You are on page 1of 48

Predicting Project Completion Date Predicting Project Completion Date Using Earned Value Management Using Earned Value

Management
NASA PM Challenge 2006 March 21-22 Galveston
Ray W. Stratton, PMP, EVP
714-318-2231 raystratton@ mgmt-technologies.com

MMVI, Management Technologies

Presentation Outline
Refresher on EVM concepts The Problem with SPI The Earned Schedule Concept Comprehensive Example Research Results Earned Schedule Maturity Conclusions References and Contact Information

MMVI, Management Technologies

What Could be New About EVM?


In the 1900s..... EVM used in DoD, NASA, DoE, DoT, elsewhere Provided Cost and Schedule Variances (CV, SV) Computed Cost and Schedule Performance Indices (CPI, SPI$) Produced Estimated Cost at Complete (EAC) 21st Century Improvements to EVM Provides SV in time units Computes SPIt based on time units Produces Estimated Date of Completion
MMVI, Management Technologies
3

Refresher on EVM concepts


The Problem with SPI The Earned Schedule Concept Comprehensive Example Research Results Earned Schedule Maturity Conclusions References and Contact Information

Refresher on Earned Value Concepts


How earned value management is different from cost reports and schedule updates.

MMVI, Management Technologies

Basic EVM Concepts


Relate the money spent to the work done Combines schedule status with cost information Requires common units of measure Fundamental concepts The work has value equal to its budget The project equity is the sum of the value of all work done to-date Building the equity (Earned Value) should equal the budget planned for the work done (spend

appropriately)
The equity should accumulate at the rate planned

(stay on schedule)
MMVI, Management Technologies
5

The Three Key Elements of EVM


Only three terms (two we already have) Planned Value (PV) Actual Cost (AC)

Earned Value (EV)

MMVI, Management Technologies

The Planned Value (PV)


The schedule (plan) to build project equity from zero to the total project value The expected gain in project equity as each piece of work is completed Previously budgeted cost of work scheduled (BCWS)

Value ($ or hours)

Planned Value

Performance Measurement Baseline (PMB)

MMVI, Management Technologies

Time
7

The Earned Value (EV)


The project equity gained, regardless of the cost to accomplish the work. The gain in project equity as a result of completed work Previously budgeted cost of work performed (BCWP)
Now

Value ($ or hours)

Planned Value Earned Value

Time
MMVI, Management Technologies
8

The Actual Cost (AC)


The total cost of the completed work Previously actual cost of work performed (ACWP)
Now

Value ($ or hours)

Planned Value

Actual Costs Earned Value

Time
MMVI, Management Technologies
9

Analyzing Variances From the Plan


Now

Value ($ or hours) Planned Value


Schedule Variance

Time

{}

Cost Variance

Actual Costs

Earned Value

MMVI, Management Technologies

10

Cost Performance Index (CPI)


Did the cost of adding equity equal the equity added? CPI = progress/cost CPI = EV/AC Greater than 1.0 is good, less than 1.0 is bad Example
CPI = EV WORK _ DONE 1000 hrs = = = 0.66 AC COST _ OF _ WORK _ DONE 1500 hrs

(this is not good)


MMVI, Management Technologies
11

Schedule Performance Index (SPI$)


Did a months of schedule produce a month of progress? SPI$ = progress/plan SPI$ = EV/PV Greater than 1.0 is good, less than 1.0 is bad Example
SPI $ = EV WORK _ DONE 1200 hrs = = = 1 .2 PV WORK _ PLANNED 1000 hrs

(this is good)
MMVI, Management Technologies
12

Refresher on EVM concepts The Problem with SPI The Earned Schedule Concept Comprehensive Example Research Results Earned Schedule Maturity Conclusions References and Contact Information

The Problem with SPI


Weve been using SPI for 30+ Years, What could be wrong with it?

