ANALISA HARGA SATUAN PEMBAYARAN

KEMENTRIAN : KEMENTRIAN PEKERJAAN UMUM


UNIT ORGANISASI : DIREKTORAT JENDERAL CIPTA KARYA
SATUAN KERJA : PENGEMBANGAN PENYEHATAN LINGKUNGAN PERMUKIMAN KALTIM
PAKET PEKERJAAN : PEMBANGUNAN DRAINASE PRIMER (LANJUTAN) KOTA BALIKPAPAN
LOKASI : KOTA BALIKPAPAN
TAHUN ANGGARAN : APBN 2011

JENIS PEKERJAAN : Pasangan Batu Kosong


SATUAN PEMBAYARAN : M³

HARGA SATUAN JUMLAH


NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Mandor HO 0.0400 85,000.00 3,400.000
2 Pekerja HO 0.8000 50,000.00 40,000.000
Total A 43,400.000

B MATERIAL
1 Batu Gunung M3 1.2000 290,000.00 348,000
Total B 348,000

C PERALATAN
1 Alat Bantu Ls 1.0000 5,000.00 5,000
Total C 5,000

HARGA SATUAN (A + B + C) 396,400

ANALISA HARGA SATUAN PEMBAYARAN

JENIS PEKERJAAN : Pasangan Batu Gunung/Batu Kali 1 : 4


SATUAN PEMBAYARAN : M³

KUANTITAS HARGA SATUAN JUMLAH


NO. URAIAN SATUAN
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Mandor HO 0.0750 85,000.00 6,375
2 Tukang Batu HO 0.4500 75,000.00 33,750
3 Pekerja HO 1.8000 50,000.00 90,000
Total A 130,125
B MATERIAL
1 Batu Gunung M³ 1.2000 290,000.00 348,000
2 Pasir Pasangan M³ 0.2300 200,000.00 46,000
3 Semen Kg 162.8800 1,060.00 172,653
Total B 566,653
C PERALATAN
1 Alat Bantu Ls 1.0000 5,000.00 5,000
Total C 5,000

HARGA SATUAN (A + B + C) 701,778


ANALISA HARGA SATUAN PEMBAYARAN

JENIS PEKERJAAN : Pasangan Plesteran 1 : 4


SATUAN PEMBAYARAN : M²

HARGA SATUAN JUMLAH


NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Mandor HO 0.0200 85,000.00 1,700
2 Kepala Tukang HO 0.0150 80,000.00 1,200
3 Tukang HO 0.5000 75,000.00 37,500
4 Pekerja HO 0.4000 50,000.00 20,000
Total A 60,400
B MATERIAL
1 Pasir Pasangan M³ 0.0210 200,000.00 4,200
2 Semen Kg 4.6000 1,060.00 4,876
Total B 9,076

C PERALATAN
Total C

HARGA SATUAN (A + B + C) 69,476

ANALISA HARGA SATUAN PEMBAYARAN

JENIS PEKERJAAN : Pemasangan Pipa PVC + Ijuk


SATUAN PEMBAYARAN : Titik

HARGA SATUAN JUMLAH


NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Tukang HO 0.1180 75,000.00 8,850
2 Pekerja HO 0.0750 50,000.00 3,750
Total A 12,600

B MATERIAL
1 Pipa PVC + Ijuk Ls 1.0000 7500 7,500
Total B 7,500

C PERALATAN
Total C

HARGA SATUAN ( A + B + C ) / Meter / 2 20,100

ANALISA HARGA SATUAN PEMBAYARAN

JENIS PEKERJAAN
: Pasangan Wire Mesh Ø 6 mm
SATUAN PEMBAYARAN : M²

HARGA SATUAN JUMLAH


NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Kepala Tukang HO 0.0057 80,000.00 456
2 Tukang HO 0.0160 75,000.00 1,200
3 Pekerja HO 0.0160 50,000.00 800
Total A 2,456

B MATERIAL
1 Wire Mesh Ø 6 mm M² 1.1000 34,000.00 37,400
Total B 37,400

C PERALATAN
1 Alat Bantu Ls 1.0000 $ 1,000 1,000
Total C 1,000

HARGA SATUAN ( A + B + C ) 40,856


ANALISA HARGA SATUAN PEMBAYARAN

: Cerucuk / Tiang Pancang Ulin 10/10 ­3 m


JENIS PEKERJAAN
SATUAN PEMBAYARAN : Titik

HARGA SATUAN JUMLAH


NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Mandor HO 0.03330 85,000.00 2,831
2 Kepala Tukang HO 0.00270 80,000.00 216
3 Tukang HO 0.26670 75,000.00 20,003
4 Pekerja HO 0.20000 50,000.00 10,000
Total A 33,049

