You are on page 1of 120

W..

e_ :

NASA

Technical

Memorandum

4628

Recommended Maintainability
A Continuous Maintainability

Techniques

for Effective

Improvement Initiative Steering Committee

of the NASA

Reliability

and

December

1994

(NASA-TM-4628) RECOMMENOEO TECHNIQUES FOR EFFECTIVE MAINTAINABILITY. A CONTINUOUS IMPROVEMENT INITIATIVE OF THE RELIABILITY AND MAINTAINABILITY STEERING
| w

N95-31530

NASA 105 p H1/38

Unclas

COMMITTEE

(NASA)

0060399

Ira!

J]

ii

mmm

mini

mJ

_J W

IL

h_

PREFACE

Current success
. w ,

and future

NASA

programs degree reliability,

face the challenge risk. and performance, benchmark. expectations

of achieving technical track a proven without

a high degree record

of mission system of or

with a minimum such as safety, ultimately within objectives risk. levels

of technical

Although

risk has several of overall safety of the accomplishment

elements, effectiveness mission program appropriate

will be the NASA cost and schedule

This will foster

r w

compromising

A key CharaCteristic of maintainability

of systems throughout

effeci_veness the program

is the impiementation life cycle. a system can be restored

Maintainability
n

is a process

for assuring

the ease by which

to

operation following a failure. and/or on-orbit maintenance. undertaken provide schedule program, a continuous a path toward benefits. operational

It is an essential consideration for any program requiring ground TheiOffice of S_._ty"and Mission Assurance (OSMA) has initiative life cycle to develop a technical roadmap while almost that will cost and result from in the desired degree costs of maintainability are a characteristic system availability realizing always

improvement achieving early cost savings

Although

of any assurance on NASA initiated early

and improved

__ w

a properlY administered maintainability programs has demonstrated the value the program life cycle. provides within guidance NASA.

assurance program. Past experience of an effective maintainability program

This memorandum development Defense,


w

towards The degree

continuous developed to which

improvement from these NASA, proven

of the life cycle Department evaluation is consistent of be may with technical methods of the techniques should

process and industry

It has been

experience.

imposed represent

resides

with the project/program, However, risk. in program advocates Therefore, possible

and will require each applicable the information Product Team design success should Also,

an objective suggestion presented (IPT)

applicability
w

of each technique. an increase which

not implemented approach for NASA

OSMA systems

policy,

an Integrated proven degree

acquisition. in the highest

this memorandum maintainability of mission

be used to communicate and implementation while balancing

knowledge resulting

that will promote risk.

cost effectiveness

and programmatic
w

Frederick Associate Safety

D. Gregory Administrator

for

and Mission

Assurance

DEVELOPING The development Maintainability from NASA provide NASA operating technique CENTER Appreciation individuals

ACTIVITY
U

of this technical (R&M) Steering

memorandum Committee,

has been which consists

overseen of senior

by the NASA technical

Reliability

and

representatives exists to the and


m J m

Headquarters

and participating for the continuous represents

NASA

field installations. of the R&M

This Committee discipline within on designing

recommendations community,

improvement

and this manual

the best technical

"advice"

maintainable systems from the participating Centers and the Committee. Each presented in this memorandum has been reviewed and approved by the Committee. CONTACTS is expressed in the preparation for the dedication, of thismanual. time, and technical Without the support contributions of the following Centers,

of their individual

and their enthusiastic personal c-bmmittee, the capture oftlie possible. All of the NASA The Committee maintainability Centers members techniques.

support and willingness m_inffinab_tytechniques -"

to serve on the NASA R&M Steering _ofi/a_ned in this manual would not be
R

are invited listed below

to participate

in this activity and contribute for more information

to this manual. pertaining to these


i

may be contacted

Mr. Donald George CR85 Marshall

Bush Space Flight Center Alabama 35812

Mr. Leon Migdalski John F. Kennedy Space Center RT-SRD-2 KSC HQS 3548 Kennedy Space Center, Florida 32899
B I

C. Marshall Bldg 4203 Space Flight Lalli

Center,

Mr. Vincent Lewis 21000 MS 501-4 Cleveland, Mr. Malcolm Lyndon Bldg. Houston,

Mr. Ronald Lisk Center 0152 Road 44135


u

Research Code Ohio Brookpark

NASA

Headquarters SW

Code

QS
g

200 E Street, Washington,

DC 20546

Himel Space Center Code NB2


m

B. Johnson Texas

45 RM 618A,

77058
w

ii

m I

.J w

TABLE SECTION

OF CONTENTS PAGENUMBER i ii ii v v v ........................... MAINTAINABILITY vi

PREFACE ................................................................ DEVELOPING ACTIVITY .................................................. CENTER CONTACTS ...................................................... ......................................................

w
I. INTRODUCTION A. B. C. II.

Purpose .......................................................... Control/Contributions ............................................... Maintainability Technique TECHNIQUES Format FOR Summary EFFECTIVE

RECOMMENDED Management

Program

22 w

Technique Technique Technique Design

PM-I : The Benefits of Implementing Maqntainability on NASA PM-2 : Maintainability Program Management Considerations PM-3: Maintenance and Engineering : Selection Handling False of Robotically Mechanisms Mitigation Compatible Fasteners .................................... ................................... and Concept for Space Systems .......................

Programs .............

....

PM-2 PM-8 PM-14

Factors DFE-I

Technique Technique Analysis Technique Technique Technique Technique Technique

DFE-2 DFE-8

DFE-2: and Test A T-l:

Alarm

Neutral

Buoyancy Time

Simulation

of On-Orbit

Maintenance

............

AT-2 AT-7 AT-12

A T-2: Mean

To Repair

Predictions

............................. Model

A T-3: Availability A 7-4: Availability, to Support AT-5: Rocket Power

Prediction and Analysis ........................... Cost, and Resource Allocation (ACARA) Maintenance Failure Requirements Detection ......................... Using an Average

AT- 17 Signal AT-21

Engine

Technique Design

......................................... Considerations and Refurbishment Protection Practices ............... Systems .......

Operations Technique Technique Technique Technique Technique

and Operational OPS-I OPS-2: OPS-3: OPS-4: OPS-5:

: SRB Maintainability Electrical Connector

OPS-2 OPS-9 OPS- 11 OPS- 17 OPS-20

.............................

Robotic Removal and Application of SRB Thermal GHe Purging of H 2 Systems ............................... Programmable Logic Controller ...........................

III

TABLE SECTION: Operations Technique Technique Technique Technique Technique Technique m. and Operational OPS-6: OPS-7: OPS-8: DC Drive Design - Solid

OF CONTENTS

(CONT.) PAGE NUMBER

IBm

Considerations State Controls

(cont.) ............................ ..................... Loading .... OPS-24 OPS-28 OPS-32 OPS-36 OPS-39 OPS-42

ACVariable Frequency Drive Systems Fiber Optic Systems .....................................

OPS-9: Pneumatic OPS-IO: Modular OPS-11: A: Pneumatic

Systems-Dome Loaded Pressure Regulator Automatic Power Source Switching Device System Contamination TECHNIQUES Protection FOR

.................

m m

APPENDIX FUTURE

CANDIDATE

DEVELOPMENT

............................................

A-1
g

il

IB

m_

m w

1v

I.
r

INTRODUCTION
PURPOSE is a process a failure. and for assuring Designing support the ease and by which a system within rather can be restored maintainable In addition, projects. consider and requirements could result when to systems NASA

A.

Maintainability operation
f

following afford costs

operating a necessity

cost effective, NASA. than successful of R&M as advertised costs

(both cannot

on-orbit

on the ground) the temptation be avoided. in end-items phase

has become to reduce

to lose public should

by designing In the past, manner.

less than costs relaxation Additional

In this era of total program to reduce not be are attempts up

shrinking life front


L_

budgets,

up front

cycle costs

has resulted maintained

that did not perform for the early a series of both

properly made The


w

in a cost effective to correct is to present effectiveness contains useful is to provide (both

late in the design purpose

relaxation

of requirements. techniques be interpreted that can NASA systems. as a with:

of this manual operational technique The objective

of recommended flightnone should

increase Although

overall each

and ground-based to minimize

information, a set of tools

requirement.
W

the risk associated

Restoring Conducting

failed functions complex

ground

and flight based) maintenance the NASA operations mission utilizing aging equipment

and highly visible capability

Sustaining a technical or facilities. provides effort;

to support

This document maintainability considerations operations will include EVA

(1) program (2) design design

management analysis

considerations considerations; processes that address and on-orbit

- key elements (3) analysis and testing NASA

of an effective and test and (4) Updates

and development considerations ground

- quantitative and operational a section operations

and qualitative to on-orbit (including

techniques;

field experience. experience and ground-based

applicable

maintenance

with practical operations

from NASA

maintenance

simulations). This document is a valuable resource for continuous improvement ideas in executing the systems development process in accordance with the NASA "better, faster, smaller,
w

and cheaper"

goal without

compromising

mission

safety.

B.
L .

CONTROL/CONTRIBU_ONS will be revised periodically to add-new techniques or revisions to the existing on should be in this

This document techniques contractors

as additional and NASA

technical

data becomes

available.

Contributions Any technique

from aerospace based

Field Installations that appears

are encofir_/ged. appropriate

project/program

experience

for inclusionin

this manual

submitted for review. memorandum (Figure

Submissions should be fo _n-nattedid_entical!y to the techniques 1) and sent to the address below for consideration. and Space Administration

National Aeronautics Code QS 300 E Street S.W. Washington,

DC 20546

Organizations submitting techniques that are selected for inclusion in this manual will be recognized on the lower portion of the first page of the published item. Contacts listed earlier in this document should be used for assistance. If additional information on any technique is desired, the contacts listed earlier in this document can be utilized for assistance. C. MAINTAINABILITY TECHNIQUE FORMAT SUMMARY

The maintainability techniques included in this manual are Center-specific descriptions of processes that contribute to maintainability design, test, analysis and/or operations. Each technique follows a specific format so users can easily extract necessary information. The first page of each technique is a summary of the information contained, and the rest of the technique contains the specific detail of the process. Figure 1 shows the baseline format that has been used to develop each technique.

=_

Technique Title, page numbeJ Technique XXX-._ *_

IB

TECHNIQUE FORMAT
Techniaue: A brief statement defining the design technique and how it is used. andor impact on resource expenditure

Benefits: A concise statement of the technical realized from implementing the technique.

improvement

Key Words: Any term that captures the theme of the technique Utilized for document search purposes. Application Experience: and/or industry. Technical Rationale: Identifiable programs

or provides

insight

into the scope.


m

or projects that have applied the technique

within NASA

A brief technical justification

for the use of the technique. NASA Center. The

BB

Contact Center:

Source of additional

information, usually sponsoring

Techniaue Description: A technical discussion that is intended to give the details of the process. information should be sufficient to understand how the technique should be implemented. References: Publications that contain additional information about the technique.

'* Each technique within a section is identified using one of the following acronyms 'ollowed by the associated sequential technique number. PM: Program Management DFE: Design Factors and Engineering AT: Analysis and Test OPS: Operations and Operational Design Considerations

specific to that section


m

Figure 1: Technique

Format Definitions

vi
! I

Program
w

Management
success is the development limited resources. for rapid of systems Early that are reliable definition of both with today's

A fundamental and affordable hardware

key to program to operate

and mission

and maintain

and software

requirements

that provide

the capability

restoration

when failures some additional system

occur is essential.
w

While incorporation the resulting benefits

of a maintainability will include

program

may require

early investment, availability. with

operational are intended to develop,

cost savings to provide foster,

and improved management

The techniques

included

in this section necessary

personnel a successful technique to achieve

an understanding program

of all information

and integrate costs.

maintainability provides optimum

that will enhance mission on a specific

success

and lower

overall

Each

high-level application.

information

subject,

and can be tailored

or expanded

Page PM- 1
W

U
m

im ii

mm

II

z R mD

I B

m
Wi

L_ Im

mm

II

The Benefits

of Impleraenting

Maintainability

on NASA

Programs, Technique

Page PM-I

Technique

Programmatic provisions for ease of maintenance greatly enhance hardware and software system operational effectiveness for both inspace and ground support systems.

':i:i:_:: i:-:_:i_:iiii_:_-_.i:ii:._:_!_i_-..:'_'_!_?.i_i:_?_:i_-ii.:i?ii_i:!_ _'i_i:_i_i_:,.'.:i:'_-'._.:.:_.:'_ii !_i:_:._!_:_:_;_:..`._._..:_!._!_!_._;_._._.:_i_k_.!!_:_.iiii:.:_#.`:.._..:::_!::._!._.:_`:_.:._::i_:::_:_!_i:.::_..`._.`:._?:i!_.`..:_:_.`..:_:!:_.`.:_`.._!_..:_:._:._?.`.._i_i.`_.`..i_i_ f_!:..':_._._!:i::.! ._:_ ._'!i_'::!::! _i_::_:'._..;._..`._:_.:_4._...._.._!_..``_`:_i..`.:.._?.;_.:_:i_:_._:_ii_._ _:._._:_i:i:?.i_:::_:_:!:i:i:_:is_i_a_:_._._._..:_:`:_'.._.k:[_?;._._:_.:`.:_:_`::::.':_:_:_:_:_::::_:!:i_i_:_:_:_:_i:i_:_:_g:_:_::::.:_: _:._,'._,'-_:.'.*'.: :_i:_-:::_._::_.'." ::_.'.':?-!._:i:!_ -::.'._:_ __;i:'_ ___-.'-_ _-'.:_:_:_:'.:::_:_:m::-:::-'." i.:_i_i:-.:_iiii_i_:,:_:?'.;._i_._..,.!_!_!_._!-_:" _ ..`::_:_:_:i.`:.:_:_:_i::<i:?..::_t_:._.!_.::_::_::`::_;g_:!.:_:i:i_:i_:i:i:i:_:_:_:_:._:._.:::._:.:_:i:_.:_:i:_:_.x._z._:_..._:_!:_!_ _'::.:_:i:_-'::_ _i:_;'.": ":",_._i_:_ _'_;_ ......... =============================================== .... _i,__

e_)_ __._.::_._i_._i_``_`!_.:.._._'.:_:_.`_:::_`:_::.`:::_:::.:::_:_:_::_:_:_:_:_::*_:._::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: ................. ::_,:_:_:_,:.,.,...:_:._:::._::.,:::::.:_,:::.,_,.:.. ,,: :,,:,.,,,


_ _ .-..,...... .?. ......... _:,_::':':_".,.'_:_!_ ............. _.:_i!i_:.:!!_!._:.:.:.::_!.:.._.....`!.:..``....`.._....:._.:.:......`_...._?..:_..`:!_.:...._i_...._:...::_....:.`:_..._._:_;_......_...:_i!_........:._......:._ .......... :'.:"i_'"'"_:_:'_ _: i" !_!

: :_:$'..'::.:::."::_:_'._. ::'".':._::::-:":::::'_:_:::::_!!:'.'

: _:..:.:-_:::':':":':'_.$':::::::::::':,:::::::::::_.::_.:::::.':::::5::." :::: :'2:..:....,..'.'_.::U.' ._ _._...-:..:4.:...>'..:_.-.-.:-.-:, _:`::.:....:.:._:.:_.::.:.:_.+:.`_:.::::::::._._:.:_..:_:_:.:._:._:+_+::.._:._:.:_:_:.:_:_._......_:_.:_.+_._ _::-...:---:--c.,._.-.:.:::..::.'-%:$ -. , ::::::::::::::::::::::::::::: _:::".:::_:.'.:_:_%".::_:" <:_-:_.:_-'.: _.:.'. :::::::::::::::::::::::: :::: _.'.<-'.':?.!:!: :E:._'_-'.:!:i_:_.'.:E_:_.'.':_!::$i:i:i:i:.::i:i:_::_:_:!:_:.'.:i:_:: :i:_::::._::: :.::i:'_:_:_kq_:_ ::_ _:_'_._ i:: _.

,'-:::_:._:_:_::_:':::-5:_.::_:'..::_:':_:_:_:_:$:::_ :.:_<._.:._:.:+:_:+:.:.:.:_:.:.._`...:_:.:.:._<_:+:.::;:<.:._:_2:_..:.:_:::::::_::::..<_:.:._:.:.a:.:_.x.:.:.:.:.x_:<.:<.:.:_`:.:.:.:.:._:+:.:_:.:.:.:_:.:.:_._:_..:._<:`+:_:.:_:.:_:._:.:+:.:.:.:.:_.._:::._:::.._..:_ :_'...'_..:,,:,-.:?.::_,.:.._::_.,..<:_,:._-_::_:: _.,,-.._:,,._::::,::._:.:.:_.:.,,:..,_,,.._:.:.:.:....:.:.:.:.:,.:,,,..,:. _!:.....!_!i!_.:_._.i_.i.:.:`:ii_i_.i._r..i...:_:_:_..`::._.._:._!_!_:.._.:_._...>:_!_._.`:_i_._:_ii`_!_!_!_:_i_i_i_i:i_;_!_!_i_!_:_ii!_:_i_ :': :: _._ _.i_ _.". :_::_:_'-':__!_. ::-':::_::+':::-:-'_. :._:-_:_::_:_

-':_-::::-:-:-:-:-:-.'--'-':,':':'.:: .......... ,__'.-" :::*.'.':':'_::>:::_:.-:::_::::.":."-":_.".".:" ::'::_:..'-_::i-:'_:::.,::_:_#:.-"_:_:'i_/..:!::::i:_:_:_._:_."_':i:_..':. ":::;::::'.-:!:_-:.':#_:_'._::'::?.::::!::::';'.:._._ _':':_.!_'_.i_i.:i;_.".::._ i_.:ii-'!_ii_i!i:,:i:_:_ii:_._:-._:".<._?:i_._!!-:::'.:,_ _:_ _ii!

:::::::::::::::::::::::::::::::::::::::: ':.::_::_ !:::?._:_?-_:'_'_::':_::::-5:_::-::_:..:_:$:_.:::'_,'.:.::::_.:._:: .'..:::.::::::::::.:_:.:.:-:..:,:.:.tt: :.2-'.:.'-....". ........ :.:..:-:-: :.' +:.:.':*:-:...:.....,-... ......-..-,...........:.-...--.--'.-------.----'--.--:.:. -_'.".'-<-.":-'.'.'..'.'. :.'-'--<< .<-_.-:-+_:. :.::_'-':_:'-'_$.: :!:!:::::_:_:::::::::::-.::?.: :?.::.:_:_::: ......... .... .... _: -.. ::.. ::.::::::'

:_ t-_i_ _#ii_..'..'_::_ _._i?..'_i_'.._:_i_-;._i.'::_._;..!._._i;..._i_ :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: -._.:_:._:_._<_._:_:_!:!:_.....`_:::._::_:_._.`::_.._.`..:i.`..:!:!::.._:_:_i_._::i::_ _:''_:::_:-_';" :-_:_:_:_-:'.


_; :._ _g__i:_: "_'.. _?.._:.-':!'!i_'iii_i'i:':?._ii-i-_i'_!_.:'.f._ _ :_"-i_ i.:: _:! __:._:: _: :__?:.!_:_,.'.:_:_:i:?_;:.,'_._ _'.._ _'_:'_ _: :_::._ ._:-_ :_.,.':: _! _i::_ E'i_i:'...'.'i:i_-::_!.'.._?." :_'?.':_: :g!::::: :_._(<_ _:.::_.'..:_: :-_-":_!:'-:':i._
:_ ...::_:::_::::'-:.:-:_:_::-:::::.:.:.:.:-_ ::::::::::::::::::::::::::::::::::::::::::: :_::_..::::_ :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: _._:: _: :::x 4_: :::._:: _.:::_.:: _:._ _: _ ._: .'.:.'. _: ::::::::::: :::::::::::.<::??:i_::_..:_.::_!?-_:.::_:.::_:!(:$_:!_:_:i$_i:: :_ : :'_: ::_::: :_:': _:_ _:_ _:_ :_:: _:_:_:_ _: :_:: _: :_:-_::: :_:.:_:_: :-:::::::::::::::::_ :_::_?.:-.':.::'::::_

Benefits

Implementation increasing

of maintainability availability

principles and reducing

can reduce lifecycle

risk by costs. that

operational

Provisions for system maintainability also yields long term benefits include decreased maintenance times, less wear and tear on project personnel, and extended useful life of ground and in-space assets.

Key

Words

System maintainability, program management, lifecycle availability, concept development, human factors

costs,

Application Experience
_5

International Shuttle GSE,

Space Space

Station

Program,

Hubble

Space

Telescope,

SRB's,

Acceleration

Measurement

System,

and others.

Technical Rationale

Maintainability in-space early

requirements

for programs resolution

that require have Lack

ground

and/or support in process with

maintenance

and anomaly

to be established can result

in the program program reduce maintenance, costs.

to be cost effective. activities risk. Including

of management in the design associated

to properly increased
_z_r r _

fund maintainability the number improve

up-front

maintainability

will greatly system program

of operational the availability

problems

of the system,

and reduce

Contact

Center

All

NASA

Field

Installations

..

Page PM-2

The Benefits

of Implementing

Maintainability

on NASA Programs, Page 2 Technique PM-1

Be_fits on NASA Techniqm

of Implementing Programs _ PM-1

Maintainability

environment

under

which

maintenance

is:

II

performed. Applying maintainability principles will enhance the systems readiness/availability through testability, factors such as visibility, accessibility, of
ill i

simplicity,

and interchangeability

Over the years, NASA has =successfully launched manned spacecraft to the moon, unmanned probes into the outer the sc' system, and developed space zems for earth orbitable reaches_f reusable missions.

sent -

the Systems being maintained. Using maintainability prediction techniques and other = qu_titativ e m_n_tainability analyses can greatly enhance the confidence in operational capabilities of a design. These predictions can also ai___d !n des!gn whe_sex, considered. schedule program dec!sions_an_d options savings [fade studies _ of the erfil-design impacts are being and fewer phase of support

l I

NASA alS _performs v_uable atmos.pheric research and development of ground systems, all of which contain complex hardware and : ,ftware that must be maintained during all :_ases of operafior[s environments. shrinking becoming budgets, an-d-in multiple in this age of more with less is theme. doing However,

i
g

Also, cost will result

in- tl3e oPerational due to decreased

maintenance

time, minimization

the overall

programmatic

equipment, and increased system availability. Another benefit is a decrease in management overhead including planning later on in the life cycle maintainability and development. TIC BENEFITS planning maintenance/logistics as a result as a full concept of

NASA space flight programs are being driven towards more automated, compact designs in which fewer support resources _e _nefits will be This of ...... available technique principles programs, scenario. than in past programs. will outline well-defined regardless Emphasis

par-trier in early

implementing

and user-friendly on all NASA on how and

PROGRAMMA

ii

of maintainability is placed

of the operational

Maintainability Program Implementation Project management is responsible for implementing development effective maintainability on a program via of specific requirements for cost maintenance in the early phases of

m
I

why a maintainability program can enhance the effectiveness of a system and its overall operation. maintainability systems provides It must be noted, of unmanned a different however, deep space that

system

of the life cycle.

Trade studies of the impacts

set of challenges.

maintainability design on life cycle costs are used to evaluate the balance between cost of designing to minim!ze the associated increase resulting a times. savings Usually, realized maintenance times and m system availability in maintenance cost of designingportion of =

Mal tainabilitY is defined inNASAHandbook 53(_).4(1E), "Maintainability Program Requirements for Space Systems," as: "A measure of the e a_ system or equipment operational consistent and rapiditY with which can be restored to

,= .

from the decrease the up-front

in maintainability the life cycle.

is much less than the cost


u

status following a failure," and is with NHB 7120.5, "Management

over the operational

of Major Systems and Projects." It is a characteristic of equipment and installation, personnel availability inthe_qu_ed s_.kiH levels, adequacy of maintenance procedures and test equipment, and the physical Page ....