MMVI, Management Technologies

13

Two Serious Problems with SPI$


SPI$ fails in the end SPI$ = EV/PV At project completion EV = PV SPI$ = EV/PV = PV/PV = 1.0 at project end Implications:
At project start SPI is reliable At some point SPI accuracy diminishes Toward the project end it is useless

SPI$ does not show weeks or months of schedule variance What most people want to know and understand
MMVI, Management Technologies
14

Graphing the Problem with SPI$


1.2 1.1
TIME Project schedule improvement or false indications due to SPI?

3 months

SPI$ 1.0
SPI$ .9 .8
Original Project Finish Actual Project Finish

MMVI, Management Technologies

15

Using CPI and SPI$ in Estimating the Final Cost


Simple extrapolation Final cost = cost of work done + (work left/past performance) Assumes future performance is same as past (generally true) EAC (CPI) = AC+(BAC-EV)/CPI = BAC/CPI EAC (CPI, SPI$) = AC+(BAC-EV)/(CPI*SPI$)
Toward the end of the project how accurate can this term be?

MMVI, Management Technologies

16

Refresher on EVM concepts The Problem with SPI The Earned Schedule Concept Comprehensive Example Research Results Earned Schedule Maturity Conclusions References and Contact Information

The Earned Schedule Concept


Creating a Schedule Performance Index that is accurate to the end of the project.

MMVI, Management Technologies

17

At What Point Did I Expect to Attain my Current Earned Value?


AC is not shown in this example since this is about Earned Schedule!

Budget or staff hours

When work was to be done (PV)! Work done (EV) 6 months 10 months Actual Time (AT) i.e., NOW Earned Schedule (ES) i.e., How much have you accomplished and when were supposed to?

Time

MMVI, Management Technologies

18

Some New Terms


AT = Actual Time (now, or data date) ES = Earned Schedule (Point in time when current progress was planned to occur) PD = Planned Duration (planned project duration) ED = Estimated Duration (estimated project duration) PCD = Planned Completion Date (Planned project end date) ECD = Estimated Completion Date (Estimated project end date)

MMVI, Management Technologies

19

Some New Formulas


SVt = ES - AT (Schedule Variance in time units, note subscript versus SV$) SVt = 6 months 10 months = -4 months SPIt = ES/AT (SPI in time units) SPIt = 6/10 = 0.6

MMVI, Management Technologies

20

The Traditional and the New


Planned Budget (BAC)
BAC

Planned work (PV) Funds spent (AC)

Budget Spent Cost Variance (CV) Work Done

Schedule Variance (SV$)

Work done (EV)

Planned Duration (PD) Actual Time (AT) Earned Schedule (ES)


MMVI, Management Technologies

Schedule Variance (SVt)

Planned Completion Date

21

Traditional and New EVM Analysis Tools


Traditional
EV SPI $ = PV EV CPI = AC EAC = BAC CPI

New
ES SPI t = AT
ED = PD SPI t

ECD = start _ date + ED


SVt = ES AT

SV$ = EV PV

CV = EV AC

MMVI, Management Technologies

22

Refresher on EVM concepts The Problem with SPI The Earned Schedule Concept Comprehensive Example Research Results Earned Schedule Maturity Conclusions References and Contact Information

Comprehensive Example
Putting all the pieces together.

MMVI, Management Technologies

23

Comprehensive Example
Planned Budget (BAC)
12 BAC

Planned work (PV) Funds spent (AC)


7 PV 5 AC 4 EV

Budget Spent Cost Variance (CV) Work Done

Work done (EV)


6 ES 10 AT 18 PD

Planned Duration (PD) Actual Time (AT) Earned Schedule (ES)


MMVI, Management Technologies

Schedule Variance (SVt)


24

Comparing EV and ES Schedule Analysis


Traditional
EV $4 SPI $ = = = 0.57 PV $7
SV$ = EV PV = $4 $7 = $3

New
ES 6months SPI t = = = 0.6 AT 10months

SVt = ES AT = 6months 10months SVt = 4months

ED = ?
MMVI, Management Technologies

PD 18months ED = = = 30months SPI t 0.6

25

New Analysis Products


Schedule performance index {SPI(t) or SPIt} Schedule Variance {SV(t) or SVt} Estimated Duration (ED) Estimated Completion Date (ECD)

MMVI, Management Technologies

26

Refresher on EVM concepts The Problem with SPI The Earned Schedule Concept Comprehensive Example Research Results Earned Schedule Maturity Conclusions References and Contact Information

Research Results
Does Earned Schedule really work?

