You are on page 1of 11

IND-BARATH ENERGY(UTKAL) LTD.

AT-SAHAJBAHAL, TEHSIL LAKHANPUR, DIST: JHARSUGUDA, ORISSA

EXECUTIVE SUMMARY
ENVIRONMENTAL IMPACT ASSESSMENT & ENVIRONMENTAL MANAGEMENT PLAN
PROPOSED 2X350 MW COAL BASED POWER PLANT

(JANUARY 2009)
Prepared by

S.S Environics (India) Pvt. Ltd


Plot No : 361/2314 Sustenance At/P.O : Patrapada, Dist : Khurda, Bhubaneswar-751019

Executive Summary for Thermal Power Plant IBEL

EXECUTIVE SUMMARY ES 1.0 INTRODUCTION

M/s- Ind-Bharat Energies (Utkal) Ltd, of IBPIL Group, Hyderabad proposes to


commission 700 (2x350) MW coal based power plant at Sahajbahal village of Jharsuguda district, Orissa. The nearest major town is Belpahar which is about 25 km from the project site.

M/s S.S. Environics (India) Pvt. Ltd., (SSE), Bhubaneswar, has been retained to
carry out Environment Impact Assessment (EIA) study and to prepare Environment Management Plan (EMP) for the proposed coal based power plant. The study has been carried out as per the guidelines of Ministry of Environment & Forests (MOEF) and Orissa State Pollution Control Board (OSPCB), Bhubaneswar. The proposed project is designated to be developed under the Environmental Impact Assessment (EIA) Notification and amendments under Environment (Protection) Act (EPA), 1986. Proposed project falls under Category A as per the notification issued on 14th September 2006 by MOEF. As the first step of the notification issued on 14th September 2006, MOEF has issued terms of reference (TOR) for carrying out the EIA/EMP study vide letter No. J13012/31/2008-IA.II(T) Dated the 19th August, 2008 based on the duly filled Form-I along with pre feasibility report submitted and subsequent presentation made to appraisal committee for thermal power plant. In accordance to the approved TOR, an area of 10 km radius centering the proposed project site has been considered as study area and the scope of work for the fieldworks under environmental baseline survey were carried out from 1st March, 2008 to 31st May 2008 except for the data generated for ground level ozone concentration during the period October 2008 to December 2008. ES 2.0 PROJECT DESCRIPTION Location of the Project The proposed thermal power project site is located at Sahajbahal village of Lakhanpur Tehsil, Jharsuguda District, Orissa State and has the following coordinates (as per Survey of India topo-sheet no. 64 -O/14, scale 1:50,000): Latitude Longitude Land Requirement The details of land envisaged for the proposed project are as given below: Sl. No. A. 1. 2. 3. Particulars Main Power Plant Plant Coal Handling system including railway marshalling yard Water system Area (Hect.) 36.0 60.0 22.0 : 21 o 39' 06 N to 2104016 N : 83o 55' 28 E to 8305616 E

S.S. Environics(India)Pvt.Ltd.

Executive Summary for Thermal Power Plant IBEL

4. 5. 6. B. C. D.

Road Misc. storage yard Ash handling system

08.00 24.0 2.5

Sub total
Green belt for power plant and ash pond area Ash Pond Township Total

152.5
57.5 20.0 10.0 240.0

Proposed land is flat land with 195-212 m above mean sea level (MSL). The land is mostly barren land with some of for single crop cultivation without any seasonal cash crops. The existing land use pattern as per revenue records is as per given hereunder: Sn 1 Particulars Govt. Agriculture Irrigated Unirrigated Homestead Fallow Others Subtotal Total Plant Details The main facilities/machinery envisaged for the proposed project is summarized hereunder: 2 nos of steam boilers with associated accessories. Each boiler shall generate steam @ 975 tph at TMCR, 170-176 kg/cm2 (abs.) and 5415 0C; 2 nos of steam turbine with associated accessories; Coal handling and water treatment facilities; For ash disposal, a pond covering an area of 49.42 acres (20 hect.) is envisaged within the project premises; Raw water shall be brought through pipeline from Mahanadi river which is approx. 4 Km from proposed project site, A Railway sliding from Belpahar Coalfield of MCL to the proposed project site; and Township for around 200 families. Raw Material The coal and water are the main raw material for the proposed project and details for the same are summarized hereunder: Sn Raw Material Quantity Source Mode of Transport 1 Coal 14,700 TPD @MCR Belpahar Rail Coalfields of MCL 2 Water 65760 m3/day Mahanadi Pipeline River 30 16.67 46.67 240.0 Area (Ha.) Pvt. 0.0 192.53 0.8 193.33

