INTERNAL INTEGRATED MANAGEMENT SYSTEM AUDIT SCHEDULE FOR FINANCIAL YEAR 2012/2013 Effective date: CW 20' 2012
Date Safety & Health Environment System Audit Plant Area Audit Criteria Objective
= PROCESS = SYSTEM
6 June 2012
HA 1
- To ensure all chemical are label and manage properly by comply the requirement. - To ensure the safety signage are implement.
Nurul
Faizah
Yes
9.00 am to 1.00 pm
7 June 2012
Waste Management System - Waste bins (green & orange waste bin)
HA 1
Paint Shop / ISO 14001 satandard, Body Shop / company procedure & Assembly Shop / work instruction. Logistic
- To ensure the waste segregation - To ensure the worker awareness of the useful of waste bin
- Document review (Form and Work instruction, if Shakira / any). Razif / Hamimah - Document assessment (evidence). Mohamad / - Verification of records. Fakhruddin - Interview & work observations. - Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
Nurul
Faizah
Yes
9.00 am to 1.00 pm
13 June 2012
HA 2
- To ensure all chemical are label and manage properly by comply the requirement. - To ensure the safety signage are implement.
Ayu
Padzil / Salahudin / Ridwan / Hamimah Roslan / Khalib / Faizal Padzil / Salahudin / Ridwan / Roslan / Khalib / Faizal
Faizah
Yes
9.00 am to 1.00 pm
14 June 2012
Waste Management System - Waste bins (green & orange waste bin)
HA 2
Body Shop / ISO 14001 satandard, Assembly Shop / company procedure & Commercial work instruction. Vehicle / Logistic
- To ensure the waste segregation - To ensure the worker awareness of the useful of waste bin
- Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
Sobrie
Ayu
Faizah
Yes
A drinking bottle containing a washing solution was found in a scheduled waste bin in the Volkswagen operation, the bottle was not marked with the content. (HA1)
9.00 am to 1.00 pm
20 June 2012
Fire Extinguisher
HA 1
- Document review (Form and Work instruction, if Shakira / - To monitor the fire extinguisher are comply with any). Razif / Mohamad - Document assessment (evidence). the regulation. Hamimah Mohamad / - Verification of records. Fakhruddin - Interview & work observations.
Faizah
No
9.00 am to 1.00 pm
21 June 2012
Waste storage
HA 1 & HA 2
ISO 14001 satandard, Schedule waste company procedure & area work instruction.
- Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
Iqbal
Faizah
Yes
- The scheduled waste, SW305 was found retained more than 180 days (9Oct-2011) in scheduled waste store. (HA1). - No date of generation on scheduled waste was evident for SW429 and SW419 in scheduled waste store. (HA1)
9.00 am to 1.00 pm
27 June 2012
First Aid
HA 1
- To ensure the first aid are allocate at the right place. - To monitor the medical used.
- Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
Nurul
Faizah
No
9.00 am to 1.00 pm
28 June 2012
HA 1
Paint Shop / ISO 14001 satandard, Body Shop / company procedure & Assembly Shop / work instruction. Logistic
- Document review (Form and Work instruction, if - To ensure the secondary containment has been any). applied respectively. - Document assessment (evidence). - To ensure the spill kits are placed at the - Verification of records. potential spill / leakage area. - Interview & work observations.
Erina
Nurul
Faizah
Yes
There have been a few drums with used oil stored in a temporary storage area with no proper labeling about the content and also no secondary containment (HA2)
9.00 am to 1.00 pm
4 July 2012
MSDS / CSDS
HA 1
- To ensure the MSDS are place at area that have chemical. - To ensure the worker understanding.
- Document review (Form and Work instruction, if Shakira / Razif / any). Mohamad Mohamad / Hamimah - Document assessment (evidence). Fakhruddin - Verification of records. / Marzuki - Interview & work observations. - Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations. - Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
Faizah
Yes
The MSDS for Chemfill Buffer (S829A8226) was not available on site (chemical store) (HA1)
9.00 am to 1.00 pm
5 July 2012
HA 1
ISO 14001 satandard, Waste Water company procedure & Treatment Plant work instruction.
- To ensure the effectiveness of the treatment. - To monitor the contractor performance. - To ensure the tools calibration. - To monitor the LPG gas condition.
Sobrie
Kamarudin / Hamimah
Nurul
Faizah
No
9.00 am to 1.00 pm
11 July 2012
HA 1
Body Shop
- To review the HIRARC for any changes. - To ensure the accident report was fill up the JKKP 6 form.
Ayu
Shakira
Hamimah
Faizah
No
9.00 am to 1.00 pm
IMS
INTERNAL INTEGRATED MANAGEMENT SYSTEM AUDIT SCHEDULE FOR FINANCIAL YEAR 2012/2013 Effective date: CW 20' 2012
Date Safety & Health Environment System Audit Plant Area Audit Criteria Objective
= PROCESS = SYSTEM
12 July 2012
HA 1
Body Shop
- To review the EAI for any changes. - To ensure any act or legal requirement are follow.