M
w

Several

programs

have

opted

to accept

the
[HI
D

short-term cost savings by deleting = _ maintainability requirements in the design phase, PM-3 but the associated increase in

The Benefits

of Implementing

Maintainability

on NASA

Programs, Technique

Page PM-1

maintenance during
f

and support would which An example for on-orbit isolation

costs incurred have been of this is the Space had deleted automated money. was to manpower FDIR, but when positive were ORU significant the cost center based Another Telescope where fault (FDIR),

operations Program,

significant. Station detection, saving However, requirements

and recovery up-front control concept

the program the mission operations

the alternative

L w

increase during averaged example Program. included


a

for ground

this presented

a significant

cost increase

over the life cycle. is the Hubble Maintainability early planning saved on-orbit Figure between Space

concepts and optimum the program

in the life cycle,

maintenance usage costs when

in design

repairs introducing

became maintainability

necessary. tradeoffs
w

1 accentuates

concepts

into a program

and the time at

which they are introduced. These tradeoffs can mean the difference between a successful maintainability effective one. The NASA
r--

program

and a costly,

less

Figure

1: Effect

of Implementing Program vs. Phase

Maintainability engineering process for MaintenanceLogistics Development concepts must include of the design. on a program the basis system for a program

systems

should require that the system be designed ease of maintenance within it's specified operating environment(s), personnel maintainability and should (design experts) and ensure that the proper

Concept early

Development and logistics characteristics concept is a of end-items It provides support support

of the maintenance the maintainability The maintenance and support it is operational. once

in the life cycle

Z ,

operations

and funds

are committed
L

to development

of the process

plan for maintenance for design

to achieve maximum program benefit. Program schedule will be affected by lack of system maintainability because necessary ground support will increase, maintenance times will be higher, necessary maintenance actions will increase, EVA will be at a premium, and system availability will be lower. Table 1 highlights key program benefits.

of the operational the logistics

and also defines

L,

program, which will determine of spares and tools necessary The use of other logistic tools and test equipment, parts, will be optimized maintainability planning element. Derivation solidifies the life cycle

the application for maintenance. such as and spare

resources, facilities

_=_

through including as a key operational early on in aspects many operational

of these plans

Y_

Page PM-4
H

The Benefits

of Implementing

Maintainability

on NASA Programs, Page 4 Technique PM-I

Table

1: Maintainability Benefits

Programmatic

Testability Testability system replaceable is a measure component(s). of the ability to detect them at the lowest with The speed faults and to isolate

Enhanced System Readiness/Availability - Reduced Downtime - Supportable Systems - Ease of Troubleshooting and Repair

which faults are diagnosed downtime and maintenance deficiencies in Space Shuttle

can greatly influence costs. For example, Orbiter testability


I

System Growth Opportunities - Hardware/Software Modifications - Interchangeability - Modular Designs - Decreased Storage Considerations Reduced Maintenance Manpower Reduced Operational Costs Compatibility with other Programs Reduced Management Overhead

design have caused launch delays, translate to higher program costs. technology capability automatic substantially maintenance maintenance replacement systems systems, advances diagnostics reduces personnel costs of non-faulty referred continue and complexity

which As
i

to increase of FDIR

the
n

of systems,

use of
II

as a means

the need for highly and can decrease by reducing

trained

the erroneous FDIR (BIT) or test diagnostic

of the program, thus allowing for integrated design and support planning development. MAINTAINABILITY Visibility Visibility design is an element of maintainability maintainer that provides the system DESIGN BENEFITS

equipment.

include

both internal

to as built-in-test (BITE),

II
II

built-in-test-equipment diagnostic equipment equipment systems,referred (ATE),

and external test ground i

to as automatic

test sets or off-line

used as part of a reduced

visual access maintenance tasks component

to a system component for action(s). Even short duration space shuttle orbiter downtime inspection can increase greatly

support system, all of which will minimize down-time and cost over the operational life cycle. Simplicity System simplicity relates to the number of subsystems that are within the system, the number of parts in a system, and whether the parts are standard or special purpose. System simplification reduces spares investment, enhances the effectiveness of maintenance troubleshooting, and reduces the overall cost of the system while increasing the reliability. For example, program the International has simplified Space the design Station and Alpha

i
m

such as NASA

if the component

is blocked

from view. reduces

Designing for visibility maintenance times. Accessibility Accessibility be accessed greatly impact

is the ease of which during maintenance maintenance times

an item can and can if not

inherent in the design, especially on systems where on-orbit maintenance will be required. When accessibility is poor, other failures are often caused by removal/disconnection incorrect re-installation of other items hamper provide system access, Causing rework. of all replaceable, maintainer. maintainable and that

potentially increased of the space station, operational Command which space problems with the Freedom is the data station. different

the on-orbit maintainability thus avoiding many that might have flown is the Programl One example Subsystem, backbone processing for the consisted units,

L_ g

Accessibility items will to the

and Data Handling processing central Formerly,

key time and energy

savings

the system

of several Page PM-5

The Benefits
z

of lmplementing

Maintainability

on NASA

Programs, Technique

Page PM-1

of several multiple different comprises standard of orbital factors station Reduced


w

different network CPU,

central standards.

processing and several

units,

However, development

early evaluation can assure results

during concept application Use of of these designs

level architecture, only one network and a greatly design replaceable

early

The new design standard, reduced were one number definite

anthrop0metriee0nsiderations. evaluations

leads to improved

units (ORU's). criteria changes to this space

largely in the areas of system provisions for equipment access, arrangement, assembly, storage, benefits improved and maintenance of the evaluation lower supportability task procedures. The include less time to costs, and improved systems,

Maintainability

in the design subsystem.

effect repairs, can also be a direct Maintenance and Summary Implementation design in quantities safety.

maintenance

training costs skilled personnel

result requires

of design

simplification.

skill levels commensurate with the complexity of the maintenance characteristics of the system.
LJ

of maintainability about operational and unmanned

features systems.

in a The

can bring

cost savings

An easily maintainable restored to service maintenance personnel,

system thus

can be

for both manned

quickly available increasing

by the skills of of the system.

programmatic benefits hardware and software of maintenance program, Telescope.

of designing system for ease and reduction and can save a Hubble and exposure by in the programs Remote Space micro-

the availability

are numerous,

as seen with NASA's Maintenance environment is a difficult

Interchangeability Interchangeability component without refers to a component's for ability to be replaced with a similar a requirement

in a hostile, Minimal features NASA

gravity

undesirable implementing design. have also or features system

task for humans. maintainability successful which

time to this environment The most in all facets restoration

can be achieved

recalibration. This flexibility in design reduces the number of maintenance


w

procedures maintenance

and consequently costs.

reduces

been those

included

maintainability management on projects

t_

Interchangeability

of the life cycle. by redundancy is particularly

allows for system growth with minimum associated costs, due to the use of standard common end-items.
r

and contingency

planning

essential to assuring mission success where manned intervention is either undesireable or impractical.

Human Human should identifies prohibiting provide

Factors factors design requirements proper factors also design discipline features or and to design in be applied structure to ensure

References 1. NASA Space Handbook "March 5300.4(1E) Requirements 10, 1987, NASA for

consideration. that impede also identifies maintainers. drawings

The human task performance maintainer body requirements Normally,

and equipment

by inhibiting movement, necessary for

"Maintainability Systems, Headquarters. 2. NASA Major NASA

Program

an efficient

workspace

the system before detailed

Handbook

7120.5,

"Management "November

of 1993,

must be well specified or sketches anthropometric

and represented

Systems

and Projects,

Headquarters

evaluation

can be effective. Page PM-6

The Benefits

of Implementing

Maintainability

on NASA Programs, Page 6 Technique PM-1 I

3. Air Force "Maintainability

Design

Handbook

1-9 Electronic

(for Ground

Systems)," Second Edition, Febm_r'y 25, 1988, United Aeronautical 4. Systems

Revision 7, States Air FOrce

Division. Engineering Design and


m

"Maintainability

Cost of Maintainability," Revision II, January 1975, Rome Air Development Center. 5. Reliability, Maintainability, and

Supportability (RMS) Guidebook, Second Edition, 1992, Society of Automotive Engineers G- 11 International Committee. 6. MIL-STD-470B Program for Systems 30, 1989, Department RMS

aim

"Maintainability and Equipment," of Defense i May


I

i
m i.al I

Page PM-7

ilI

Maintainability Program Management Considerations, Page 1 Technique PM-2

Technique
T

Identify program management considerations necessary when implementing maintainability principles for NASA spaceflight, atmospheric, or ground support programs.

_::.

=======================

_J

ilMil:li,!ii:i

LJ

Nl!!l!j!illili l!i li !I!i l!l,i !


=========================================

::: :::?.;:::::_:%:8.._:_ _:_ :: .'::_ _.:_ _:.

.::

:::_::'::::::.,..'.._:::_::::::::::::::_ :F.,. ::::::::::::::::::::::


:::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::

Benefits

Early and effective planning and implementation of a maintainability program can significantly lower the risk of reduced system operational effectiveness resulting from maintainability design shortfalls. This reduces maintenance time/support, which directly relates to reduced operating costs and increased system operational time.

KeyWords

Maintainability Management, Maintenance Quantitative Requirements, Maintainability

Concept, Logistics Planning

Support,

Application Experience

Hubble Space Telescope, Measurement System

SRB's, Shuttle GSE, and Space Acceleration

Technical Rationale

Decisions by program management to establish maintainability requirements early in the program will provide design impetus towards a system with higher operational availability at lower operational costs Lower downtime and less complicated maintenance actions will be needed when maintenance is required.

Contact

Center

NASA

Headquarters

__

Page PM-8

Maintainabili_F

Program

Management

Considerations, Technique

Page PM-2

Maintainability Considerations Technique PM-2

Program

Management

PROGRAM

Z g

This technique considerations principles NASA. to realize downtime. Maintainability providing

outlines to observe

management when applying on a program information and reduced system


D

the at
g

of maintainability It also provides cost savings

on how

This information on NASA

complements Programs," a have


PROGRAM CONTROL

PM- 1, "Benefits

of Implementing by m for establishing once

guidelines

maintainability program been understood. Program establishing maintainability and ensuring application throughout 1 provides development Maintainability management proper early adequate

the benefits

is responsible integration in program control of

for

development of the Figure 1: Maintainability Development


r_

of the maintainability discipline the development program. Figure flow diagram program of its goals for an effective beginning with

Program

II

reflect

the function objectives

(mission)

of the on if the of to do

and objectives,

system/subsystem operational system time. of

and the impact

followed by development of the program/system maintenance concept and the Mainta[nability Program control these Plan, and establishment during and operations. development of program design, elements production is The order and evaluation program

of the program

isnon'operational System availability

for any length

(the ability of the


m

(manufacturing) important, process.

system to operate whenever called upon so) is very important, _and maximum availability Program should maintainability goals

be a goal of the program. and objectives in


= i =

as each affects

the next step in the

must be developed ....... AS

with cost and schedule

(1) ESTABLISH MAINTAINABILITY PART OF THE OVERALL SYSTEMS ENGINEERING AND PLANNING PROCESS. Set Goals and Objectives of the maintainability is to measure or restored designed OPERA TION

mindi hqwever, careful considerationo must also be given to the technical-and operational goals of the program. These qualitative by analyzing goals the
D w

and objectives

are developed

system oPerating cycle, the physical maintenance support environments, equipment mission Attention of support duplication characteristics and cost objectives. must programs during also be given to avoid development consistent

and and other with

One of the missions program be retained when maintainability

H
J

the ability of an item to to a specified into a system condition should to existing needless of new
H

maintenance

is performed.

The degree

Im

Page PM-9
H

Maintainability

Program

Management

Considerations, Technique

Page PM-2

support derivation

systems.

Development goals

of the will lead to of in the concept, discussed

repair

policies,

and maintenance costs.

resources at

to

maintainability maintainability maintainability following

and objectives

the desired acceptable interfaces development shown

level of maintainability life-cycle and feedback engineering and operational 2. personnel in the product and provide techniques management's and support paths

of the maintenance requirements

The many between product are disciplines and other

plan, and definition

maintainability in Figure

paragraphs. with Other Engineering

Establish Interfaces Disciplines Maintainability engineering analysis of safety, costing discipline reliability,

While is a system system and life-cycle that combines human factors,

maintainability involved process design

must

be to

engineering

intimately development design analysis, relationship

inputs and the

and equipment to optimize

design with a knowledge

through

it is program between

the maintenance design and to provide Its goal is problems.

responsibility

to develop

characteristics an awareness to optimize

of system of interface

maintainability

and the of a

rest of the system This support

engineering

disciplines.

the combination

of design features,

is key to establishment

TEST AND EVALUATION


E REQU|REMENTS DEF|N|'_ON I SYSTEM DESIGN AC'R_PI'r_ES I

Design Feedback Characteristic:

SYSTEM AVAILABILITY PERFORMANCE


-': 4

Operational Suitability Analysis

SYSTEM READINESS PERFORMANCE

SYSTEM Trades II _' I _ PERFORMANCE I Design d

F_

Operations & Support Concepts

|1_ _' ........................ _

Test& Evaluation

I I

Design Feedback

Figure
w

2:

System

Reliability,

Maintainability Page

and Support

Relationships

(typical)

PM- 10

Maintainability

Program

Management

Considerations, Technique

Page PM-2

concurrent relationships Maintainability

engineering Program

process. Plan.

These in the

These logistics system

elements planning down

are also important maintainability during can define how much

_ in that

must be mirrored

contributors

to system

time is required operations. downtime operations.

(2) DEVELOP MAINTENANCE LOGISTICS CONCEPTS EARL CONCEPTUAL PROGRAM.. The program basis design contains policy. It defines and depot repair replacement, philosophy, concepts, responsibilities, responsibilities, maintenance these maintenance maintainability as mission reliability constraints, maintenance ground successful dictate repaired elements). overall repair policy, system policy, maintenance overall concept PHASE

AND Y IN THE

maintenance For example, minimum system during

OF THE

can be held to a with the that of all It is important monitor inclusion the

if spares are co-located management development Both closely to ensure concepts

provides and

the

Program logistics

for establishing = quirements detailed

maintainability on maintenance

on the program,

maintenance the program. development

and logistics of lower-level Resources aspect

concepts drive

early in

planning

requirements.

organizational availability, level of sparing and principles

Assess Another

Existing important

maintenance,

of planning

for a

vs. replacement

skill level requirements, diagnostic/testing contractor payload (PM-3 concept analysis profile, maintenance maintenance

new program is assessment of the existing logistic and support infrastructure. As an example, system numerous the infrastructure at KSC comprises assembly of the NSTS=: the launch pad, buildings,

and support

and crew time allocations provides is based details Development of the on initial inputs and

for

on each of

and support personnel and equipment. These are important factors to consider when planning for new structures programs that will use KSC base. If some of the can be used will be as the central operations

and program availability system

such

existing

and equipment costs

system

by the new program, and operational reduced. management During Ttie from the of

then the developmental of the program stages, support and

requirements, and personnel concept program,

mass properties

considerationsl from a similar

early planning

may be developed tailored

should

also look at how the new

up, or may come New

to meet the needs may also :e.g. instead outweighs of

program can adapt to the existing infrastructure, and what equipment personnel may be used to eliminate unnecessary costs.

the new program. maintainable replacement Definition

technology concept,

the maintenance because cost. of logistics

items may be scrapped the cost of repair

the

Establish master

a Maintainability program and control program. planning

Program plan is the document

Plan for the detailed attain the

The maintainability and support concepts is a maintainability activities goals program. program program

It provides necessary-to

function &the maintenance concept. The operational environment of the system, the level of support concept, drivers personnel defined by the maintenance are important programs. and cost and schedule for the logistics/support

and resources

and objectives

of the maintainability

It must be developed with the _ contractor(s) if they exist, or if the is in-house, all developmental and

Page PM-11
l

Maintainability

Program

Management

Considerations, Technique

Page PM-2

operational complexity be integrated process.

disciplines

must be represented. with the type and or equipment

The

plan must be consistent of the system It identifies

These requirements are intended as rules system designers follow to meet overall program mission, concepts. goals and objectives. environment, absolutely can include parameters. requirements They include operational unless and system early and

and must

with the systems how the office program the three Production, major

engineering the phases

They must be baselined

contractor/program
w

will tailor program

not changed

necessary. both of the on Quantitative are usually based timing at each

maintainability throughout Development, Support. elements

to meet requirements The requirements quantitative maintainability maintainability result system and Operations/ the following and qualitative values

Typically it contains shown in Table 1" 1. Elements

of maintainability availability

allocations made

Table

of the Maintainability Plan dement of the

and operational

Program Duties involved

requirements, level down assembly

with allocations to the replaceable

of each organizational in the accomplishment

module, are

or component

level as needed. requirements

maintainability tasks cited in the product specification or statement of work. Interfaces other engineering,
B

Examples of quantitative shown in Table 2:

between

maintainability reliability,

and safety,

Table

2. Examples

of Quantitative

project

organizations, software, and logistics.

such as design Maintenance

Requirements manhours per operating (MTTR)

maintenance, Identification

hour (MMH]OI-I) task, and Mean-Time-To-Repair Mean-Time-To-Restore-System

of each maintainability schedules, documentation

narrative supporting

task descriptions,

of plans for

(M'rrgS)
Fault detection and isolation of subsystems task times

task execution
w

and management of the nature and extent that

Description

End item change out time Unit removal/installation times Availability

the maintainability function formal and informal design authority approval of maintainability cycle for drawing

participates in reviews, and personnel release. in

They may be established

at any, or all, levels of two

of maintenance and can help define maintenance criticalities and reduction (3) PROVIDE UNIFORM QUALITATIVE AND QUANTITATIVE MAINTAINABILITY REQUIREMENTS. Maintainability established design requirements maintenance are Program concept. necessary requirements purposes. system First, components. they address are used to accomplish

Qualitative maintainability

design features which are vital in achieving the maintainability goals, but cannot be measured. For example, elimination of of safetywire/lockwire, standardization

from the Maintainability

Plan and the derived

Page

PM- 12

Maintainability

Program

Management

Considerations, Technique

Page PM-2

fasteners, coding orbital program Examples handtools intermediate designing personnel. qualitative requirements

use of captive of electrical wiring Second, maintainability

fasteners,

and colorused on

and existence the chance historical References

of these

examples success

will enhance (based on

are some basic requirements qualitative the

of program experience).

programs.

IB

are used to meet customer/ and enhance of the system. of common and and

requirements include levels

maintainability:characteristics specification

I. NASA Space

Handbook "March

5300.4(iE), Requirements 10, 1987, NASA for

"Maintainability Systems, Headquarters. 2. Air Force "Maintainability Systems)," Second

Program

only for organizational of maintenance,

Z
! I

11

so that only one skill level is required level maintenance Design Handbook Edition, 1-9, Electronic Revision States 7,
g I

for all organizational

(for Ground

(4) EXERCISE PROGRAM E VAL UA TI ON. The maintainability part of the systems design include design program engineering

CONTROL

AND

February

25, 1988, United Systems

Air Force

Aeronautical must be an integral process and all Activities and of 3.

Division. Engineering "Revision Design II,


l

''Maintainability 1975, Rome

and

Cost of Maintainability, January, Center.

and development reviews,

activities. development

Air Development
I

implementation maintainability maintainability of program supplier evaluation Summary Program control

of methods effectiveness,

for assessing dissemination Subcontractor/ implementation 4. Reliability, Supportability Edition, 1992, Maintainability, and _S) Guidebook, 'Second Society of Automotive RMS
J

data, and proper test and evaluation.

is also a key areas for program

and monitoring.

Engineers G- 11 International Committee. Related Techniques

management's practices based

participation on NASA Whether systems,

in the of sound programs is and Technique PM- 1, "Benefits of ImPlementing Maintainability on NASA Programs"

development maintainability extremely contains beyond, system system guidelines depending apT.,'oach p"

and implementation important.

the program or is orbital for increased and lower above are


J

ground operations,

maintainability effectiveness costs. towards

plays a key role in and availability, outlined

Technique PM-3: Space Systems."

"Maintenance

Concept

for
J

providing The steps success,

_m

life cycle

and can be tailored However,


g

on the type

of program.

the importance _essional

of a concurrent relationships personnel disciplines

engineering

and the existence

of intimate between and other systems


i

ma:ntainability engineering

can not be overstated,

Page PM- 13
m

Maintenance

Concept

for

Space

Systems, Technique

Page
PM-3

Technique

Develop provide influence

a maintenance systems

concept

early

in the program support.

life cycle

to

a basis for full maintainability design to ensure of repair minimization

It should be used to for ease of

that attributes

maintenance,

and down time, and logistics

support will be present


::_ ================================================================================================

in the final design.

ili!i!iiiii__iiili/iiiiiiiilii/i/iiiiiii/ii :: : :._ _:._:: :.__:_ : _:.__:._ :_ .'.::':_:::::::::


::_';4::::._::::::: _. ::::::: ::::,_:: ::::::::::::::::::::::::::::::::: :_:_:_:.. :::::::::::::::::::::::::::::::::: :::::::::::::::::::::::::::::: :::::::::::::::::::::

:_ _::: :.:: :::::__:_. :':.'.':: : : :?.::_ : :_: :_ : :_ _:_::._ ::_ ::. :::._ : :._4._: :::_:::.::

_::::::::

:_:: :::::::._ : _:.__::: _:'. : _::_:.'::':: : :._._ _:_

:: :._ $_:: :_.,::.:: ::::_:: ._'_

.<:._:,_!:i_:i:!;i:!:i:_:_:_:i:i:_:_:i:i:i:i:_::...:_:.._.:?,:.::.._ ..._:::i::::.::._)!:::. ::.'.::_:::_S.'.::. _::::::::::::::::::::::::::::::::::::::::::::::::::::::':.'::;::':

:.'..:.:.:..,:.:.:..,:._.:.'.. :.:.>>'._:.:....,:.:.:.:,. ::..:.:...,'.:..,:+

.,:-:........

i_iiiiiiiIIiiIiii_!i_iIIiiii!i_.:..`.._i_i!!Ii_iiiI_i_iiiiiii_i_i___i!i_iiii_i!iii!IiI!_i_i!_iiIi!!iIiii_!!!!iiii_i_ _itlli!i_iii_ii_iiiiiiiiiiii!i!iililiiit!i/!iiiiiii_iiiiliii_iiilili_iili/ii '_: g__:'_ ":::: ":::&?::: :: ::_*i_ _::: "_::: :::*:*._ :*:::_:_::: _.:: * ::::_'_:_:_':_ _::': :::," .".': _.'.'.'.': .".':_::: *::'. :!.':!:: ?.'::: ::?.::: .':::: :':_:*: _,::_ *_*:_N_:::_i_
:::::::::::::::::::::::::::": _.::'_::::::: :':'_:::: :'_ :" :':>:':'_:':':+'_:':': :'::':':':':< <':"_:+:':':':':':': :':"_:'_:[:i:i::" :::: f::..'.:.,. _.: :::::::::::::::::::::::: :::_:: :: ._:._:_ ?.:::::::: .,. :_:_ _ _ ::" ::::: :..:::::::::::!: _.:_:_.:::::: :,,'.:!:::!:: :_: ::::::::::::::::::::::::::::::::: ::.:.:::: :.,..::::. :_ _:,:.:..,:.:.:.:.:_.:.: _..._:+:+:.:+:.:.:.:-:.:.:.:.:.:,:-:.:.:.._:,:,._ :_ -:.:.:,:.:.:_.:.:.._:,._ ,_:_ :.:.._ :.:-:.:.:.::_ :._ + :.:.z.:.:.z._: _:::::_:_ :: .:.:::. _.::: .,:::: _:::::::.,:::::::::::::. :::: :.:::::: :. :::: :::::::::::::::::::. ::::::::::::::::::::::::::::::: .-.. :_.,. ?_ :::::::..).:.':.-_ _'_ ::..:_:::: :::::::::::::::::: _::::::::::: ::: :::_:::::::::::::::: ::::::::: :::::..: .>:_:_: 5:_ :_ .::_::_ :_ ::: :_ :_: ::: .q_ :::::: _:::_::.: _ _:_:::::: :::::: _._:::::::_ :::: :::::::::::_: _ ::: :_. ::::::::_ _:_:_:::::: :::::::::-:::: :::::: :::: :::::: ::::::::: :::::: ::.::...':::_ ::::_::. _.::_:::::::::::_: :::: :_:::':::_ _. ::::: :_::;: _:,::_.'. :_. :::::::_ ::::::::::::::::::::::::::::::::::::::::::::::::::::: =======================================

:_:: ?.':_ ::_:::"::::::::: *?_::: _: ::::::: :::_'.': ::_i _._ _'.'__'_ _ _:_ _."" _ _ __ '._:_:'.';_'_-_ _ ;__ _ _ _._ :_:_:_:_ _._._ _ "__ _ _ _ _._._ _ _ _ _ _':_ :._ _ _! _._i _! _ !-_ _t_ _._ _!_i.'.._i _i_:_//_i_i_ _i_!!l_ ._._i/_i __i_i_i_i/.-'.:..'_! _i_i_i _i_i/_::_i l_i_ _::_._ _ i_i_ i_i_i_fi_ i_i _.::_!_i _!_ i_i_:_..':_!_ _ _ _i_?_i _i_i_ _ _i_: ::_ i!_::_?_i _._::_!_i_ i__ _i_i_
:::::::_:_.:. ::::::::::::::::::::::::: _._.._._>_`_..._:_._._:_..`._.._.`...'_._..__._.__.

