Scenario 1 2G&3G Site together, 3G site has been already On air

First Day: Second Day:

MOS

Check Material and troubleshooting

Feedback Result

Install 2G BTS module and prepare all cables

Install MW equipment (local site)

MW commission and allignment

Third Day:

Install MW equipment (oppsite site) BTS&MW Dismantle Checklist (1 person)

Fourth Day:

Chain transmission test (in night)

HW BTS integrate with HW BSC

Night: Swap BTS Scenario 2 Downtime

Fifth Day:

Dismantle NSN site, pack the NSN site as the standard

Delivery NSN site to transporter

5/8/2013

HUAWEI Confidential

Page1of5

144165673.xls.ms_office

Security Level:

Scenario 2 2G only, have temporary space and power

First Day: Second Day:

MOS

Check Material and troubleshooting

Feedback Result

Install 2G BTS cabin at temporary place and complete the power cables, prepare the jumpers.

Install MW equipment (local site) Install IDU in BTS

MW commission and allignment

Third Day:

Install MW equipment (oppsite site) BTS&MW Dismantle Checklist (1 person)

Fourth Day:

Chain transmission test (in night)

Power on HW BTS, and Check BTS inner cables wether install as QC standard.

Night: Swap BTS Scenario 2 Downtime

Fifth Day:

Pack the NSN site as the standard

Delivery NSN site to transporter

5/8/2013

Confidential Information of Huawei. No Spreading without Permission

Page2of5

144165673.xls.ms_office

Security Level:

Scenario 3 2G only, no space, have power

First Day: Second Day:

MOS

Check Material and troubleshooting

Feedback Result

Install MW equipment (local site and opposite site, IDU in temporary space)

MW commission and allignment (use battery)

Third Day:

Prepare all the BTS cables(power cable, ground cable, transmission cable, jumper) in the right place

BTS&MW Dismantle Checklist (1 person)

Fourth Day:

Chain transmission test (use battery)(in night)

Check BTS inner cables wether install as QC standard.

Night: Swap BTS Scenario 3 Downtime

Fifth Day:

Pack the NSN site as the standard

Delivery NSN site to transporter

5/8/2013

Confidential Information of Huawei. No Spreading without Permission

Page3of5

144165673.xls.ms_office

Security Level:

Scenario 4 2G only, no space, no power


First Day: Second Day:
MOS Check Material and troubleshooting Feedback Result

Install MW equipment (local site and opposite site, IDU in temporary space)

MW commission and allignment (use battery)

Third Day:

Prepare all the BTS cables(power cable, ground cable, transmission cable, jumper) in the right place

BTS&MW Dismantle Checklist (1 person)

Fourth Day:

Chain transmission test (use battery) (in night)

Check BTS inner cables wether install as QC standard.

Night: Swap BTS Scenario 4 Downtime

Fifth Day:

Pack the NSN site as the standard

Delivery NSN site to transporter

5/8/2013

HUAWEI Confidential

Page4of5

144165673.xls.ms_office

Security Level:

Scenario 5 2G only, have temporary space, no power

First Day: Second Day:

MOS

Check Material and troubleshooting

Feedback Result

Install 2G BTS cabin at temporary place and complete the power cables, prepare the jumpers.

Install MW equipment (local site) Install IDU in BTS

MW commission and allignment (use battery)

Third Day:

Install MW equipment (oppsite site) BTS&MW Dismantle Checklist (1 person)

Fourth Day:

Chain transmission test (use battery) (in night)

Check BTS inner cables wether install as QC standard

Night: Swap BTS Scenario 2 Downtime

Fifth Day:

Dismantle NSN site, pack the NSN site as the standard

Delivery NSN site to transporter

5/8/2013

HUAWEI Confidential

Page5of5