6 TRABAJO COLABORATIVO N1
COSTOS Y PRESUPUESTOS
102015_180
DIXON BENAVIDES
TUTOR:
SEBASTIAN MURILLO BARAHONA
UNIVERSIDAD NACIONAL ABIERTA Y A DISTANCIA
ABRIL DE 2010
Solucin punto 1
COSTOS POR RDENES DE PRODUCCIN
O.P 093.
FECHA NREQUISICIN MATERIAL CANTIDAD VALOR
08-11 2789 1851 600 Mts. 1.880.000
08-12 2792 1851 80 Mts. 256.000
08-16 2794 1851 100 Mts. 320.000
08-22 2796 3597 40 unidades 784.000
08-24 2800 1851 40 Mts. 128.000
08-24 2803 4031 140 cajas 396.000
TOTAL 3.764.000
Procedimiento.
1. 2789 200 Mts. X 3.080 = 616.000
320 Mts. X 3.150 = 1.008.000
80 Mts. X 3.200 = 256.000

TOTALES. 600 Mts. 1.880.000


2. 2792 80 Mts. X 3.200 = 256.000
3. 2794 40 Mts. X 3.200 = 128.000
60 Mts. X 3.200 = 192.000
TOTALES. 100 Mts. 320.000
4. 2796 40 unidades X 19.600 = 784.000
5. 2800 40 Mts. X 3.200 = 128.000
6. 2803 120 cajas X 2.800 = 336.000
20 cajas X 3.000 = 60.000
TOTALES. 140 Cajas 396.000
MANO DE OBRA DIRECTA O.P. 093
CODIGO
OPERARIO N DE HORAS
TRABAJADAS VALOR BASICO
HORA VALOR PRESTACIONES SOCIALES
CESANTIAS
VACACIONES
PRIMAS INT. CESANTIAS
OTRAS
2034 88 4.880 429.440 36.073 21.472 42.944 4.294 19.325
2045 86 4.880 419.680 35.253 20.984 41.968 4.197 18.886
2046 106 4.940 523.640 43.986 26.182 52.364 5.236 23.564
2047 116 4.940 573.040 48.135 28.652 57.304 5.730 25.787

2048 48 4.960 238.080 19.999 11.904 23.808 2.381 10.714


2057 6 4.960 29.760 2.500 1.488 2.976 298 1.339
2067 140 4.860 680.400 57.154 34.020 68.040 6.804 30.618
2077 65 4.880 317.200 26.645 15.860 31.720 3.172 14.274
2099 42 4.860 204.120 17.146 10.206 20.412 2.041 9.185
TOTAL 3.415.360 286.890 170.768 341.536 34.154 153.691
CODIGO
OPERARIO N DE HORAS
TRABAJADAS VALOR BASICO
HORA VALOR APORTES SEGURIDAD SOCIAL
SALUD
PENSIONES
PARAFISCALES
ARP
2034 88 4.880 429.440 36.502 34.355 38.650 3.865
2045 86 4.880 419.680 35.673 33.574 37.771 3.777
2046 106 4.940 523.640 44.509 41.891 47.128 4.713
2047 116 4.940 573.040 48.708 45.843 51.574 5.157
2048 48 4.960 238.080 20.237 19.046 21.427 2.143
2057 6 4.960 29.760 2.530 2.381 2.678 268
2067 140 4.860 680.400 57.834 54.432 61.236 6.124
2077 65 4.880 317.200 26.962 25.376 28.548 2.855
2099 42 4.860 204.120 17.350 16.330 18.371 1.837