_..'.' _ _

_::_ ====================================================================================================================================================== :::::::::::::::::::::::::::::::::::::::::::::::::::::::: <:_ :_::: '" ." .:_:" .:: " : " ." -::: .... ". ':: !:. ' : ._!_!_:_`_i_!._!_i_._i_._i_._``_..`._.`.._?. . :::::::::::::::::::::::::::::::::::::::: :._:._::_::._..'&:::::._

_._ _ ._..'.'_ _ i_,..'i_


_.:

:::::::::::::::::::::::::::::::::::::::::::::::::::::::

::::::::::::::::::::::::::::::::::::::::::::::: ::_................ :'::':'.':_i:_i_:_':'..' :':,.:::_..':':':'..'::.':::::.':-':::'_.._':':'. .... _'.":':':'.':':'_:'...+_:_':'_:'::_:::::::::':':'. :':':':':_. :_':':':':'_:':':'::':':'_:'::'.':' ":':_'_.':*::':'_:' _':' _:_ .................. _ .................. _ .............. ::::::::::::::::::::::_!'_" :_,_::"_:: _::::_ ....... "_*:::: *::::::'"_iii:::*_:::'_:"_':': :'_....... "_::_::_::::*:::: :_ ........._: *:**::::_::_':::_ *:_::
:::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::

Benefits
w

Effective planning

development and design

of a maintenance support of a maintainable

concept planning system.

can enhance The maintenance

the concept activities

effectiveness

of maintenance

and aid both logistics for maintenance level.

can also provide assessments of cost savings and resources allowable at each maintenance
_

Key Words

Maintenance Maintenance

Concept,

Spares

Requirement,

Logistics

Support,

Plan, Maintainability

Requirements.

Application Experience

Space

Acceleration

Measurement

System

(SAMS),

Combustion

Module-

1 (CM- 1) Shuttle/Station

Experiment.

Technical Rationale

The need to identify servicing techniques

quantity, required

cost,

types

of spares, a space

and related mission requirements maintenance

to sustain

system

capability is a prime driver in developing maintainability for a space system at the onset of its design. A system
L

concept conceptual

should

be developed requirements

to define

the basis

for establishing in the system the practical and maintenance by applying concept. the basis The

maintainability for design, number of space principles

and to support concept

design

phase. layout, systems of problems prescribed

The maintenance and packaging associated can be reduced,

provides support

of the system with product

and its equipment.

if not eliminated, maintenance

in the system's

Contact

Center

Lewis Research

Center

(LeRC)

,..,

Page PM- 14

Maintenance

Concept for Space Systems, Page 2 Technique PM-3

Maintenance Technique

Concept PM-3

for

Space

Systems

orbital ground

space

program

where

on-orbit

and

maintenance Policy policy (levels)

is planned.

The maintenance the program, maintenance It establishes responsibility maintenance (maintenance to maintain structuring eliafinate m: and application

concept

provides detailed

the basis for for planning of system. of _ required in .......

Repair support echelons

overall maintainability

design

requirements

The repair

should

consider

the 1.

and contains the scope

to be provided

at the maintenance in Table

policy for the operational of maintenance for each level (echelon) and the pers0_el manning a space system. and skill levels)

summarized

Table

1. Echelons

of Maintenance

resources

Early development concept plan can of problems that


Where Performed System Maintainer Basis

Organizational Maintenance
On-orbit

Depot Maintenance
ii

of the maintenance occurrence operation.

the maintainability or reduce system

NASA Center or Contractor Center Engineers and Technicians Repair and return equipment to stock inventory Repair at module, ORU, and component level

interrupt

Flight Crew

The maintenance must early conceptual minimize operational being current principles, used development Space phase.

concept design

for a new system during the to is during the phase of a program approach experiment to incorporate support Acceleration

be systematically maintenance on Space programs Station prescribed

formulated problems This proactive Station-based at LeRC Program Space

Repair and retain equipment

Type of work accomplished

Inspect equipment

Remove

and

Measurement System (SAMS) and Combustion Module One (CM-1) operational and repair policy, Elements This maintenance planning basis concept will aid in logistics design by providing the Organizational Organizational performed flight crew) maintenance personnel, and occupied support and will guide and identified sparing requirements.

replace modules and ORU's

Repair and maintain ground support equipment Calibrate equipment

Adjust equipment

for establishment

of maintenance

Maintenance maintenance is maintenance (e.g., This and repairs

requirements in terms of tasks to be performed, frequency of maintenance, preventive and corrective numbers equipment, Inputs include: availability weight design The concept maintenance and skill levels, tools, a mission constraints, should elements repair profile, to the maintenance requirements, downtime, items, personnel test and support and information. should reliability size and concept system overall

by the using organization on its own equipment. consists skills, tools, of functions of authorized

within the capabilities Organizational equipment,:

and test equipment. are generally and use of the time available at

level personnel

w_th the operation and have minimum

and crew support as they apply

considerations. the following to a manned

for detailed maintenance checkout; consequently,

or diagnostic the maintenance

Page PM- 15

Maintenance

Concept

for

Space

Systems, Technique

Page PM-3

this level is restricted equipment equipment, removal modules referred forwarded performance. front

to periodic Cleaning

checks of

of

any on-orbit

repair

actions identified

are planned,

they

should be clearly

in the concept.

panel adjustments, of certain Replaceable boxes, Level.

and the plug-in (ORUs), and Units

and replacement and Orbital to as black

At the organizational level, failed items should be either discarded or sent to the NASA policies limited at plug-in Center or contractor for exchange and repair requirements. in accordance Corrective should with repair/discard maintenance, of faulty ORUs period. to have and to be Prime ready be specified

are removed

to the Depot

identified

in the system

Depot Maintenance Depot maintenance is maintenance performed NASA Centers or contractor facilities for completely equipment maintenance tasks to repair overhauling actions. faulty provides and rebuilding highly The support equipment the complex as well as to perform

to replacement modules, during should should

performed equipment access fasteners Level

the mission be designed

for maintenance.

Quick-opening

includes

also be specified.

to the part of Replacement for proper should level of ORU compatible within failure the same consider parts ranking standards and also The design definition rates ORU.

level, if deemed maintenance for equipment serves @stem

necessary. calibration supply

This level of purposes, for spares.

the necessary

as the major Availability

for hardware Relative

of ORLPs through considerations can also level of level at the analysis

reliability (Ao) is defined as the point in time, the It is a function active time, contribute replacement

and maintainability criticality toward definitions. should and ORU the proper

Operational probability system

Availability

and mission

that at an arbitrary i.e., is "up." of maintenance,

is operable,

The required be specified levels.

of the frequency maintenance administrative system,

of replacement plug-in module

time, waiting

time, logistics as:

time, and the ready time of the

and is expressed UPTIME o TOTAL TIME

Maintenance and support of a system should involve two-tier maintenance echelons. The first level provides for repair select modules of the end-item faulty or diagnostic on-orbit by replacing plug-in through

(1)

defective identified procedures. evacuated maintenance

and ORUs

use of specified

Where:

Faulty ORUs should then be to the second level of the echelon (depot Center level), for repair which if NASA for

UPTIME operable

= the total time a system state, and = the combination in which downtime spends

is in an

will be at a NASA deemed necessary. of faulty center/facility

The particular

should items.

act as the depot

TOTAL TIME and downtime, which Repair Normally, performed a system

ofuptime is the time in state.

repair

in an inoperable Policy should modules not be

Skill Level Hardware and ground repair. If

Requirements should be designed to aid on-orbit and design not be required maintenance, a system. inspection,

v_ Replacement on-orbit repair on any plug-in

Special

skills should

or 0RUs.

to maintain

The following

Page PM- 16

Maintenance

Concept for Space Systems, Page 4 Technique PM-3

features Plug-in

should be incorporated: module special and 0RU tools, design to minimize for

Custom-made Long-lead

components/parts

time items of spares required availability according for each to sustain on-orbit to the the

installation/removal hand tools, skills. Plug-in designed

time and requirements and maintenance

The quantity system required should

and the total quantities operational be determined

modules

and ORUs

should

be by removal

following: Items that are critical to system operation

for corrective

maintenance

and replacement. Plug-in preventive with respect module and 0RU designs maintenance requiring hours,

Items that have high failure rate Items that have limited life In the initial spares to the maximum should be purchased the layers early provisioning practical, directly period spares and

maintenance

should

be optimized extent

to the access, complexity.

and maintenance Software be designed corrections minimum

from the actual subcontractor, costs period plus a


w l

and its associated

hardware

should with

manufacturer; to eliminate each tier. should short period cover

i.e., lowest-tier

so that software revisions/ can be easily installed on-orbit skill level requirements. training for payload identify hands-on center training, at the NASA flight

of support

at
I

The initial provisioning of operation, experience of spares. shelf life should be acquired quantities Spares

test and evaluation, with the system.

to gain sufficient This

Flight crew operation crewmember where crewmembers hardware.

operational will provide acquisition of Spares identified to ensure

should

a basis for fully competitive


m

the system

is built, to familiarize with limited and should that adequate when shelf lives should be
U

with the removal/replacement

periodically of spares with and

Spares support

Philosophy of spares should be required to a maintainable system: spares. development Development and and spares system test

are available expired replaced.

needed.

Two basic types

be removed

spares and operational spares are those acquired activities, production. operations The quantity sustain to support integration,

that must be identified planned assembly, to support

Procurement of spares should be initiated sufficient advance of need to account for procurement production lead time (administrative lead time). and

in

check-out on-going

Operational on-orbit.

spares are those

that must be acquired

The location of the spares inventory (onorbit and on-ground) should be a function spares required quantities during to the the on-orbit stowage allocation capabilities

of

of development and the total availability

for each system,

the required

and requirements. A volume/weight analysis should be conducted to determine the quantity to sustain availability. and types of spare items necessary satisfactoryoperationai The volume/weight analysis shall

planned test activities, integration, assembly, and check'out test should be determined according to the following:

Page PM- 17

Maintenance

Concept

for

Space

Systems, Technique

Page PM-3

assure weight stowage Breakout

available limits, area. should

or planned and planned

payload

volume

and

to be functionally,

mechanically,

electrically, as practical

or available

on-board

and electronically as independent to facilitate maintenance. The concept operating/testing problems various types should also describe

be addressed

during

initial

provisioning process Reference procurement equipment other effective. personnel.


w

and throughout 1. Breakout directly manufacturer, whichever A spare

the replenishment 5900.1,

techniques of items

to identify of the skills system

in accordance

with NMI

and consider

the complexity in the space personnel or hardware). maintenance

is the spares from the original prime proves contractor, most costlist should and technical or

and associated (for all software, The techniques problems. safety concept.

maintenance firmware, will identify

source,

item requirement

In all cases

of fault

simulation, damage

the to

be maintained

by procurement

of personnel

and potential should should Also,

system/equipment Principles and Concepts failure safety

be evaluated request a Failure be the basis for

in the that a

The concept fault tree analysis simulation.

Diagnostic/7"esting The system detection should requirements should

meet the following as a minimum: have the capability

determining

Modes, Effects, and Criticality Analysis should be used to evaluate and determine to fault simulation. maintenance monitored, Preparation Functional Diagnostic isolate Repair replace, access Clean, time: adjust, Some of the fundamental are as follows: time actions to be evaluated,

The system

detect, isolate and support the display of failures to the plug-in module level. Crew observations may be used as a method visual general should checkout, of items. for lighting, of failure detection of the following: displays, speakers.

and recorded

keyboards/buttons, System
L :

and visual inspection check-out time time: fault locate

and fault and

design

provide repairable

the capability and level without

for monitoring, isolation requiring removal

fault detection,

gain access,

remove

to the on-orbit

align, calibrate, service time

and close

lubricate,

Manual override and/or inhibit capability all automatic control functions should be provided
[_

Functional Responsibilities Maintenance The prime program

check-out for

of the repair

action

for crew safety

and to simplify

Contractor maintainability controls for assuring

checkout

and troubleshooting. of the system detected should crew. be devoid of be either to

contractor's should provide

All failures automatically the flight Accesses

and enunciated

crew or the ground and covers should

adequate hardware. through

maintenance of purchased Such assurance is achieved the following: of subcontractors of demonstrated a maintainable product. from the capability to

sharp corners/edges and be equipped areas for safe maintenance activities. Systems/subsystems/items should

with grasp

Selection standpoint produce

be designed

Page PM- 18

Maintenance

Concept

for

Space

Systems, Technique

Page PM-3

Development of
specifications subcontractor-produced Development requirements Close (both minimize facilitate interface

adequate

design for the

ground processing

or maintenance

and test requirements product.

operations. The rationale for supporting these recommendations should include factors such as reduction in ground support
l m

of proper to impose liaison

maintainability

turnaround
COSTS.

time and operational

on each subcontractor. with the subcontractor areas) to and to of problems design

II technical Allocation Action: identified complexity, requirements. of Crew Time for _: _ in accordance reliability, Maintenance
m

in design early

and maintainability identification

communication or interrelation review program

Crew time for maintenance

should

be of the exist

II

and correction problems.

with system and criticality methods U

items to the system Continuous that each maintainability and assessment is implementing effectively. Maintenance responsible for or repair for maintenance identification in accordance to assure his subcontractor

and mission

Analytical

which can be used to prioritize and allocate crew time for maintenance actions.

Responsibilities for Payload Director of field installations launch activities planning necessary preparation, should be responsible

RefeYencg$

|
Instruction, NMI Spare Policy, Office: 5900.1A, DC, II

maintenance,

1. NASA NASA

Management

Parts Acquisition Responsible

and for providing to support related requirements. include: a system problems activities

the resources

HM/Procurement

the efficient problems These

of maintenance with system responsibilities Implementing track, and status maintenance characteristics Providing collection quantitative estimates. identify growth

Systems Division, Washington, November 6, 1992. 2. NASA Management 5350.1A,

Instruction, Planning Responsible 26,


I

Maintainability that will identify, related to routine to the design and sofcware. Policy, Office: Quality, 1991. NMI Q/Office

and Maintenance NASA of Safety

and Mission

attributable

Washington,

DC, September

of flight hardware information

for use in a data the accuracy and availability can be used to reliability and to from ground design of

3. NASA Program NHB

Handbook, Requirements

Maintainability for Space Systems, _=_ :_ ........

mi

system

to improve

maintainability This information trends "lessons experience. during

5300.4(1E),

Reliability,

Maintainability, Publication, 19871 4. Space

and Quality Assurance DC, March 10,

failure

influencing learned"

Washington,

characteristics

m t

communicate maintenance

Acceleration Experiment, Plan,

Measurement SAMS-SS Center,

System
U

(SAMS) Recommending responsible improvement hardware/software, to the Program Manager, of flight in Assurance NASA 5. for design and development areas for design the efficiency Space

Product (Preliminary), Ohio.

SAMS-SS-005

Lewis

Research

to increase

Acceleration

Measurement

System U

Page PM-19

Maintenance

Concept for Space Systems, Page 7 Technique PM-3

(SAMS) Integration Lewis 6.

Experiment, Agreement, Research Station

Express Ohio.

Payload PIA, NASA

SAMS-SS

Center,

Space

Program,

Space

Station

Program Definition and Requirements, Sections 3 and 4, SSP 30000, NASA Lewis Research Center,
w

Ohio. Module Plan, One (CM-1) NASA Experiment, Research

7. Combustion Product Center, Ohio.

Assurance

Lewis

8. Blanchard, Edward
w

Benjamin

S., Jr. and Lowery, Electronics and 1969. Principles Inc., N.Y.,

E.

of General

Dynamics,

Division, Practices,

Maintainability McGraw-Hill

Page PM-20
=_

wig

mi

i
U

aiD

wi

|_

Design
|_

Factors

and

Engineering
The objective of the A4aintainabilityfunction m a cost effective discipline is to influence condition influence system design such that the end product downtime. design In order for principles to

can be maintained the Maintainability obtain

operational

with minimum

to provide

maximum

to a program,

these objectives

must be implemented programs

early in the design phase. in this section

Techniques as design

that have proven for

to be beneficial future programs.

on previous

are presented

recommendations

Page DFEF = w .

II

mm

ii

m i

im

II

II

Im

m RB

Selec#on
J

(f Robotically

Compatible

Faswners" and Handling

Mechanisms, Technique

Page 1 DFE-1

Technique

Provide

guidelines

for the design

of maintainable

equipment selection

for criteria for

compatibility with dexterous robots by outlining associated fasteners and handling fixtures.

; r i

2 ,

_'_'i'_'_'i'i'_'B'_'j_;ii'i_i'i'i 'I_, _i'iJi'i':ii'i'iii'i':':i:i:i:i:iiiii_,i:_:':i :_:i:i:i:i:iS_TEiE_'i'Oi'N'i_i'i_ 'FI _'R_B_|i_

iiiiiiiiiii !i iiiiiiii iii iii{iiii iii iiiiiiiii !iiii iiii iiiiiii!!iiiiiYiiiill iJii iiii iiiii !iiiii iiiiiii !iii !iiiii iiiiiii i ii iiii i

_L:_i:_:_:_:_;i:_:_i:

i::Miii!iiii fk_l _:_ ::!! ::i_ii!i :2:!i! i::::i:: ii::ii:: i::i::iii:::: i!i ii]iff:ili!i::ii:: iii::iiii::::i i::ii!i::::::::_::_i:: _::_::_i_::_ _ i_!: _:_:_:i __:_ _:_ ........... _i!i::!_:_i;:!i_;_._i:_::i_i!_:i!i!!_i::!_::_::!i::ii!::i_::i::::ii::i_i_:::_::::_::!::_!!:_::ii::iiii_::i::_i_i_:_!i_!ii_iiiiii::iiii_i_ ii::ii:: _ i i _ ii_ _+_#:_i_i::::::::ii!::ii::ii::i_::i_

i!iii_iiiiiii_ii_ii_i_iiiii_ii_ii_iiiiii!iii_iiiiiiiiJiiiiiiiiiiiiiii_ii_i!_iii!iiiii_!!_i_!ii_i!iii_ii_iiiiii_iiiiiiiiiii_i_iiiiii_iiiiii_iiiii_iii_i_i_iiii!i!_ii_i_iD.:_Ei|i_iiii_i_iE_i_i_i_._

iiiiiii_iiiiiiiJiii!i_iiiii_iii_iiiii_i_iii_!_i_iW_ii_J_!i_iiii_i_iii_i_i_iJ_i_i
Benefits The application of these guidelines to the design process will increase the effectiveness of dexterous robots by allowing of robotics components used during maintenance because Extra Vehicular Activity (EVA) tasks must be simplified intrinsically compatible EVA tasks. availability inferior designs to accommodate will facilitate robotics the simplified for optimized design tasks. In addition, with robots is robotically (which

performed

dexterity

to that of a human to less system and on-orbit

crew member), downtime systems.

(less time consuming) and higher

This equates for both ground

Key Words
7

Robotically

compatible;

maintenance:

fasteners;

handling

fixtures

Application Experience
w

International

Space

Station

Program

Technical Rationale

The following the criteria

selection

guidelines

enable

design

engineers

to identify their

required

for robotics

compatibility

and to tailor

specifications to different provide general concepts

robotics systems and environments. They for using robotically compatible fasteners and Station program

handling fixtures that have been applied on the Space and states the advantages of these concepts.
==: ,,,t..=,

Contact L_

Center

,lohnson

Space

Center

(JSC)

Page DFE-2

Selection

_f Roborically

Comparibh,

Fasteners

and

Handling

Mechanisms', Technique

Page DFE-

2 1

_m

Selection Technique Before

of Robotically Mechanisms DFE-I an ORU

Compatible

Fa._'teners

Provide

for alignment. and binding. by


m

and Handling

Avoid jamming

Withstand the loads that may be imparted the robotics systems. or other component Provide adequate access. Simplify the operation ....... Assist ORUal_gnment and S0_d6ck and harddock functions. "Softdock" is defined the initial temporary or more inadvertent attachment. Reference pieces release attachment prior between pre_ent of equipinen(t_

designing

for robotics compatibility, the feasibility of such an effort must first be assessed. Some ;tei-ns (e.g., thermal blankets), because should &their by robotics show (i) if the by a of flexibility, Systemsl ORU cannot be manipulated

[]
as two

The assessment

[]
m

or component

can be manipulated a major redesign to make it robot effect

to permanent
I

robot, (2) if not, whether the_tem will be required compatible, be d-etermined Reference that might of designing is determined be manipulated determined affects robotics Figure detailed which the system, and (3) what by simple will have on weight

the redesign that can

2 lists a number

of guidelines t9

and
m

and cost (a factor ana]_yses),

reqt!!ren2ents

that may be applicable

designing for-iobotics Compatibility of Space Station hardware. Reference 3 lists a number analysis Once to it of different robotically compatible fasteners and handling fixtures for Space Station use. The purpose assist designers to their system contractual in objectives design tbllowing FASTENER I)ESIGN by Provide for alignment provisions may be implemented guides, of these and (3) options,
m

1 describes be used for robotics

a preliminary compatibility.

to determine

the feasibility

of this technique,

however,

is to

that the item can be designed by a robot, of(l) it must then be relates layout, to and components how the design (2) the system's with which illustrates

in applying the stated ORU's and not to list and handling are addressed

concepts
l

requirements. for fastener section.