MMVI, Management Technologies

27

Empirical Evidence (Henderson)


Findings derived from a small set of real life project data
Commercial IT Infrastructure Expansion Project Phase 1
Earned Schedule, Independent Estimate At Completion (time) - IEAC(t)
as at Project Completion: Week Starting 15th July xx
Planned Schedule Earned Schedule cum IEAC(t) PD/SPI(t)

40 35 30 Duration (Weeks) 25 20 15 10 5 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

Actual Time (Weeks)

Henderson, K., 2003, Earned schedule: a breakthrough extension to earned value theory? A retrospective MMVI, Management Technologiesanalysis of real project data, The Measurable News, Summer 2003, 21, 13-17

28

Academic Research
(Vanhoucke) Created 3,100 project activity networks Constructed a schedule for each network Simulated (executed) activity duration and cost in a controlled way (9 execution scenarios, each schedule subjected to each scenario 100 times) Monitored and forecasted at each reporting period Analysed the data (3.100 x 9 x 100 = 2.790.000 project data sets)

Vanhoucke M., Vandevoorde St., A Simulation and Evaluation of Earned Value Metrics to Forecast the Project Duration, Ghent University, Working Paper 2005/312, June 2005

MMVI, Management Technologies

29

The Nine Simulation Scenarios


Critical Path Activities Real Duration < Planned Duration Real Duration = Planned Duration Real Duration > Planned Duration Non-Critical Path Activities Real Duration < Planned Duration Real Duration = Planned Duration Real Duration > Planned Duration
MMVI, Management Technologies
30

Research Process

MMVI, Management Technologies

31

Academic Research Results

The results reveal that the Earned Schedule method outperforms, on the average, all other forecasting methods.

Vanhoucke M., Vandevoorde St., A Simulation and Evaluation of Earned Value Metrics to Forecast the Project Duration, Ghent University, Working Paper 2005/312, June 2005

MMVI, Management Technologies

32

Refresher on EVM concepts The Problem with SPI The Earned Schedule Concept Comprehensive Example Research Results Earned Schedule Maturity Conclusions References and Contact Information

Earned Schedule Maturity


Current state of Earned Schedule development and deployment

MMVI, Management Technologies

33

Earned Schedule Maturity


First paper: March 2003, PMI-CPM Measurable News Over twenty presentations and publications A growing trend and management expectation Yet to appear in commercial EVM software products Early Adopters USAF Lockheed Martin Boeing Belgium Management Technologies (education, processes)
MMVI, Management Technologies
34

USAF Planning
Air Force understands the potential of Earned Schedule Demonstrate Earned Schedule on a sample set of programs Build a body of evidence on a larger set of programs Validate the Earned Schedule as a value added program management tool Integrate Earned Schedule as a tool in Air Force Acquisition

MMVI, Management Technologies

35

Lockheed Martin, Program #1


PD IEAC(t) Linear (IEAC(t))

PD

IEAC(t)

Linear (IEAC(t))

IEAC(t) = (PD SPIt)


55
55

50
50

PD = 48
45
45 1 2 3 4 5 6 7 8

PD = 54

9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

2 3

5 6

7 8

9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

MMVI, Management Technologies

36

Lockheed Martin, Program #2


IEAC(t) 50
IEAC(t) = (PD SPIt)

Linear (IEAC(t))

45

40
PD = 39 AD = 42

35 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41
MMVI, Management Technologies
37

The Good News!


Previously EVM was great at cost management EVM was ok at schedule management, sometimes Now EVM can address both cost and schedule well EVM can estimate
Cost at completion Completion date!