TOTAL 3.415.360 290.306 273.229 307.382 30.738


O.P 094.
FECHA N REQUISICION MATERIAL CANTIDAD VALOR
08-10 2787 2301 330 Unidades 726.000
08-10 2788 3597 25 Unidades 490.000
08-12 2791 1548 750 Kilos 5.106.000
08-13 2793 2301 100 Unidades 224.000
08-21 2795 1548 300 kilos 2.052.000
08-23 2798 1548 640 kilos 4.337.600
08-23 2799 2301 90 Unidades 201.000
08-24 2804 4031 60 Cajas 180.000
08-27 2806 3597 80 Unidades 1.600.000
TOTAL 14.916.600
Procedimiento.
1. 2787 330 Unidades X 2.200 = 726.000
2. 2788 25 Unidades X 19.600 = 490.000
3. 2791 600 kilos X 6.800 = 4.080.000
150 Kilos X 6.840 = 1.026.000
TOTALES 750 Kilos 5.106.000
4. 2793 100 Unidades X 2.240 = 224.000
5. 2795 300 Kilos X 6.840 = 2.052.000
6. 2798 640 Kilos X 6.840 = 4.377.600
7. 2799 90 Unidades X 2.240 = 201.600

8. 2804 60 Cajas X 3.000 = 180.000


9. 2806 80 Unidades X 20.000= 1.600.000
MANO DE OBRA DIRECTA O.P. 094
CODIGO
OPERARIO N DE HORAS
TRABAJADAS VALOR BASICO
HORA VALOR PRESTACIONES SOCIALES
CESANTIAS
VACACIONES
PRIMAS INT.
CESANTIAS
OTRAS
2034 84 4.880 409.920 34.433 20.496 40.992 4.099 18.446
2042 58 4.880 283.040 23.775 14.152 28.304 2.830 12.737
2046 34 4.940 167.960 14.109 8.398 16.796 1.680 7.558
2048 68 4.960 337.280 28.332 16.864 33.728 3.373 15.178
2057 80 4.960 396.800 33.331 19.840 39.680 3.968 17.856
2069 16 4.860 77.760 6.532 3.888 7.776 778 3.499
2077 14 4.880 68.320 5.739 3.416 6.832 683 3.074
2078 84 4.880 409.920 34.433 20.496 40.992 4.099 18.446
2085 68 4.940 335.920 28.217 16.796 33.592 3.359 15.116
2099 44 4.860 213.840 17.963 10.692 21.384 2.138 9.623
TOTAL 2.700.760 226.864 135.038 270.076 27.008 121.534

CODIGO
OPERARIO N DE HORAS
TRABAJADAS VALOR BASICO
HORA VALOR APORTES SEGURIDAD SOCIAL
SALUD
PENSIONES
PARAFISCALES
ARP
2034 84 4.880 409.920 34.843 32.794 36.893 3.689
2042 58 4.880 283.040 24.058 22.643 25.474 2.547
2046 34 4.940 167.960 14.277 13.437 15.116 1.512
2048 68 4.960 337.280 28.669 26.982 30.355 3.036
2057 80 4.960 396.800 33.728 31.744 35.712 3.571
2069 16 4.860 77.760 6.610 6.221 6.998 700
2077 14 4.880 68.320 5.807 5.466 6.149 615
2078 84 4.880 409.920 34.843 32.794 36.893 3.689
2085 68 4.940 335.920 28.553 26.874 30.233 3.023
2099 44 4.860 213.840 18.176 17.107 19.246 1.925
TOTAL 2.700.760 229.565 216.061 243.068 24.307
O.P 095
FECHA N REQUISICIN MATERIAL CANTIDAD VALOR
08-09 2785 1548 600 Kilos 4.080.000
08-09 2786 3597 100 Unidades 1.912.000

08-12 2790 2301 260 Unidades 556.400


08-22 2797 2301 180 Unidades 403.000
TOTAL 6.951.400
Procedimiento.
1. 2785 600 Kilos X 6.800 = 4.080.000
2. 2786 80 Unidades X 19.000 = 1.520.000
20 Unidades X 19.600 = 392.000
TOTALES 100 Unidades 1.912.000
3. 2790 90 Unidades X 2.200 = 198.000
160 Unidades X 2.240 = 358.400
TOTALES 250 Unidades 556.400
4. 2797 180 Unidades X 2.240 = 403.200
MANO DE OBRA DIRECTA O.P. 095
CODIGO
OPERARIO N HORAS
TRABAJADAS VALOR BASICO
HORA VALOR PRESTACIONES SOCIALES
CESANTIAS
VACACIONES
PRIMAS INT.
CESANTIAS
OTRAS
2042 75 4.880 366.000 30.744 18.300 36.600 3.660 16.470