The six design fixture in the


I

the design system 1, which

other

and (3) the

requirements

it will interface the process tbr as

[]
AND HANDLING FIXTURE
m

redesigning

for robotics

compatibility 1, shows

REQUIREMENTS
m

in Reference the design the design

the sequence in a process items. the in in that the ORU,

of items higher

flow impact Although alteration schedule applying should approach system, Once performed compatible begun, bidirectional

of the lower

Alignment design system alignment Markings described


Fa,_teners

as
m

the sequence may result delays, robotics

may be altered, in increased costs, The processes

(1) markings,

(2) alignment system

of the robotics guides,

and its control in this section. are


!

and in less flexibility compatibility. indicate

Only the second and robotics in References

is addressed

arrows

be performed that considers and robot the above

using an integrated the impacts analysis design have on each other. is is

system designs I, 2, and 3.

mentioned

There

are more

options

available are captive

for aligning
w

and design fasteners

of the robotically or handling fixtures then must be to:

fasteners integral ORU

than there

are for handling Therefore,

fixtures. and are an


F_

For example, contains

fasteners proper

the objectives

part of an ORU.

if the
!

alignment

features

and is

Page

DFE-3

Selection

of Robotically

Compatible

Fasteners

and Handling

Mechanisms, Technique

Page 3 DFE-1

+
Dr.fine Factors for Loads of SalYtv

Revise L_ w

Robot's Pa rameters/ Capabilities

Determine/ Revise System's Parameters

, Define/St'lcct Torque Fastener Values, Location and Type, Dennc/Sek'ct Fi_llll't_ ._lll(| Handling Lo;itiou

and Markings Targets DefiJle/Design

Alignmenl Define/Design Guides

,7

FigTire 1. f'roce+s'x for

RohrJlic'._

("om/_alihi/iO_

De.s_q77

properly

aligned

and inserted, as well.

the fasteners However, since

will

be properly
w

aligned

incorporation to the fixture alignment References

of alignrnent features is confined and end effector. The ORU design, which is discussed in 2 and 3, is an important

handling fixtures are grappled independent of the insertion and alignment of the 0RU, the

feature

Page DFE-4

_=_

Selection

of Robotically

Compatible

Fasteners

and

Handling

Mechanisms, Technique

Page DFE-1

m i

consideration, complexity. used for Space below. Alignment Robotic is proper fastener

since it can lessen The alignment Station fasteners

fastener being are described

microfixture about about

allows

positional

misalignments of

of

techniques

0.3 inch and angular +3

misalignments

=--

Cylinder-over-cone of Tool testing to Fastener that, between structure, Head provided there inch the fastener a 7/16has shown The microconical tool slips over and attaches collets to the microconical interface, which is shaped like a cone. The allowable translational
=

visual contrast with a flat head

head and the surrounding by the robotics end effector

can be easily captured (nut driver).

and angular microconical respectively A VOID


Fltsteil

misalignment tolerances for the tool are 0.25 inch and +1 ,

Z mu

Earlier concepts specified or recornmended rounded heads because it was believed the rounded head would accommodate greater misalignment tolerances. It was found, however, that a flat-headed fastener provided the robot tolerances top. Alignment of Fastener to Nut the end with the same misalignment as the same fastener with a rounded

.lAMMING
ers

AND

BINDING

Ill

Once

alignment begins

is accomplished to enter of cross-threading portion by using

and the Cross, _


z

fastener threading

the nut, th_e_ris still by aligning the nut


!

the possibility

can be avoided

using the unthreaded can also be avoided thread consists housing internal springs diameter of three that, threads that force

on the bolt, and it an expandabie A Zipnut within are by or in a

The bolt is aligned

to a nut by tapering

nut; i.e., a Zipnut. separate of a nut. them segments when assernbled,

(pilot) of the bolt and by having a cone or countersink around the nut. For fasteners that form an assembly terminology, are housings Handling handling V-slot which FLvtures techniques are described for Space below. Station fixtures Insertion insertion technique is used with the and H handle, which interface with Purpose mechanism Dextrous (OTCM). Manipulator tool The OTCM the corners 2 for a or the ORU or that are, in Space mechanisms," tapered contain Station there "attachment

form the

The segments to a minimal

held against

the threads

of a bolt or screw them to separate

"fingers."

diameter,

and a ramp that allows The two alignment

come together, depending which the bolt is inserted. inserted, the segments allowing back and away,

on the direction When a bolt is to slide the b01t to slide

are allowed

The V-slot microfixture the Special (SPDM) changeout

through without obstruction. This type of nut is described in detail in Reference 2. Handling When fixtures concept Fixtures compatible above (i.e., the handling which apply the slot in the V-groove

end effector

using robotically as described

fits as a V into the grooves closes its V-shaped of the microinterface detailed fixture description). tolerance tolerance is approximately misalignment misalignment

of the H handle

grooves around (see reference The positional allowed of about

microinterface or X handle), care must be taken that the corners are rounded. This precaution must be taken to keep the handle ii

for the H +2. The

0.5 inch with angular

from binding to the end effector, as happened in t]ie JSC _?obotlcslabora;cories with the firs( H handle concept which had sharp corners.

Page

DFE-5

Selection

of

Rohofically

Compatible

Fasteners

and

Handling

Mechanisms, Technique

Page DFE-I

The corners

of the H handle

(renamed

the X effect

following

methods: Fasteners fasteners is the best method to carry and insert for the of robotics for the robot operation. This eliminates the probability

handle) were rounded, was thus eliminated. WITHSTAND IMPARTED FASTENEIL9 SSP 30000, specifies LOADS AND table

and the binding

Use Captive Use of captive THAT MAY BE FOR simplifying the need

BY ROBOTICS" HANDLING

SE._TEMS

FIXTURES of Safety," the

fasteners and thus increases mission success. Reduce number Number

3-3, "Factors

that for metallic

flight structures,

of Operations selected required. can reduce the need for the rotation. the For example,

-2

general factor of safety ultimate of 2.00. PRO VIDE Fasten ers Adequate access ADEQ

is a yield of 1.25 and an

The type of fastener of operations using the Zipnut

eliminates

UA TEA

CCESS

rotation,

since the bolt can be slid through with a single of Fastening the robot should (as

nut and then tightened for fasteners is provided by Choose Forms use more eliminated. increase and described necessitate more a Proper than Forms 1 degree

designing described robotics freedom disengage requires

a proper layout of the system as in reference 3. The fastener selection scheme) if more can be influenced than 1 degree of by the robot A lever, 1 degree significantly the higher access by the access

of fastening Levers, the access

that require for example, space

to be

of freedom requirements

(or fastening
_-7
w

not only will

is required more to operate than

to engage for example, and more access

the fastener. requires

previously), but may also force moment accommodation control software. Excessive

and

of freedom

complex

therefore space
W

than that required (motor), space.

to engage value, lessening For Space

A void Fasteners To engage

Requiring

Torque

bolt.

In addition,

the torque

fasteners

that require

excessive

the larger Station, Handling


w

the end effector robotics no levers FLvtures

the allowable
w

torque (ie., 50 foot-pounds or over), the robot must stabilize itself with one arm, constricting the allowable replacing additional configurations for removing and In the ORU. hardware This necessitates for robot stabilization. when

will be used by robots.

Certain placed access its jaws resolved

small so close space around

Space

Station

ORU's

are being to open was

general, systems forces Reduce Using heads is Handling

care must be taken for fasteneing that will be present. Sizes different will reduce and

using robotic

to each other the interface. the interface

that inadequate The problem interface in a "stabbing" i.e, access the space

due to the reaction

is provided

for the robot

by using the microconical around By using

T.vpes of Fastener the number of tools

Heads required

that snaps motion.


L_2

sizes and types

of fastener

a tool that does not require an interface:

jaws to open microconical significantly

around reduced.

by the robot. Fbctures of the interface can be simplified

Z=i

tool, the required

The grasping
a =

Simplify

the Operation operation

Fasteners can be simplified by the

The robotics
= .

by allowing the robot to grasp the interface fiom a number of different orientations. For

Page DFE-6

Selection

of Robotically

Compatible

Fastener_"

attd

Handling

Mechanisms, Technique

Page DFE-1

example,

the microinterface

and the

Handling Alignment described Alignment The location significantly

FL,ctures and sofldock below. Functions of the handling impact ORU fixture can The alignment. functions are

microconical interface can be grasped from two different orientations of the OTCM relative to the handling fixture, from while the X handle can There it only be grasped one orientation,

may be some instances, however, in which would be advisable to limit the allowable orientations. For example, if the robot can

grasp an ORU from only one orientation, there is less chance that the ORU will be improperly inserted ASSIST in its base plate. AND

further the handling fixture is from the ORU's center of gravity, for example, the mote difficult it is for the robot to maintain a line of insertion attachment that will be perpendicular plate. to its

ORU ALIGNMENT AND HARDDOCK

SOFTDOCK FUNCTIONS Fasteners When designing

Other location

factors

to be considered

when guides,

placing the B and the

handling placement discussed dependence So.fidock Softdock ORU fastened. fastening handling Functions features are lacking for the ORU, of of the via the tapering on the housings

fixtures

are the size of the ORU, These items are 3 because of their features.

and type of alignment of fasteners. in Reference on ORU Function features

robotically

compatible

ORU's, may

the alignment guides and softdock features be incorporated as part of the ORU, or

fasteners with these features may be designed or selected. Sofldock fasteners are thus more complex and are called "attachment mechanisms" in the Space Station Program. Alignment below. Alignment If alignment and sofldock functions are described

may be used to prevent away" without The three prior by the mentioned

an
m m i

fi'om "floating the ORU fixture.

to its being
I

This may also be achieved releasing above

handling fixtures for Space Station have holes in their centers for fasteners, which allows the OTCM to grasp the ORU, insert it, and then drive the bolt with its nut driver without ever releasing Re[erences the ORU handle.

they can be incorporated pins, or fingers, located attachment mechanisms.

m m

Softdock

Functions Program, sofldock either on 1. t?ohoticx System_ htter/'ace Standards, I ?drone l, Robotics A ccommodation Requirements 2. are Rohotic'x (Draft), SSP 30550. Standard.', Standards"
W m u

For the Space Station Freedom attachment mechanisms achieve through an outer ramped separate pulled the use ofdetents casing method. of the attachment

that are housed The Zipnut is

mechanisms ,S);stems Interlace Interface is made to }drone (Draft), 3. 2. Robotics SSP 30550. Proce.s:sfor AchJevJng Report
u

or via the Zipnut

such that if an attempt together allowing

the bolt from the nut, the segments

the bolt to be remo\,ed functions 7he [)e.s'i_l Robotics (;ompatibJlity, No. <TBD>. Contractor

via rotation only. The Zipnut thereby as an excellent sofidock attachment.

Page DFE-7

False Alarrn Mitigation

Techniques, Technique

Page I DFE-2

Technique

Minimize by applying probability and other

the occurrence principles electronic of false alarms

and effect and techniques

of Built In Test (BIT) that are intended the reliability of BIT

false alarms the in avionics

to reduce

and increase

equipment.

:::::::::::::::::::::::::::::::::::::::::::::::::::::

:::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::

:::-::::

::::

::_.

.._.'.._.-_-.+-..._

......

_.q::._.:.

...... _:!

_ _i i _i i _ _i_/! i! i _:'.' ".x::._:_:::: ._:: :::::::::_: :::::::::::::::::::::: :_ _:::: :.,.::'.:::::..,:_ ::_:.,.': : _:_:_:_ _:::q::_?:_:::::: _.'.':i:':i i" !:!:_._:!:!:!:!:_:!:!:!.'.:_:_:_ i i:_:i:_:_:_ _._?.':_'." i:i._:i:_:_:_:_:_:.!! _::_ i i:;:_:i_:::!:_5 ! _ i _i__i _._ ! i _! _i_! r_

#iiii!i/i/ii:,

:i::iiiii::ilii/i/jii!/!!
.__:, _ i_ _.__._i_,_:_!i!_ii_i_._:q:!:_:._i:;i_:_:.._.,'_:_:: ?..:._ :: :_:_ ::: ::: :::: _:: ::: ::: _:._: :i::: :_:i:_._ _:_ _:, _._ ::_: :: :_:: _ _:. _::.:.'..-"::_._' :::: :._:_ :_:: :_':_._:_: _: :_ ::: ?..:_'.._: :_.:::_g:: :._::: ::::.".:_.::.>_:: :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: :::.:.:.:-!:_, .:...,..:,. :._. ,._:..,_...:._._ .:..: ....... +...._ ................. _......._..._ _.:: _,_. - .._.._ _. ........... x.:.- .:.:.:.-:- .:.:.:.:_.:_....:. :::::::::::::::::::::::

_li!_i!!liii!i!i!ii!iiliii I_! _!_iif/i_: _iiiiii!ii_iiii!i)iii i!i_i_i_i_iiiiiii/iiii!i!ili!ii iii iiiilii i_ iii!!_i_i_i_;""'f_____ iiiiiiii::iiiii"'"ii_::"'iii"'! i"'::i"_i"!_:'':: _ ............. if"i::iff:f" ]i:::: %i_ii!i#:ii_::!_::_i!i_i!!ii_iiiiii_::!_!i!!::!!iii!iiiiiii_ii_iIiiiiiiiii iiiiiiiii iilii iiiii iii lli ii!i
::::::::::::::::_:::::_:_'..:_ _:_:._::._?._!_._:':_._i_:'.._!?:i _'?." i :?i..'..:i:_:_:i._._ _: ::/_ : :::::::::::::::::::::::::: :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::

iii_iIiiii_i_!i_iiii_iiIi_Ii_iiIii_iI_ii_iiiiiiii::_iiiiiiii_iIiiii_iiii_ii_ii :: :::::::::.,.: ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::


::::::::::::::::::::::::::::::: :::: : ::_:::. "_i_'_/i_._i_'_'_!i_-_!:_ :, ,...,..:: :.: '?:..'.' _.'._..../.._....._._._......,._..,. ........... ......_.... ::::::::::::::::::::::::::::::::::::::::::::::::::::::: !'":..:: _. >......... _. .......................... _ <_.:. .:........ __..._ ...... _....,.:+,

_::..:._:.::"::::.:::::._.::::::::::::::::::::::::::::::::::::::::::::: ================================================================= ================================================================================================================== . . . .... ....... +.. ::....... . ,.,..:.. _., .::. _.,..._, ,_ ........... _. _<_

:!:!"!P'"::!:!_;i'_!_:i:i!!_i_:ii_:%:%!_!i!i!_?:i%!:'!;_::: .:. 'ii :_!:_:::: li............. i!": !ii:':"%: :!_i :";!!i;!i_;:!ii_::!_i:"!i!_!i!i!;i_!!'.,'.i:i_;i_/:_:_-:'_!i :%_i tli_!_i_i/_j_ii_.';..'::_ !iliii_!! .-11_lt i! i_i_i!ii!i#ii l
:::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::

Benefits

Effectively number increases

implementing a system's

BIT techniques Decreasing result

automatically the number

reduces

the manlife

of BIT false alarms. availability The overall

of BIT false alarms

and decreases is a reduction

the maintenance of the system's

hours required. cycle cost.

Key Words

Anomalies,

Built-In-Test,

False Alarms,

Circuit Monitoring

Application
_.i

Experience

International System

Space

Station

Program,

National

Space

Transportation

Technical Rationale

The reliability number identify mission. as other critical

of a system's

BIT can be determined of failures reliability requirement.

in part by the

of false alarms and report Testability design as any other

it experiences.

If the BIT can not accurately then the test has failed its must be considered A system being just as for with the same level of importance can not removed

the occurrence must be treated BIT performance

disciplines.

perform its mission false maintenance.

if its components

are constantly

Contact

Center

Johnson

Space

Center

=== w

Page DFE-8

False Alarm

Mitigation

Techniques, Technique

Page 2 DFE-2

False Alarm Mitigation Technique DFE-2

Techniques

the test data

reported

while

only requiring

m I

single computer Continuous

or processor.

Monitoring monitoring with BIT filtering offa of a of the but only of a of a single can of the voting BIT results scheme. With

In order to mitigate Built In Test (BIT) cope with a limited

false alarms, circuitry amount

a system's

Continuous this technique, integration signal over

must be able to of anomalous

be used in place

are based measurements

performance. NASA Handbook 5300.4 (1E) defines a false alarm as "an indicated fault where no fault exists." system to detect Based on this definition, only with BIT a_ions.The this technique _" _nd]cadons0f unnecessary of a system is concerned maintenance

of successive a period

of time instead

check of the signal. The monitoring signal does not have to be continuous sampled signal over the time period. comparing the current

m u

mai_ncdoh-ffhi_'-cause or report the occurrence is not a

-The-fi-lteHng reading of the

inabiii@ .......i_olves

with past and future

readings

of a failure, a "fails to alarm condition", false alarm and is not addressed,

same signall disregarding measurements.

This filtering aI!ows for the of sporadic out-of-limit Only when the same a signal is out-ofm

BIT should be designed to distinguish between actual failures and anomalies which must be tolerated limits. due to adverse anomalies To accomplish and techniques specifications, and design in the system operating within conditions acceptable or that are normal principles the system documents, implemented Voting With Scheme is called scheme, or more the "Voting all test data different Scheme." are computers. of the

limits for a predefined of tests identify BIT flag be set.

time limit or a sequence failure, should the

this, the following must be mandated requirement policies and design. in

To maximize monitoring,

the effectiveness the BIT data

of continuous
= = i m m m

must be recorded. can

Once recorded, the data need to be summarized and evaluated so that trends be tracked manage implemented. monitored be limited. collected restricted. be used data. failure Once and weaknesses controls The number and the maximum should identified. should of signals sample be all this data,

To help II

One technique the voting analyzed A failure

rate can data are period, be can of old a


n w w

The time span over which be set at a reasonable computing

by three is declared

only when a majority

and the type of data accumulated Finally, that do not require the information be created. log should

should techniques

computers detect the same failure. An example of this type of architecture is the Space Shuttle Orbiter Avionics System. The five General Purpose Computers (GPCs) are all interconnected to the same 28 serial data channels. processing extensive effective complicated or triple more sensors The GPCs and require perfo_ ai[system-level agreement an on requires a majority

the storage is gathered,

This failure modifications the BIT,

log is the basis to the system's instant not related

for future
i

BIT.

To improve failure

all test signals.

This technique false

every

of anomalous to an identified

use of resources at mitigating version redundant

but is extremely alarms. A less two or of

performance

of this is the use of double monitors. Having the reliability

mode should be analyzed and the root causes identified. Some form of corrective action must be taken change cannot to avoid be made, recurrence. Ira design must be
D

in series increases

then the BIT

Page DFE-9
m

False Alarm Mitigation Techniques, Page 3 Technique DFE-2 modified


_=_

to accommodate anomaly.

the non-failure

An excellent boundary

technology Boundary

for combining level testing scan is the is

unit

causing

level testing with system scan. requires BIT to be be able to This in the and application boundary provide

The need for modification flexible. control flexibility Test parameters easily changed. allows

of a partitioning of integrated

scan ring at the to access

and limits must be should changes the test sequence.

circuit (IC) designs and observability In Figure logic section, and a boundary of boundary 1, an IC is

The operator the necessary

controllability

or even change

via scan operations. related

shown with an application input and output, of a series path consisting

BIT to be made
w

if false alarms start occurring. Station's Command System uses programmable and standard data of

scan scan

For example, Data Handling Deadman processor

the Space

Timers (SDP's).

in the multiplexer/ The response intervals

cells (BSC), one BSC per IC function pin. The BSCs are interconnected to form a scan path between the host IC's Test Data Input pin, (TDI) pin and Test Data Output (TDO) for serial access. During Normal Output normal Data 0qDO). IC operation, through However, Input

demultiplexer

(MDM's)

k=O

the timers can be adjusted by the system controller to accommodate changes in system configuration or mode of operation. However, the BIT software must be changed without disturbing the system operation. For this to be possible, the BIT soi_ware software. Architecture is must be independent of the operating Decentralized

input and output each BSC, when from the Data is can

signals pass freely

(N-DI) to the Normal the IC's boundary from each BSC

the boundary

test mode partitioned be shifted

is entered,

in such a way that test stimulus in and applied

Another technique for mitigating false alarms the use of a distributed or decentralized BIT architecture.
W

output (N'DO). The test response captured at each BSC input (NDI) out for inspection. Internal testing

can then be and shifted of the

With this approach

the BIT is

implemented directly replaceable of incorrect decentralized

so that a "NO GO" on a given test the implied failure to a Locating most of the BIT the possibility Although primarily the of reduces unit.

isolates

application logic is accomplished by applying test stimulus from the input BSCs and capturing External neighboring accomplished the output the input BSCs. test response testing at the output interconnects assembly test stimulus is from at BSCs. and of wiring

internal to a unit greatly isolation

of a failure. consists

ICs on a board by applying BSCs

BIT concept some system

unit level tests, required.

level testing

is still

and capturing This application

test response of a scan

TDO APPLICATION BSC

TDI OUTPUT

BSC

"

_-_

LOGIC

Sb='O

Figure

1: Built

In Test Architecture

Page DFE- 10

False

Alarm

Mitigation

Techniques, Technique

Page DFE-2

path at the boundary embedded test access testing problems.

of IC designs

provides

an can on

References 1. Coppola, Built-In-Test 1979. 2. Malcolm, Analysis Conditions, Anthony, (BIT), A Design Guide for April

capability

that can overcome or system details RADC-TR-78-224,


l

The unit level tests 2). More

also be combined level verification applying Standards "System these 1149.1

for a subsystem (Figure

techniques

are in IEEE Scan" and 1149.5 Bus." should be of the BIT that of 3. NASA Maintainability Space Systems, 4. John G., Highland, False RADC-TR-81-220,
=

"Boundary

Richard Alarm August

W., 1981.

and Maintenance

of Built-In-Test

Finally, high-reliability used in the design. hardware should the hardware

components The reliability

II

Handbook

5300.4

(1E), for
m

at least equal

or exceed

it is testing.

The BiT software

Program Requirements March 10, 1987. Inc., Primer, TESTABILITE, 1989.

also needs to be thoroughly tested and verified to ensure that it will not be a source of false alarms. effort Accordingly, and resources adequate amounts of must be allocated during

Texas Instruments

Test and Emulation

the design phase. The designer should not be unduly limited by memory size, component count, These false system or any other guidelines is unique allocated resource. The Each to

m ! l

are not all inclusive. is very complex. and must be approached

alarm problem

__=
m l

differently. The best approach is simply eliminate each factor as it is identified.

m
=== 1

SYSTEM BOX TEST

TEST

BOARD TEST IC TEST

_ii_i..`:@_:.:ii.:_:i!!_.:_!_:i!!i!_!!:'..!_!i:.!!!!_i_ii!_ii_!_!!_i_ _iiiii::_
s.:_i8._i_.:_.)_i_i_i_.::!:_i_._i_i:i_!_._!_:._._i:i_i_!:!_!_?.i:!_._ :!i!i_i_i ii_: _ii.iii!_i_i:._ii._i!_!.!i_._i.:i_i!i_i_i_.':i!i_ii:_._:_!_i_i_i@!_!_: @!__!i!_.! _]_`%_i[i._:_:[:_:_:[:i:i:i:i:_1i].::i:?:i:i:_:_i:i:.:i:i:i:i_.:i:i:_:::i:_@ !:_:!:_:_ ?:':': ....... _ ....

::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: :i_:i:_: :_._j:

=1 w

iiiii;i:@ii::i_;::ii_::;i;i::i_;i'_::;i_ii_i!?.:_i_!!;i i:: _ _ i:: i _i::iS_

Figure

2: Typical

Test Regimen

for Space

Systems

m I

Page DIE-11
m

-__:_

Analysis And Test


Maintainability maintenance Software analysis concept testing is a very important and design that part of the design process in which on results. aspects Hardware of the and

are quantified verifies

decisions

are made based

not only

the item(s) items

in question

will perform

within

the specific

environment, design features. test processes


w

but also allows for The techniques used within

maintenance

to be identified describe

and verifies a wide range a vehicle

maintainability of analysis for and

containedwithin community

this section and

the NASA

should

provide

education,

communication,

and continuous

improvement.

Page AT- 1

mz Z I

IB

mm

ID

_rm m

[]

lid

gm

L_ lm

qmw

Neutral

Buoyancy

Simulation

of On-Orbit

Maintenance, Technique

Page AT-1

k.a

Technique

Simulate buoyancy optimum

on-orbit facility on-orbit

space maintenance to assist in making maintainability

activities by using a neutral design decisions that will ensure hardware.


: :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: _:::::_ ::_:::: _::: :::::: :_,-'. :::_:::: :_: :::.:::

of space

_!._li_._'..,.'i_._!i_ii._!_! :_:_ _:_

i_!'!_ _ _._:._ii_i::::._::_::_::_:iii_i_i:_.:__i_._:ii_`..i_!_.`..._::::.`..::_:::_':_.::_.`..:::_ii:_:i:::i::_._:_!._.`:!i:_i_i::_:: ::_.q:: :._:: :::._:: _::._ -_:: _:: :::- :_::::

i._ii_i_._:'.._
::::: :8:_::::

::::: ::: :'_::: _:':.'2:: _:_ :.::_:. _.:.:::+:.:.:.:.,_:.:.:.:-:.:.:.:.:.:.:._ .:..:: .......

_..'.. _..'._i_._._._!_:._:..`.._:`.._.`..::::::.``_i:_::::`.._._`::_._::_._:_::_!:: ! ._._.,.. ., _ _ .._........ _ ..................................................