B MATERIAL
1 Kayu Ulin M³ 0.03000 3,750,000.00 112,500
Total B 112,500

C PERALATAN
Total C

HARGA SATUAN ( A + B + C ) 145,549

ANALISA HARGA SATUAN PEMBAYARAN

JENIS PEKERJAAN : Galian Tanah ( menggunakan alat )


SATUAN PEMBAYARAN : M³

HARGA SATUAN JUMLAH


NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Mandor HO 0.0050 85,000.00 425
2 Operator Terampil HO 0.0150 75,000.00 1,125
3 Sopir Terampil HO 0.0150 75,000.00 1,125
4 Pekerja HO 0.0200 50,000.00 1,000
Total A 3,675

B MATERIAL
Total B

C PERALATAN
1 Excavator Jam 0.0150 350,000.00 5,250
2 Weel Loader Jam 0.0150 250,000.00 3,750
3 Dump Truck Jam 0.0600 150,000.00 9,000
4 Alat Bantu Set 0.2000 20,000.00 4,000
Total C 22,000

HARGA SATUAN (A + B + C) 25,675

ANALISA HARGA SATUAN PEMBAYARAN

JENIS PEKERJAAN : Beton Tumbuk ( Bo )


SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH
NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Mandor HO 0.1500 85,000.00 12,750
2 Kepala Tukang HO 0.0500 80,000.00 4,000
3 Tukang HO 0.5000 75,000.00 37,500
4 Pekerja HO 6.0000 50,000.00 300,000
Total A 354,250

B MATERIAL
1 Batu Pecah 1/2 ­ 2/3 cm M³ 0.7200 280,000.00 201,600
2 Pasir Pasangan M³ 0.5510 200,000.00 110,200
3 Semen Kg 220.0000 1,060.00 233,200
4 Kayu Bekisting M³ 0.0150 1,800,000.00 27,000
Total B 572,000

C PERALATAN
Total C

HARGA SATUAN ( A + B + C ) 926,250


ANALISA HARGA SATUAN PEMBAYARAN

JENIS PEKERJAAN : Cor Beton Campur 1 : 2 : 3


SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH
NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Mandor HO 0.16220 85,000.00 13,787
2 Buruh Terampil HO 0.48650 55,000.00 26,758
3 Buruh Tak Terampil HO 2.54600 50,000.00 127,300
Total A 167,845

B MATERIAL
1 Batu Pecah 1/2 ­ 2/3 cm M³ 1.00500 280,000.00 281,400
2 Pasir Pasangan M³ 0.50500 200,000.00 101,000
3 Semen Kg 350.27030 1,060.00 371,287
4 Kayu Bekisting M³ 0.01500 1,800,000.00 27,000
Total B 780,687

C PERALATAN
1 Concrete Mixer Jam 0.73000 300,000.00 219,000
2 Concrete Vibrator Jam 0.73000 25,000.00 18,250
3 Water Jet Pump Jam 0.06330 20,000.00 1,266
4 Alat Bantu LS 1.00000 20,000.00 20,000
Total C 258,516

HARGA SATUAN ( A + B + C ) 1,207,047

ANALISA HARGA SATUAN PEMBAYARAN

JENIS PEKERJAAN : Kansteen ( Kerb Penghalang )


SATUAN PEMBAYARAN : M1
HARGA SATUAN JUMLAH
NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Mandor HO 0.00070 85,000.00 60
2 Buruh Terampil HO 0.00150 55,000.00 83
3 Buruh Tak Terampil HO 0.00370 50,000.00 185
Total A 327

B MATERIAL
1 Batu Pecah 1/2 ­ 2/3 cm M³ 0.03100 280,000.00 8,680
2 Pasir Pasangan M³ 0.03200 200,000.00 6,400
3 Semen Kg 28.00000 1,060.00 29,680
Total B 44,760

C PERALATAN
1 Concrete Mixer Jam 0.00500 300,000.00 1,500
2 Concrete Vibrator Jam 0.00500 25,000.00 125
3 Water Pump Jam 0.00570 20,000.00 114
5 Dump Truck Jam 0.00450 150,000.00 675
6 Alat Bantu LS 1.00000 20,000.00 20,000
Total C 22,414