2 3 4

S.S. Environics(India)Pvt.Ltd.

ii

Executive Summary for Thermal Power Plant IBEL

Manpower The total manpower envisaged for the proposed power plant is 525. Project Cost Total estimated cost of the project is Rs 3000.0 crores. ES 3.0 DESCRIPTION OF THE ENVIRONMENT Air Environment: Micrometeorological data were collected with respect to wind speed, wind direction, humidity, rainfall and temperature and cloud cover by manual observation at Sahajbahal village; and ambient air quality monitoring was carried out at a total of 9 locations. The wind velocity remained in the range from calm to 18.5 m/s for most of the days in summer season. The dominant wind direction was from Southwest. The concentrations (g/m3) of Suspended particulate matter (SPM), Respirable particulate matter (RSPM), SO2, NOx and CO in the core zone as well as buffer zone on a 24 hourly basis are in the range of 93.50 136.10 g/m3, 19.035.82 g/m3, BDL 5.58 g/m3, BDL-11.90 g/m3 , BDL-0.11 mg/m3 respectively and the value of O3 on a 1 hourly average basis ranged between BDL 0.012 ppm. These values are well below stipulated standards of CPCB. Dustfall measurement in the study area at 5 (five) locations. The lowest value was at Bhagaban Palli (1.4 metric tonne/ sq.km/month) while the highest value was at Samleitikira (2.7 metric tonne/ sq.km/month). Noise Environment: Ambient noise monitoring was carried out in the study region at seven locations. The noise levels in residential area are in the range of 47.3 51.3 dB(A) at day time and 40.8 42.7dB(A) at night time respectively. Water Environment: To assess the water quality, water samples were collected from 12 locations with 3 locations for surface water and 9 locations for ground water. Water samples were analysed for physio-chemical, bacteriological and biological characteristics. Values of physico-chemical parameters for surface and ground water were observed to be below the stipulated standards. In surface water, the density of total coliforms (9602200 MPN/100 ml) was comparable to any normal water quality with slight organic contamination in surface water near villages. The surface water resources are compared with the standard for IS-2296 under Class-C while the groundwater was with BIS-10500 for drinking water. Land Environment: Soil samples were collected from 5 locations from study area and analysed for physico-chemical status, nutrient status. Texture of soil -sandy loam at two locations while loam at other three locations, Bulk density- 1.37 1.59 gm/cc, porosity 17.2- 21.6 %, Normal soil: Moderately acidic, Nutrient status: Organic carbon, total nitrogen, sulphate and potassium were found to be in the range of 2.9 3.9 %, 0.061 0.086 %, 0.13 -0.18% and 0.05 0.09%. Using satellite imagery, the land use pattern of the study area have been studied and discussed in detail in chapter 3 of EIA/EMP Report. Biological Environment: A detailed survey has been carried out to assess the floral and faunal species present in the study area. The list of flora and fauna observed during the field visit is presented in chapter 3 of EIA/EMP Report. Mammals like Sloth Bear (Bhalu), Wild Boar (Barha), Spotted Deer (Harina), Indian Wolf (Gadhia), Hanuman Langur (Hanumankada), Common Mangoose (Neula), Malbar Giant Squirrel (Bela khai musa), etc are seen. Among birds Bani, Pata chadhei, Baga, Kajalapati, Koili, Batasia, Baya, Kumbhatua, Damarakao, Kua, Hansarali, Matia chila, Kala

S.S. Environics(India)Pvt.Ltd.

