You are on page 1of 14

Membancuh dan Meletak Konkrit Dengan Tangan.

TITLE/PROJECT: Pembanggunan Perumahan Era Moden Koperasi Malaysia. DESCRIPTION: Reinforced in-situ concrete grade 25 in isolated column. ELEMENT/TRADE/ WORK CATEGORY KERJA KONKRIT UNIT RATE m3 220.70 OUTPUT (RM) DATA MANIPULATION Checklist: 1. Material 2. Labour 3. Overhead 4. Profit DATA: Konkrit gred 25 = konkrit campuran 1 : 1, 1/2 : 3 Kos simen = RM 11.08/kampit (50 kg) Kos pasir = RM 44.31/m3 Kos batu baur = RM 32.60/m3 Wastage = 50% LABOUR CONSTANT: Pekerja biasa = RM 50.00/day A. Kos Bahan 1 m3 simen = 28 kampit x RM 11.08 1, 1/2 m3 pasir = 1.50 m3 x RM 44.31 3 m3 batu baur = 3.00 m3 x RM 32.60 Wastage = 50% Kos bahan untuk 5.50 m3 Kos bahan /m3 = RM711.77 5.50 m3 B. Labour Membancuh Pekerja biasa = 2.00 jam x RM 50.00 8.00 jam Mengangkat dan meletak. Pekerja biasa = 8.00 jam x RM 50.00 8.00 jam Total material & labour. Overhead = 10% Profit = 5% Total / m3

RM 310.24 66.47 97.80 474.51 237.26 711.77 Cost of material / m2. RM 129.41

RM 12.50

50.00 62.50 191.91 19.19 9.60 RM 220.70

Kerja Konkrit Oleh Sub-Kontraktor Buruh.


TITLE/PROJECT: Pembanggunan Perumahan Era Moden Koperasi Malaysia. DESCRIPTION: Reinforced in-situ concrete grade 25 in suspended floor slab not exceeding 100mm thick. DATA MANIPULATION Checklist: 1. Material 2. Labour 3. loji. 4. Overhead 5. Profit DATA: Sebut harga konkrit siap bancuh = RM 149.37/m3 (incld. delivery) output kren meletak konkrit untuk lantai = 25 m3/hari Wastage = 2% Profit & Overhead = 15% LABOUR CONSTANT: Sebut harga konkrit oleh subkontraktor buruh = RM 70.00/m3 A. Kos Bahan 1 m3 konkrit siap bancuh Wastage = 2% Cost of material / m2. B. Labour Kos mengangkut dan meletak konkrit Sebut harga subkontraktor buruh C. loji Kos kren/m3 = RM 500.00 25m3 Total material, labour & Plant. Overhead = 10% Profit = 5% Total / m3 ELEMENT/TRADE/ WORK CATEGORY KERJA KONKRIT UNIT RATE m3 278.72 OUTPUT (RM)

RM 149.37 2.99 RM 152.36

70.00

20.00 242.36 24.24 12.12 RM 278.72

Genting Bumbung Konkrit Manca.


TITLE/PROJECT: ELEMENT/TRADE/ WORK CATEGORY Pembanggunan Perumahan Era Moden Koperasi Malaysia. BUMBUNG DESCRIPTION: UNIT RATE 380mm x 230mm interlocking concrete roofing tiles to 75mm head lap and 35mm side lap laid at 40' pitch, each tile hailed every alternate m2 105.54 course on 50mm x 25mm sawn pressure treated S.G. B timber battens OUTPUT (RM) DATA MANIPULATION Checklist: 1. Material 2. Labour 3. Overhead 4. Profit DATA: Genting konkrit 380mm x 230mm = RM 1.40/ no Kayu 50mm x 25mm = RM 1.80/ m Paku = RM 4.50/ kg Paku baten 63mm panjang = 220 no./ kg Paku genting 50mm panjang = 260 no./ kg Jarak Kasau = 600mm Overhead = 10% Profit = 5% LABOUR CONSTANT: Tukang genting = RM 60.00/day Pekerja biasa = RM 50.00/day A. Kos Bahan Genting = 16.81 no x RM 1.40 Baten kayu = 3.28 x RM 1.80 Paku baten = 6 no x RM 4.50 220 no Paku genting = 25 no x RM 4.50 290 no Wastages = 5% Cost of material / m2.

