School #1 Scheduler: Karo Topchyan
Activity ID Activity Name Original Early Start Early Total
Finish Float 2010 2011 2012
Duration Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
First Floor 139 17-Nov-11 29-May-12 58 29-May-12, First Floor
HPCC42190 MEP Stubouts 3 17-Nov-11 21-Nov-11 2 MEP Stubouts
HPCC42180 Start Steel Erection Bldg #4 0 21-Nov-11 0 Start Steel Erection Bldg #4
HPCC42200 Erect Structural Steel 14 21-Nov-11 08-Dec-11 0 Erect Structural Steel
HPCC42210 Plumb/Line Structural Steel 3 09-Dec-11 13-Dec-11 -2 Plumb/Line Structural Steel
HPCC42220 Weld/Bol t Structural Steel 7 14-Dec-11 22-Dec-11 -2 Weld/Bol t Structural Steel
HPCC42230 Exterior Wall Framing 18 23-Dec-11 17-Jan-12 87 Exterior Wall Framing
HPCC42240 Install Bldg #4 Curtain Wall 1st Flr 7 18-Jan-12 26-Jan-12 87 Install Bldg #4 Curtain Wall 1st Flr
HPCC42250 Rough MEP 6 27-Jan-12 03-Feb-12 87 Rough MEP
HPCC42260 Install Elevators 12 06-Feb-12 21-Feb-12 87 Install Elevators
HPCC42270 Install/Layout Interior Walls 18 22-Feb-12 16-Mar-12 87 Install/Layout Interior Walls
HPCC42280 Start Interior Drywall Bldg #4 0 19-Mar-12 87 Start Interior Drywall Bldg #4
HPCC42290 Install Insulation 8 19-Mar-12 28-Mar-12 87 Install Insulation
HPCC42310 Structure Complete Bldg #4 0 22-Mar-12 106 Structure Complete Bldg #4
HPCC42300 Tape/Finish Drywall 7 29-Mar-12 06-Apr-12 87 Tape/Finish Drywall
HPCC42380 Finish MEP 1st Floor 5 02-Apr-12 06-Apr-12 95 Finish MEP 1st Floor
HPCC42390 Install Ceiling System 7 02-Apr-12 10-Apr-12 93 Install Ceiling System
HPCC42320 Install Doors & Hardware 3 09-Apr-12 11-Apr-12 92 Install Doors & Hardware
HPCC42330 Restroom Fixtures/Finishes 7 09-Apr-12 17-Apr-12 88 Restroom Fixtures/Finishes
HPCC42340 Install Windows 7 09-Apr-12 17-Apr-12 88 Install Windows
HPCC42350 Install Gym Wood F looring 2 09-Apr-12 10-Apr-12 87 Install Gym Wood F looring
HPCC42360 Install Basketball Backstops 2 21-May-12 23-May-12 58 Install Basketball Backstops
HPCC42370 Install Telescoping Bleac hers 4 23-May-12 29-May-12 58 Install Telescoping Bleac hers
Second Floor 86 23-Dec-11 20-Apr-12 47 20-Apr-12, Second Floor
HPCC43170 Install Concrete Metal Decking 6 23-Dec-11 30-Dec-11 47 Install Concrete Metal Decking
HPCC43180 MEP Stubouts 2 02-Jan-12 03-Jan-12 47 MEP Stubouts
HPCC43190 Pour Concrete Decking 4 04-Jan-12 09-Jan-12 47 Pour Concrete Decking
HPCC43200 Cure Concrete Decking 21 10-Jan-12 07-Feb-12 47 Cure Concrete Decking
HPCC43210 Exterior Wall Framing 5 08-Feb-12 14-Feb-12 47 Exterior Wall Framing
HPCC43220 Seal Concrete Deck 3 15-Feb-12 17-Feb-12 47 Seal Concrete Deck
HPCC43230 Install Bldg #4 Curtain Wall 2nd fl r 1 20-Feb-12 20-Feb-12 47 Install Bldg #4 Curtain Wall 2nd fl r
HPCC43240 Rough MEP 2nd F loor 7 21-Feb-12 29-Feb-12 47 Rough MEP 2nd Floor
HPCC43250 Install/Layout Interior Walls 5 01-Mar-12 07-Mar-12 47 Install/Layout Interior Walls
HPCC43260 Finish MEP 2nd Floor 5 08-Mar-12 14-Mar-12 47 Finish MEP 2nd Floor
HPCC43270 Install Insulation 7 15-Mar-12 23-Mar-12 47 Install Insulation
HPCC43280 Tape/Finish Drywall 5 26-Mar-12 30-Mar-12 47 Tape/Finish Drywall
HPCC43290 Interior Drywall Complete Bldg #4 0 30-Mar-12 47 Interior Drywall Complete Bldg #4
HPCC43300 Restroom Fixtures/Furnishes 5 02-Apr-12 06-Apr-12 47 Restroom Fixtures/Furnishes
HPCC43310 Install Doors & Hardware 3 09-Apr-12 11-Apr-12 47 Install Doors & Hardware
HPCC43320 Install Windows 7 12-Apr-12 20-Apr-12 47 Install Windows