2046 28 4.940 138.320 11.619 6.916 13.832 1.383 6.224


2057 86 4.960 426.560 35.831 21.328 42.656 4.266 19.195
2066 71 4.860 345.060 28.985 17.253 34.506 3.451 15.528
2069 140 4.860 680.400 57.154 34.020 68.040 6.804 30.618
2077 84 4.880 409.920 34.433 20.496 40.992 4.099 18.446
2078 37 4.880 180.560 15.167 9.028 18.056 1.806 8.125
2085 36 4.940 177.840 14.939 8.892 17.784 1.778 8.003
2099 52 4.860 252.720 21.228 12.636 25.272 2.527 11.372
TOTAL 2.977.380 250.100 148.869 297.738 29.774 133.982
CODIGO
OPERARIO N HORAS
TRABAJADAS VALOR BASICO
HORA VALOR APORTES SEGURIDAD SOCIAL
SALUD
PENSIONES
PARAFISCALES
ARP
2042 75 4.880 366.000 31.110 29.280 32.940 3.294
2046 28 4.940 138.320 11.757 11.066 12.449 1.245
2057 86 4.960 426.560 36.258 34.125 38.390 3.839
2066 71 4.860 345.060 29.330 27.605 31.055 3.106
2069 140 4.860 680.400 57.834 54.432 61.236 6.124
2077 84 4.880 409.920 34.843 32.794 36.893 3.689

2078 37 4.880 180.560 15.348 14.445 16.250 1.625


2085 36 4.940 177.840 15.116 14.227 16.006 1.601
2099 52 4.860 252.720 21.481 20.218 22.745 2.274
TOTAL 2.977.380 253.077 238.190 267.964 26.796
O.P. 096.
FECHA N REMISION MATERIAL CANTIDAD VALOR
08-24 2801 1851 500 Mts. 160.000
08-24 2802 3597 100 Unidades 1.986.000
08-27 2805 2301 115 Unidades 257.000
TOTAL 2.403.000
Procedimiento.
1. 2801 50 Mts. X 3.200 = 160.000
2. 2802 35 Unidades x 19.600 = 686.000
65 Unidades x 20.000 = 1.300.000
TOTALES 100 Unidades 1.986.000
3. 2805 115 Unidades X 2.240 = 257.000
MANO DE OBRA DIRECTA O.P. 096
CODIGO
OPERARIO N HORAS
TRABAJADAS VALOR BASICO
HORA
VALOR PRESTACIONES SOCIALES
CESANTIAS

VACACIONES
PRIMAS INT.
CESANTIAS
OTRAS
2042 42 4.880 204.960 17.217 10.248 20.496 2.050 9.223
2045 84 4.880 409.920 34.433 20.496 40.992 4.099 18.446
2047 58 4.940 286.520 24.068 14.326 28.652 2.865 12.893
2048 69 4.960 342.240 28.748 17.112 34.224 3.422 15.401
2066 124 4.860 602.640 50.622 30.132 60.264 6.026 27.119
2067 36 4.860 174.960 14.697 8.748 17.496 1.750 7.873
2069 21 4.860 102.060 8.573 5.103 10.206 1.021 4.593
2077 94 4.880 458.720 38.532 22.936 45.872 4.587 20.642
2078 59 4.880 287.920 24.185 14.396 28.792 2.879 12.956
2099 48 4.860 233.280 19.596 11.664 23.328 2.333 10.498
VALOR 3.103.220 260.670 155.161 310.322 31.032 139.645
CODIGO
OPERARIO N HORAS
TRABAJADAS VALOR BASICO
HORA
VALOR APORTES SEGURIDAD SOCIAL
SALUD
PENSIONES
PARAFISCALES