SPIt can record project outcome in lessons learned

MMVI, Management Technologies

38

Credit to Discoverers, Advocates, & Researchers


Henderson Kym, Earned Schedule: A Breakthrough Extension to Earned Value Theory? A Retrospective Analysis of Real Project Data,The Measurable News, Summer 2003 Robert Handshuh, New Concept in Earned Value - Earned Schedule, PMI Southeast Regional Conference USA, June 2005 Walt Lipke & Kym Henderson, Earned Schedule Status Update and Early Adaptor Applications Feedback, 17th IPMC November 2005 Vandevoorde St., Vanhoucke M., A Comparison of different project duration forecasting methods using earned value metrics, Ghent University, working paper 2005/312, June 2005
Approved for Publishing in International Journal of Project Management State of the Art Report on Forecasting Duration Methods
MMVI, Management Technologies
39

Refresher on EVM concepts The Problem with SPI The Earned Schedule Concept Comprehensive Example Research Results Earned Schedule Maturity Conclusions References and Contact Information

Conclusions
So What?

MMVI, Management Technologies

40

What We Know About Earned Schedule


Faithful to the projects end Provides a reliable means to calculate an estimated completion date Provides a useful schedule performance metric for project history and lessons learned May provide a better estimated completion date than critical path methods!

MMVI, Management Technologies

41

Why use ES?


More intuitive schedule information Schedule variance in time units (intuitive to most people) Cost variance in resource ($$) units SPIt retains utility to project end SPIt does not automatically creep toward 1.0 near project end SPIt captures the final project schedule performance data Can finally estimate Project Completion Date

MMVI, Management Technologies

42

Refresher on EVM concepts The Problem with SPI The Earned Schedule Concept Comprehensive Example Research Results Earned Schedule Maturity Conclusions References and Contact Information

Reference and Contact Information


Tell me more!

MMVI, Management Technologies

43

Seminal Documents
Lipke, Walter, Schedule is Different, The Measurable News, March and Summer 2003 Henderson, Kym, Further Development in Earned Schedule, The Measurable News, Spring 2003 Henderson, Kym, Earned Schedule: A Breakthrough Extension to Earned Value Theory? A Retrospective Analysis of Real Project Data, The Measurable News, Summer 2003
The Measurable news is a quarterly publication of the Project Management Institutes College of Performance Management www.pmi-cpm.org
MMVI, Management Technologies
44

Other References
Earned Schedule Status Update and Early Adopter Applications Feedback Presentation facilitated by Walt Lipke and Kym Henderson, 17th IPMC November 2005 Earned Schedule Leads to Improved Forecasting: Presentation by Walt Lipke, intended for 17th IPMC November 2005 Earned Schedule in Action:Paper by Kym Henderson, published PMI CPM Journal, The Measurable News "Spring" 2005 Forecasting Project Schedule Completion by Using Earned Value Metrics, Presentation by Ing. Stephan Vandevoorde, Senior Project Manager, Fabricom Airport Systems and Prof. Dr. Mario Vanhoucke, Ghent University, Belgium, Early Warning Signals Conference, V.U.B. Brussels, June 2005 Not Your Father's Earned Value: Earned Schedule overview paper by Ray Stratton, published on Projects@Work (http://www.projectsatwork.com) 24 Feb 2005 Connecting Earned Value to the Schedule:Paper by Walt Lipke, published PMI CPM Journal, The Measurable News, "Winter" 2004
MMVI, Management Technologies
45

One-Stop Shopping
Comprehensive Library of EVM and Earned Schedule Papers Presentations

http://sydney.pmichapters-australia.org.au/ Click Education, then Presentations and Papers for .pdf copies

MMVI, Management Technologies

46

In Closing
If you are not practicing Earned Schedule as part of your Earned Value Management System you are practicing 20th Century
Earned Value Management!

MMVI, Management Technologies

47

Discussion and Questions

Ray W. Stratton, EVP, PMP President, Management Techologies PMI CPM Vice President, Research and Standards 714-318-2231 raystratton@mgmt-technologies.com www.mgmt-technologies.com

MMVI, Management Technologies

48

You might also like