Name of the Procuring Entity Standard Form Number:SF-INFR-57 Revised on: August 11, 2004

CONCRETING OF CEMETERY ROAD - PROPOSED PANABO CITY ETERNAL GARDENS

BRGY. NEW VISAYAS, PANABO CITY

Contract Reference Number Name of the Cotract Location of the Contract

Abstract of Bids as Read


Contract Name: CONCRETING OF CEMETERY ROAD - PROPOSED PANABO CITY ETERNAL GARDENS Contract Location: Brgy. New Visayas, Panabo City Implementing Office: Approved Budget for the Contract NAME OF BIDDERS Total Amount of Bid Bid Validity Form of Bid Security Bank/Company Number/Date Issued Validity Period (Bid Security) Bid Security Submitted (Amt)
Required Bid Security (2%)Cash/Bank Required Bid Security (5%) Surety

Sheet: Date: Time:

1 Jan. 24, 2013 2:00 PM Package 1

City Engineer's Office P FGM P 1,925,905.92 120 days Bid Securing Declaration 1,928,213.61 BIDDERS DECK 1,918,218.03 120 days Surety Bond Great Domestic Insurance 120 days P P 38,564.27 96,410.68 96,450.00 38,564.27 96,410.68

Credit Line(CLC) Submitted


Required Credit Line (10%)

P P

192,821.36 NFCC - P39,844,270.46 Sufficient/Complying

192,821.36 NFCC - P35,185,439.50 Sufficient/Complying

Bank/Company if CLC Amount of NFCC or CLC Remarks

ATTY. GAY GERLE M. PELOTON City Legal Officer/BAC Chairman

ENGR. GLENN A. OLANDRIA City Engineer/BAC Vice-Chairman

DANILO C. LUCAS City Budget Officer/BAC Member

MADERA M. BAUTISTA CGDH-GSO/BAC Member

NEMESIO L. RASGO CEEMD Officer/BAC M

ENGR. GLENN A. OLANDRIA PMO/End-user Unit

ROLANDO SUMABAL Head, BAC-TWG

_____________________________ Representative

_____________________________ Representative

Name of the Procuring Entity Standard Form Number:SF-INFR-57 Revised on: August 11, 2004
CONSTRUCTION OF PANABO CITY MARICULTURE COMPLEX (BAYWALK-PHASE I)

BRGY. CAGANGOHAN, PANABO CITY

Contract Reference Number Name of the Cotract Location of the Contract

Abstract of Bids as Read


Contract Name: CONSTRUCTION OF PANABO CITY MARICULTURE COMPLEX (BAYWALK - PHASE 1), COASTAL ROAD Contract Location: Brgy. Cagangohan, Panabo City Implementing Office: Approved Budget for the Contract NAME OF BIDDERS Total Amount of Bid Bid Validity Form of Bid Security Bank/Company Number/Date Issued Validity Period (Bid Security) Bid Security Submitted (Amt)
Required Bid Security (2%)Cash/Bank Required Bid Security (5%) Surety

Sheet: Date: Time:

1 Jan. 24, 2013 2:00 PM Package 2

City Engineer's Office P 1,910,377.92 BIDDERS

Escalante
P 1,907,562.80 120 days Bid Securing Declaration

MCSLDC
1,904,734.18 120 days Surety Bond Travellers Insurance & Surey Corp. 120 days 120 days

FGM
1,908,079.08 Bid Securing Declaration

P P

38,207.56 95,518.90

95,600.00 38,207.56 95,518.90

38,207.56 95,518.90

Credit Line(CLC) Submitted


Required Credit Line (10%)

P P

191,037.79 NFCC - P77,776,339.30 Sufficient/Complying

191,037.79 NFCC - P12,118,880.70 Sufficient/Complying

191,037.79 NFCC - P39,844,270.46 Sufficient/Complying

Bank/Company if CLC Amount of NFCC or CLC Remarks

ATTY. GAY GERLE M. PELOTON City Legal Officer/BAC Chairman

ENGR. GLENN A. OLANDRIA City Engineer/BAC Vice-Chairman

DANILO C. LUCAS City Budget Officer/BAC Member

MADERA M. BAUTISTA CGDH-GSO/BAC Member

NEMESIO L. RASGO CEEMD Officer/BAC M

ENGR. GLENN A. OLANDRIA PMO/End-user Unit

ROLANDO SUMABAL Head, BAC-TWG

_____________________________ Representative

_____________________________ Representative

Name of the Procuring Entity Standard Form Number:SF-INFR-57 Revised on: August 11, 2004
CONCRETING OF SALVACION BRGY. ROAD - FROM RELAMPAGOS RES.

