Professional Documents
Culture Documents
After our overview article on Lundin Minings operations in IM December, Paul Moore looks in detail at the newly expanded Neves Corvo zinc plant, plus future underground mining expansion plans focussed on the Lombador orebody
Aerial view of the Neves Corvo surface operations areas. Longhole ring drilling is planned in the zinc stopes, and drift-and-fill stoping will maintain mining practices as used in the existing operation. Mucking will be via conventional LHDs to stockpiles where front-end loaders will be used to load the material into trucks which will haul the material up the Lombador ramp to the 550 level materials handling system. Lombador will be ventilated using a combination of dedicated surface fresh air and exhaust shafts, and some air from the Neves and Corvo areas via the 550 level haulage. Dewatering will be direct to the surface using dirty water GEHO pumps. Mine services (water, backfill, power, communications etc) will be provided by extension of the existing facilities into Lombador.
he two most recent developments at the Lundin-owned Neves Corvo mine in Portugal are the Lombador Phase 1 mining project and a major expansion of the zinc plant to a 1 Mt/y capacity that has already been completed, with a further expansion to 2.5 Mt/y possible as a result of the Lombador development post 2013. In September 2011, Lundin Mining announced the results of the main feasibility study for the Lombador Phase I project, which is designed to exploit only the upper portions of the Lombador zinc/copper ore bodies. The conclusion was it can be developed as a profitable and value accretive extension to the Neves-Corvo mine. The following is a review of some of the technical aspects of implementing both of these major projects. The new zinc plant is expected to run at its full new capacity of 1 Mt/y in 2013 and 2014, ramping up from 0.5 Mt/y in 2011/2012. The production forecasts assume that the zinc plant will be used exclusively to process zinc ore over the next three years, although the plant has already been proven to have the flexibility to process either zinc or copper ores at the 1 Mt/y throughput rate.
truck hauled up an inclined ramp to the 550 level materials handling system, and then onwards to surface via the Santa Barbara shaft. The basis for the Lombador Phase One expansion from a mining perspective is the extraction of the Lombador South orebody, together with portions of the Lombador East and North orebodies. Maximum use is made of the mines existing extraction facilities and infrastructure. The first zinc ore production from the Lombador Phase One expansion is expected to occur in October 2013 from crosscut development, and full-scale production commences in late 2014. This schedule requires aggressive development of the main Lombador access ramp down to the base of Phase One at the 255 level. Three production panels are proposed commencing at the 260, 360 and 460 levels with mining progressing in an up-dip direction in each panel. The orebodies will be mined using a combination of optimised bench-and-fill (OBF) and drift-and-fill mining methods, with the OBF method being used in the massive sulphide zinc orebodies, and drift-and-fill mining in the stockwork copper ores. The OBF mining method is a bottom-up overhand mining method which involves a primary secondary sequence of extraction, with each stope being paste filled. Primary and secondary stope dimensions are 15 m wide and 20 m high. The mining areas will be accessed via a footwall ramp extending down from the 550 haulage level. Conventional drill and blast development, mucking and hauling, and rock support will be used in all Lombador mining
The bench and fill mining method has long been used at Neves Corvo in areas where the mineralisation is of sufficient thickness and continuity high unit costs, it was chosen because it is highly flexible and can achieve high recovery rates in high grade orebodies with complex and flat dipping geometry. The initial copper reserves at Neves Corvo, largely in the Graa and Upper Corvo orebodies, averaged in excess of 8% Cu, and it was important to select a method that extracted all of this high grade mineralisation. Drift and fill stopes at Neves Corvo are normally accessed from a footwall
6KDIW6LQNLQJ
5DLVH0LQLQJ
The roof of the enlarged area will be drilled with up holes and blasted, creating the initial void for the blasting of the hanging wall wedge Lastly, inclined holes will be drilled down from the drilling crosscut, and the hanging wall wedge will be blasted sequentially into the void. If difficulties are encountered with opening up, an alternative of pulling a slot through may also be utilised. The 5x5m drilling crosscuts are not enlarged as they are in the bench and fill mining currently used in other parts of Neves Corvo. Following extraction of the hangingwall wedge, the remainder of the stope will be extracted using downhole rings, blasted and mucked in groups of three rings. Primary stopes will be backfilled using paste fill (with 5% cement). Filling will normally be up to the floor of the upper drill drift, but the option is also available to fill this drift partially or fully (and mine back through the fill at a later date), if this would assist in minimising adverse ground behaviour before development of the secondary stopes commences. Following the filling of the primary stopes the drilling and mucking crosscuts for the secondary stopes are mined. Extraction of the secondary stopes then proceeds with hangingwall wedge blasting, using the same drilling layout and sequence as used for the primary stopes. Extraction of the remainder of the secondary stopes then proceeds, as for the primary stopes. A review of the hoisting capacity of the Santa Barbara shaft was completed by Stantec Engineering during the Feasibility Study. The annual hoisting capacity for the existing plant (at baseline) is estimated at 4.5 Mtpa, or 12,900 tonnes per day (tpd), at 350 working days per annum. The PFS considered the use of conveyor and truck haulage options for the transportation of material from Lombador to the 550 level crusher. It is worth noting that despite the overall depth of Phase One (from 700 to 900m below surface) it is only, at its maximum, 300 vertical metres from the existing conveyor extraction facility on the 550 level. This work demonstrated that the
development time necessary for an inclined conveyor would result in a production start-up date posterior to the next forecast high zinc price cycle, hence ramp haulage was the preferred alternative.
