Safe Work Procedure Set Up Surface Drill Rig Document No: Document No Page 2 of 4
Purpose
The purpose of this manual is to provide the operator with the correct information to safely set up a surface drill
Scope
This manual covers the set up a surface drill,
Learning Outcome
At the completion of this training module the operator will be competent to set up a surface drill
PPE Requirements
Hard Hat, Safety Glasses, Safety Boots, Hearing protection, Gloves SAFETY NOTE :
Safe Work Procedure Set Up Surface Drill Rig Document No: Document No Page 3 of 4
STEP
POTENTIAL HAZARD
SAFE WORK PROCEDURE 1. Receive work instructions about the aim, scope, purpose and location of and access to the drilling job and determine likely geological formations for drilling job. 2. Check required hole parameters (e.g. size, depth). 3. Determine location and nature of any installed services near or crossing the proposed drill path. 4. Obtain all necessary permits/consents where required (e.g. to construct or dispose of waste). 5. Develop contingency plans for changes in geological conditions (e.g. depths, materials used in construction).
STEP
POTENTIAL HAZARD
PREPARE TO DRILL
SAFE WORK PROCEDURE 1. Check all required personnel, equipment and supplies are available. 2. Select and wear required personal protective equipment. 3. Check equipment is in good operational condition. 4. Walk and inspect the drill site, noting any services, hazards, obstacles or other items relevant to the job. 5. Identify any services by inspection and from preliminary investigation and confirm exact location (e.g. by digging). 6. Implement hazard control measures for identified hazards. 7. Erect/place safety barriers were needed. 8. Check all modes of communication. 9. Select suitable lay down areas for separate storage of chemicals and fuels or other incompatible items. 10. Select locations for ancillary equipment to provide maximum efficiency and minimal risk to personnel.
Safe Work Procedure Set Up Surface Drill Rig Document No: Document No Page 4 of 4
STEP
POTENTIAL HAZARD
SAFE WORK PROCEDURE 1. Interpret plans and position hole collar accurately from plans using tape measure or measurement wheel. 2. Set rig up over peg or marker. 3. Construct a site sketch to show hole positions and site features. SAFE WORK PROCEDURE 1. Ensure a solid foundation (drill pad) for the rig. 2. Align drill at correct azimuth using sight pegs or a similar method. 3. Position drill correctly with hole peg or marker. 4. Level drill using rig jacks. 5. Set mast at correct angle. 6. Lock mast in position.
STEP