Actual Work Critical Remaining Work Summary Page 8 of 9 TASK filter: All Activities

Remaining Work Milestone © Primavera Systems, Inc.


Dry Run #3 East Los Angeles High School #1 Scheduler: Karo Topchyan
Activity ID Activity Name Original Early Start Early Total
Finish Float 2010 2011 2012
Duration Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
Roof 32 20-Feb-12 03-Apr-12 98 03-Apr-12, Roof
HPCC44070 Install Roof Curbs 7 20-Feb-12 28-Feb-12 98 Install Roof Curbs
HPCC44080 Install Roof Metal Decking/Rigid Insulation 9 29-Feb-12 12-Mar-12 98 Install Roof Metal Decking/Rigid Insulatio
HPCC44090 Install Roofing Membrane 8 13-Mar-12 22-Mar-12 98 Install Roofing Membrane
HPCC44100 Finish Roofing Mechanical 4 23-Mar-12 28-Mar-12 98 Finish Roofing Mechanical
HPCC44110 Finish Build-Up Roof w/Cap Sheet & Reflective Coating
4 29-Mar-12 03-Apr-12 98 Finish Build-Up Roof w/Cap Sheet & R
North Elevation 31 23-Apr-12 04-Jun-12 54 04-Jun-12, North Elevation
HPCC45070 Start Exterior Plaster Bldg #4 0 23-Apr-12 47 Start Exterior Plaster Bldg #4
HPCC45080 Install Exterior Doors & Hardware 4 23-Apr-12 26-Apr-12 81 Install Exterior Doors & Hardware
HPCC45090 Install Overhead Roll-up Door 1 23-Apr-12 23-Apr-12 84 Install Overhead Roll-up Door
HPCC45100 Exterior Plaster Scratch Coat 10 23-Apr-12 04-May-12 54 Exterior Plaster Scratch Coat
HPCC45110 Exterior Plaster Brown Coat & Cure 14 07-May-12 24-May-12 54 Exterior Plaster Brown Coat & C
HPCC45120 Exterior Plaster Finish Coat 7 25-May-12 04-Jun-12 54 Exterior Plaster Finish Coat
West Elevation 31 23-Apr-12 04-Jun-12 47 04-Jun-12, West El evation
HPCC46130 Exterior Plaster Scratch Coat 10 23-Apr-12 04-May-12 47 Exterior Plaster Scratch Coat
HPCC46140 Exterior Plaster Brown Coat & Cure 14 07-May-12 24-May-12 47 Exterior Plaster Brown Coat & C
HPCC46150 Exterior Plaster Finish Coat 7 25-May-12 04-Jun-12 47 Exterior Plaster Finish Coat
HPCC46010 Exterior Plaster Complete Bldg #4 0 04-Jun-12 47 Exterior Plaster Complete Bld

Actual Work Critical Remaining Work Summary Page 9 of 9 TASK filter: All Activities