alternative locations for end-of-shift parking (in the orebody, or at the crusher). An important consideration as the work evolved became the number of trucks operating simultaneously on the ramp at any point in time, as a consequence of possible ventilation restrictions, and results were in part evaluated to minimise this. The simulation demonstrated that a truck haulage system in the Lombador ramp can meet the required production capacity under a variety of conditions. It also allowed the potential benefit of different management and control systems to be evaluated.
Equipment selection
Consultants AMC were engaged in the feasibility study to undertake a comprehensive equipment selection process, and develop an equipment replacement schedule. This included capital and operating cost estimates to a feasibility standard. Annual productivities for the primary mining equipment were calculated from first principles. Annual productivity rates for cablebolt drilling and insertion equipment and charging platforms were taken from the PFS in preference to a first principles approach. The Lombador life-of-mine stope mining schedule and other assumptions were used to determine the equipment requirements specifically for Lombador below the 550 level. A total site LOM was used to determine the total site equipment requirements for the life of the operation. Based on the mining equipment replacement strategy, the model determined a purchase schedule for additional and replacement equipment for the life of the operation. It was recognised that some mining equipment from the existing Neves Corvo mining areas could be transferred to Lombador as the former mining areas gradually become depleted. The OBF mining method is not currently practiced in Neves Corvo and its success is highly dependent on accurate and productive longhole drilling. Production blast holes, up to 21 m in length, must be fan and tilt drilled in the primary and secondary zinc stopes using uphole and downhole drilling techniques. Current longhole drills at Neves Corvo are not capable of this type of drilling to the accuracy required for the OBF stopes. The production up-holes drilled into the hanging wall wedge of the OBF stopes will require some consideration with respect to explosive charging. Currently all blast holes are charged with pre-sensitised emulsion that does not have the viscosity to remain in vertical and near vertical up-holes. A number of blast
designs have been developed for the HW wedge to minimise the number of up-holes required. Charging of these up-holes would be with packaged emulsion explosives. Different explosive loading vehicles are preferred for the large OBF stopes and the smaller and somewhat physically constrained copper drift and fill stopes. It is highly preferable that additional undergound haulage trucks purchased for Lombador are able to travel unhindered up and down the Castro ramp that leads from the surface to the 550 level. Each truck will need to traverse to the surface for major maintenance during its life in the operation and the removal of any large items to allow the truck to travel to the surface or any other mining areas is highly undesirable. Given the long up-hill loaded travel by trucks from the Lombador mining areas to the 550 level crusher, the selection process for trucks aimed to maximise haulage productivity through increased payload, increased speed or both. The proposed equipment selection has been based on the following criteria: technical functionality, including requisite technology; equipment productivity; equipment performance, actual or perceived; make and model currently on site; and make and model recently purchased for site. The following summarises the selections that were made. All operational development and drift and fill drilling at Lombador will require conventional twin boom Jumbo drill rigs. The existing twinboom Jumbo drill rig fleet consists of eleven machines, predominantly Atlas Copco Boomer 282S rigs with three Sandvik Minimatic H205D rigs. The last two drill rigs purchased were Atlas
Copco Boomer 282S rigs commissioned in October 2006 and January 2008 and the purchase of additional machines of this type has been recommended for the Lombador project. The existing rockbolting drill rig fleet consists of eight machines, almost entirely Sandvik Robolt drill rigs. The last two drill rigs purchased were DS410-C rigs that were commissioned in May 2009. However, an Atlas Copco Boltec 235 was selected as the preferred choice for the installation of Swellex bolts, to standardise with existing on site equipment and the preferred supplier of other drilling equipment. The OBF mining method requires tilted and fan drilling of production blast holes in the Lombador zinc stopes. Both uphole drilling and downhole drilling are required. These drilling methods are not currently practiced in the Neves Corvo mining areas. Up-hole drilling is required for the second stage of the HW wedge and down-hole drilling from the top drive for stages