,'._ _....... _-.,. -_ +_ ._ ..--:.. _. ....... '..* -._.'... :_,'. -., ...... :: ::;::: :'.'::: .'.': _:_.".':_::._ ::: _::: :_-'.'_:: :_:: _ ?.,','._:::_ ._,:_:: ::::::

:.:.._ _:: :::_:._._:::'.: :__:: ,:: _:_.::_:_:_:_.'.:.__::_ ? _:_5:i:_:':_:._:.'.' _:.:_:: _..-: _: _::: 15:;: _.::._:::: _::: ::::: :._:::._ ._:::::::_: _::::::::

_._ii_#_.:#_.:..._!_::_:_:::_!_:.._i_._i_!_:::_._...:.`:_?.._:_:_:_;:_:_:_:_:_:_:_:_:_:?_:_:_._:_:_:_:_:_:_ :_i_::_.`.._:_:_:_i_..._i:_-:_._`._ !ii!ii illiliiiiiiii!!iii!iiilliiill iiiiiiiiii _:. II/


:::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: _:!:i:i:_:_:_:i:i:_:_:_ _:::_:.'.5!_ [i!ii_!;_ _._i_i_ii_i.":_!_i_(:':..'.'_ _ _.':_:'_ .".._ _._......... _...!:?... :: .-_:....._..._.:.:_::.::::::: ,':_'_.:-:.+:.:::.:.:::.:.:::::_::::::_.:_:::_'__':: ..... _2 '_'_. ....... ::"_ ........ _..._...+..._._?._:_:::::_::::::::::::::::_:_:._:::.::_:._:_::::_.::_:::: :: :::::-:: : _::_ _ _ ._:' _ ":':'_:_'+:+:':':':'":':"_:'" _._."_.:_.:._.:::_._.._:::_..._.....::...:_::::._:::_._:::::::::::._:_.:::::::.::::_._:.:::._:::.:::_::::._.`:_::_: .< _ .._'_. ' .'::_:_ _ ' _ _2" .':::.'::.:. :: _.::::.::.:::+::.:_:.:.:+:.:_-5:::.:.:.:+_..,:.,.:...._.. -..-_.._.,_..-_ ...... _.......... _._ ....... _'--'.'_':.<'-_.+'.-...._+..+:.-.*._:-..'....._,_......_.-._._5 _ _::-: _ _. ::: ::: :::::::_" ::'" :::::::::i _:_:i:i:_:_ i:_:i:_:_:_:_ _:!:_.'.':_:_ __:_::"i:i:i:_:i:_!:!:i:!"':_:i::::'._ .".'_: .'.':: : :';:_: ::: _.:: :.'.':-_ ::::: ::'_ "": :._.'_ _: : _ : .'.':!:_:.'.::_::"""" :_.,.'_:_: _'::_/: _: :_:.,.':::: :_:: ::: : : : :,,._:: _::::: ::::::- "::::::: _:: _::: _:: :::__: : : . ..::::'.: .... ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: ::::_._ ::_._._.-.'... _._--====================================================== ::,_.:...:: _.:: :_.:..:;_i_!i:.:.::-_.:..::.'..:-_ .-.._._...,....... ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: ....

._:::_:::._:: :_. ::::::_::. :i: _ i!_!i_ _:_:_i_;i_..'.' ?.i_._iii


F_ t J

i:_i__i__!____i._...'.'__!_'_i_ii:iiii_ii_i_li_i_:iii'::" " " . : " "':'"! ..... i"_' :: ....... _'" ....... ": : +' _"............... _"-"_i "" " ........ :::::::::::::::::::::::::::::::::::::::::::::::::

"

..i::

,.'"

.i:_" " .......

::_:'

"

!:."

'.

:'

.._::_:_i:_:!.'.':i:i:!:i:i:_:i:i:i:::i:_:_!::_:_.:_::'.i:i_._:_:i:i:

iiiii/iiiiiiilt ii iii i!i!i!iiiiiiiiiiiii i i !ii ii!i _iI!i_':_i_iiIi::i_ii_i_ii!_ii_i_iiiIi_i_I?:_i_i_ii?:i_!_i_i!_iI_Ii_i_i_i_ii_ii_I_iiIiIi_iIiIi_i_ii_i_`i`:_iI_i_;iI_i_i_i::ii_i_::


Benefit Neutral buoyancy simulation cost-effective, stability timeliness. this process can provide specific valuable design information for It designing-in effectiveness tools, accessibility, of crew by utilizing modularity, simplicity, and standardization. information aids, criteria on the specialized that can be accessibility; and

_ ::::::::::::::::::::::::::::_::.'..:::_:::_:!:!`::_:._!..`._?:!_!_:_:_:.:._._!ii!_ +'"' +'" '::::::::::::::::::::::::::::::::::::::::::::: "::' :' :::" _:_'" +_ ................... _ :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::

..'.'._!_! :_._:::-_::._:_ ?." _ ..'.'_: ::_:_ _ ......... +'_ " .......-'.'_! _'"'" :_:....... + "" _'" :._,_:.,'::::.'.':::: _'_ _"'"'" _''' _'::: ._:._ _: ._ _ _.,'_ Z_ _- ,_::_ '_S_ :"." :

can also provide

aids, crew maneuvering Maintainability include: component

and operational

established fasteners operation

accessibility, systems installation; of crew stability aids and tools.

and the configuration

Key

Words

Neutral

Buoyancy

Simulation,

Maintainability Maintainability, Special

Design Tools,

Criteria,

Space Weightless

Maintenance Environment,

Activities, Orbital

On-Orbit Maintenance

Simulated ORU

Application Experience

Skylab, Space

Hubble Station,

Space Apollo

Telescope,

Space

Shuttle

Orbiter,

International

Technical Rationale

Equipment environment accurate determining weightlessness

and crew means

interface

testing hardware

in a simulated stage in NASA and tool design

weightless programs features other base, is an and forms and of

at an early development of assessing simulations crew capabilities

and requirements. (e.g., parabolic flight,

While motion

computer models) have proven effective in specific applications, underwater simulations have proven particularly beneficial in hardware development, crew/hardware since they can accommodate times. interface design, and operations planning, a large worksite volume and extended test

Contact

Center

Marshall

Space

Flight

Center

(MSFC)

..

Page AT-2

Neutral

Buoyancy

Simulation

of On-Orbit

Maintenance, Technique

Page

A T- 1
u

Neutral Buoyancy Maintenance Technique A 7'-1

Simulation

of On-Orbit

T.V. monitors, subjects, pressure subjects,

communications taping

with test capability, of test systems. space suited

audio/video and lightning

and de, th displays

warning

The neutral beenused

buoyancy since 1968to

facility

at MSFC

has

effectlve-ly

simulate design activity _

Support of up to four Shuttle crew members.

mm

mm

the weightlessness in th-e establishnaentpf criteria, particularly

of space,

and has assisted Umbi!ical'supplied life support Operational underwater primary


B

rnaint_nabilFty in extravehicular

systems. Remote Manipulator Systems

II
m

(EVA). Use of full-scale neutral buoyancy simulations has also allowed for direct human hardware These purpose operations Other NASA simulating participation _veloped on-orbit of verifying in test operations, to the large for EVA environments and solidifying procedures. used for body as mock-up well as for access methods

fP.MS).
Air-lock for emergency evacuation. buoyancy 40 ft. deep The water at a range systems The tank test subject
u

simulations. way for the of

II

are a very effective

=*lae neutral measures

tank within water and

the facility

:._.d maintenance buoyancy are

is a 1.3 million-gallon diameter. maintained Fahrenheit protection corrosion.

tank that 75 ft. in is


m

neutral

facilities

temperature

hardware

development the Weightless

and test and at University and the

of 88 to 92 degrees Cathodic to inhibit up to


i

crew training Environment Johnson Buoyancy of Maryland, neutral Douglas, Neutral following

and a pH of 7.50. are used

Test Facility Space Center, Research College Facility Park, facility

(WETF) the Neutral at-the Maryland

accommodates test subjects

four pressure-suited simultaneously.

Extravehicular

Mobility of

buoyancy Buoyancy neutral overall

at McDonnell California. facility has the

Huntington

Beach, buoyancy

Units are available for four test subjects. The tank can accommodate test durations up to 6 hours. lIST Simulations simulations facility strongly (I/ST) design : in the neutral influenced the criteria

Characteristics characteristics: room. hyperbaric

The MSFC

Underwater Six-console Three-person, chamber. Floating 500-pound Removable large crane control buoyancy maintainability double-lock

for the Hubble


i

Space Telescope particularly accessibility, and

and its components; Oneofthe of of


I

with regard to visibility, simplicity.


m

for underwater 2000-pound

movement hoist, one

primary considerations space hardware components during EVA. and systems

in maintainability

of hardware

(one hoist). roof

is the accessibility To be maintained

by crew members: in space, astronaut tools. the item must be seen

section

to accommodate

components and reached

of a hardware

hardware.

by a pressure-suited

ma

or be within range of the appropriate

Page AT-3

II

Neutral

Buoyancy

Simulation

of On-Orbit

Maintenance, Page 3 Technique AT-1

Altogether, Units (ORUs) on-orbit. batteries, assemblies, guidance cameras. science pounds. equipment spacecraft. so components

some Some

70 Orbital of the largest reaction

Replacement ORUs wheel fine field planetary over 700 in of the doors and are

inch double types and keyhole simulations standardized torque maintenance connector simulation criteria presence, texture Response alignment, torque Studies

height

hex head bolts J-hooks, captive Neutral

in three fasteners,

on the HST can be replaced

of fittings:

fasteners. have proven bolt heads, in space.

buoyancy and of ORU electrical

computers, science sensors, experiments These items

that the use of clearances, To achieve

instruments, and wide weighs

limits reduces

the complexity

One of the telephone-booth-sized are mounted the perimeter with large inspected

standardization, neutral buoyancy studies have evaluated such geometry (wing-tab and surface shapes). ease of length, and diameter) ridges, studied of grip,

bays around

as connector (knurls,

The bays open

can be readily

and irregular included

handled. Using neutral buoyancy simulations, design features of these components were validated, verified, and refined to ensure that the ORU features of modularity, accessibility, in the design. a series of crew and simplicity Other features aids; stability were

variables firmness required

and level of

to lock the connectors. scoop-proof, connectors. connectors Atmosphere Platform, and in robotic

of this type led to the development If

U
-= j --2

inherent included

of a standard for blind-mate, low-force, and subminiature accepted would as a standard, be used these in the Upper

including handrails, portable handles, tether attachments, and foot restraints. Neutral buoyancy simulation studies also determined the placement HST and the accessibility. crew mobility transporting, Door latch of foot restraints on both the RMS arm for maximum These design features during ORUs. were also simulations stowed Instrument ORUs give the unstowing,

Research Satellite, Explorer International Space Station, manipulators. Human significant factors studies have

been a

and stability and stowing

part of neutral

buoyancy

simulation tests with large space structures. For example, experiments have been conducted structural experienced element general neutral EVA for 4 hours, to determine during test subject while assembly tetrahedral conditions buoyancy productivity in ground assembly the effect lengthy of fatigue An a 36 repeatedly rate and These higher time for on productivity EVA

design in neutral the HST.

criteria

addressed involving ORUs

buoyancy Science

All internally

operations. assembled truss structure the subject's were simulations

except

the Radial by doors

are concealed

that must be opened before

and closed by a crew member are installed or removed. Simulations A design increasingly maintenance using neutral standardization ORUs. and Design criterion

heart

monitored.

demonstrated conditions Assembly

Influence

to be significantly tests. tasks

that has become studied to

in space simulated structural 20 percent

than in comparable

important in on-orbit and which has been

was approximately flight. The in flown of Structures

buoyancy simulation is of the EVA interface of standardization

less in actual Assembly project,

Experimental EVA (EASE)

The practice

an experiment

became a key issue in HST development with the decision to mount ORUs with 7/16r

on Space Shuttle mission STS 61-B, revealed that a flexible structure can be

Page

AT-4

Neutral

Buoyancy

Simulation

of On-Orbit

Maintenance, Technique

Page AT-1

assembled in underwaterconditionswith
learning curve determined test subject; Structural of the strength, of 78 percent. coordination, It was that learning rate is independent

When

possible,

conduct buoyancy

paper

computer

m U

simulations,

and one-g

dry run simulations simulations.


I

prior to neutral Principal

or size of the suit. Limitations limitations of neutral buoyancy The principal

or the fit of the pressure configurations

have been used at simulator In one to were

the MSFC neutral buoyancy obtain human factors data. experiment, six-element data used to obtain

simulations include: (1) the need to design hardware to accommodate the effects of water corrosion, to body (2) varying water pressure of movement. of with depth, the water The impact and (3) frictional resistance

i
[] ii

tetrahedrons

on learning

and on the

and equipment

relative value of a variety of assembly aids. The structural elements in these tetrahedrons were inches 11-foot-long in diameter. were tubes used of PVC plastic, 4 at Sleeve-locking to join the beams or "joint structures on fatigue, cluster."

of not taking

full advantage

the neutral buoyancy simulation capabilities at MSFC and other locations could mean
B

connectors the nodes Much collect members' more

entering knowledge

a space tasks,

mission

without

full
u

of the structure, complex

of the effects emphasis simulations

of weightlessness in EVA's. be placed mission on II

were used to and on crew

on mission Maximum conducting Failure

particularly should

information

ability to deal with complicated

with the highest success.


1B

configurations and hardware. A single 3 6element tetrahedral truss served as a baseline structure assembly quantifying evaluating Results much neutral land. assembly This large kinematics significant the subjects the following when running problems: Assign two safety divers per test subject and monitor the for comparing with two-person productivity assembly structural other single-person assembly, changes aids, and for for due to the

fidelity possible probability anomalies, (man-hours), References Publications

to ensure

to do so results

in a greater
II

of incurring safety hazards, increased maintenance resources and hardware damage.

use of various

_z

configurations. experiments learning rate is of on dry conditions

lllB

of structural higher

assembly

that contain related

additional are listed

__= I

have shown

that test subject in the weightless

information below:

to this practice

buoyancy operations

than in conditions is aligning drag.

The most time-consuming time consumption of water factorin

task during the beams. is due to the is not a process if the less,

1. Akin, David Neutral Buoyancy Telerobotics Cooperative Vol.

L. and Howard, Simulation for

Russell Space

D.:

II1

Operations, Intelligence 1991.

In SPIE,
m

Fatigue None to avoid

Robotics

in Space,

the assembly

II, pp. 414-420,

pace themselves. considerations a simulation

must be taken

2. Akin, David L. and Bowden, "EVA Capabilities Large Space for Structures,"

Mary of

L.: -

the Assembly IAF-82-393, of Technology,

Massachusetts Institute October 1, 1982. 3. Akin, David

to manage test subjects

the umbilical performance.

L." A Design

Methodology
[]

Page AT-5
U

II

Neutral

Buoyancy

Simulation

of On-Orbit

Maintenance, Page 5 Technique A 7"-1

for Neutral Operations, Institute


! ,

Buoyancy 88-4628-CP,

Simulation September

of Space 1988 J.:

11. Lessons Neutral Activities, Douglas Beach, Buoyancy Stage

Learned MDC

Document

from Testing Huntington

Massachusetts

Buoyancy Astronautics CA, October

Simulation H34111, 1987. for Company,

of Technology, Mary

McDonnell

4.

Barnby,

E. and Griffin, Methodology EVA

Thomas for

Neutral Satellite Interfaces, Factors


w

Buoyancy Servicing Society 1989.

Studying

12. Sexton,

I.D.: Report Simulations 103583,

Neutral Orbit Activities, June

Crewmember of the Human Meeting, pp.

of Transfer NASA/MSFC,

Proceedings

Contingency

Extravehicular

33rd Annual

149-153,

NASA-TM1992. 13. Sexton,

5. Designing Maintenance
E

an Observatory in Orbit:

for Space April

J.D.:

Test Report

for

Neutral Space

The Hubble NASA/MSFC,

Buoyancy Telescope Operations: Maintenance

Simulations Maintenance Simulations

of Hubble of liST

Telescope 1987. 6. EIA

Experience,

and Refurbishment Mission Study,

and Refurbishment H ORU Access May 1989.

Standard

for

Connector,

Electrical, S18,

and New Block NASA/MSFC,

Rectangular, Low-Force, XXX-1991 Standards 1991.

Blind-Mate, Subminiature, (drag), Institute,

Scoop-Proof AN/S/fEIA National

p_

American

Inc., November

7. Griffin, B.N.: Zero-G EVA Servicing of Space AIAA-86-2312, Twenty-First September 8. Neutral Checkout Operations, AIAA, Century, 3-5, 1986. Buoyancy Procedures

Simulation Verifies Station Modules, Space Reno, Station Nevada, in the

Simulator for NBS

Test and Test

NBS-TCP-90,

NASA/MSFC,

=._

April

17, 1992. G.: Space Telescope Simulations - The First 1982. of the Buoyancy December

9. Sanders, Fred Neutral Buoyancy Two Years, NASA/MSFC, 10. The Design Space Final

NASA-TM-82485, June

ancl Development Telescope Report Essex for Neutral Contract

Hubble Trainer,

NAS8-35318, 31, 1990.

Corporation,

Page AT-6
= Z

ii

_ _-b r

<_%

_i

_i

|
i

ND

miD

Hi

Mean Time to Repair

Prediction, Page 1 Technique AT-2

Technique

Predict or depot constant

the mean time to repair systems level) using failure rate, analytical and should

(MTTR) methods. be used

of avionics

and ground intermediate assumes a

electronics

at any level of maintenance

(on orbit,

This technique accordingly.

::::_: ::_: ."._:: :_

! ! _:_:: _ ::! :: ::: .'.'::_:.':: ._[_i:_:[:::

iii_:iii._i_i._i_ _!i!_!ii!i_ii_'i_ilil ::::,:_%..'::.':'_z+:':_.'.

_+:_:_._.:.:_:.:.:.:._.:.:.:.:.:.:.:.:.:.:.:._+:.:.:._.:.:.:_:...:.:.:.:_:.:_:_.:.:`.._:.:.`._.:_::.::::_:.:_::_:.:_. :_..:.:_:.:._...:._:.:`:.:.:.`.._:_:.:.:.:...:.:`:.:_:.:_:.:.:_:.._.:.`.._.:_..:._.`..`...`_._::.`.`:::::::_.:_::._:_:::::_ :_.:,

::_//_i_ili_i_
_.:::'::::::" 'i_::._ _::.::::::::..-.:.:.:_

:::::::::::::::::::::::::::::::::::::: ................. _.._._....._.._.._ .......... ., ........_._.._._.:::.._:._::::._:.::::::.,._r<: ::::::::::::::::::::::::::: "'".'_'""._'_'"'_w:_


:::: :::::_:: ::: ::_: :_::::_:::_:!:_:_?.'::::_:_i:i:i:_:_i:i_i :_:"_li._ :.".':_:::._ _:.__: :::<_:_:: _::: _ _::_: :'_!_:_:::_: ::: ::: ::: _:: ::: _:?_::_ ::: _'::: ::?.:::: ?::: :: :_ _:x.:!::':!:?.!:?-._ .: _:i:_::'-i:_:'.':_ ?.'::!'i:_?_,':_ ::_ _:::::. _:::_:::::::?-:::_._:.::._:::_:::_:_::::_:_::::::: i:_:.__-_:_:: _:.@ _:: _.:__::::_:::::._:_-_ fi::._::': ::_: :_::_::: .'::_ :_ ::_._:: :: ::i._ _: _:':_ :::::: :: :::::::_:::_::::::::_._:::::::::::::::::::::::::

l !iiiit!i! ti ...... i

....................... ......................... ...................... ..,,.:. .......... .....

i/i/i/ii_i/i_ii!!.,"i_i_i_ii_i!._!_i_i_ ........... ?,.':_:::_:.".:_::::_:_ ......... .,'._:,_,.::::*:::' ....... :::::::::::::::::::::::::::::::::::::::::::::::: :_:._ ........"_::_._ ...........'.::._
m [::.:-:_!ii[:-.::%:::.:._.:.:.:.:::.:.:.:. _.:..::::.:.:_:.:.::.:.::.:. :.:.:.:.._:.:.::+:...:.:.:.:_:..

=================================================================================================================

:::::::::::::::::::::::::::: :::::::::::::::::::::::::::::::::::::::

.-

. ::.

._:_:_:i:_:::_:i:!:::::i:::: .,'..":_ ,'::: :_..':'_';:'_i:::::::::::-:::. _ :.":::: .':._:::: :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: i:::_ :::_: :_:?':_ :::: ::.".':-.':_._::: :._ ::._:.":': ::_._ ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: :_;

Benefits
LJ

The predictions modification, logistic

can be used to highlight or a change of design.

those

areas of a system improvement, downtime

that

exhibit poor maintainability an early assessment requirements

in order to justify the system

They also permit the user to make predicted and and consistent with the system

of whether

are adequate

operational

requirements

and allocations.

Key Words

Maintainability Parameter, Mean Time To Repair Prediction, Failure Rate, Maintenance Action

(MTTR),

Space

Application
w

International

Space

Station

Program

Experience

Technical Rationale
H

This MTTR approach product

prediction

technique a design

is a fast, simple, baseline for repair programs

accurate times.

and effective Design and

for providing assurance logistics

engineers

can use the MTTR

data to effectively for a pending

define sparing, design.

and maintenance

Contact

Center

Johnson Space Center

(JSC)

Page

AT-7

Mean

Time

to Repair

Predictions, Technique

Page

-w

A T-2
m

Mean

Time

to Repair A T-2 the MTTR

Predictions

to troubleshoot, failed system for MTTR

remove, component.

repair,

and replace

Technique In general, average corrective isolation

An interval a lower

estimator limit
I

can be developed data, within bound.

from the mean of and a upper For example, from a


I

of a system which

is an estimated of fault purposes,

the sample sample

elapsed

time required

to perform consists

with a confidence confidence MTTR

maintenance, and correction. is divided reassembly,

data set, one can find with 90-percent that the range mean. 3.2 to 4.2 will contain the exact due to I Unfortunately, can never be found

For analysis alignment

fault correction interchange, :tasks. generally relatively number would the failed operational difficult mounted to assess the current MTTR

into disassembly, and checkout .........

the population dataunce_ainties. Log-Nq_rmal The distribution describe system The is reflects number points. repair short

of a system

The repatr_ime

o-Ta_n-ain_aiffdbl_ti_

consists: of both a large number of_ short-time repair periods and a small of long-time repair periods. usual by a spare occur when The former case where at the diagnosis to the more

D]stn'bution most commonly used to of occurrence because a large grouped about data of it frequencies

correspond

the actual

unit is replaced would

time is the log normal duration value, is shown repair-time, closely shape

site on detection

of a failure. part is

long downtimes complicated data provides

of observations The general

or removing nuts.

a defective

some modal distribution Without statistical illustrate

and long repair-time of log normal 1. in Figure

due to, for instance, Having a co!lection the design Time engineer

rusted/stripped of such fi_dd an opportunity (MTTR) of the

the Mean system

To Repair according

getting

involved

in the derivation can be found example

of the in any will

as it matures,

or to predict

distribution

equations textbook,

which

of a new system system.

to its features

the following

i
=_ m

with the current MTTR used system. is a useful

how MTTR

of a replaceable

unit may
m

parameter

that should

be of a the

early in planning The parameter

and designing is used of system

stages

in assessing components;

accessibility/locations for example, should removed be located

iii

a component where

that often fails it can easily be The estimated MTTR in for


Frequency

and replaced.

may also dictate changes in system designs order to meet the turn-around time criteria critical addition, life cycle repair Activity to repair MTTR systems, such as communication on the Space helps which Station. includes spend on a and

life support

systems

In the cost

the parameter

in calculating

cost of a system, or how much

of the average task, (EVA)

time technicians time is required

Extravehicular for astronauts Figure


Timeto Repak (0

a system. 1: Lognorma! Distribution


I

is defined

as the average

time necessary
z m m

Page

AT-8

Mean Time to Repair

Predictions, Page 3 Technique AT-2

be calculated Example replaceable

from

a finite observed

set of data.

