Package No. 5
CONCRETING OF J. P. LAUREL ROAD FROM NATIONAL HIGHWAY TO BRGY. SITE
Brgy. J. P. Laurel, Panabo City
Contract Titile:
Location:
Bidder:
Address:
Approved Budget for the Contract (ABC):
Bid Prices
ABC
Item No.
102 (2)
103 (1)
103 (3)
104 (1)
105 (1)
201
311
404
405
SPL-1
SPL-2
SPL-3
Description
Unit
cu.m.
cu.m.
cu.m.
cu.m.
Sub-Grade Preparation
sq.m.
Aggregate Base Preparation
cu.m.
Portland Cement Concrete Pavement sq.m.
Class A (0.20m thick)
Reinforcing Steel
Structural Concrete
CHB Canal Lining with Plastering
Project Signboard
Warning Devices
kgs
cu.m.
sq.m.
units
units
Quantity
Unit Price
(Pesos)
Amount
(Pesos)
As Calculated
w/o Tax
Amount
12% Tax
w/ 12% Tax
Unit Price
(w/o Tax)
Total
(w/o Tax)
Variance
186.00
16.59
9.00
316.00
1,528.35
276.00
157.56
265.66
1,534.43
543.71
24.66
892.37
29,305.28
4,407.28
13,809.91
171,810.93
37,689.78
246,295.32
200.86
573.55
1,718.16
699.56
58.31
969.23
37,359.96
9,515.19
15,463.44
221,060.96
89,118.09
267,507.48
33,357.10
8,495.70
13,806.64
197,375.85
79,569.74
238,845.97
4,002.85
1,019.48
1,656.80
23,685.10
9,548.37
28,661.52
37,359.95
9,515.18
15,463.44
221,060.95
89,118.11
267,507.49
179.34
512.10
1,534.07
624.61
52.06
865.38
33,357.24
8,495.74
13,806.63
197,376.76
79,565.90
238,844.88
1,528.35
1,240.44
1,895,825.89
1,170.77
1,789,346.33
1,597,630.65
191,715.68
1,789,346.33
1,045.33
1,597,630.11
-5.62%
90.20
7,401.30
1,196.81
2,628.07
6,570.18
110,089.74
94,218.50
177,127.70
2,628.07
6,570.18
77.85
6,335.78
1,109.31
5,085.56
11,413.56
95,021.37
80,654.48
164,177.88
5,085.56
11,413.56
84,840.70
72,012.93
146,587.39
4,540.68
10,190.68
10,180.88
8,641.55
17,590.49
544.88
1,222.88
95,021.58
80,654.48
164,177.88
5,085.56
11,413.56
69.51
5,656.95
990.46
4,540.68
10,190.68
84,841.82
72,012.97
146,588.08
4,540.68
10,190.68
-13.69%
-14.40%
-7.31%
93.51%
73.72%
2,785,724.31
2,487,254.03
298,470.48
2,785,724.51
2,487,251.49
-0.15%
1,220.57
12.73
148.00
1.00
1.00
2,789,778.60
Remarks:
As Read
Unit Price
Amount
(Pesos)
(Pesos)
KMMPC is a tax exempt cooperative. Inclusion of tax is considered in the correction of bids pursuant to GPPB Circular No. 02-2010 issued on 24 November 2010.
Bid price as read of the bidder is inclusive of tax as reflected in the detailed estimates. High variances for most items are observed.
Bid price is within the Approved Budget for the Contract (ABC).
27.49%
115.90%
11.97%
28.67%
136.45%
8.61%
No. 5
SITE
o City
179.34
512.10
1,534.07
624.61
52.06
865.38
0.00
0.00
(0.00)
0.00
(0.00)
(0.00)
1,045.33
69.51
5,656.95
990.46
4,540.68
10,190.68
(0.00)
0.00
0.00
0.00
0.00
0.00
City of Panabo
Package No. 5
CONCRETING OF J. P. LAUREL ROAD FROM NATIONAL HIGHWAY TO BRGY. SITE
Brgy. J. P. Laurel, Panabo City
Contract Titile:
Location:
Bidder:
Address:
Approved Budget for the Contract (ABC):
Bid Prices
ABC
Item No.
102 (2)
103 (1)
103 (3)
104 (1)
105 (1)
201
311
404
405
SPL-1
SPL-2
SPL-3
Description
Unit
cu.m.
cu.m.
cu.m.
cu.m.
Sub-Grade Preparation
sq.m.
Aggregate Base Preparation
cu.m.
Portland Cement Concrete Pavement sq.m.
Class A (0.20m thick)
Reinforcing Steel
Structural Concrete
CHB Canal Lining with Plastering
Project Signboard
Warning Devices
kgs
cu.m.
sq.m.
units
units
Quantity
Unit Price
(Pesos)
Amount
(Pesos)
As Calculated
w/o Tax
Amount
12% Tax
w/ 12% Tax
Unit Price
(w/o Tax)
Total
(w/o Tax)
Variance
186.00
16.59
9.00
316.00
1,528.35
276.00
157.56
265.66
1,534.43
543.71
24.66
892.37
29,305.28
4,407.28
13,809.91
171,810.93
37,689.78
246,295.32
141.63
340.25
1,321.60
557.59
30.60
859.72
26,343.18
5,644.75
11,894.40
176,198.44
46,767.51
237,282.72
23,520.78
5,040.05
10,620.00
157,320.04
41,756.31
211,859.52
2,822.49
604.81
1,274.40
18,878.40
5,010.76
25,423.14
26,343.27
5,644.86
11,894.40
176,198.44
46,767.07
237,282.66
126.46
303.80
1,180.00
497.85
27.32
767.61
23,521.56
5,040.04
10,620.00
157,320.60
41,754.52
211,860.36
1,528.35
1,240.44
1,895,825.89
1,250.00
1,910,437.50
1,705,747.26
204,689.67
1,910,436.93
1,116.07
1,705,745.58
90.20
7,401.30
1,196.81
2,628.07
6,570.18
110,089.74
94,218.50
177,127.70
2,628.07
6,570.18
80.45
6,462.39
1,165.15
4,000.00
9,000.00
98,194.86
82,266.22
172,442.20
4,000.00
9,000.00
87,674.22
73,451.98
153,966.28
4,000.00
9,000.00
10,520.91
8,814.24
18,475.95
480.00
1,080.00
98,195.13
82,266.22
172,442.23
4,480.00
10,080.00
71.83
5,769.99
1,040.31
4,000.00
9,000.00
87,673.54
73,451.97
153,965.88
4,000.00
9,000.00
-10.80%
-12.69%
-2.65%
70.47%
53.42%
2,780,471.78
2,483,956.44
298,074.77
2,782,031.21
2,483,954.06
-0.28%
1,220.57
12.73
148.00
1.00
1.00
2,789,778.60
Remarks:
As Read
Unit Price
Amount
(Pesos)
(Pesos)
BMPC is a tax exempt cooperative. Inclusion of tax is considered in the correction of bids pursuant to GPPB Circular No. 02-2010 issued on 24 November 2010.
Bid price as read of the bidder is inclusive of tax as reflected in the detailed estimates. High variances for some items are observed.
Bid price is within the Approved Budget for the Contract (ABC).
-10.11%
28.08%
-13.87%
2.55%
24.08%
-3.66%
0.77%
No. 5
SITE
o City
126.46
303.80
1,180.00
497.85
27.32
767.61
0.00
(0.00)
0.00
(0.00)
0.00
1,116.07
71.83
5,769.99
1,040.31
4,000.00
9,000.00
(0.00)
(0.00)
(0.00)
(0.00)
-