TO ADLAON SCHOOL (PHASE I) BRGY. SALVACION, PANABO CITY

Contract Reference Number Name of the Cotract Location of the Contract

Abstract of Bids as Read


Contract Name: CONCRETING OF SALVACION BRGY. ROAD - FROM RELAMPAGOS RES. TO ADLAON SCHOOL (PHASE I) Contract Location: Brgy. Salvacion, Panabo City Implementing Office: Approved Budget for the Contract NAME OF BIDDERS Total Amount of Bid Bid Validity Form of Bid Security Bank/Company Number/Date Issued Validity Period (Bid Security) Bid Security Submitted (Amt)
Required Bid Security (2%)Cash/Bank Required Bid Security (5%) Surety

Sheet: Date: Time:

1 Jan. 24, 2013 2:00 PM Package 3

City Engineer's Office P 1,867,502.12 BIDDERS

SOUTHLAND ENT.
P 1,857,494.40 120 days Bid Securing Declaration

P P

37,350.04 93,375.11

Credit Line(CLC) Submitted


Required Credit Line (10%)

P P

186,750.21 NFCC - P4,911,428.53 Sufficient/Complying

Bank/Company if CLC Amount of NFCC or CLC Remarks

ATTY. GAY GERLE M. PELOTON City Legal Officer/BAC Chairman

ENGR. GLENN A. OLANDRIA City Engineer/BAC Vice-Chairman

DANILO C. LUCAS City Budget Officer/BAC Member

MADERA M. BAUTISTA CGDH-GSO/BAC Member

NEMESIO L. RASGO CEEMD Officer/BAC M

ENGR. GLENN A. OLANDRIA PMO/End-user Unit

ROLANDO SUMABAL Head, BAC-TWG

_____________________________ Representative

_____________________________ Representative

Name of the Procuring Entity Standard Form Number:SF-INFR-57 Revised on: August 11, 2004
CONCRETING OF PUROK MANGGA TO KM. 30 NATIONAL HIGHWAY (PHASE III)

BRGY. CAGANGOHAN, PANABO CITY

Contract Reference Number Name of the Cotract Location of the Contract

Abstract of Bids as Read


Contract Name: CONCRETING OF PUROK MANGGA TO KM. 30 NATIONAL HIGHWAY (PHASE III) Contract Location: Brgy. Cagangohan, Panabo City Implementing Office: Approved Budget for the Contract NAME OF BIDDERS Total Amount of Bid Bid Validity Form of Bid Security Bank/Company Number/Date Issued Validity Period (Bid Security) Bid Security Submitted (Amt)
Required Bid Security (2%)Cash/Bank Required Bid Security (5%) Surety

Sheet: Date: Time:

1 Jan. 24, 2013 2:00 PM Package 4

City Engineer's Office P 1,851,392.94 BIDDERS

FGM
P 1,843,054.86 120 days Bid Securing Declaration

P P

37,027.86 92,569.65

Credit Line(CLC) Submitted


Required Credit Line (10%)

P P

185,139.29 NFCC - P39,844,270.46 Sufficient/Complying

Bank/Company if CLC Amount of NFCC or CLC Remarks

ATTY. GAY GERLE M. PELOTON City Legal Officer/BAC Chairman

ENGR. GLENN A. OLANDRIA City Engineer/BAC Vice-Chairman

DANILO C. LUCAS City Budget Officer/BAC Member

MADERA M. BAUTISTA CGDH-GSO/BAC Member

NEMESIO L. RASGO CEEMD Officer/BAC M

ENGR. GLENN A. OLANDRIA PMO/End-user Unit

ROLANDO SUMABAL Head, BAC-TWG

_____________________________ Representative

_____________________________ Representative

Name of the Procuring Entity Standard Form Number:SF-INFR-57 Revised on: August 11, 2004
CONCRETING OF PEDESTRIAN/BICYCLE/TRICYCLE/SHED LANE