How

to Implement estimating

the MgTR the MTTR

Process of a new

Accurately 1: The repair unit (ORU) times t_ for an orbital are observed to be 1.3, the

system is more than applying the derived formulas on field data of any existing systems. The designer concept system; is going must know how With the overall and where maintenance the system the then and operating for example, to be operated out. can proceed procedure system conditions of the new

1.5, 1.7, 1.8, 2.2, 2.6, 3.0, 3.1, and 3.9 hours.
r

Using log normal distribution MTTR of the unit. Solution:


ti '= in ti

to estimate

and how its failed units this background, the exposed to approximate that has been data. After certain

will be swapped designer (1) statistical methods, the Maximum maintenance

of the new system,

select an existing
w

Utilizing
=

to similar operating mature between designer

conditions

and that has a the similarity the conversion system data Once this is are

Likelihood estimated

Estimator (MLE), or the best value of the mean is:

set of operating the two systems

is assessed,

then can determine

(2)
i

factors needed to make the existing more applicable to the new system. done, the predictions more meaningful and accurate.

for the new system

Then,
w

t / = 0.79124
Likelihood Estimator of the is: _1 n _ 1_:1 (t/i t/ /2

The Maximum variance


i

Elements The MTTR replaceable

of MTTR prediction of a system where in order begins at the unit level (RUL) and replaced predictions defines to its original the MTTR's a defective to restore Then the by units.

s/2_

(3)

unit is removed the system system integrating MTTR MTTR

condition.

Then,

s / 2 = 0.1374

are accomplished of maintainable

The following
$/2

the elements

used in the

prediction

of a system: Time associated with those

_t = MTTR

= e

(?, -T)
(4)
0.1374) 2 _

Fault Isolation: tasks required

to isolate

the fault to the item.

(0.79124
w

Disassembly: Therefore, the mean of the log normal is: Interchange: and replacement access during distribution of this example is: and its variability of time to repair

Time

associated

with gaining identified

to the replaceable the fault correction

item or items process.

Time associated of a faulty item. associated faulty

with the removal replaceable item or

= MTTR

_/(e _'2-

1) (s)

suspected Reassembly:

=2.36 _/(e '1374- 1) = 0.90 h

Time

with closing is performed.

up

the equipment

after interchange

Page

AT-9

Mean

Time

to Repair

Predictions, Technique

Page

A T-2
==

Alignment:

Time

associated

with aligning the

comparable similar System

systems

and components of use and operation.

under

system or replaceable corrected. Checkout: operational. Constant result useful failure rates:

item after a fault has been ...... with the verification and the system is

conditions Level

= m

Prediction level, MTTR is calculated by items' of the replaceable

Time associated corrected

At the system summing

that a fault has been

the product

MTTR's and their corresponding failure rates; the result is then divided into the sum of all The rate of failures or chance predominantly that in the replaceable
llsystem =

items' failure as:


system

rates.

Mathematically,

l_om strictly random occurs life period of a unit.

Causes.

it can be e_pj_d

This type of failure

m B

K factor: performed

For on-orbit

tasks, a conversion elemental factor

factor

_ 1
)u

),iMT
i=1
I

may be applied environment. derived from from the neutral Ground Rules

to convert

task times Where _,i = failure to be rate repairof may be or

in 1-g environment The conversion data of past buoyancy

to Micro-gravity

similar programs testing.

(6)
i= 1

and Assumptions certain ground rules and

In the prediction, assumptions Mean apply:

and system
does not which is break1 2

variance:
n i= 1

Time To Repair (MTTR.) non-related

include the maintenance generally fill out a requisition, time, time waiting Worksite

overhead,

= (-i)
As an example, system have (V), and failure

x,'- a,'
the three (Z,): OR.Us of a Variance MTTR'S,

task time such as time to time to go get tools, for parts, etc. considered.

assume rates

the following

time is the only variable experiences

MTTP. V
All equipment rate. a constant failure ORU ORU2 ORU 3 Total: 1 4.5 2.3 11.4 0.5 0.7 0.56 12.7 500.0

MTTP.*;
57.15 1150.00

All tasks are performed sequentially by one crew member unless otherwise noted. Maintenance established appropriately The prediction recorded experience is performed maintenance trained depends in accordance procedures personnel. upon the use of data from and and with

2..2.2 25.08 514.9 1232.23 to calculate the system

Apply the above MTTR:

formula

reliability

and maintainability obtained

that have been

Page AT-10

Mean Time to Repair

Predictions, Technique

Page 5 AT-2

MrrR

_t_

1 514.9

(1232.

and its variance:


(7)
F

2 _ 1 (0.5x12 system (514.9)2

+ .0 7_><5002 + 0 56x2 The results" o/the above e_/ampl-e indicate most MTTR
w

that the

otten

failed

unit will essentially of a system. is a straight in estimating

drive the

and variance the prediction and is useful Even is used

Overall,
L_

forward a system's if the the phase,

process MTTR. prediction

with a limited early

set of data,

in the design

derived value should help in shaping a preliminary design guideline for the system. In addition, the prediction can also verify logistics requirements and later stage. maintainability References 1. Lamarre, B. G., MathematicalModelling, &Electronic and J.A. p372 - 373. for Cliffs, Press, by: J.E. Arsenault Science Probability at some

Reliability
w

and Maintainability Edited Computer Irwin, Prentice

Systems, Roberts, 2. Miller,

and Statistics

Engineers, pl16.
w

Hall Inc., Englewood

3. MIL-HDBK-338-1 A, Electronic Reliability Design Handbook, Department of Defense.

LA

Page

AT- 11

Ill

il
M

Ill

Availability Prediction and Analysis, Page I Technique AT-3

Technique

Estimate where

or predict availability

the future is defined

availability

of a system, time. unit,

function, Availability

or unit function, may unit,

as the probability state at a random a repairable units,

that the system,

or unit will be in an operable


:...;
=

be assessed a system systems.


:::::::::::::::::::::::::::::::::: :_:::::::_.: _::_ _:_:_.,. ::..... _.._........ ::..:: ........

for a single

component,

a replaceable

of many replaceable

or a function

performed

by multiple

__.::: :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: :[:_' .:_:_i_i_!i_..':_i_...'::::'::::::'_..",.'_i]_::i [_:::.'.':_:::.".5::.'.'::

::_ ::', ::::5 _:::::

:'::.. :::: ::.::: ::::_ :::: _.::::::::::::::::::::::::::: ::::::::::::::::::::: ._::._.<: ::: .<:::::::.<::.<:::: :: :.::::::,.:

........

:..:...:

...::,_ ...............

._. s.. ._. _.5 ... _..._:...

:._:::_::::_:_::_:_::_::::_:..::::::_::_:_.`:.``.h:_::`..!:_iii_:ii_.`.._`.._:_h`._:_:.``_:`.._!:`.._:_!._i_.:::::

."._:_: :! ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::

i_,_.iiiii!i!:.,
::: !

::::::::::::::::::::::::::::::::::::::::::::::::::

:i::_!! i_i!::i _iiii/iIt_i lil._::::::::."::::"

'::::'i:_:_:!:::::"

:" ':" ".'

"?

-':i" 'il !'! ........

"''"

"'"

"

"...........

:._lii_jiiiliii_i_iiiii_i_iii:,..i!::lil!

: :_'.: _:: :::_: ::i: ::_:_:_:_:_:i:_:':i:_:i:!:_:!:!:!?::_i::'_::;_:_:_

!_._::::::.:.:.:...:.:<::::.5:_.:.:.:.:.:..e._:.:.:.:.:.:.:.:.:.:.:.. :.:.:.:.:.:.:-:.:,.:::.:.:._: :.,. ========================================================================================

i iliiiItili/iii !iiiiii!iiil!lii!iiiiiiii!i?i/ii!
i:!: ?:_" ::_ _:.:.'.':_!: :_.":_:_:_:_:: _: .'.':: ._:_..: :). :_ :?::::?.._'..::'-'-_: _ i ."..!___}_!_ii_:..::!:._

_:! i_':_.::!ii:_!:

_:i :_ :i:_:_:_ :i:_:_ :_:_: .'?.':_:_ ,'::: _:?_:_i:_:i::'.:: ::_:i :_ _:_:_ i:::::i:_: i:_: ::i_: _: :i:i: _.::_:f." I:._:::::::.'.':::

:_ _:::::

.".': :_: :__:_ :._

e?_:_ _ "_..',,_:_._ __ ..'.:_ _:.; _i_ i_:'.. __ _ _ _!


w :_.,._:_:'_:_:_: ::.'..: :.::: :_: _: .'::: ::_: :_ .,':._::._ .,'_::_:_ :?.::_:;

_::::-:. _::::::.: .'.'_.: _.-'.'* ::_,_i_..';_: :_. _:: s_::: .,.-::: .,..::: _:: _-..t.i,,._}:_._'.'._!:i:_:,_i.,.':._:.,::_i::.:!:::_.,:_ _ _g_. __: :_:: :_._ :_._ :_: :._: :_:::_:::::::: .,.:._: s_ :::_.: :.,_ ::::::::::: :_ :_.._ :::_: :_ ::::: :i:_::;. . _: :_::: :.:: :.:_:::: v::_: 1:::: :.:.:.:.:._:_.:.:.:.:_.::.::::.. <. _._... ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::

:::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: _:_:.::!:_:_:.:_:_:_:_:.:::.:_:_:_:[:_:.:_:.``..._:_:!_:i:!:!_[:_:_:_:_:_:::_:i:!:_:!:_:_:._.:_:_:._:_.`.:_:.:_:::_:_:::_:_:_:_:i:!:!:[:_i:_:!:..`...`.[:!:_:!::`.!:_!:!::`.!:_:!:..`.!_._:_:_`'.:_:_:_:::!.,....[:_:_:_::._:_.:.._.`..:_:[:_::_:!:_:_:._:_:.:_:!:.:!:_:!:.``::_:::_:_._.._:_:_:.._:_:_:_:::::

Benefits

Availability performance to compare technique operational help assess support logistics savings logistics

prediction measures system increases

and assessment

methods

can provide a given costs.

quantitative design or This

that may be used in assessing to reduce life cycle of mission success

alternatives

the probability

by ensuring predictions will of maintenance anticipate of long term

readiness. Analyses based on availability design options and can lead to definition that will increase resource future needs, system based and provide

concepts

availability,

and maintenance in operations support.

and maintenance

costs

on optimization

=. = = =

Key Words

Availability, Stochastic

Achieved Simulation,

Availability, Maintainability,

Inherent

Availability, Markov

Operational, Model

RMAT,

Application Experience
:

International

Space

Station

Program

Technical Rationale

Availability any system components. control

estimation whose These

is a valuable profile include systems

design allows those

aid and assessment for repair that operate simulation

tool for such as

operating

of failed units or on earth

centers,

system

test facilities,

or flight

systems/facilities. Applying availability techniques is also an extremely valuable development of maintenance concepts

prediction and analysis process for guiding the and requirements.

Contact

Center

Johnson

Space

Center

(JSC)

wa_

Page

AT-12

Availability

Prediction

and Analysis, Page 2 Technique A T-3

= m

Availability Technique

Prediction ,4 T-3

and Analysis

calculation generally

does not include or logistic are beyond

such times as of the


II
m

administrative

delay time, which

the control

Availability using various Availability restorable through reset. restored foundation of reliability parameters parameters prediction estimated but overall system within paths. Availability combinations

can be predicted methods is a characteristic items or systems,

or estimated of repairable and assumes to operation or that

designer, and does not include preventive maintenance time. However, effective tradeoffs using possible. the basic times Trade-off and parameters and some 1, in Reference are techniques

and measures.

a failed item can be restoied It is a function

sample uses are included Section 5.5.:

m m

maintenance,_ec0nIigu_tio_or of how often a unit A Another availability measure of availability, achieved as: and how fast the unit can be both the establishment (R&M) these can be where OT is the total time spent in an operating state, TCM is the total corrective maintenance time that does not include before-and-after or administrative maintenance waiting checks, supply, periods; and TPM preventive directed than the a OT+ between Availability items, system or A_, can be expressed

fails (reliability)

after failure (maintainability). to support and maintainability and trade-offs is created and analyses. for components, spacecraft availability the system estimation that perform

m g

OT
TCM+ TP (3)
l

by availability or units, on the

or ground is based of the units the functions, operations

III

and connectivity

m m

i.e., the series and redundant

is the total time spent

performing

maintenance. Aa is more specifically toward the hardware characteristics Measures of availability, called the A third basic measure only using operational time, support availability, time: corrective time. of availability, considers operational considers availability the operating measure, and logistics

which policies.

il

One basic measure

inherent availability, is useful during design process to assess design characteristics. the as-designed characteristics the estimated (MTBF) parameters. measure
as:

The measure reliability

involves

all repair
u

and maintainability

and pi-dveia-tive ma_rttenance delay time, and logistic realistic a This is a more

and can be calculated mean-time-between-failure repair The predicted

administrative

and mean-time-to of inherent

(MTTR)

or estimated is calculated

definition of availability in terms providing measure to assess alternative maintenance and logistics It is usually support defined concepts of a system associated or fianction. with the operation

availability

_m

by the equation:

M'TBF Ai = MTBF + MTTR (1) Uptime The MTTR time in the inherent availability
m I

Uptime + Downtime

Upti Total

(2)
!

Page

AT-13
m l

Availability

Prediction

and Analysis, Page 3 Technique A 7"-3

where Uptime an operable time the system

is the total time a system is in an inoperable and Downtime, specified state.

is in

Mean Mean

Value

Estimation of system availability

state, and Downtime

is the total or Total as a often

value estimation

The sum of Uptime requisite perform operating a critical

is usually performed by algebraically combining component, LRU, and ORU availabilities When of components, being down, calculated LRU's, the system When using equation (1). the system is composed results of a number the failure is units' item in the system of these involves availability using simple

Time, is usually known,

time, or is a given time to function. Downtime

or ORU's, availability

is broken down into a variety of subcategories such as detection and diagnosis actual
= .

of any one of which parts, the calculated availability. redundancy, estimates Boolean procedures

time, time waiting time, etc.

for repair 1 shows

from the product the system block redundant

unit repair

or replacement Table

time, test

and checkout

basic difference between measures defined above. Table 1:

the availability

can be calculated mathematical similar

decomposition block 1, See Reference

to reliability methods.

Commonly Used Availability Measures Function


i i

diagram solution Section 10.4.

Availability Measure
i i

of."

Excludes:
"1.... I

Computer-Aided Simulation Availability prediction using simulation stochastic approach. reliability, modeling simulation Stochastic

computer-aided

Inherent

hardware

design

(A,)

ready time, preventative maintenance downtime, and administrative downtime

may use either a or a Markov model simulation modeling for the system's and other

uses statistical

distributions

maintainability,

Achieved
L_

hardware design but also includes active, preventative, corrective rnaintenanee downtime and

logistics time and administrative downtime

maintenance and delay time parameters. These distributions are used as mathematical models for estimating individual failure and restoration times and can include failure effects and other operational conditions. A computer program generates random draws from these distributions to simulate when the

_--i

Operational
t

Product

of actual

All inclusive

system failures, tracks time. calculate

is up and down, repairs, system These failure or function

maintains effects, capability

tables etc., and over to (2).

of

(Ao)

operational environment including ready time, logistics time, and administrative downtime

data may then be used system using estimates Simulation equation

and output

operational

availability Estimation may be Stochastic Discrete programs operational analyses

System
w

or Function in a limited mean

Availability fashion

Methods simulation to perform and such as systems

System/function derived combining

availability value

estimates of the

event

stochastic

by algebraically

are recommended availability for large, repairable

estimates

predictions

system units, or more rigorously by using computer-aided simulation methods.

the space station or large ground systems and facilities. These methods simulate and

Page

AT- 14

Availability

Prediction

and Analysis, Page 4 Technique A T-3


u

monitor systems collection following

the availability or functions process of Replaceable

status Units

of defined of a The (PUs). used: fa_qUre times

used during determine functional

a simulation queuing criticality

run to dynamically based upon level of

that are composed is generally futur_

priorities

and the current

remaining redundancy failure occurs. Maintenance and available waiting

after the simulated


l m m

(i)_ Generate predicted parameters.

simulated

for each designated

RU based on distributions

is simulated

by allocating and spare action available).


m

RU reliability

maintenance for resources

resources maintenance to become

parts to the awaiting operating time, are encountered, or function failures

(or

m l m

till

(2) Step through simulated and when failure events evaluate the failure status given encountered. the specific

Groups of maintenance actions may also be packaged into shiRs of work. If the system under activity activity consideration both or EVA) or IVA) is in a space external or internal (extravehicular (intravehicular environment,

impact

can be considered. simulation will yield measure method model a single value on and to as
m I
g ! !

(3) Repair or replace maintenance maintenance criticality system repaired function a future generated. Generation maintenance input distribution policy on the availability

the failed RU using a and procedure of required priority Once or an RU is or and or the current based When used, (called the stochastic an iteration) component many is
m

each run of the simulation

resources, of the failure,

of the availability the chance repairs cover Therefore, possible,

that depends

or function or replaced, status failure

status.

or unit failures during are required

the system

that happened as many potential

that iteration.

is reset

appropriately,

iterations

time for the RU is again

failure situations a better in the of the and repair required results has simulations variation, may be accurate availability.

and to give the analyst of the variation failure measure availability The number availability measure. on the iteration as a function of iterations

understanding of simulated actions model failures and as resulting variations process. depend for accurate in the output for RUs requires RU time-to-failure parameters and factors

in the random

the estimated

will
u

that define the frequency of other scheduled or unscheduled maintenance. The maintenance failures, environmentally To evaluate particular actions can include maintenance or human-induced the effect point of a simulated capability equipment tasks, and failures. failure at a preventive

to iteration Experience

variation

shown that in system availability with a large iteration-to-iteration 200 to 1000 required estimate iterations or more system and to obtain a statistically

of the average

on the function's

operational

in time, minimal

cut sets of

For example, Maintainability

the Reliability Asse-:

failure events that define the system or function failure conditions can be used. Minimal generated cut sets of failure from reliability events block can be diagrams or and then

ment Tool

(RMAT)

is

a stochastic computer-aided method like that described at Johnson maintainability Space Center

simulation that has been used for assessing the


B

fault tree analysis

of the functions,

and availability

characteristics
m I

Page AT- 15
m

Availability Prediction and Analysis, Page 5 Technique A 7"-3 of the Space RMAT specified station function outage RMAT, perform differences configurations Station. The output of the space state as cycle impact resources equipment, concepts availability These the life cycle Station and supporting References 1. The same simulation RMAT) availability
i

costs,

availability

prediction defined spare etc.),

and the test

includes mission) function

the percent spends

of total (or

analysis

are critical (personnel, facilities, on overall

to understanding parts,

time each defined in a "down" away

of insufficiently

maintenance

well as the percent (is zero analysts trade

of time each defined from functional Using able to the tolerant). that quantify alternative

and maintenance operational probabilities. reduce with deploying system. greatly

is one failure failure studies in terms

system

and mission costs

success

at J'SC have been

analyses

can therefore associated a space

between

Space

or ground

of their respective and maintainability

operational availability measure estimates.

MIL-HDBK-338; Handbook, Rome, NY,

Electronic Reliability 1989.

Reliability Analysis

methods

(such

as

Design Center, such 2.

that provide measures resource

for operational will also provide usage measures needs

maintenance as maintenance

O'Connor,

J.T.; PracticalReliability John Wiley 1991. & Sons Ltd.,

manpower

and spare

part requirements. With this capability, JSC has been able to estimate the maintenance manpower
_-.--

Engineering, Chichester,

needs,

including

EVA Station

requirements, alternative Markov A Markov to computer complex technique conjunction Reliability Examples analysis assumptions

of various configurations.

Space

Model

Approach or state-space analysis well suited of is tool particularly simulation when

process,

a mathematical
w

of the availability the necessary This analysis to use in or Tree Analysis Analysis

systems

are valid. with Fault Block

also is well adapted Diagram

(RBDA). 1 or in as

of the use of Markov may be found reliability textbooks

process

in Reference

such standard Reference 2. Failure analysis to costly

to use availability during the design sub-optimization

predictions process

and may lead

of the as-designed

system reliability and maintainability characteristics. Where operations and support costs are a major portion of the life

Page

AT- 16

U
[]

i
m

[] J

imp

m
| L_Jm L_a

"

T!

ii

Availability,

Cost, and Resource

Allocation

(ACARA) Model

to Support

Maintenance

Requirements, Page 1 Technique A 1"-4

Technique

Employ cycle Cost tool

statistical

Monte

Carlo

methods scheduling (ACARA) Center

to analyze by using program,

availability, which

life

cost (LCC), and Resource developed

and resource Allocation at Lewis

the Availability is a soPtware

Research

_!i!_!!_:_!_._:_._!_!!_!_$5i_i_i_._iii:_ii_!_!:_![_!!:_i:i_[:i_i_i:i:_:i_i_:_::;_:_:._.`._:_$`._:_:_:_.``.:_:!:!:_:_!_: _::!::::_ :_:::?.::_i::.,.':.,::i:: _:_ "<:'_ :.`..::_._.`..::::::_$i.`_:_i_!:i_i:i:i:_:._:_:_:_:i:_:>.`..:_:_:i:[:_:_!:_:!:!_:_:_!:[:i:_ i'.-'_: "Y.'.':'_ _:.:" _::_::::: .'::'>.'_?._::: .".:_?.:: .".'?.':?.: :_::!._ :._._::_
_+::: ._/...:: _.::::::,' ::::::::::::::::::::::::::::::

i_. i!!JlllU_
::::. ::::::::

:::::::::::::::::::::
._: :::::_ :_ _ :.q:: '.:: ,..:

_., :_:_:_:::.:_:: ..,.:: :,:.:_::.:.:.:::_::_.,..: _: ::...................... ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::


:_i_i_il."..I_!i_i:_:i_!ii:':_;i;_.."._ii;i_ii" _:: ::i::: .- ' _' ": '" :: i:_. :!:"':_i!!:":!!_::!"!:''::! ........ :"":'::!!iiii_::!_C'::(':! :" ..._!..."_!;!_;_i.`.._i..`_:`.._i;!i_!_i_ii_`:_ig:_!:i:`...`:_:`..!_$``

iiiiiIilit!!iil!ili iiii
i_}_!._ i_i:i "_!_. :_}-":: :':::::_:_:_ :..': ._: ::..'.: "::_:::: :i: :._ii_ i_!i
u

::i_i_iI_::i_iii_!_iiIiiii!iii_iIi!i_ii_ii_iiiii?:i::ii_::i_i_::i_::::iii`:iii_`iiI_iiIiiii
iiitiii!}liiliiiiililiiilllt i_:_:_$$_i:_:_:[:i_.:'_:_,_:>:i:_:i: !i_ ""?";':'::iF"$t:?:::: _::::::_::::: :._ :::x ':_::._.:.>_.::.._.:
._.: ...... +._ _,...

_::

'i..... "" ! . "- - ' _::! _:iHH_ _ i_::_ :_i i li_ii:! i!_i_._i_ii!_ _!_._?:_..'._ _:`_i_i?.._.:_?._ii:;i_i!?_i!_!._!:::_I_ii:_:?...?._:!_:_:_:?._i_i:_i:i:i_i:i.`..$i:;_i_i: :_:_: _:::: :.",":: _ :: _?::: .".;-_ .".': _.'.': :!:: "_'>;:

+. _..:.:.:.:.:.._:_..... _. .?_:_::_....'. _: :::

Benefits

The ACARA maintainability, system's Also,

program is an inexpensive reliability and availability requirements parameters

tool for conducting simulations to assess availability, output state

maintenance (percentage

over a prescribed

time interval state capability),

k.d

availability

such as equivalent

availability and number

of time at a particular

of state occurrences

can be computed.