RM 23.53 5.90 0.12 0.29 29.84 1.49 RM 31.33

Genting Bumbung Konkrit Manca.


B. Labour. Tukang genting = 0.30 jam x RM 60.00 8 jam Pekerja biasa = 0.30 jam x RM 50.00 8 jam Total material & labour. Overhead = 10% Profit = 5% Total / m2

RM 2.25

1.88 6.33 91.77 9.18 4.59 RM 105.54

Bumbung Genting Tanah Liat Biasa.


TITLE/PROJECT: ELEMENT/TRADE/ WORK CATEGORY Pembanggunan Perumahan Era Moden Koperasi Malaysia. BUMBUNG DESCRIPTION: UNIT RATE 265mm x 165mm plain clay roofing tiles to 70mm head lap laid at 35' pitch, cach tile twice nailed every fifth course on 50mm x 25mm sawn m2 105.54 pressure treated S.G. B timber battens. OUTPUT (RM) DATA MANIPULATION Checklist: 1. Material 2. Labour 3. Overhead 4. Profit DATA: Genting tanah liat biasa 265mm x 165mm = RM 1.00/ no Kayu 50mm x 25mm = RM 1.80/ m Paku = RM 4.50/ kg Paku baten 63mm panjang = 220 no./ kg Paku genting 44mm panjang = 290 no./ kg Jarak Kasau = 600mm Overhead = 10% Profit = 5% LABOUR CONSTANT: Tukang genting = RM 60.00/day Pekerja biasa = RM 50.00/day A. Kos Bahan Genting = 62.16 no x RM 1.00 Baten kayu = 10.26m x RM 1.80 Paku baten = 17 no x RM 4.50 220 no Paku genting = 25 no x RM 4.50 290 no Wastages = 5% Cost of material / m2.

RM 62.16 18.47 0.35 0.39 81.37 4.07 RM 85.44

Bumbung Genting Tanah Liat Biasa.


B. Labour. Tukang genting = 0.46 jam x RM 60.00 8 jam Pekerja biasa = 0.46 jam x RM 50.00 8 jam Total material & labour. Overhead = 10% Profit = 5% Total / m2

RM 3.45

2.88 6.33 91.77 9.18 4.59 RM 105.54

Kaca Tingkap Logam.


TITLE/ PROJECT. Pembanggunan Perumahan Era Moden Koperasi Malaysia. DESCRIPTION: 6mm thick clear float glass to metal with clips and putty in panes 0.50 - 1.00. DATA MANIPULATION Checklist: 1. Material 2. Labour 3. Overhead 4. Profit DATA: Kos kaca apungan cerah 6mm tebal = RM 59.65 Clip untuk memasang kaca = RM 1.00 Wastage = 3% Overhead = 10% Profit = 5% LABOUR CONSTANT: Tukang kaca = RM 70.00 A. Kos Bahan Kaca apungan cerah 1kg dempul = 1kg x RM 10.00 Clip untuk memasang kaca Wastages = 3% Cost of material / m2 B. Labour Tukang kaca / m2 = 0.60 jam x RM70.00 8 jam Total material + labour ELEMENT/TRADE/ WORK CATEGORY GLASS UNIT RATE m2 89.72 OUTPUT (RM)

59.65 10.00 1.00 70.65 2.12 RM 72.77

RM 5.25 78.02

Overhead = 10% Profit = 5% Total / m2

7.80 3.90 89.72

Kaca Tingkap Kayu.


