Professional Documents
Culture Documents
SCOPE OF REVIEW
The review for the year 2008-09 covers the performance of 390 coal / lignite based thermal units (above 25 MW capacity) aggregating 74914.5MW.
OVERALL PERFORMANCE
PLANT LOAD FACTOR Plant Load Factor (PLF) of 77.22% at National Level was achieved during the year. Highest ever PLF of 91.04% was achieved by the thermal units under Private Sector. Among all the sectors (Central, State and Private) PLF of 91.04% achieved by Private Sector stations was highest at the National level. 500 MW capacity group achieved the highest PLF of 85.33% among different capacity groups. BHEL/BHEL make units (258 units aggregating to 57852 MW) registered the highest PLF of 80.03% among units of different make. Station-wise PLF:
Dahanu Thermal Power Station (500 MW) of M/s Reliance Infrastructure Ltd. in Maharashtra achieved the highest ever PLF of 100.99 %. PLF of following two thermal power stations viz. Dahanu TPS (2x250 MW) of Reliance Infrastructure Ltd. and Budge Budge TPS (2x250 MW) of CESC Ltd. were above 100%.
Station Name
Capacity
Organisation
PLF %
DAHANU TPS
500
100.99
500
CESC Ltd.
100.53
PLF of 8 Thermal Power Stations was above 95% while PLF of 18 thermal power stations was above 90%. PLF of Dadri NCTPP (4x210 MW) was maximum (99.36 %) among all central sector Stations.
IV
PLF of GHTPS at Lehra Mohabbat (2x210 MW) was maximum (95.99%) among all State Sector Stations. Unit-wise PLF:
13 Thermal Units achieved PLF greater than 100%. Among these 10 were from Central Sector Utility (NTPC), two were from Pvt. Utilities (Reliance and CESC) and one from State Sector Utilities (RRVUNL) as per details given below:
Station Name
KORBA STPS
Unit No.
3
Capacity (MW)
200
Organisation % PLF
KORBA STPS
200
SINGRAULI STPS
200
DAHANU TPS
250
250
DADRI (NCTPP)
210
DADRI (NCTPP)
210
UNCHAHAR TPS
210
SIMHADRI
500
SINGRAULI STPS
200
KOTA TPS
195
RAMAGUNDEM STPS
500
RIHAND STPS
500
NTPC NTPC NTPC Reliance CESC NTPC NTPC NTPC NTPC NTPC RRVUNL NTPC NTPC
105.70
104.70
103.60
103.60
102.60
102.50
102.00
101.90
101.60
101.50
101.10
100.50
100.40
Total
13
3625
41 thermal units achieved PLF above 95% while PLF of 98 units were more than 90%. Korba STPS Unit #3 (200 MW) of NTPC Ltd. in Chattisgarh achieved the highest PLF of 105.70 %. This was also the highest ever PLF achieved by any unit so far. PLF of 103.60 % of Unit #2 of Dahanu TPS (250 MW) of Relience Infrastructure Ltd. in Gujrat was the highest among all Private Sector units. PLF of 101.10 % of Unit #6 of Kota TPS (195 MW) of RRVUNL was the highest among all State Sector units.
PLANNED MAINTENANCE Energy loss on account of planned maintenance reduced to 5.66 % from 7.54 % during 2007-08. The average duration of boiler overhaul and capital maintenance was achieved as 24 days and 53 days respectively. Average duration of boiler overhaul in private sector was lowest (18 days). No private sector unit was taken for capital overhaul.
V
FORCED OUTAGES Energy loss on account of forced outages increased to 9.29 % from 7.71% during 2007-08. Energy loss on account of forced outages due to Reserve Shutdown of units reduced from 0.29% to 0.22 % of the maximum possible generation. Main cause of forced outage was due to various boiler problems. Out of the total number of forced outages of 7647, outages on account of boiler problems were 3436. Maximum number of outages (2058 out of total No 7647) were the outages of duration lasting up to 3 hours. Maximum loss of generation (21705 MUs) was due to long duration forced outages (over 25 days).
OPERATING AVAILABILITY An all time high overall Operating Availability of 85.05% was achieved as against 84.76% achieved during 2007-08. The overall Operating Availability of Generating Stations under Private Sector Utilities was 92.73% which was the highest among different Sectors. 500 MW group had the highest Operating Availability of 89.91% followed by 201-220 MW (88.65%) & 195/200 MW group (88.65%). The Operating Availability of BHEL/BHEL make units was 86.86% which was highest among the units of different make. The highest Operating Availability of 91.09% was achieved during the month of MARCH, 2009. SECTORWISE OPERATING AVAILABILITY
SECTOR
CENTRAL
87.59
STATE
82.67
PRIVATE
92.73
BHEL/BHEL
86.86
BHEL/ ABL
75.61
VI
MAKE
CHINA/ CHINA
74.29
RUSSIA/RUSSIA
82.44
OTHERS
79.19
EFFECT OF OUTAGES ON GENERATION RELIABILITY WITH REFERENCE TO THE GENERATION PROGRAM : Mean Time between Failures (MTBF) of the units reviewed during the last two years was as under:
MTBF Range (Days)
Absolute 135 31 35 40 53 34 27 30
%
35.06 8.05 9.09 10.39 13.77 8.83 7.01 7.79
Absolute 134 43 39 27 50 61 21 15
%
34.36 11.03 10.00 6.92 12.82 15.64 5.38 3.85
385
100.00
390
100.00
This indicates that mean time between failures (MTBF) of 45.39% of the total no. of thermal units was more than 25 days and all such units may be considered as most reliable units. Similarly, 9.23% of the thermal units with MTBF less than 5 days could be considered as unreliable units. Following 17 coal/lignite based thermal units (NTPC-11, APGENCO= 2 and one each of Neyveli Lignite Corporation, CESC, Tata Power & Reliance Infrastructure Ltd.) operated continuously for more than 200 days till end of 31st March 2009.