Ziffi
Razif
Hamimah
Faizah
No
9.00 am to 1.00 pm
18 July 2012
HA 1
Assembly Shop
- To review the HIRARC for any changes. - To ensure the accident report was fill up the JKKP 6 form.
Ayu
Shakira
Hamimah
Faizah
No
9.00 am to 1.00 pm
19 July 2012
HA 1
Assembly Shop
- To review the EAI for any changes. - To ensure any act or legal requirement are follow.
Nurul
Mohamad
Hamimah
Faizah
No
9.00 am to 1.00 pm
25 July 2012
HA 2
Body Shop
- To review the HIRARC for any changes. - To ensure the accident report was fill up the JKKP 6 form.
- Document review (Form and Work instruction, if any). Mohamad - Document assessment (evidence). - Verification of records. - Interview & work observations.
Padzil
Hamimah
Faizah
No
9.00 am to 1.00 pm
26 July 2012
HA 2
Body Shop
- To review the EAI for any changes. - To ensure any act or legal requirement are follow.
- Document review (Form and Work instruction, if any). Mohamad - Document assessment (evidence). - Verification of records. - Interview & work observations. - Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations. - Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations. - Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations. - Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
Padzil
Hamimah
Faizah
No
9.00 am to 1.00 pm
1 August 2012
HA 2
Assembly Shop
- To review the HIRARC for any changes. - To ensure the accident report was fill up the JKKP 6 form.
Erina
Faizah
No
9.00 am to 1.00 pm
2 August 2012
HA 2
Assembly Shop
- To review the EAI for any changes. - To ensure any act or legal requirement are follow.
Erina
Faizah
No
9.00 am to 1.00 pm
8 August 2012
HA 1
Logistic + B10
- To review the HIRARC for any changes. - To ensure the accident report was fill up the JKKP 6 form.
Ayu
Marzuki
Hamimah
Faizah
No
9.00 am to 1.00 pm
9 August 2012
HA 1
Logistic + B10
- To review the EAI for any changes. - To ensure any act or legal requirement are follow.
Ayu
Marzuki
Hamimah
Faizah
No
9.00 am to 1.00 pm
5 September 2012
HA 2
Logistic
- To review the HIRARC for any changes. - To ensure the accident report was fill up the JKKP 6 form.
- Document review (Form and Work instruction, if any). Hamimah - Document assessment (evidence). - Verification of records. - Interview & work observations. - Document review (Form and Work instruction, if any). Hamimah - Document assessment (evidence). - Verification of records. - Interview & work observations. - Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
Azmadi / Ooi
Hamimah
Faizah
No
9.00 am to 1.00 pm
6 September 2012
HA 2
Logistic
- To review the EAI for any changes. - To ensure any act or legal requirement are follow.
Azmadi / Ooi
Hamimah
Faizah
No
9.00 am to 1.00 pm
12 September 2012
HA 2
Commercial Vehicle
- To review the HIRARC for any changes. - To ensure the accident report was fill up the JKKP 6 form.
Sobrie
Khalib
Hamimah
Faizah
No
9.00 am to 1.00 pm
IMS
INTERNAL INTEGRATED MANAGEMENT SYSTEM AUDIT SCHEDULE FOR FINANCIAL YEAR 2012/2013 Effective date: CW 20' 2012
Date Safety & Health Environment System Audit Plant Area Audit Criteria Objective
= PROCESS = SYSTEM
13 September 2012
HA 2
Commercial Vehicle
- To review the EAI for any changes. - To ensure any act or legal requirement are follow.
Sobrie
Khalib
Hamimah
Faizah
No
9.00 am to 1.00 pm
19 September 2012
Fire Extinguisher
HA 2
- Document review (Form and Work instruction, if - To monitor the fire extinguisher are comply with any). the regulation. - Document assessment (evidence). - Verification of records. - Interview & work observations.
Ziffi
Faizah
No
9.00 am to 1.00 pm
20 September 2012
Sewage system
HA 1
ISO 14001 satandard, Sewage company procedure & Treatment Plant work instruction.
- To ensure the effectiveness of the treatment. - To monitor the contractor performance. - To ensure the tools calibration.
- Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
Iqbal
Kamarudin / Hamimah
Nurul
Faizah
No
9.00 am to 1.00 pm
26 September 2012
First Aid
HA 2
- To ensure the first aid are allocate at the right place. - To monitor the medical used.
- Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
Ayu
Faizah
No
9.00 am to 1.00 pm
27 September 2012
HA 1
External Surrounding
- To review the Aspect Impact Analysis for any changes. - To ensure the MSDS are place at the area. - To ensure the storage is comply with MSDS and legal requirement.
- Document review (Form and Work instruction, if any). Hamimah - Document assessment (evidence). - Verification of records. - Interview & work observations.
En. Jamal
Nurul
Faizah
No
9.00 am to 1.00 pm
3 October 2012
MSDS / CSDS
HA 2
- To ensure the MSDS are place at area that have chemical. - To ensure the worker understanding.
- Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
Ziffi
Faizah
Yes
The MSDS for Chemfill Buffer (S829A8226) was not available on site (chemical store) (HA1)
9.00 am to 1.00 pm
4 October 2012
HA 2
Body Shop / ISO 14001 satandard, Assembly Shop / company procedure & Commercial work instruction. Vehicle / Logistic
Padzil / - Document review (Form and Work instruction, if - To ensure the secondary containment has been Salahudin / any). Ridwan / applied respectively. Hamimah - Document assessment (evidence). Roslan / - To ensure the spill kits are placed at the - Verification of records. Khalib / potential spill/leakage area. - Interview & work observations. Faizal - Document review (Form and Work instruction, if - To ensure contractor follow the Aspect Impact any). Analysis & HIRARC. - Document assessment (evidence). - To ensure that all the HAMM requirement been - Verification of records. followed. - Interview & work observations.
Ayu
Faizah
Yes
There have been a few drums with used oil stored in a temporary storage area with no proper labeling about the content and also no secondary containment (HA2)
9.00 am to 1.00 pm
10 October 2012
HA 1 & HA 2
External Surrounding
Nurul
Hamimah
Faizah
No
9.00 am to 1.00 pm
11 October 2012
HA 1
OHSAS 18001 Paint Shop (Pre satandard, company treatment + ED procedure & work Coating) instruction.
- To review the EAI for any changes. - To ensure any act or legal requirement are follow.
- Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
Ayu
Shakira
Hamimah
Faizah
No
9.00 am to 1.00 pm
17 October 2012
HA 1
OHSAS 18001 Paint Shop (Pre satandard, company treatment + ED procedure & work Coating) instruction.
- To review the HIRARC for any changes. - To ensure the accident report was fill up the JKKP 6 form.
- Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
Ziffi
Razif
Hamimah
Faizah
No
9.00 am to 1.00 pm
18 October 2012
HA 1
OHSAS 18001 Paint Shop ( ED satandard, company Sanding + Seam procedure & work Sealant) instruction.
- To review the EAI for any changes. - To ensure any act or legal requirement are follow.
- Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
Nurul
Mohamad
Hamimah
Faizah
No
9.00 am to 1.00 pm
IMS
INTERNAL INTEGRATED MANAGEMENT SYSTEM AUDIT SCHEDULE FOR FINANCIAL YEAR 2012/2013 Effective date: CW 20' 2012
Date Safety & Health Environment System Audit Plant Area Audit Criteria Objective
= PROCESS = SYSTEM
31 November 2012
HA 1
OHSAS 18001 Paint Shop ( ED satandard, company Sanding + Seam procedure & work Sealant) instruction.
- To review the HIRARC for any changes. - To ensure the accident report was fill up the JKKP 6 form.
- Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
Nurul
Mohamad
Hamimah
Faizah
No
9.00 am to 1.00 pm
1 November 2012
HA 1
OHSAS 18001 Paint Shop satandard, company (Primer + Primer procedure & work Sanding) instruction.
- To review the EAI for any changes. - To ensure any act or legal requirement are follow.
- Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
Nurul
Mohamad
Hamimah
Faizah
No
9.00 am to 1.00 pm
7 November 2012
HA 1
OHSAS 18001 Paint Shop satandard, company (Primer + Primer procedure & work Sanding) instruction.
- To review the HIRARC for any changes. - To ensure the accident report was fill up the JKKP 6 form.
- Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
Nurul
Mohamad
Hamimah
Faizah
No
9.00 am to 1.00 pm
8 November 2012
HA 1
OHSAS 18001 Paint Shop (Top satandard, company Coat + Touch procedure & work Up) instruction.
- To review the EAI for any changes. - To ensure any act or legal requirement are follow.
- Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
Nurul
Mohamad
Hamimah
Faizah
No
9.00 am to 1.00 pm
21 November 2012
HA 1
OHSAS 18001 Paint Shop (Top satandard, company Coat + Touch procedure & work Up) instruction.
- To review the HIRARC for any changes. - To ensure the accident report was fill up the JKKP 6 form.
- Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
Nurul
Mohamad
Hamimah
Faizah
No
9.00 am to 1.00 pm
22 November 2012
HA 1 & HA 2
External Surrounding
- To review the Aspect Impact Analysis for any changes. - To monitor the maintenance and the system effectiveness. - To monitor process by work instruction.
- Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
Erina
Faizah
No
9.00 am to 1.00 pm
28 November 2012
Emergency preparedness
HA 1
- Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
9.00 am to 1.00 pm
29 November 2012
HA 1 & HA 2
External Surrounding
- To review the Aspect Impact Analysis for any changes. - To monitor the maintenance and the system effectiveness. - To monitor process by work instruction.
- Document review (Form and Work instruction, if any). - Document assessment (evidence). - Verification of records. - Interview & work observations.
Sobrie
Faizah
No
9.00 am to 1.00 pm