Standardisation Required for accurate fan and tilt drilling Standardisation Required for cablebolt and production drilling R2900G Standardisation with recent purchase and performance / acceptance 966H Standardisation TH550 Higher productivity and parts commonality with existing 40t trucks Charmec 1610B Standardisation Utilift 6405B Standardisation Scamec 2000S Standardisation 12M Grader Standardise supplier Hilux Standardisation
The main mine ramp portal at Neves Corvo level and 550 level which are fed ore and waste by the underground fleet of 40 t Sandvik Toro trucks. The 700 level crusher station is equipped with a Boliden Allis 1,050 x 800 mm crusher of 600 t/h capacity that currently crushes ore and waste from the Upper Corvo, Neves and Graa orebodies, and Zambujal and Corvo Southeast. The crusher feeds into four 1,500 t capacity storage bins ahead of the Santa Barbara shaft loading pocket. The 550 level crusher is equipped with a Svedala Arbra 1,500 x 1,200 mm crusher of 400 t/h capacity that crushes ore from the Lower Corvo orebody and other lower sections of the mine. The crusher feeds into two storage bins of 600 and 400 t capacity. Material is crushed to <250 mm and fed onto conveyor TP12 which is a 742 m long inclined conveyor on 25% gradient which delivers the crushed material to the 700 level bins. The conveyor is suspended from the roof of a 4 x 4 m conveyor gallery. It runs at a speed of 3.2 m/s, and has an installed capacity of 400 t/h. It is powered by two 225 kW motors. Rock hoisting utilises a conventional ground mounted 2.4 MW double drum winder, hoisting opposed 17.5 t capacity bottom dump skips each travelling on four 38 mm rope guides. The hoisting speed is 12.5 m/s and the cycle time is 82 seconds. After hoisting the crushed ore is fed to an overland conveying and stacker system. The ore is then dumped directly from the mine stacker conveyor into a run-of-mine park. The capacity of the stockpile area is around 150,000 t. The ore is reclaimed via a front end loader and fed into a chute for conveying to the existing jaw crusher. A new pre-screen equal to the existing copper pre-screen will be installed to compliment the existing zinc crushing operation.
Milling improvements
ROM ore is dumped from the mine stacker to the ore park. The ore is then fed to a pre-screen for screening at 20 mm. The oversize reports to the primary jaw crusher, while the undersize reports directly to the fine ore bin. The crushed coarse ore is conveyed to the secondary cone crusher. The conveyor system has a rated capacity of 200 t/h. The secondary crusher product is conveyed to the tertiary crusher screen with the oversize (+20 m) reporting to the tertiary cone crusher and the undersize reporting to the fine ore bin. The crushed ore is reclaimed from the 1,500 t fine ore bin via a single feeder and fed to the rod mill feed conveyor. The grinding circuit consists of a single line comprised of a 3.81 m diameter by 4.877 m long rod mill and two 3 m diameter by 4.1 m long (450 kW) primary ball mills and a single stirred mill (930 kW). The rod mill product is pumped to the ball mill circuit via two feed distributors (one operating and one standby), for distribution to two primary ball mill sumps. The rod mill discharge together with the ball mill discharge, is pumped to cyclone clusters for classification. The cyclone clusters operate in closed circuit with the ball mills. The cyclone overflow, at a P80 product size of 200 microns, is fed to the secondary grinding mill circuit. The cyclone underflow returns to the ball mills. The new rod mill is powered by a single 900 kW single ring gear pinion drive with a
Crushing considerations
Zinc ores are first crushed underground before being hoisted to surface. The mine has two underground primary crushers located at 700
frequency convertor driven squirrel cage induction motor. Grinding media are steel rods. Media addition is performed manually with a rod loading device directly in front of the mill. The mill motor power draw and mill load is allowed to vary in response to changes in ore grindability. Process water is added in ratio to the solids feed rate to give a mill discharge density of approximately 70% solids by weight. The ground pulp discharges to a sump and pumps deliver the slurry to the primary ball mill cyclone clusters. The cyclone feed pump capacity exceeds 120 m3/h. The two existing ball mills treat approximately 65 t/h each to give a product size of around 80% passing 200 microns. The ball mills operate as overflow discharge mills at ball loadings of up to 35%. Balls are fed manually into the mill based on power draw. The primary cyclone overflow reports to the secondary