Key Words

Maintainability

Modelling,

Availability,

Computer

Simulation

Application Experience

International

Space

Station

Program,

LeRC

Micro-gravity

Experiments

Technical Rationale

The development Space Station maintenance understanding time. and resource probability and ACARA system

of the Space payloads

Station

and other requiring

space

systems

(i.e., on an of LCC, failures,

and experiments)

long-term with emphasis a given period availability, and Weibull optimum spares, component

support dictates maintenance planning of the level of support required over is written specifically for analyzing scheduling distribution schedules A combination functions component The scheduling

The program

of exponential

are used to model replacement will comply vehicle

to achieve on-site

performance.

with any constraints

on component production, resupply crew manpower and equipment.

capacity,

Contact

Center

Lewis Research

Center (LeRC)

Page

AT- 17

Availabilite,

Cost,

and Resource

Allocation

(ACARA)

Model

to Support

Maintenance

Requirements, Technique

Page

A 1"-4
m

Availability, (A CARA) Technique Requirements

Cost, Model A T-4

and Resource to Support

Allocation

Frequency Lifecycle

of failure cost,

and repair. hardware,

Maintenance including transportation, and maintenance. including


I
I

The ACARA represented comprising description identify diagram system Monte

program by reliability series,

models block

systems diagrams

Usage of available resources, maintenance man-hours.

parallel, blocks.

and M-of-N A hierarchical is needed to contained ACARA Inputs =_ A RBD must be prepared for ACARA simulate depicts blocks RBD a system's a system, depicts availability. and the arrangement function. depict system, physical but rather =:_ to of the

parallel redundan_

of the system Given simulates techniques

the subsystems (RBD)

and blocks a reliability

The RBD

in the system. the program Carlo

block of a system, of the using block &time

representation period

a performed

the behavior to generate

over a specified

does not necessarily in the actual

connections

failure and repair intervals as a function of exponential and/or Weibull distributions. ACARA following: interprets tables =_ i.e., availability states and the results of a simulation and charts for the and displays

shows the role of each block in contributing to the system's function. The blocks are sequentially numbered as B 1, B2, B3, etc. and subsystems are numbered as S 1, $2, etc, which are defined from the inside out. Figure 1 shows an example blocks of a system with its corresponding Beginning each parallel and subsystems. set of blocks, is

[]

|
II

Performance, reliability

of capacity

with the innermost or series

set of blocks

[]
4
1 (Var) i

(Bin)
= =

16

Battl

(Vat) I-:]. I

[9" Baet

I0

Bat_

I-i

I
I

11

Bat

I-i

Figure

1: Diagram

of Blocks

and Subsystems

Page AT- 18

Availability,

Cost,

and Resource

Allocation

(ACARA)

Model

to Support

Maintenance

Requirements, Technique

Page

A T-4

partitioned subsystems.

into a subsystem with other

which or

in turn

may combined

blocks

parameter Between Wearout

is equal to the Mean Failure (MTBF). failure function. is also modeled The shape new)

Time

by the must be its

The system subsystems: Subsystems

shown

in Figure

1 contains

Weibull

factor

1 or more. 1 and 2 are both variable arrangement of batteries. contain 9 through respectively 8 and Blocks M-

If the block

with an initial age is installed, from its first time-toLikewise, if it this period is

(i.e., it is not brand of-N parallel These Blocks 11.


m

initial age is subtracted failure due to wearout.

subsystems 6 through

undergoes a failure-free period, added to its first time-to-failure. ACARA generates time-to-failure

events models

Subsystem 2 in parallel.
w

3 consists

of Subsystems

1 and

using

one or a combination

of these

and assigns the minimum resulting time for each block as its next failure event. The 4 is a binary of diodes, M-of-N Blocks parallel 3 through early failure model is canceled by assigning probability by an to the block of zero; large of MTBF; type an early failure failure, and wearout large mean also simulates life. redundant pairs of failure,

Subsystem
w

arrangement 5.

random

by an excessively

Subsystem 5 is a parallel arrangement two turbines, Blocks 1 and 13. Subsystem 3 through Modeling 6 comprises arrangement 5 and Blocks Time-toFailure the entire 2 and 12.

excessively ACARA

system

and is a series
= =

of Subsystems

active and standby blocks. A standby block is installed as dormant and its time-to-failure is initially modelled by random failure, in

which the MTBF is multiplied by its characteristic "Dormant MTBF Factor." Then, the corresponding active time-toand is failure is modelled by early, random, wearout failure until the active block replaced. for Modeling part upon resources. i.e., initially spare block Down Time depends and local in of spares Ifa

The ACARA program uses the Weibull distribution function to model the time-tofailure for the system. The shape and scale factors are adjusted to modify the form of the distribution. Uniform random numbers from 0 to 1 are generated the reliability, failure(i.e., and wearout models. R. ACARA mortality), infant These and substituted uses the early random failure, by userfailure)

The downtime

for a failed block spares when

the availability These located

failure

(life-limiting

may be local spares, the block fails, the

models

are adjusted

at the site. replaced

defined parameters failure characteristics


w

to approximate the of each block.

is available

is immediately

and downtime are available,

will depend Random Weibull shape failure is modelled by the distribution function where factor is equal to 1 (equivalent and the scale distribution) (MTTR). the to the ACARA according quantities

only on the mean-time-to-repair If no local spares a replacement production type, the constraints

will schedule for that block

to the schedule

exponential

Page
r

AT- 19

Availability,

Cost,

and Resource

Allocation

(ACARA)

Model

to Support

Maintenance

Requirements, Technique

Page

A 7"-4

on mass, resupply constraints determine Once allow

volume, vehicle.

and delay associated and loading ACARA spares also checks agents

with the to

mE

the manifesting

to the

on the maintenance when the block

can be replaced. are met to ACARA the MTTR's then it. The for
[]

all the above the block

conditions

U
il

to be replaced, depends MTTR's separate upon

estimates that block Examples

the time required type.

to replace

time-to-repair for up to three

may be specified maintenance agents agents. assumes


i
m

II

of maintenance

are crew,

equipment, and robotics. ACARA that the maintenance actions occur simultaneously, so that the block's

repair agent the be or to


m !

time is determined by the maintenance having the maximum MTTR. During simulation, set equal Reference of ACARA data information. the Computer Information University References 1. Stalnaker, Dale K., ACARA 103751, User's February the time-to-repair to the maximum 1 for a complete of graphs stochastically. guide and defined

II

may either MTTR Refer

to be determined

i
m

on the use for entering from and


I

and the explanation ACARA Software Center

and the output

[]

may be obtained Management at the 542-3265. (706)

(COSMIC)

of Georgia,

Manual, 1991. 2. Hines,

NASA-TM-

W.W.

and Montgomery, Science, 1980

D.C.,

Probability Wiley

and Statistics

m Engineering 2nd Ed., John


w

and Management & Sons,

Page

AT-20

Rocket Engine Failure Detection Using an Average Signal Power Technique, Page 1 Technique A 7"-5

Technique

Apply a univariate failure prediction algorithm using technique to rocket engine test firing data to provide indication. variations The predictive in the average maintenance signal power technique over time.

a signal processing an early failure tracking the

involves

_:.::::'.:::::.-'.:?. ::__:..'.:::..'.::::!::::_._:'_i:_:i:_._:i:_!:!:i:_:i .......


::::::::::::::::::::::::::::::::::::::::::::::::::::::::

ii/:ili:i:_:ii:i:i:::i:_i..iiiii_i!i..,._ii_%_!i_liiii_
"'":.":!"'_::: ............ "............. :!::" -":::_'"::!""i:!:!_,.:i i_ i_ ::i:i:i:iiiii i:_:::: _: "'i'i'i_'..:'..' _.__' ............ .,.:

__ _'''':'' w

" -.::,....,:..-

..::....

+......:.,.........:::::.%,..: !_i

:::i :_: iii!)_ :._

::

N/_i_il_isili_i_l_iNi_:,slsii_i::iiiiiii::ili!i!i!::i_i!:iiii/i_-iiiiiiiiil _._::: ::::::::: :_::: _!_.:.'_ .>:.'_ __!_[_'.:i_:':_.;.':'_:.,'.i:_:i.... _"::


====================================================

itiliiiiiiiliiilli!iiiiiiiilililiiiiii!iiiiiiiiiil!ii iiilii iiiii!iiliiii!iiWiiiiiii!i

......

_:_::i_i::!::iiii::iiiii_i i_ :: iii_::::::::_ii _ii/_ ii/ii.::3!iii::i_i_i ._.'".'-.:'..: . :::..'_.'.::; '.'.!i ............. __!i!_i_!_i_i_..": i_ii_i..'.._._!i!_i_!_!

Nl!ii i#i ii!iii 4 !iiiiiiiiiiii !ii iiiiliiiiiiiiiiiiiiiii

Niiiiill!i!il iNil i iiiiiiNii _:_..`._:_:_i_:i_..!..:*.._:_:_:_:_*_::_:#_`::_i_i_*.`_:ii!_...._i ........._ii:i.:::: .......................... _[i::....:::ii._i::iii_::_::_::i_ii_i_i/#iiiiii#_ii#i!_i_::::iii::iiii!i


Benefits This technique the traditionally algorithm significantly using major
_:_

will therefore used

reduce

unnecessary system. times

failures

attributed signal

to

redline-based indication of failures damage.

The average than the present warning

power of of

can be used with engine earlier limits. certain failure

test firing data to provide method to avoid techniques are not capable

redline hardware

Limit monitoring

detecting

modes

with sufficient

and facility

Key Words

Rocket

Engines,

Failure

Detection,

Detectability

Application Experience
W

Space

Transportation

System

(STS)

Technical
E L_ ,

Detection

of anomalous

behavior

is critical

during the operation

of the

Rationale

Space Shuttle Main Engine (SSME). Increasing the detectability of failures during the steady-state operation of the SSME will minimize the likelihood of costly engine damage and maintenance. The average algorithm because failure indication parameters, thus power signal algorithm is superior to the time series more parameters contribute to the first simultaneous times. This increases the agreement between several

increasing the likelihood that an engine anomaly has occurred. This method also reduces the number of false failure indications that can prematurely
w

shut down

the engine

during

testing

or operation.

Contact

Center

Lewis Research Center

(LeRC)

Page AT-21
w

Rocket Engine Failure Detection

Using an Average Signal Power Technique, Page 2 Technique A T-5


m

Rocket Engine Failure Detection Average Signal Power Technique Technique A T-5

using An

average signal power calculations are performed over 2-second, 50-percent overlapping window for nominal test firings at both 104- and a 109-percent-rated power levels. A smaller time increment must be used to improve the failure detection capability of the algorithm. The average plUs three standard deviations of/he average signal poWer _e computed for all the nominal firings at both engine power ievels._ Tiaese Values are combinedto calculate the thresholds (see Reference 1). A safety factor ranging from 1.5 to 3.5 is needed to ensure no false failure indications are computed for the nominal firings. The range of safety factors reflected signal behavior variations that occurred over seven nominal A2 firings. When used in the failure detection mode, failure &the average signal power of a parameter to fall outside its threshold results in a failure indication. Also shown in Table 1 are the thresholds calculated from the SSME nominal test firings based on the average signal power algorithm along with the associated safety factors.

[]
m

For discrete random processes, probabilistic functions are-used to describe the behavirr of the rocket engine system. The Power Spectral Density _SD)is computed to describe how the variation of the random process is distributed with frequency. For stationary=si_ais,- t_e Pg-D is bandi|_nqied to l/(2T), where T is the sampling interval in seconds. Average Signal Power Calculations The PSD is defined as the discrete-time Fourier transform of an autocorrelation function. (The derivation &the autocorrelation function is shown in Reference 1.) When the autocorrelation function is evaluated at zero lag, then an expression for the average signal power (ASP) of a random stationary process results:

+__1
2T

P =

r I0] =

f
1
2T

(1) Table 1: Signal Threshold and Safety Factor for SSME's Average Power Safety Factor
1.5 1.5 1.5 2.5 1.5 1.5 1.5
m J w m

P=(f) = discretetime Fourier transfor r=[0] = reverse discret Fourier transfor

Parameter

Threshold

Mixture Ratio MCC Coolant Discharge

0.00112 200 125 1598 2509 436 232

The average signal power for several SSME para_ _ters is determined by calculating the autoc _ elation at zero lag for the parak ers provided in Table 1. The assu_, _ion is made that the signal is stationary over the computation interval. The

MCC Hot Gas Injector Pressure LPOP Shaft Speed LPFP Discharge Pressure IqPFP Discharge Pressure Fuel Preburner Chamber Pressure

Page AT-22
I

Rocket

Engine

Failure

Detection

Using

an Average

Signal

Power

Technique, Technique

Page AT-5

PBP HPOP

Discharge Discharge

Pressure Pressure Temperature

911 268 0.04 47 4 6 A B A B 32 38 154 104 550000

1.5 1.5 3.0 1.5 1.5 1.5 2.0 2.5 3.5 3.5 3.5

one nominal thresholds algorithm shown illustrates parameter, test firing. average the application

firing were shown

tested

using signal 1

the of is power

in Table

2. An example test firing

of the average anomalous

PBP Discharge MCC HPFP HPOP HPFT HPFT I-IPOT I-IPOT Pressure Inlet

to a SSME the interval HPFP Figure signal

in Figures

1 and 2. Figure over which

the average and one of time.

Pressure

signal power

was computed discharge 2 displays

for a single pressure the resulting

Inlet Pressure Discharge Discharge Discharge Discharge Shat_ Speed Temperature Temperature Temperature Temperature

power, algorithm

as a function

As shown, signal power

the threshold

for the average has been exceeded.

I-IPFP

Algorithm

Implementation

A system identification and signal processing software package on a RISC workstation provides the average signal power Simulator number algorithm. data test
7000 G_0 m
b

Command and Data from a predetermined

(CADS) of SSME

firings are used to establish indication thresholds. Several considered


W

the failure

system

conditions indicate include

must be does an engine sensor fault.

Gg00

i!l

to ensure

that the algorithm failure,

not erroneously These conditions

68OO

a_

propellant tank venting and propellant transfer. detection techniques before, or concurrently, monitoring algorithms
w

and pressurization, Sensor failure with safety in order to eliminate failure problem. sensor being Typically, problems of the are

I _ ! I$1_IIIIIIII_IIIIIIIIRIII
GT_

IIIlUlUlIIIIItlll IIIIIllllJlJl IJ!


$700

_ t

must be exercised , I I I I
TI_.

I
I
sic

the possibility interpreted all parameters removed algorithm.


w

of a sensor exhibiting

as an engine

prior to the application

Failure
m

indication

thresholds signal

are established power tests. and firings of nominal Figure Power 1: Application Algorithm of the Average Signal

by applying algorithm

the average to a set number four

For the SSME

anomalous

to the HPFP Pressure

Discharge

Page

AT-23

Rocket

Engine Failure Detection

Using an Average

Signal Power

Technique, Page 4 Technique A 7"-5

25OO ........

FAILIII[ INDIr..ATIGII

_._,,..,,.'_-,_, _.,_,_,_,,_.-i.
o 50 Ioo I._ 2oo TI_. zso u _ j_

I
= m

Figure 2: Average Signal Power for Interval with the Failure Indication Threshold

that

i
m

Nomenclature: HPFP HPFT HPFTP HPOP H:POT LPFP MCC high pressure high pressure high pressure high pressure fuel pump fuel turbine fuel turbopump oxidizer pump

high pressure oxidizer turbine low pressure fuel pump main combustion chamber :=

B
H

PID " p-_ameter identification SSME space shuttle main engine

Reference Meyer, = F_lure 90,!993. C.M., Zakrajsek, Using Techniques, J.F., Rocket System AIAA Paper Engine

Detection

Identification

July 1990.

Page

AT-24
m

caw

Operations
w

7m,_

And Design
This section provides operations operations improvement. system designers engineer or design experience a rich source to support and related

Operational Considerations
of ideas to any organization those field operations. experience The that that is involved techniques can from be reflect used in either actual spaceflight spaceflight continuous hardware they provide to

to achieve of flight Also,

They can provide to make with

a mechanism easier,

for feearback safer,

operators to operate.

the systems valuable

and less costly

=:= = =

the design environment.

information also can serve

on the latest

technology

advances tool for

in the operations personnel,

These techniques transfer of knowledge

as a communications of professional processes, to making

operations

Iwl

allowing for contained feedback

and enhancement NASA

development. process

The techniques improvements, and

herein to design

are the most up-to-date engineers, as possible. all of which

operational

are dedicated

NASA

systems

as maintainable

and cost efficient

Page

OP S- 1

mm

mm

I
m

m_m

I
m mm

ii

mm_

IB

m w

L_

m J

SRB Refurbishment Practices, Page 1 Technique OPS-1

Technique

Engage launch. reworking (MRB)

in refurbishment Boosters These

activities (SRB's)

to rebuild after

and prepare

for reuse Orbiter (2) board

of

the Solid Rocket

each Space (3) material

Shuttle review

refurbishment

activities

include:

(1) inspection, (5) corrosion buildup.

of anomalies acceptance

to specification, part

or scrapping, for storage

(4) cleaning, replacement, or return

protection

and prevention,
t L-I

(6) scheduled

(7) test and checkout,

and (8) preparation

to flight

L__ LJ w

Benefits

Key Words

Refurbishment, Galvanic

Maintainability Sealant,

Design Electronic

Criteria,

Salt Water

Protection, Testing

Corrosion,

Component

Vibration

Application Experience
w

Space Motor

Shuttle Solid Rocket (SRM).

Booster

(SRB),

Space

Shuttle

Solid Rocket

Technical Rationale

Through structures

the past decade and components; successful

of maintaining MSFC refurbishment

the SRB

by refurbishing have failure

the

and its contractors specifications hardware For example, recovered performance,

developed to

and implemented that have proven the proven impact


L

and procedures to adhere from of otherwise and possible salt water

their effectiveness. of refurbishing in unacceptable expenditure

practice

can result

scrapping resources,

usable hardware, schedule delays.

of unnecessary

Contact

Center

Marshall

Space

Flight

Center

(MSFC)

Page

OPS-2

SRB Refurbishment

Practices, Page 2 Technique OPS-I

SRB

Refurbishment OPS-1

Practices
.

Table

1. SRB Maintainability

Factors

Technique Solid Rocket encompasses the reusable

Booster

(SRB)

Refurbishment to return to a

2. 3.

the activities

required

Accessibility Commonality of Fasteners Electrical Subsystem Installation Removal

and

SRB component

4.
.

flightworthy condition after SRB ignition, l_off, and flight; separation from the external tank; descent (free fall and and parachute); ocean impact; and retrieval. When the decision was made to recover reuse the SRB hardware, organized criteria Flow Figure to formulate for a reus_le a design the maintainability booster__The design S_K!3_. .................. in team I, ......... as

Thrust Vector Control (TVC) Subsystem Installation and Removal Ordnance Installation and Removal

team was

6. Markings and Color Coding 7. Unitization of Subsystems 8. lrreversibility of Connectors 9. Tool and Equipment Design 10. Spares Provisioning

Ii

Chart forMaintainability 1. The maintainability

is shown

produced the Solid Rocket Booster Maintainab_ilty-Design (_ritei'ia-Document a document that was used by designers .. they conceived each design feature, performed the necessary tradeoffs of the design design design parameters, team included features factors and made other design The as a and product engineering decisions. maintainability

Design Process Condderations Table2Ti]-st-s_]calm_intenanee were water considered impact, during designed the design The SRB was incorporating the parachutes; electrical/electronic Vector Control

. a_ions

that

process.
m

t withstan__d launch, environments,of I 0 flights for Thrust and for the


I B

and towback the capability 20 flights (TVC)

for
I

components, components, and 40 flights

goal and incorporated

the desired of process. in

maintainability Maintainability

into components the design that were

SRM components; structures. welded aluminum ring, which and/or

the end item throughout during the design Table 1.

SRB structures mechanically except

are typically fastened tank attach fastened steel.

considered

of the SRB are shown

for the external

is mechanically

Recover Dccision and Reuseto

Maintainability Estalish Design Criteria

for Design Pease

___

and/or Manufactme Assembly

Test

I
Preflight Storage and Refurbish
Rcgovct

(_atio_ aad Launch

Figure

1. S_

Flow

Chart for Maintainability

......

Page

OPS-3

SRB Refurbishment

Practices, Technique

Page OPS-1

Table
1. 2.
w

2. Maintenance

Actions

to some

components

of the TVC

system.

Inspection Troubleshooting Calibration and Adjustment

2. The aft skirts

of the first few SRB'S damage. The the addition of rings. of the aft rings and force with the the from 115

3.

4. Repair

experienced water impact corrective action included gusset Foam reinforcements was sprayed components.

to the structural on the interior Impact by increasing

All aluminum painted insulation. D6AC


z L_

structural The SRM

assemblies segments

are first are forged are

skirt to protect the TVC water diameter decreased

the reinforcement

and then coated steel. and/or being All structural alodined primed

with an ablative components as appropriate, with aluminum are designed intrusion by surfaces, fastened

was reduced

of the main parachutes The larger water the SRB's

cleaned before paint.

feet to 136 feet. from 88 ft/sec

parachutes impact velocity (60 mph to 51.5

and top coated cgmponents salt water

The mechanically from

to 75.5 _sec

and steel structural


w

mph, respectively). 3. During initial teardown water and corrosion were mating correct sealant joining. surfaces of structural were modified to both this problem, to be applied and inspection, found between members. to require surfaces application the before

to be protected applying
w

sealant

between

adjoining

installing the fasteners with sealant, torquing the fasteners, and applying a fillet of sealant along the edge of brackets where they join the main structure. The electronic/electrical

the To

the sealant

specifications

components exposed to salt water and the external surfaces &these components system permit are painted. The TVC system is a closed-loop the intrusion external

are sealed, hydraulic

that does not The SRM

4. To modified a.

eliminate skirt,

potential

water

entry into areas were

of sea water. surfaces

the forward

the following

segments' surfaces insulator

are protected and the internal

or redesigned: The aft seal on the forward from a rectangular skirt was

with an epoxy

paint finish,

are protected by the propellant that is bonded to the inside surfaces Areas not protected insulation are grease.

changed

to a "D"

of the SRM segments. with paint or bonded-on protected

configuration to allow better contact between the forward skirt and the forward dome b. of the SRM. A fillet of sealant was added between

with a water-repellent Improvements areas

LJ

B_

Specific Typical redesigned

of the SRB that have been as a result and below: in the aft To team of trouble

or modified

the access door and the surrounding structure after final close-out of the forward skirt.

r--

areas found during recovery refurbishment are discussed 1. Galvanic prevent added corrosion

occurred

c. Sealant was added to the mating surfaces and the installation bolts of the separation parachute nut housing attach fittings. improved for the main

skirt of the first few SRB's recovered. this from recurring a zinc coating and bolted the design metal anodes to selected

components,

(Zinc bars)

5. The following

practices

Page

OPS-4

SRB Refurbishment

Practices, Technique

Page OPS-1

II

III I

El

i gml

z
maintainability, parachute a. parachute deployment,

SRB

Flight

Configuration were being returned to the vendor refurbishment. After refurbishment, acceptance test procedures including (ATP) performed, testing. caused vibration for were

and

inflation: To avoid abrasive during foam damage that material frustum structure.

and thermal
11111

occurred deployment, were

main parachute and ablative &the support

The vibration the remaining of

level of these tests life of the component the excessive lifetime components) has been of electronic presents parts of spare a unique effort not be until (except

added

to portions

to be reduced. expenditure vibration eliminated The constant problem

To prevent components'

and the main parachute b. To avoid damage

for the range safety system to the parachutes are rather pattern pattern. and thermal testing improvement during deployment, the parachutes zig-zag

during normal turnaround.

now packed

in a circular

than the previous c. The opening canopy to allow

parts by the manufacturer because the improved quantity

to the SRB refurbishment

at the top of the main was decreased quicker inflation in of the

are often parts

parachute diameter parachute. 6. After every

interchangeable A sufficient procured

with their predecessors. must requirements

to meet logistics parts.

the components flight electronic components improved

are redesigned

to use the

Page

OPS-5

OI QIN,JJ.., is oF I :)On,"QU ITY


N

SRB Refurbishment

Practices, Technique

Page OPS-1

Typical Figure seconds reentry,

Refurbishment 2 depicts the SRB

Procedures flight 125 flight, the SRB'S During (it is not

Table

3.

Typical

Structure Flow
water impact

Refurbishment

configuration. are jettisoned

After approximately from the external tank.

into the Shuttle

1. 2.

Tow SRB from Remove water. Place Safe Wash Remove TVC

area

to dock with potable

SRB from

ocean,

Rinse

the nose cap is jettisoned

3. 4. 5. 6. 7. 8. 9. 10. 11. 12.

