Abstract of Cost for Extension and Construction of RCC Slab Culverts from

Ch 35000 to 54000 of NH 110 (Jehanabad-Arwal Section) For the Year


2009-2010
Part - II (A) CD Portion (Ch: 35000 m to 54000 m)
ABSTRACT OF COST OF CULVERTS AND BRIDGES
SL No Chainage Size of Culvert Nature of Work Nos Amount (In Rs)
1 35327 1*3.0m*1.25m Construction 1 1521190.59
47200, 52375, 45504,
2 41865, 46370 1*3.0m*1.5m Construction 5 7754341.65
3 51840 1*1.5m*1m Construction 1 992048.11
4 36377 2*3.6m*2.5m Construction 1 2657259.99
5 38335 1*4.0m*1.5m Construction 1 1611066.50
39120, 47320, 39290,
39615, 39965, 40125,
6 49610 1*2.5m*1.5m Construction 7 10645384.70
7 48005 1*2.5m*2m Construction 1 1751635.21
8 49451, 43610, 50500 1*2m*1.5m Construction 3 4543821.52
40490, 46315, 46360,
50127, 43275, 43680,
43820, 44278, 49025,
9 49827, 50327 1*1m*1.5m Construction 11 12863245.39
10 40678 2*2.5m*3m Construction 1 2836538.39
11 40820 2*2.5m*2m Construction 1 2215826.64
12 40995 1*1.5m*2m Construction 1 1416073.50
13 41122 1*3.0m*2m Construction 1 1781734.29
41157, 41325, 42575,
14 53225, 46490 1*1.0m*1.0m Construction 5 4816610.91
15 43880 2*1m*1m Construction 1 1244668.65
16 37600, 46575 5*1.5m*1.5m Construction 2 5837690.67
17 46640, 49315 2*1.5m*1.5m Construction 2 3649362.80
18 43427 2*1m*1.5m Construction 1 1507513.37
46925, 47190, 48465,
48810, 38219, 41358,
19 42150 1*1.5m*1.5m Construction 7 8610166.48
20 50957, 51425 1*.5m*1.0m Construction 2 1877146.21
21 52022 1*4m*4m Construction 1 2740452.26
22 51550 2*3m*2m Construction 1 2273794.73
23 35028 1*3.4m*2m Ext of Wd - 6.4m to 12m 1 1136457.84
24 35847 1*3.5m*2.15m Ext of Wd - 6.4m to 12m 1 1152303.75
25 36770 1*3.5m*2m Ext of Wd - 6.4m to 12m 1 1140327.82
26 52880 1*4m*2m Ext of Wd - 6.4m to 12m 1 1087946.49
27 53120 1*1m*1m Ext of Wd - 6.4m to 12m 1 584642.25
28 53575 2*2.5m*2m Ext of Wd - 6.4m to 12m 1 1299142.61
29 47585 2*16m Replacement 1 21054268.00
30 53 rd Km 7*24.0m Replacement 1 66953055.93
35475 to 39375 (Different 1*6*1000 mm
31 Metal Deep Proportions Dia (HP Culvert) Replacement 11 17706636.96
32 45620 2*1000 mm Dia Replacement 1 623380.32
Total Rs 77 197885734.53
Say Rs 197886000.00