iii

Executive Summary for Thermal Power Plant IBEL

Titter, Chila, Haladibasanta, Kochilajhai, Kathahana, Pecha, Chataka, Dhauka, Gharachatia and Pecha. Similarly, reptiles like Naga, Chiti, Dhamana are also seen. During the field survey and discussion with the local villagers as well as Forest Dept., it was found that some of the Siberian birds do visit the Hirakud reservoir during winter. As suggested, a site specific wildlife conservation plan is in process of preparation. Socio-economic Environment: Demographic Structure of Study Area: Population: 52767, Sex ratio: 951 females/1000 males, Literacy rate: 61.04%, Scheduled caste: 19.26 %, schedule tribe: 29.68%. Infrastructure: moderately good. ES 4.0 ANTICIPATED ENVIRONMENT IMPACTS & MITIGATION MEASURES Land Use Pattern About 80.55% (193.33 hect.) of total land proposed to be acquired belongs to private land while rest i.e. 19.45% (46.67 hect.) belongs to government land. All private land proposed to be acquired is mostly barren with some of for single crop cultivation without any seasonal cash crops. While government land proposed to be acquired is designated as Fallow land (30 hect) and others (16.67 hact). Ecology The overall impact on the terrestrial ecology can be considered positive, as green belt, will be developed and maintained by IBEL in the area. Out of total area of 240 Ha., an area of about 57.5 ha. has been kept for greenbelt development/plantation within the premises.

It is evident from the above discussion that the project site does not have any ecological sensitive areas. Flora & fauna present on project site are common types. As the construction phase shall be confined to the proposed project site only, hence, impacts on the ecology due to construction of the proposed project are not envisaged.
Air Quality The details of air pollution generation hereunder: Sn Particular Sources s 1 Stack Boilers emission

and its management during operation are given Parameter SPM, SO2, NOX & CO Control/Treatment 1. ESP with designed outlet dust concentration of 50 mg/Nm3; 2. Stack height is 220 m which is larger than the value as per 14Q0.3, where Q is the SO2 generation in Kg/hr; 3. A well-designed burner system to limit the core flame temperature to keep the NOx concentration equal to less than 750 mg/Nm3; 4. Keeping a positive oxygen balance; and 5. An ammonia dosing system before ESP shall be provided.

S.S. Environics(India)Pvt.Ltd.

iv

Executive Summary for Thermal Power Plant IBEL

DG sets 2 Fugitive Emission Crushers and ash storage in silo Transfer points during collection and transportation of coal and ash SPM

1. Stack height as prescribed by MoEF 1. Bag filters with designed outlet dust concentration of 50 mg/Nm3 1. Bag filters with designed outlet dust concentration of 50 3 mg/Nm 2. HCSD conveying system for ash transportation 3. Water sprinklers and spray system 1. Water sprinklers and spray system 1. Adequate thickness of insulating material with proper fastening shall be provided

Thermal Emission

Storage of Coal & Ash Boilers and pipelines used for steam

Heat

Prediction of Incremental Ground Level Concentrations (GLCs) of particulate matter, SO2 and NOx is made by using Industrial Source Complex Short Term Model Version-3 (ISCST 3) software developed by US Environmental Protection Agency (USEPA) under two scenarios. Scenario I represent the assessment of impact considering twin flue stack of 275m height and Scenario II represents the assessment of impact considering single flue stack of 220m height. The finding of the same is given below. Pollutants Sn SPM SO2 NOx 1 Predicted incremental Value due to Operation of Plant Scenario I 0.70178 21.33305 (4000,-3600) (4000,-3600) Scenario II 1.94392 (3000,-3000) 47.7422 (3000,-3000) 10.52735 (4000,-3600) 29.08755 (3000,-3000)

Water Resources During the operation of proposed project, the total water requirement shall be 65760 m3/day. River Mahanadi is considered to be the source of fresh water for the proposed project. The river water shall be brought to the plant by laying pipelines i.e. from the intake point to the proposed project site. Investigations (refer chapter 3) indicate that plenty of surface water is available in the study area. The permission for withdrawal of water is in the process. The withdrawal of water resources during the operation phase will not have significant impact on the water resources of the area. Water Quality The waste water treatment and management plan is developed with zero discharge concepts. The salient features of the envisaged waste water management are as follows: v

S.S. Environics(India)Pvt.Ltd.