HARGA SATUAN ( A + B + C ) 67,501


ANALISA HARGA SATUAN PEMBAYARAN

JENIS PEKERJAAN : Pasangan Batako


SATUAN PEMBAYARAN : M²

HARGA SATUAN JUMLAH


NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Mandor HO 0.02500 85,000.00 2,125
2 Kepala Tukang HO 0.01000 80,000.00 800
3 Tukang HO 0.10000 75,000.00 7,500
4 Pekerja HO 0.50000 50,000.00 25,000
Total A 35,425

B MATERIAL
1 Semen PC Kg 12.50000 1,060.00 13,250
2 Pasir Pasangan M3 0.04000 200,000.00 8,000
3 Batako Bh 12.50000 5,000.00 62,500
Total B 83,750

C PERALATAN

Total C

HARGA SATUAN (A + B + C) 119,175

ANALISA HARGA SATUAN PEMBAYARAN

JENIS PEKERJAAN : Pembuatan Tanggul Eks Galian


SATUAN PEMBAYARAN : M²

HARGA SATUAN JUMLAH


NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Mandor HO 0.00500 85,000.00 425
2 Operator Terampil HO 0.01500 75,000.00 1,125
3 Sopir Terampil HO 0.01500 75,000.00 1,125
4 Pekerja HO 0.02000 50,000.00 1,000
Total A 3,675

B MATERIAL
Total B

C PERALATAN
1 Excavator Jam 0.01500 350,000.00 5,250
2 Dump Truck Jam 0.03000 150,000.00 4,500
Total C 9,750

HARGA SATUAN (A + B + C) 13,425


ANALISA HARGA SATUAN PEMBAYARAN

JENIS PEKERJAAN : Pemasangan Buis Beton 1/2 Ø 30 Cm


SATUAN PEMBAYARAN : M1
HARGA SATUAN JUMLAH
NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Kepala Tukang Batu HO 0.00300 80,000.00 240
2 Tukang Batu HO 0.03000 75,000.00 2,250
3 Buruh Tak Terampil HO 0.06000 50,000.00 3,000
Total A 5,490

B MATERIAL
1 Buis Beton 1/2 Ø 30 Cm Bh 2.00000 60,000.00 120,000
Total B 120,000

C PERALATAN
1 Alat Bantu LS 1.00000 1,000 1,000
Total C 1,000

HARGA SATUAN ( A + B + C ) 126,490

ANALISA HARGA SATUAN PEMBAYARAN

JENIS PEKERJAAN : Urugan Pasir


SATUAN PEMBAYARAN : M³
HARGA SATUAN JUMLAH
NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Mandor HO 0.01000 85,000.00 850
2 Pekerja HO 0.30000 50,000.00 15,000
Total A 15,850

B MATERIAL
1 Pasir Urug M³ 1.20000 100,000.00 120,000
Total B 120,000

C PERALATAN
Total C

HARGA SATUAN (A + B + C) 135,850


ANALISA HARGA SATUAN PEMBAYARAN

JENIS PEKERJAAN : Pasangan Wire Mesh Ø 10 mm


SATUAN PEMBAYARAN : M²
HARGA SATUAN JUMLAH
NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Kepala Tukang HO 0.00570 80,000.00 456
2 Tukang HO 0.01600 75,000.00 1,200
3 Pekerja HO 0.01600 50,000.00 800
Total A 2,456

B MATERIAL
1 Wire Mesh Ø 10 mm M² 1.10000 95,000.00 104,500
Total B 104,500

C PERALATAN
1 Alat Bantu Ls 1.00000 1,000 1,000
Total C 1,000

HARGA SATUAN ( A + B + C ) 107,956

ANALISA HARGA SATUAN PEMBAYARAN

JENIS PEKERJAAN : Pemasangan Buis Beton Ø 50 Cm


SATUAN PEMBAYARAN : M1
HARGA SATUAN JUMLAH
NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Kepala Tukang Batu HO 0.00300 80,000.00 240
2 Tukang Batu HO 0.03000 75,000.00 2,250
Total A 2,490

B MATERIAL
1 Buis Beton Ø 50 Cm Bh 2.00000 125,000.00 250,000
Total B 250,000

C PERALATAN
1 Alat Bantu LS 1.00000 $ 1,000 1,000
Total C 1,000

HARGA SATUAN ( A + B + C ) 253,490


ANALISA HARGA SATUAN PEMBAYARAN

: Cerucuk / Tiang Pancang Ulin 10/10 ­4 m


JENIS PEKERJAAN
SATUAN PEMBAYARAN : Titik

HARGA SATUAN JUMLAH


NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Mandor HO 0.03330 85,000.00 2,831
2 Kepala Tukang HO 0.00270 80,000.00 216
3 Tukang HO 0.26670 75,000.00 20,003
4 Pekerja HO 0.20000 50,000.00 10,000
Total A 33,049