ARP
2042 42 4.880 204.960 17.422 16.397 18.446 1.845
2045 84 4.880 409.920 34.843 32.794 36.893 3.689
2047 58 4.940 286.520 24.354 22.922 25.787 2.579
2048 69 4.960 342.240 29.090 27.379 30.802 3.080
2066 124 4.860 602.640 51.224 48.211 54.238 5.424
2067 36 4.860 174.960 14.872 13.997 15.746 1.575
2069 21 4.860 102.060 8.675 8.165 9.185 919
2077 94 4.880 458.720 38.991 36.698 41.285 4.128
2078 59 4.880 287.920 24.473 23.034 25.913 2.591
2099 48 4.860 233.280 19.829 18.662 20.995 2.100
VALOR 3.103.220 263.774 248.258 279.290 27.929
Solucin punto 2
Unidades totales Ut= 6000
Unidades terminadas Uterm.= 5200
Unidades en proceso Uproceso=700
700 80% 560 Material
80% 560 M.O
50% 350 C.I.F
Uter= 5200 ----80% procesan
= 4160 ---- (1040 estn en proceso)
Clculos de preparacin:
Costo material

CUmaterial = ---------------------------N unidades terminadas


8540.000 8540.000
CUmaterial = ------------------------- = ------------------- = 1482.64
5200 + 560 5760
4100.000
CUMO = ---------------------- = 711.81
5200 + 560
2860.000 2860.000
CUcif = ------------------- = ----------------- = 515.315
5200 + 350 5550
Costo Unitario Total = CUmaterial + CUMO + Cucif
CUT = 1482.64 + 711.81 + 515.315
CUT = 2709.76
Clculos de empaque:
1620.000 1620.000
CUmaterial = ------------------------- = ------------------- = 311.5385
4160 + 1040 * 100% 5200
3690.000 3690.000
CUMO = ------------------------- = ----------------- = 771.321
4160 + 1040 * 60% 4784
1700.000 1700.000
CUcif = ------------------------- = ----------------- = 355.351

4160 + 1040 * 60% 4784


CUT = 311.5385 + 771.321 + 355.351
CUT = 1438.21
Total Costo Unitario produccin:
Costo Unitario de Preparacin = $ 2709.76
Costo Unitario de Empaque = $ 1438.21
Departamento de Preparacin
Terminadas y transferidas 5200 * 2709.76 = 14090.752
Terminadas y retenidas
EN PROCESO:
Materiales = (700 * 80%) * 1482.64 = 30278,4
M. O = (700 * 80%) * 711.81 = 398613,6
Cif = (700 * 50%) * 515,315 = 180360,25
Total distribucin costos = 15500.004,25
Departamento de Empaque
Terminadas y transferidas 4160 * 4147,97 = 17255.255,2
En proceso: costos propios.
Materiales = (1040 * 100%) * 3115385 = 321000,04
M.O = (1040 * 600%) * 771,321 = 481304,304
Cif = (1040 * 600%) * 355,351 = 221739,024
-----------------1027.043,37
Costo proceso anterior = 1040 * 2709,76 = 2818.150,4

Costo Preparacin Costo Empaque


Materiales 8540.000 Materiales 1620.000
M.O 4100.000 M.O 3690.000
Cif 2860.000 Cif. 1700.000
---------------- --------------$ 15500.000 $ 7010.000
Clculos costo unitario y ajuste vitrina enfriadora
PRAPARACION:
Cu Material = 8540.000 / (5200 + 700 * 80%)
= 8540.000 / (5200 + 560)
= 8540.000 / 5760
= 1482.64
Cu MO = 4100.000 / (5200 + 700 * 80%)
= 4100.000 / 5760
= 711.81
Cu Cif = 2860.000 / (5200 + 700 * 50%)
= 2800.000 / 5550
= 515.31
Cu Total = $2709.76
Terminadas y transferidas al proceso de empaque:
5200 * 2709.76 = 14090.752
En proceso.
Materiales = (700 * 80%) * 1482.64 = 830278.4

Mano Obra = (700 * 80%) * 711.81 = 398613.6


Cif = (700 * 50%) * 515.31 = 180360
Total Costo Unidades de Proceso = 1409.252
EMPAQUE
Cmaterial = 311.54
CMO = 771.32
CCif = 355.35
Cu Total = 1438.21
Terminadas proceso Empaque = (1438.21 * 700) = 1006.747
Costo total vitrina = 7478.692 + 1006.747
Costo total = 8485.492