Station Name
Unit No.
Capacity (MW)
Duration in days
Singrauli STPS
200
13-Sep-07
24-Jun-08
285
Korba STPS
500
24-Oct-07
30-Jul-08
280
Korba STPS
200
19-Oct-07
21-Jul-08
276
Raichur TPS
210
21-Oct-07
14-Jul-08
267
Dahanu TPS
250
25-Oct-07
Korba STPS
200
3-Aug-08
250
7-Nov-07
257
240
239
Singrauli STPS
200
14-Nov-07
Talcher STPS
500
14-Aug-08
234
229
VII
Station Name
Unit No.
Capacity (MW)
Trombay TPS
500
Korba STPS
200
Period of continuous operation of the unit To date From date 31-Mar-09 and 17-Aug-08 Continued 7-Jul-08 16-Feb-09
Duration in days
226
224
Trombay TPS
500
12-Jun-08
13-Jan-09
215
Ramagundem STPS
200
31-Oct-07
30-May-08
212
62.5
19-Jun-08
15-Jan-09
210
210
4-Nov-07
26-May-08
204
Rihand STPS
500
7-May-08
Singrauli STPS
200
11-Sep-08
202
201
OPERATIONAL INPUTS 84 (80 coal based & 4 lignite based) Thermal Power Stations provided information regarding coal/ lignite supplies. Total generation loss of 10.9 BU was reported due to shortage of coal/ lignite. There had been shortfall in the gas supplies during financial year 2008-09. Loss of generation due to shortage of gas based on possible operation of power plants at 90% PLF was 33.71 BU. However the loss of generation, as reported to CEA was 11.99 BU only. . All India specific coal consumption increased to 0.743 kg/kWh from 0.731 kg/kWh in 2007-08. Specific Coal Consumption was lowest in Southern Region (0.706 kg/kWh) and highest in Western Region (0.773 kg/kWh) All India weighted average specific fuel oil consumption (SFOC) in the power stations was worked out as 1.93 ml/kWh.
AUXILIARY POWER CONSUMPTION Auxiliary power consumption at national level marginally increased to 8.32% as compared to 8.17% during 2007-08 mainly due to higher auxiliary consumptions by some non-stabilised units. Trombay Station of Tata Power Co. Ltd achieved the lowest auxiliary power consumption (4.39%) in the country. Among Central Sector Stations, Sipat STPS of NTPC achieved the lowest auxiliary power consumption (5.04%). Among State Sector Stations, Wanakbori TPS of GSECL achieved the lowest auxiliary power consumption (7.05%).
VIII
Among different capacity groups, the lowest auxiliary power consumption was 6.18% in 500 MW group. BHEL/BHEL units had the lowest auxiliary power consumption (8.14%) followed by RUSSIA/ RUSSIA (8.16 %).
There were no grid disturbances during the year in Northern Region. However, there were minor grid disturbances in the Eastern, Western, Southern and North-Eastern Regions during the year 2008-09. Frequency profile of different Region was as under:
Percentage of time of operation of two different power systems
Max.
Region
Below 49.0
Above
Frequency
Min. Frequency
50.5
(Hz)
(Hz)
(Hz)
(Hz)
(Hz)
6.97
92.92
0.12
50.76
48.44
Southern
9.34
90.58
0.08
50.96
48.25
There was an overall improvement of 3.17 % in operating Station Heat Rate (SHR) during the year 2008-09 over the preceding year as indicated below:
Year No. of Stations analyzed Capacity ( MW) Weighted Average Design SHR (kcal/kWh) Weighted average Operating SHR (kcal/kWh) % Operating SHR Deviation with respect to Design SHR % improvement () / deterioration (+) in Operating Station Heat Rate over preceding year (-)5.49 (-)3.17
2007-08 2008-09
53 67
37830 56075
2376.8 2347.9
2703.91 2618.2
13.76 11.51
Renovation and Modernisation (R&M) and Life Extension (LE) of an existing power station provide additional generation at low cost with short gestation period. It also results in improvement of environmental emissions and improvement in availability, safety and reliability. The Partnership in Excellence (PIE) program was launched by Ministry of Power in August, 2005 to improve performance of such stations which were
IX
running at PLF much below 60%. The PIE program had been concluded in all identified thermal power stations by June 2008. There has been improvement in most of the Thermal Power Stations with significant improvement in the following:
Sl. No. Name of the plant / utility Capacity under Program PIE PLF before PIE Program (AprSep 2005) PLF after PIE Program (2007-08) 70.9 %
630 MW
45.5 %
Chandrapura / DVC
390 MW
58.8 %
69.4 %
Rajghat / IPGCL
135 MW
42.5 %
75.5 %
Ennore / TNEB
280 MW
22.0 %
59.3 %
Dhuvaran / GSECL
280 MW
27.0 %
71.0 %
215 MW
28.3 %
72.9 %
During the 11th Plan 53 numbers (7318 MW) out of which 33 numbers (4524 MW) in state sector and 20 numbers (2794 MW) in central sector have been identified for taking up for life extension program. 76 units (18965 MW) out of which 27 units (6015 MW) in state sector and 49 units (12950 MW) in central sector have been identified for implementation of R&M works during the 11th Plan period.