grinding circuit. The secondary mill is a Metso vertical stirred mill VTM1250 fitted with a 930 kW motor. The mill operates with 20 mm steel balls which are feed via a ball loading hopper. A final product of 45m is achieved. The primary cyclone overflow together with the secondary grinding mill discharge is pumped to a cyclone cluster. The cyclone overflow, at a P80 product size of 45m, is fed to the flotation circuit. The cyclone underflow returns to the secondary stirred mill. The flotation circuit consists of a row of new rougher machines (20 m3) to complete the aeration, copper roughing, lead roughing duties. Zinc roughing and primary cleaning is carried out in three banks of new 40 m3 tank cells. Subsequent cleaning of the various rougher
concentrates occurs in existing conventional flotation cells. The product from the grinding line reports to a conditioner tank prior to being pumped to the aeration cell. The copper rougher concentrate, combined with the copper cleaner tail is reground in a 2.4 m diameter by 3 m long (200 kW) ball mill. The ground copper rougher and copper cleaner block tail is pumped and cleaned in the copper recleaner flotation machines. The copper recleaner concentrate is pumped to the copper first cleaner. The copper first cleaner concentrate is then pumped to the copper second cleaner. The copper first cleaner tail then returns to the regrinding circuit. The copper second cleaner concentrate is the final copper concentrate and is pumped to the copper plant thickener feed tank. The copper second cleaner tail returns to the copper first cleaner. The copper rougher tailing, together with the copper recleaner tailing, both report to the lead circuit conditioner tank. All copper cleaning duties are carried out in existing 8 m3 Denver flotation cells. The reject products from the copper circuit report to a lead conditioner tank prior to gravitating to the lead rougher cells. The lead rougher concentrate, combined with the lead cleaner tail are reground in a 3 m diameter by 4.1 m long (450 kW) ball mill. The ground lead rougher and lead cleaner block tail are pumped and cleaned in the lead recleaner flotation machines. The lead recleaner concentrate is pumped to the lead first cleaner. The lead first cleaner concentrate is cleaned in the lead second cleaner cells. The lead second cleaner concentrate is the final lead
concentrate which is pumped to final tailings. The lead second cleaner tailing is returned to the lead first cleaner flotation cells. The lead rougher tailings, together with the lead recleaner tailings, report to the zinc circuit conditioner tank. All lead cleaning duties are also carried out in existing 8 m3 Denver flotation cells. The reject products from the lead circuit report to two zinc conditioner tanks prior to being pumped to the zinc rougher flotation cells. The zinc rougher concentrate, combined with the zinc cleaner block tail, are reground in a Metso VTM1250 Vertimill to a product size of 15 microns. The ground zinc rougher and zinc cleaner block tail are pumped and cleaned in the zinc recleaner flotation machines. The zinc recleaner concentrate is pumped to the zinc first cleaner. The zinc recleaner tail returns to the zinc rougher. The zinc first cleaner concentrate is pumped to the zinc second cleaner with the zinc first cleaner tail returning to the regrinding circuit. The zinc second cleaner concentrate is then pumped to the zinc third cleaner. The zinc second cleaner tail returns to the zinc first cleaner feed. The zinc third cleaner concentrate is the final zinc concentrate and is pumped to the zinc thickener feed tank. The zinc third cleaner tail returns to the zinc second cleaner. The zinc rougher tailing, together with the zinc recleaner tailing, report to the final tailing collection tanks for pumping to the copper plant tail discharge system. Final copper concentrate is pumped to the existing copper plant thickener. Final lead concentrate is discarded while final zinc concentrate is thickened in a 20 m diameter thickener. The thickened concentrate is pumped to a concentrate storage tank. The thickened slurry is filtered via two Metso VPM 1530-40 filter presses. The discharge from the filters is conveyed to the zinc concentrate storage building. Water recovered from the concentrate thickening is combined with the water recovered from the filters and reclaimed. Flotation tailings are pumped to the existing discharge system. Water reclaimed from the tailing pond is returned to the industrial water tank for recycling to the plant. Water from the zinc concentrate thickener is collected in the thickener overflow tanks and used in the zinc flotation circuit and filtration. Reclaim water from the tailings pond is also used as make-up in the thickener overflow tanks. Fresh water is provided as makeup water to the process water reservoir. IM