TITLE/ PROJECT. Pembanggunan Perumahan Era Moden Koperasi Malaysia. DESCRIPTION: 5 mm clear sheet glass to wood with screwed beads in panes 0.10 - 0.50. DATA MANIPULATION Checklist: 1. Material 2. Labour 3. Overhead 4. Profit DATA: Kos Dempul = RM 10.00 Kaca Keping Cerah 5mm Tebal = RM 45.95 / m2 Wastage = 10% LABOUR CONSTANT: Tukang Kaca = RM 70.00 / Day A. Kos Bahan Kaca keping cerah Kos dempul = 2.00 kg. x RM 10.00 Wastages = 10% Cost of material / m2 B. Labour Tukang kaca / m2 = 1.00 jam x RM70.00 8 jam Total material + labour Overhead = 10% Profit = 5% Total / m2 ELEMENT/TRADE/ WORK CATEGORY GLASS UNIT RATE m2 93.50 OUTPUT (RM)

RM 45.95 20.00 65.95 6.60 RM 72.55

8.75 81.30 8.13 4.07 RM 93.50

Kayu Gelegar Lantai.


TITLE/ PROJECT: ELEMENT/TRADE/ WORK CATEGORY Pembanggunan Perumahan Era Moden Koperasi Malaysia. KERJA KAYU DESCRIPTION: UNIT RATE 50 mm x 125mm sawn pressure treated S.G. B timber floor members m 21.13 DATA MANIPULATION Checklist: 1. Material 2. Labour 3. Overhead 4. Profit DATA: Kos kayu 50mm x 125mm = RM 15.95/m. Kos paku 1 kg = RM 4.50 Wastage = 10% Overhead = 10% Profit = 5% LABOUR CONSTANT: Tukang kayu = RM 65.00/day A. Kos Bahan Kayu Pembaziran & pertindihan = 10% Paku = 0.02 kg x RM 4.50 Cost of material / m2. B. Labour Memotong dan memasang kayu. Tukang kayu = 0.09 jam x RM 65.00 8.00 jam Total material & labour. Overhead = 10% Profit = 5% Total / m OUTPUT (RM)

RM 15.95 1.60 0.09 RM 17.64

0.73 18.37 1.84 0.92 RM 21.13

Kasau Bumbung Kayu Curam.


TITLE/ PROJECT: Pembanggunan Perumahan Era Moden Koperasi Malaysia. DESCRIPTION: 50 mm x 100mm sawn pressure treated S.G. B timber pitched roof members. DATA MANIPULATION Checklist: 1. Material 2. Labour 3. Overhead 4. Profit DATA: Kos kayu 50mm x 100mm = RM 12.75/m. Kos paku 1 kg = RM 4.50 Wastage = 10% Overhead = 10% Profit = 5% LABOUR CONSTANT: Tukang kayu = RM 65.00/day A. Kos Bahan Kayu Pembaziran & pertindihan = 10% Paku = 0.02 kg x RM 4.50 Cost of material / m2. B. Labour Memotong dan memasang kayu. Tukang kayu = 0.10 jam x RM 65.00 8.00 jam Total material & labour. Overhead = 10% Profit = 5% Total / m ELEMENT/TRADE/ WORK CATEGORY KERJA KAYU UNIT RATE m 17.17 OUTPUT (RM)

RM 12.75 1.28 0.09 RM 14.12

0.81 14.93 1.49 0.75 RM 17.17

Turapan simen dibancuh dengan tangan.