Executive Summary for Thermal Power Plant IBEL

Sn 1

Particulars Cooling Tower blow down & Boiler blow down DM water Domestic water

Generation Rate (m3/hr) 415 (412+3)

Disposal Shall be used for Coal Handling plant, dust extraction & suppression and ash handling system. Shall be used for spray in coal yard after treatment Shall be used for greenbelt development after treatment in STP

2 3

7 10

Total

432

Solid Waste The details of main solid waste generation and management are summarized hereunder: Sn Type of Source Quantity Disposal Waste 1 Coal rejects mill Coal crushing screening & 268275 TPA (@ 365 days per annum) Through conveyor, rejects will be stored in the silo and from silo it will be the of transported 2 Fly Ash Boilers 1931580 TPA (@ 365 days per annum) through

truck for reuse. Manufacturing cement, bricks / blocks for captive use and sale. Disposed off as High Concentration Slurry in the ash pond. 3 Bottom ash 482895 TPA (@ 365 days per annum) 4 Sludge Raw Plant water 7 tpd during Filling of abandoned coal mines Disposed off as slurry in the ash pond. Disposed off in OC pits of MCL Shall be used for landfill Treatment non-monsoon season 32 tpd during monsoon season ETP STP 6-12 kg/day 0.2 tpd Shall be disposed off as hazardous waste Shall be used for plantation as manure

S.S. Environics(India)Pvt.Ltd.

vi

Executive Summary for Thermal Power Plant IBEL

Occupational Health & Safety During operation phase, dust causes the main health hazard. Other health hazards are due to gas cutting, welding, noise and high temperature and micro ambient conditions especially near the furnace doors, platforms and steam pipelines which may lead to adverse effects (Heat cramps, heat exhaustion and heat stress reaction) leading to local and systemic disorders. Injuries in industries are usually of minor nature like bruises, cuts, and abrasions because of manual handling. However, serious accidents due to common reasons like fall from height and entrapment of limbs in machinery are also possible. The following measures are envisaged: Almost all material handling systems are automatic i.e. unmanned. The workers engaged in material handling system are provided with personal protective equipment like dust masks, respirators, helmets, face shields, etc.; Any worker found to develop symptoms of dust related diseases is changed over t o other jobs in cleaner areas; General Health Measures

a) Sanitary facilities shall be well equipped with supplies (e.g., protective creams) and employees shall be encouraged to wash frequently, particularly those exposed to dust, chemicals or pathogens; b) Ventilation systems shall be provided to control work area temperatures and humidity; c) Personnel required to work in areas of high temperature and/or high humidity shall be allowed to take frequent breaks away from these areas; and d) Pre-employment and periodic medical examinations shall be conducted for all personnel, and specific surveillance programs instituted for personnel potentially exposed to health hazards. General Safety Measures a) Conveyors and similar machinery shall be provided with a means for stopping them at any point; b) Shield guards or guard railings shall be installed at all belts, pulleys, gears and other moving parts; c) Elevated platforms and walkways, and stairways and ramps shall be equipped with handrails, toe boards and non-slip surfaces; d) Electrical equipment shall be grounded, well insulated and conform with applicable codes; e) Employees shall be provided with hard hats, safety boots, eye and ear protection, and snug fitting gloves as appropriate; f) Masks and dust-proof clothing shall be provided to personnel working in areas with high dust levels; and g) Procedures shall be strictly enforced for the storage, handling, and transport of explosives, flammable and hazardous materials.

S.S. Environics(India)Pvt.Ltd.

vii

Executive Summary for Thermal Power Plant IBEL

ES 5.0

ENVIRONMENT MONITORING PLAN The recommended frequency and parameter of environment monitoring for the proposed project is given below during construction and operation. However, proposed monitoring programme shall be modified as stipulated by MOEF/ CPCB/OSPCB: Monitoring Plan during Construction Sn 1 2 3 Component Ambient Air Waste Water Noise Level Parameter TSPM, RSPM, SO2, NOx, CO pH,TDS, SS, BOD5, COD, Oil & grease and Heavy metals Hourly Leq Locations 3-4 locations at the boundary of premises Out put from septic tank/soak pit 3-4 locations within the premises Frequency 24 hourly samples, twice in a week Once in a month Continuously during working hour, twice in a week