B MATERIAL
1 Kayu Ulin M³ 0.04000 3,750,000.00 150,000
Total B 150,000

C PERALATAN
Total C

HARGA SATUAN ( A + B + C ) 183,049

ANALISA HARGA SATUAN PEMBAYARAN

JENIS PEKERJAAN
: Pancang Galam Ø 15 Cm
SATUAN PEMBAYARAN : Titik

HARGA SATUAN JUMLAH


NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Mandor HO 0.02200 85,000.00 1,870
2 Kepala Tukang HO 0.00270 80,000.00 216
3 Tukang HO 0.11680 75,000.00 8,760
4 Pekerja HO 0.08760 50,000.00 4,380
Total A 15,226

B MATERIAL
1 Kayu Galam Ø 15 Cm Btg 1.00000 25,000.00 25,000
Total B 25,000

C PERALATAN
Alat bantu Ls 1.00000 2,000 2,000
Total C 2,000

HARGA SATUAN ( A + B + C ) 42,226

ANALISA HARGA SATUAN PEMBAYARAN

JENIS PEKERJAAN : Galian Tanah ( Tenaga orang)


SATUAN PEMBAYARAN : M³

HARGA SATUAN JUMLAH


NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Mandor HO 0.04000 85,000.00 3,400
2 Pekerja HO 0.80000 50,000.00 40,000
Total A 43,400

B MATERIAL
Total B

C PERALATAN
Total C

HARGA SATUAN (A + B + C) 43,400


ANALISA HARGA SATUAN PEMBAYARAN

JENIS PEKERJAAN : Paving block kecil


SATUAN PEMBAYARAN : M²

HARGA SATUAN JUMLAH


HARGA SATUAN JUMLAH
NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Mandor HO 0.00300 85,000.00 255
3 Pekerja Terlatih HO 0.75000 55,000.00 41,250
4 Pekerja HO 0.10000 50,000.00 5,000
Total A 46,505

B MATERIAL
1 Paving block Bh 38.00000 2,000.00 76,000
2 Pasir M³ 0.10000 200,000.00 20,000
Total B 96,000

C PERALATAN
1 Alat Bantu Set 0.20000 1,000 200
Total C 200

HARGA SATUAN (A + B + C) 142,705

ANALISA HARGA SATUAN PEMBAYARAN

JENIS PEKERJAAN : Paving block besar


SATUAN PEMBAYARAN : M²

HARGA SATUAN JUMLAH


NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Mandor HO 0.0030 85,000.00 255
3 Pekerja Terlatih HO 0.7500 55,000.00 41,250
4 Pekerja HO 0.1000 50,000.00 5,000
Total A 46,505

B MATERIAL
1 Paving block Bh 28.0000 2,500.00 70,000
2 Pasir M³ 0.1000 200,000.00 20,000
Total B 90,000

C PERALATAN
1 Alat Bantu Set 0.2000 1,000 200
Total C 200

HARGA SATUAN (A + B + C) 136,705

ANALISA HARGA SATUAN PEMBAYARAN


JENIS PEKERJAAN : Pemadatan Tanah
SATUAN PEMBAYARAN : M³

HARGA SATUAN JUMLAH


NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
1 Pekerja HO 0.5000 50,000.00 25,000
2 Mandor HO 0.0500 85,000.00 4,250
29,250
ANALISA HARGA SATUAN PEMBAYARAN
JENIS PEKERJAAN : Pemasangan Batu bata
SATUAN PEMBAYARAN : M²

HARGA SATUAN JUMLAH


NO. URAIAN SATUAN KUANTITAS
(Rupiah) (Rupiah)
1 2 3 4 5 6
A TENAGA KERJA
1 Pekerja HO 0.3200 50,000.00 16,000
2 Tukang Batu HO 0.1000 75,000.00 7,500
3 Kepala Tukang HO 0.0100 80,000.00 800
4 Mandor HO 0.0150 85,000.00 1,275
Total A 25,575

B MATERIAL
1 Bata Merah 10 x 10 x 20 cm Bh 80.0000 600.00 48,000
2 Semen portland Kg 11.5000 1,060.00 12,190
3 Pasir Pasang M3 0.0430 200,000.00 8,600
Total B 68,790

C PERALATAN
1 Alat Bantu Set 0.2000 1,000 200
Total C 200

HARGA SATUAN (A + B + C) 94,565