TITLE/PROJECT: ELEMENT/TRADE/ WORK CATEGORY Pembanggunan Perumahan Era Moden Koperasi Malaysia. KERJA KEMASAN DESCRIPTION: UNIT RATE 25mm thick cement and sand (1:3) paving with steel trowelled finish to floor level or to falls not exceeding 15' from horizontal on concrete m2 9.58 base. OUTPUT (RM) DATA MANIPULATION Checklist: 1. Material 2. Labour 3. Mortar 4. Overhead 5. Profit DATA: Kos simen = RM 11.08/kampit (50 kg) Kos pasir = RM 44.31/m3 Wastage = 1/3 Overhead = 10% Profit = 5% LABOUR CONSTANT: Tukang ubin = RM 65.00/day Pekerja biasa = RM 50.00/day A. Kos Bahan Mortar simen (1:3) 1 m3 simen = 28 kampit x RM 11.08 3 m3 pasir = 3 m3 x RM 44.31 Wastages = 1/3 Kos bahan bagi 4 m3 Kos bahan / m3 = RM 590.89 4.00 m3 B. Labour Membancuh mortar Pekerja biasa = 2.00 jam x RM 50.00 8.00 jam

RM 310.24 132.93 443.17 147.72 590.89

Cost of material / m2.

RM 147.72

12.50 160.22

Turapan simen dibancuh dengan tangan.


C. Kos Mortar/m3 kos mortar 25mm tebal/m2 = RM 160.22 x 25mm 1000mm Menghampar dan merata turapan. Tukang ubin = 0.30 jam x RM 65.00 8 jam Pekerja biasa = 0.30 jam x RM 50.00 8 jam

RM 4.01

RM 2.44

1.88 4.32 8.33

Overhead = 10% Profit = 5% Total / m2

0.83 0.42 RM 9.58

Turapan Simen Dibancuh Dengan Pembancuh Konkrit.


TITLE/PROJECT: Pembanggunan Perumahan Era Moden Koperasi Malaysia. DESCRIPTION: 25mm thick cement and sand (1:3) paving with steel trowelled finish to floor level or to falls not exceeding 15 from horizontal on concrete base. DATA MANIPULATION Checklist: 1. Material 2. Labour 3. Loji 4. Overhead 5. Profit DATA: Kos simen = RM 11.08/kampit (50 kg) Kos pasir = RM 44.31/m3 Wastage = 1/3 Sewa pembancuh konkrit 5/3, 1/2 = RM 300.00 / bulan. Bilangan hari kerja = 26 hari/ bulan. Overhead = 10% Profit = 5% LABOUR CONSTANT: Tukang ubin = RM 65.00/day Pekerja biasa = RM 50.00/day A. Kos Bahan Mortar simen (1:3) 1 m3 simen = 28 kampit x RM 11.08 3 m3 pasir = 3 m3 x RM 44.31 Wastages = 1/3 Kos bahan bagi 4 m3 Kos bahan / m3 = RM 590.89 4.00 m3 ELEMENT/TRADE/ WORK CATEGORY KERJA KEMASAN UNIT RATE m2 OUTPUT (RM) 9.66

RM 310.24 132.93 443.17 147.72 590.89

Cost of material / m2.

RM 147.72

Turapan Simen Dibancuh Dengan Pembancuh Konkrit.

B. Loji. Membancuh mortar. Sewa Pembancuh/ hari = RM 300.00 26 hari Kos pengendalian pembancuh/ hari. Operator Pekerja Biasa Diesel = 1.10 liter x 8 jam x RM 1.70 Minyak Pelincir = 0.04 liter x 8 jam x RM 20.00

RM 11.54

RM 70.00 50.00 14.96 6.40 152.90

Kos pembancuh/ jam = RM 152.90 8 jam Output pembancuh = 1.25 m3/ jam Kos membancuh/ m3 = RM 19.11 1.25 m3

19.11

RM 15.29 163.01

C. Kos Mortar/m3 Kos mortar 25mm tebal/ m3 = RM 163.01 x 25mm 1000mm Menghampar dan merata turapan. Tukang ubin = 0.30 jam x RM 65.00 8 jam Pekerja biasa = 0.30 jam x RM 50.00 8 jam

RM 4.08

2.44

1.88 RM 8.40

Overhead = 10% Profit = 5% Total / m2

0.84 0.42 RM 9.66

You might also like