Monitoring Plan during Operation Sn 1 2 3 Component Ambient Air Fugitive emission Stack Parameter TSPM, RSPM, SO2, NOx, CO TSPM, RSPM TSPM, SO2, NOx, CO TSPM 3 4 Noise Level Waste Water Hourly Leq pH, Temperature, TDS, SS BOD5, COD, Oil & grease & heavy metals As per GSR 422 (E) for inland surface water Locations 3-4 locations at the boundary of premises 8-10 locations dust processing units All stacks attached to units where combustion take place All stacks attached to dust generating units At the boundary of the plant premises At outlet of ETP Frequency 24 hourly samples, twice in a week 8 hourly samples, twice in a month Once in three month Once in three month Once in two week for 24 hours Once in three months

At outlet of STP

Once in three months

IBEL shall developed in-house monitoring & testing facility to the possible extent, otherwise, shall hire the external agency for the same. Proposed monitoring and testing shall be carried out as per the methods recommended by CPCB/ CPCB/OSPCB.

S.S. Environics(India)Pvt.Ltd.

viii

Executive Summary for Thermal Power Plant IBEL

ES 6.0

ADDITIONAL STUDIES The following additional studies have been carried out with respect to the proposed power plant. Risk Assessment & Mitigation measures R & R Action Plan Rain water harvesting structures Hydrogeological study

ES 7.0

BENEFITS OF PROJECT Property Management A total 240 Ha. land is proposed to be acquired out of which 193.33 ha belongs to private land and 46.67 ha belongs to Govt. land. Land mainly belongs to single crop cultivation without any seasonal cash crops. The detail of oustees as a result of proposed acquisition of land is as per given hereunder: Sn 1 2 3 Total Particulars Land Oustee House oustee Land & House Oustee Number of Landlords 150.0 9.0 0.0 159.0

Economic Growth Increased power generation shall in general result in overall industrial growth, which in turn would generate direct and indirect opportunities of employment and business in the region. Increase in industrial growth would result in payment of applicable various types of taxes to the Government that will have positive regional impacts. Employment Establishment or expansion of any industrial activities, results in industrial growth, which in turn would generate direct and indirect opportunities of employment. As per estimate, total manpower envisaged during the operation of the proposed power plant shall be 525 in nos. In addition to above, casual labourer shall also be required during operation phase on regular basis. The unskilled labourer shall be by and large recruited from the local area and for others and preference shall be given to locals on the basis of availability of skill. In addition to direct employment, proposed project shall generate a number of indirect job opportunities on local and regional basis. The indirect employment opportunities mainly includes more industrial growth, transportation of coal, supply of essential commodities, feeding to families migrated from outsides, casual labourer etc.

S.S. Environics(India)Pvt.Ltd.

ix

Executive Summary for Thermal Power Plant IBEL

ES 8.0

ENVRIONMENT MANAGEMENT PLAN Environment Management Cell It is necessary to have a permanent organizational set up charged with the task of ensuring effective implementation of all identified mitigation measures. Conscious of this, IBEL shall create a department consisting of officers from various disciplines to coordinate the activities concerned with the management and implementation of the environmental control measures during construction and operation phase of the proposed power project. IBEL shall also develop a well-documented system to monitor and control pollution. Basically, this department shall undertake monitoring and auditing of the environmental pollution levels by measuring fugitive emissions, ambient air quality, water and effluent quality, noise level etc. and safety issues, either departmentally or by appointing external agencies wherever necessary. In case, the monitored results of environmental pollution shall be found exceeding the allowable values, the Environmental Management Cell suggests remedial actions and gets these suggestions implemented through the concerned plant authorities. The Environmental Management Cell shall also co-ordinates all the related activities such as collection of statistics w.r.t health of workers and population of the region, afforestation and green belt development. Cost of Environment Management Plan The details of estimated capital and recurring cost of the proposed environmental management plan are as per given hereunder: Sl. Capital Investment Recurring Investment Particulars No (Rs. in lacs) (Rs. in lacs) 1 Air Pollution Control 2280 60 2 Water Pollution Control 210 21 3 Noise Pollution Control 240 12 4 Solid Waste Management 1140 30 5 Environment Monitoring & Management 210 6 6 Occupational Health 240 9 7 Green Belt 180 15 Total 4500 153

S.S. Environics(India)Pvt.Ltd.

You might also like