You are on page 1of 4

Department/Section: Module No: Issuance Date:

HV Transformer/I & QC

Issued By: Work Instruction No.: Superseding Date: WI-I&QC-08

SEPARATE SOURCE VOLTAGE WITHSTAND TEST

02 01 REV Date Prepared By Name Department Designation Signature Abdul Rehman I & QC Engineer Name Department Designation Signature Checked By Raza Aftab/Muhammad Shafiq I & QC Sr. Engineer/Test Field Engineer Nature of Change Approved & Controlled By Name Department Designation Signature Jahanzeb Ahmad I & QC Manager

Note: Copying of this document is strictly forbidden. Proprietary data. Company confidential. All rights reserved.

SEPARATE SOURCE VOLTAGE WITHSTAND TEST


WORK INSTRUCTION WI-I&QC-08 Revision: 00 Page 2 of 4

1.0

PURPOSE The purpose of this document is to provide the guidelines to the Testing Engineer to check the integrity of the main insulation, between windings (major insulation) and between windings and earth (end insulation) under the temporary and switching overvoltages to which the transformer may be subjected to during its lifetime.

2.0

SCOPE This instruction applies to the in-house & final testing of the HV Transformer.

3.0

RECORDS Following items are recorded in the test reports: 1. Voltage applied on the windings. 2. Duration of the test.

4.0

ASSOCIATED DOCUMENTS The standard applicable for this test is IEC 60076-3.

5.0

DEFINITIONS NIL

6.0

RESPONSIBILITY Test will be performed under the supervision of Testing Engineer/Sub Engineer of I&QC section of HV Transformer department.

7.0

EQUIPMENTS/INSTRUMENTS Following equipments/instruments are required to perform this test. - High Voltage Step-up Transformer Phenix-USA make or equivalent, 0 300 kV, with complete set of input control module.

SEPARATE SOURCE VOLTAGE WITHSTAND TEST


WORK INSTRUCTION WI-I&QC-08 Revision: 00 Page 3 of 4

8.0

MEASURING CIRCUIT

9.0

SAFETY REQUIREMENTS 1. All connections should be tight. 2. Proper clearances should be observed. 3. Earthing should be proper.

10.0

INSTRUCTIONS The test is performed with single phase alternating voltage as nearly as possible of sine wave form of any convenient frequency not less than 80% of the rated frequency. The test is commenced at a voltage not greater than one-third of the specified test value. The voltage is increased to the test value as rapidly as is consistent with the measurement. The test voltage is applied for 60s between the winding under test and all the terminals of the remaining windings, core, frame and tank or casing of the transformer connected together to earth. At the end of the test, the voltage is reduced rapidly to less than one third

SEPARATE SOURCE VOLTAGE WITHSTAND TEST


WORK INSTRUCTION WI-I&QC-08 Revision: 00 Page 4 of 4

of the test value before switching off. The test is successful if no collapse of the test voltage occurs. In case of repeating the test, after the transformer has successfully withstood the test, the test voltage levels shall be reduced to 75% of the original value, unless otherwise agreed and provided that the internal insulation has not been modified in the meantime. Relevant test voltages are given in IEC 60076-3. 11.0 CALCULATIONS NIL 12.0 TOLERANCES NIL