(ALONG NATIONAL HIGHWAY) (PHASE IV) PANABO CITY

Contract Reference Number Name of the Cotract Location of the Contract

Abstract of Bids as Read


Contract Name: CONCRETING OF PEDESTRIAN/BICYCLE/TRICYCLE/SHED LANE(ALONG NATIONAL HI-WAY (PHASE IV) Contract Location: Panabo City Implementing Office: Approved Budget for the Contract NAME OF BIDDERS Total Amount of Bid Bid Validity Form of Bid Security Bank/Company Number/Date Issued Validity Period (Bid Security) Bid Security Submitted (Amt)
Required Bid Security (2%)Cash/Bank Required Bid Security (5%) Surety

Sheet: Date: Time:

1 Jan. 24, 2013 2:00 PM Package 5

City Engineer's Office P 1,833,953.34 BIDDERS

GREAT STREET
P 1,830,982.85 120 days Bid Securing Declaration

DECK
1,832,456.75 120 days Surety Bond Great Domestic Insurance 120 days

P P

36,679.07 91,697.67

91,698.00 36,679.07 91,697.67

Credit Line(CLC) Submitted


Required Credit Line (10%)

P P

183,395.33 NFCC - P10,325,125.00 Sufficient/Complying

183,395.33 NFCC -P33,351,486.16 Sufficient/Complying

Bank/Company if CLC Amount of NFCC or CLC Remarks

ATTY. GAY GERLE M. PELOTON City Legal Officer/BAC Chairman

ENGR. GLENN A. OLANDRIA City Engineer/BAC Vice-Chairman

DANILO C. LUCAS City Budget Officer/BAC Member

MADERA M. BAUTISTA CGDH-GSO/BAC Member

NEMESIO L. RASGO CEEMD Officer/BAC M

ENGR. GLENN A. OLANDRIA PMO/End-user Unit

ROLANDO SUMABAL Head, BAC-TWG

_____________________________ Representative

_____________________________ Representative

Name of the Procuring Entity Standard Form Number:SF-INFR-57 Revised on: August 11, 2004
CONCRETING OF SAN VICENTE ROAD

BRGY. SAN VICENTE, PANABO CITY

Contract Reference Number Name of the Cotract Location of the Contract

Abstract of Bids as Read


Contract Name: CONCRETING OF SAN VICENTE ROAD Contract Location: Brgy. San Vicente, Panabo City Implementing Office: Approved Budget for the Contract NAME OF BIDDERS Total Amount of Bid Bid Validity Form of Bid Security Bank/Company Number/Date Issued Validity Period (Bid Security) Bid Security Submitted (Amt)
Required Bid Security (2%)Cash/Bank Required Bid Security (5%) Surety

Sheet: Date: Time: 1,817,383.26 BIDDERS

1 Jan. 24, 2013 2:00 PM Package 6

City Engineer's Office P

DUBC
P 120 days Surety Bond Great Domestic Insurance 120 days P P 90,870.00 36,347.67 90,869.16 P P 1,816,383.00

FGM
1,815,359.64 120 days Bid Securing Declaration

36,347.67 90,869.16

Credit Line(CLC) Submitted


Required Credit Line (10%)

181,738.33 NFCC - P48,764,696.97 Sufficient/Complying

181,738.33 NFCC - P39,844,270.46 Sufficient/Complying

Bank/Company if CLC Amount of NFCC or CLC Remarks

ATTY. GAY GERLE M. PELOTON City Legal Officer/BAC Chairman

ENGR. GLENN A. OLANDRIA City Engineer/BAC Vice-Chairman

DANILO C. LUCAS City Budget Officer/BAC Member

MADERA M. BAUTISTA CGDH-GSO/BAC Member

NEMESIO L. RASGO CEEMD Officer/BAC M

ENGR. GLENN A. OLANDRIA PMO/End-user Unit

ROLANDO SUMABAL Head, BAC-TWG

_____________________________ Representative