SRB

on transporter. and Hydrazine solution Systems. and rinse. Team with Inspection detergent assembly. facility.

recovered), deploying the drogue parachute. After the SRB is stabilized in a vertical position, descends the frustum is jettisoned and into the ocean. Its descent is held by the drogue the jettisoning portion parachute. of the of the SRB the at water by the onto the

SRB Ordnance SRB

Assessment

aft skirt

to a safe velocity In the meantime, frustum lowering parachutes impact) recovery deploys

refurbishment TVC

Remove Critical Thermal hydrolaser.

Components. area: remove check. system removal, robotic components.

Disassembly

the three main parachutes, Once in the ocean, are jettisoned are removed

dimension protection

the remaining (which

into the ocean.

13.

Inspect,

Visual

and NDE

(XRAY

and

Ultrasonics). 14. Rework,


use.)

and the frustum

Touch-up

paint

(repaint

everyftfth

team and positioned

recovery vessel. A plug is inserted into the SRM nozzle throat and the SRB is dewatered. SRB allows vertical Removal of the water from the from a position. the SRB to be positioned to a horizontal

15. 16.

Inspect Preflight

and

identify.

storage.

position

The SRB is then towed area dock. At dockside, and placed pyrotechnics
vam_

to the disassembly

routed

to the refurbishment refurbishment

area where a document is reworked

prepared is attached to conform Engineering fuel that in a component

procedure

the SRB is lifted from the water on dollies. The SRB the TVC and an assessment anomalies solution Then the are disarmed, and documents with a detergent wash facility.

to the part. The part to the Refurbishment Specification. to flightworthy to storage.

This specification each before in the on condition

lists the requirements it is returned disassembly

for refurbishing

system

is depressurized, occurred

team inspects may have SRB is washed semiautomated removed facility.

during flight.

The SRM segments facility

are disassembled at dockside, placed

The aft skirt is

and routed to the TVC disassembly Table 3 lists a typical flow sequence refurbishment. the remainder After the of the facility. they

rail cars, and transported to the SRM contractor located in Utah. At the contractor's plant, loaded and routed All segments STW7-27443. the segments are offto refurbishment areas. must fall of this is of specification dimensions analysis requirements the effect capability

for major structure aft skirt is removed, SRB is routed


LI

that are to be reused If segment an individual

to the disassembly

meet the requirements outside required structural reusability the acceptable to determine and sealing is determined.

As the SRB components are identified by attaching

are removed,

a metal tag with per the is then

specification,

their part number and dispositioned Predisposition List for SRB Flight Hardware 2 . The SRB component
z : .. .-

on the before

All documented

Page

OPS-6

SRB Refurbishment

Practices, Technique

Page 6 OPS-1

Table4. Types of Hardware That Have Been Successfully Refurbished


1. Major Structures (Frustrum, Forward Skirt, Aft Skirt, External Tank Attach (ETA) Ring, Solid Rocket Motor (SRM) Segments, etc. 2. Electronic Components: Integrated Electronic Assembly (lEA), Integrated (1RD), etc. 3. Electrical Cables. 4. receiver Decoder

on the SRB Excluding 10A00526, Center,


.

the SRM,, Space Flight

NASA/Marshall

AL.
m

NASA/MSFC: Subject SRB Excluding NASA/Marshall

Sealing the SRM, Space

of Fasteners on the
J

to Sea Water

Exposure

10A00527, AL. for to

Flight Center, Finishes Subject

TVC Components Auxiliary Power Unit (APU), Hydraulic Pump, Hydraulic Reservoir, Fuel Service Module (FSM), etc.

NAS_SFC: Aluminum Seawater the SRM, Space

Protective and Steel Exposure 10A00528, Center, Solid Alloys

on the SRB Excluding NASA/Marshall AL. Rocket Booster


I g

Flight

nonconformances

are

reviewed

to determine 7. NASA/MSFC: Flight Plan, Space Hardware Flight Ground AL. Rocket Booster m Operations NASA/MarshaU
D

if the condition of the hardware has changed. The most critical areas to be reviewed are case membrane port threaded aft segment defects noncrack-like thickness, areas stiffener flaws, stubs. pitting, etc.) vent port and leak and and sealing surfaces,

SE-019-040-2H, Center, Solid

No surface scratches, deeper than 0.010 are 8. NASA/MSFC: Flight Hardware Requirements, NASA/Marshall Systems 9. Thiokol: Analysis Space Refurbishment SE-019-050-2H, Space Flight Center, AL,
m

(corrosion,

inch are permitted.

All segments

hydrotested to 1.125 times the Maximum Expected Operating Pressure and magneticparticle inspected.

III

and Integration. Shuttle SRM,, for Components, City, Utah.


l

References 1. NASA/MSFC: Maintainability Document, NASA/Marshall 2. USBI: Flight United 3. Thiokol: Refurbished STW7-2744, Operations, 4. NASA/MSFC: Surfaces Subject Soild Rocket Booster ...... Center, AL. 10.

Requirements Refurbishment STW7-2863, Space Thiokol: Finalization Predisposition Hardware, Technologies, Space List for SRB 10PLN-0027, Huntsville, SRM Criteria, Space USBI, AL. 11. MetalHardware, Corporation, City, Utah. Thiokol: Acceptance Case, Space 12. Thiokol: Acceptance Design Space Criteria Flight

and Acceptance Nozzle Thiokol Metal

Corporation,

Operations, Space

Brigham Shuttle

SE-019-022-21-1,

SRM,, Process for Nozzle Thiokol


J

Requirements Space

STW7-3450, Operations,

Brigham

Shuttle

Space

Shuttle

SRM,, Corporation, City, Utah.

Case Acceptance

Criteria,

New and Modified Thiokol Brigham


w

Thiokol Corporation, Brigham City, Utah. Sealing of Faying

STW7-3489, Operations, Space

Shuttle

SRM,,

to Sea Water

Exposure

Criteria

for Refurbished
l

Page

OPS-7

SRB

Refurbishment

Practices, Technique

Page OPS-1

Igniter

Chambers

and Igniter

Adapter, Space

STW7-3861, Operations,
=

Thiokol Brigham

Corporation, City, Utah.

13,

Thiokol: Refurbishment Criteria for Redesigned Assembly, Corporation, City, Utah. STW7-3888, Space

and Acceptance Barrier-Booster Thiokol Brigham

Operations,

14.
w

Thiokol: Shuttle (RSRM) Prepared Corporation.

Manufacturing Redesigned Project, for NASA Brigham Solid

Plan for Rocket

Space

Motor

TWP,- 10341 (CD), by Thiokol City, Utah. Solid Rocket United Technologies,

15. USBI: Booster Handbook, Huntsville,


w

10MNL-0028, Pictorial USBI, AL.

Representations

16.

USBI: FrustumAft Skirt Disassembly Requirements, 10REG-0032, USBI, United Technologies, Huntsville, AL.

17.

USBI: Refurbishment Engineering Specifications For Space Shuttle Solid Rocket Booster Assembly Project, 10SPC-0131, USBI, United Technologies, Huntsville, AL.

Page OPS-8

mm

II

m M

II

m m

i mm

mm

II

qm

Electrical

Connector

Protection, Technique

Page 1 OPS-2

|i

Technique

Protect covers covers

the receptacles/plug provided are unavailable, leave

ends of demated in downward

electrical plastic facing

connections caps or if

with

by manufacturer

or with generic

position.

iliiiiiili!ii/i_iii_ii_ii!i!iii!ili!i_ilil/_/i/ii/fiii
:::::::::::::::::::::::::::::::::::::::::::::::::::: .] :_::_ _:

[_i_ii i?." !?:.:i i?.' i!ii ii i:i_.i_iiiii! i_iiiiiiii_ ?.i._ i iii i:iiiii_ i:iii _:i_:i i:ii_:i:i:i:_i>)i:_:i _:i:ti:i:i:i:::i_'::[i_:i:i_:i:!:i:!:i:!:ii ::::::::::::::::::::::::::::::::::::::::::::::::::::: :i::::: ::::::::i:i: :i::.<: :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: : :::::::::::::::::::::::::::::::::::::::::::::::::::::::
: :"' : ":" "':: ,'," : ::_: :::_i:'_: ! :::':" ':':::':':':':':'i: : :>.:::::>.;::;.<')_::: i_ :?: : >.::::':':'

_ : ::_:::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::
::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: "!_ !:_ i t._: :_ i i_ iii_ _ i.:!ii: ......... F"! :i_-_''"i:: ............................... _i"_ : .5:?.._::..5:_: :::'i".'.".'(' :'<" ""

II iil i
::_.'.::1 _:_ ::: : :::::::::::::::::::::::: I

:::::::::::::::::::::

itl/i

...... :":::'_::_:::" ............... .......... _!_..": ...............

i: :" "" _ i:" :_:! ""i !!ii_

:............

' ":""

::" :':':':':':

::

X "::: ?.':,":':':'::! _ii."," _

.............................. '::::::!i:_"""':::

_'." _ :_'.'i _ ii_i _ i:_:').'i_ i! !.'.'

:,:-:::.:-.,_i:+ :_..:.:.:.:.:.: + :.:,

iiiii _ii_i_i_i_i_i_i_i_i_i_i_i_i_ii_i_i_i_!i_i_is::_i_iiii_::_,`_`_i_i_ii_ii_iii_i_;_`:_i_i_:_i iliIilIillliilii!i?:i.liiiiiiii!ii!iI!l!liiilliillililii?:iiiiii?:_!!_ [!


_.f_!_.':_!_ ::i_.:!ii:!:-1,':!: _:_.! ::::::::::::::::::::::::::
::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::

_:_I1_ iii i_i_ii/_.i/.)_il i..-.'._ >_i !i:if i!-i:il-i! ii_I"


!

lilil!lllililiili;iliiiiii iliii!iii_i

.>'_i:::::: i:_.:_..)._i:_:_:_i_ __._ i_!__ i_:!ii:ii!_?..i_:!:::::::::::::::::::::::::::: _: ======================== ::_;:._:_ .,.'::::::i.:_: .:::::

_:::_::_::_`_.:================================================================================== = =

Benefits

Moisture used. shock

collects

in the bag when

the double-bag-and-seal of the connector buildup, The use of plastic

method caps or

is

This can lead to corrosion when the connector

or possible

electrical

is reused

manufacturer's covers will prevent moisture potential hardware damage or injury.

thus alleviating

Key

Words

Connector,

Electrical

Application Experience

Space

Transportation

System

(STS)

Technical Rationale
= :

If the proper demated, there

method

of protection

is not used when of electrical shock

connectors to personnel corrosion

are rate

is the possibility

connecting receptacles/plug ends, and increased due to environmental effects.

surface

Contact

Center

Kennedy

Space

Center

(KSC)

Page OPS-9

Electrical

Connector

Protection, Page 2 Technique OPS-2

Electrical Technique

Connector OPS-2

Protection

Reference KSC-DE-512-SM, Engineering Rev. B, Guide for Design Support Equipment.

of Ground

This practice ways: Provide

can be implemented

in two
D

instructions

in operations

an__d

_ ' " II

maintenance the connector

documents after use.

for protecting (A step should _i:: _:ii_ " _

be included to inspect the c_ofs for corrosion/debris and provide: direction for corrosion/debris removal,

_i : _ "'

_
I

necess_i) if E-S-D--_-ac-once-rii, do not Use generic plastic_cal_"_i_'(he=y can be ESD generators. be used. ESD-approved _ ..... caps should Provide connector, connector

.:._::

placard or tag on or near stating method after use. to leave


I

L_

Page OPS-IO
===_l m

II

Robotic

Removal

and Application

of SRB Thermal

Systems, Page 1 Technique OPS-3

Technique

When

designing

robotic

systems optimum

for removal attention sequencing,

and application fixture and protection proven design

of thermal indexing, against hardware and operation,

protection precision robotic

materials, positioning,

pay close

to support By integrating

cell environmental

conditions.

and software practices with equipment and facility the effectiveness of robotic systems is ensured.
=

i_i_i_i_ ..... L_ !iiiiiiiiiii!/iiii/iiiii_:_ .........

#"_i _:_liii_ii_i_'.-"ii-'.'i

_i_::':::'::_i! ':':':':::_i ........... i"


:_::'.':_:_:'_ _:i:_:_ : _::_::.:. ============================================

::!!_:::::::::_ii::::_!!i::_i_il

z m

i__li_i_i.:..":..:_::_i i_ii_'.-i _li_i_iiiii i_ii_':!_ i_ ::::::::::::::::::::::


!:_ >.._:_:_:_i:_i_:_:i.,' _i::.'_i:_.,.': _ ._; _-_:_:i:_:i:_:i:_:_: :::::::::::::::::::::::::::_ :::::::::::::::::::::::::::::::::::::::::: .: ...-..._

;.q.>._:::::::::::::: ::2_ : :_:>.::_. ::" ::_ ::.::::.-*_.-::::::::_: ::_.:.:._::_:i:::i::!:!._:_::3 :.'.':::._ _.::.'::_._:!:::_!ii_'," !!_!.>-_!i_i_i

Benefits

Adherence

to proven

robot

cell design

and operational

practices

will

result in improved consistency, and increased cost-effectiveness


w

speed, safety, precision, and reliability of robotic systems over manual or

semi-automated
= :

processes.

Key

Words

Robot, robot

robotic

removal

of insulation, operational

robotic

application

of insulation,

cell design,

and robot

practices.

Application Experience
s

Space

Shuttle

Solid Rocket

Booster

(SRB)

Technical Rationale

SRB refurbishment robotic other shows under insulation SRB elements. removal.

operations removal

at KSC have schematic

resulted depicted

in the successful in the description critical operation, and, for 5 years

and application

of 68 SRB att skirts and

The facility This facility

the SRB ait skirt in its most routine maintenance,

environmentally

insulation

has been in operation

has been operational has been experienced

since its inception. in the robotic

Similar reliable operation application of insulation.

Contact

Center

Marshall

Space

Flight

Center

(MSFC)

Page OPS-11

Robotic

Removal

and Application

of SRB Thermal

Systems, Technique

Page 2 OPS-3

Robotic Thermal Technique

Removal Systems OPS-3

and Application

of SRB

the SRB structure positioned (with breathing

and the turntable

were equipment)

d
IW1 l

into the spray cell.

A technician

air and protective

was required in the spray cell during actual spraying to take thickness measurements, When the SRB is recovered for refurbishment, Space Shuttle from the ocean, and reused flights , several assist in unplugging remove specifications. meet a flatwire pounds delivery in S_ requirement. the spray gun, and disassembled on subsequent the wet insulation, if it did not meet

gi
N

layers of insulating materials and protective coatings must be removed and then reapplied. of robotic Experience systems has shown for insulation by a factor that the use removal of 10

The cured insulation had to tensile test of 50 to 100 thickness were made to the reapplied of the required Adjustments

and _ f01eranced system

IB

and the insulation and insulation

and application most operations to 1. Originally, insulation

will improve

productivity in excess

until it met specifications. structure for spraying many man-hours. After automating

Preparation

the applicationofthe (see Table 1) were

was a semi-automatic

operation. and robotizing the


i

The nine ingredients

measured by hand, placed in a large and mixer, and mixed to a uniform consistency mixture required for spraying. was pressurized and delivered

blender This to the

application ingredients blended,

of the insulation, are automatically pressurized

the insulation measured, and delivered to on a gantry

mixed,

the spray gun, which

is mounted

Table

1. Ingredients

in the SRB Insulation

robot. The gantry robot allows spraying inside the structures without the need to rotate effector sanding, spraying, the structure to perform cleaning, for access. the following inspection, The robot attach masking, of operations: is programmed to automatically an end-

=__ u

1. 2215 Adhesive 2. Ground Cork

parts A & B*

3. Glass Ecco Spheres 4. Phenolic Micro Balloons 5. Chopped Glass Fibers 1/4 inch long 6. Milled Glass Fibers 1/8 inch long 7. Bentone 27 8. Ethyl Alcohol 9. Methylene Chloride/per Chloroethylene shell

and thickness

measurements.
i

Automating and robotizing the application insulation eliminated the need for a technician in the spray cell and eliminated many of man-hours of hand work. At the start of the SRB refurbishment program, the insulation was removed manually. manually This required hold a hydrolaser psi. of 72 pounds every a technician pressurized a force that the using to to

[] [81

The original adhesive that contained z Catalyst was a carcinogenic

spray gun, which mounted structures sanded, structure turntable, operation robot were cleaned,

was attached in the spray cell. prepared inspected,

to a pedestal The i.e., SRB SRB

8,000 to 10,000 backwash technician crews insulation

This created

by hand, The

had to overcome

two 2-men Any was


== I

and areas masked

rotated

15 minutes.

that did not require

insulation.

left after this operation

was mounted on a portable which was cooidinated with the of the robot and spray gun. Then

removed by hand using nonmetallic chisels and mallets. Manual removal of the insulation from the two aft skirts required

[]

Page

OPS-12
m i

Robotic

Removal

and Application

of SRB Thermal

Systems, Technique

Page 3 OPS-3

m i

=-

/
_ Robot Arm Position for External Insulation Removal (MSA-2) Robot Arm Position for External Insulation Removal (MSA-2) Robot Arm Position for Internal Insulation Removal (Insta-Foam)

Figure

1. Example

Robot

FaciBty:

SRB Insulation

Removal

Page

OPS-13

Robotic

Removal

and Application

of SRB Thermal Systems, Page 4 Technique OPS-3

approximately 400 man-hours. Procedures for Robotic Removal Robotzing the removal of the insulation reduced the man-hours for two aft skirts to approximately 64 man-hours. The hydrolaser is mounted on a gantry robot which is located in the removal cell. The pressure to the hydrolaser has been increased to 12,000 to 15,000 psi. Technicians have been eliminated from the hazardous environment. The robot is controlled by computer. A turntable (also controlled by computers) is mounted flush with the floor. ARer removal of the insulation, the robot is programmed the hydrolaser cell. to clean

considered in areas where the water has a high mineral content. Since the water used in the insulation removal process is recycled, the water must be filtered prior to reuse to

Table 3. Best Practices for Robotic Systems


1. Gear Specifications to the environment application O D , adapton to a solvent spray and debris-laden environment). Pay close attention to the ergonomics override, 3. Provide sapport op_ational Design-_ and toaching procedures). for and in and the or water for o_ratorz

m m

il
[]

(L_, convenience ofconu'ob, visibility, manual


SUffu__.nt sit_ac in robotic facilitles equipment, mechanisms, personne_ control stations. automated shutdown

4.

to be activated

5.

the event of excessive flow, pressures, temperatures, or inadv_nt ingress of personne& Consider the use of visinn systems for alignment, completion menxur_. Provide delicate status, inspex_n, and thickness and tao_la feedback for

Table 2 lists typical reasons for using automated robot cell to apply and remove SRB insulation. Table 3 is a list of the 13 best practices in the design of robotic systewg for removal and application of insula:.on. The most predominant consideration was the high pressure water spray and debris environment encountered in the hydrolaser insulation removal process. Operational maintenance, as well as design, is important in maintaining a safe and

oveslaad sensing operaffons.

7. 8. 9. 10.

Retain manual capability for emergency and backup ot_rations. Establish precise automatic indexing of fi._ur_ with workpiece and robot to minimize setup time. Provide electrical grounding of all system elements. Purchase over-rated equipment Use only 75% or less of the capa_ in the _ design to provide grovteh potential and operatlonal/maintenance margins. Protect robot e2ements from solvents in the environment to ensure continued robot iubricatlOrL Train and use dedicated operations. penonnel for robotic

|
i

11. 12. 13.

Establish preveutive maintenance requirements during the design phase based on designed-in of maintenance features (t _, proper panel calibration test ports, eq_meut clearances,

ease

access, ct_).

table 2. Typical Reasons for Using Robots


m m

1. 2. 3. 4.

Man out-of-the-loop toxic environments.

for hazardous

and

Eff'wien_" robot does not get tire& Will do whatever it is programmed to do and will do it repeatedly. WHl handle various end effectors for sanding, cleaning, inspection, spraying, and thickness measurements.

prevent erosion and corrosion and spray equipment.

of pumping

efficient operation. Potable water is used to reduce corrosion in thepumps, valve_,_ and lines. The use of de-ionized water should be

For the SRB insulation system removal, the water is filtered tc, contain particles no greater than 5 microns. On a quarterly basis, or every 100 operating hours, high pressure water pumps are inspected and overhauled if necessary to repair or replace the pump head, pistons, dr brass _s[eeves. Preventive maintenance is performed regularly.

U
U

Page OPS-14
u

Robotic

Removal

and Application

of SRB

Thermal

Systems, Technique

Page OPS-3

Facility A robotic insulation

Requirements facility removal design of the type used for SRB and application for personnel During must of the process safety and are after the noisy removal Operators

be considered operations. Special Robotic effective emergency changeout, feedback, features system robot Design

for material

removal

allow operator and careful access process, required


w

visibility

Considerations lend themselves of automated automatic sensing, override. end-effector These of the tactile into the robotic to the

systems

provisions. personnel

application shutdown, overload and manual should at the outset

within a 50 tt. radius

to wear ear protection.

entering the area during or immediately spray operations are required to wear protective suits with self-contained inhalation apparatus to prevent with toxic fumes. Facility or contact

be designed Setup

breathing

with participation

vendor.

time can be minimized or automatic between systems the or equipment, should positioning tooling

by providing indexing coordinated operations work piece,

pre-engineered support While

and relative

design must be carefully design and robotic

with robot planning. approach systems operating engineers applicable


w

and robot.

mechanical

A concurrent engineering is desirable in the design of robotic to ensure use of the correct designed A team of representing be assigned design and of the (1) through all full robot, facility, in an optimally application. and technicians disciplines Three

be over-designed for extra margins of safety against wear and malfunctions, Care Should be taken not to grossly overdesign control system memory, memory is used. robot control particularly This could if a bubble result in slower

for the target

system

operation.

should throughout levels

time to the project operations. robot/facility components, integrated

References 1. Rice, Automated Company, NAS8-36300, Robert: Hydro Process Removal USBI January Report on the # Production contract #

of drawings

complex system

representing: proceed

(2) subsystems, should design

and (3) the reviews. design

of TPS, Report

USB-ATG-003,

Booster 1986.

30, 60, and 90 percent


w

Inc., NASA/MSFC

Three-dimensional simulations using

solid modeling computer-aided

i W

techniques will dramatically speed up the design process. (See the MSFC Guideline titled, "Concurrent Systems," Preferred and Test"). equipment, storage, dressing attention Sloped Engineering in NASA The facility pumping control stations, Reliability Guideline TM 4322, for must contain Practices systems, and for Aerospace "NASA Design support

2. Loshe, Thomas: Hydrolyzing in High Pressure Wash Facilities, Maintenance Document Center, Manual Prepared October # B8598, for Kennedy

Operations USBI Space

-_-__

4, 1991. Solid Rocket Booster # 10MNLApril 2,

3. Loshe, Thermal Software 0044, 1990.

Thomas: Protection Users

material personnel
[J

Removal

System USBI,

and clean-up. should concrete be paid to debris subfloors provide and clean-up. techniques should

Guide,

Document

United

Technologies,

Particular handling.

for easy debris collection Automated cell clean-up

4. Babai,

Majid:

Robot Aerospace

Simulation

and

Manufacturing,

Engineering,

Page

OPS- 15

Robotic

Removal

and Application

of SRB

Thermal

Systems, Technique

Page OPS-3

SAE, October 5. Fertig, Robots TABES Huntsville, 6. Special

1992, pp 11-13.

Alan R. and Tony S. Humble: Space Shuttle Societies Hardware, Huntsville (HATS),
tim I

Refurbish Conference AL,

Proceedings,

Association

of Technical 1987.

Goyermn.

en_t Pub li_cations: Maintenance Maintenance/

_,_ Gantry

_:

MM B8601, Robot MM B8604, MM B8611, Manual MM B8616, MM B8630, Operations

Preventive Preventive

and Controller End Effectors Manufacturing Assembly) Manual Tunnel STP 513, ...........
m g

Validation Robot
(Forward

SRB Insulation

SRB Aft Skirt Assembly-MSA-2 MSA-2 Manual Cover Assembly : _ .

TPS Operations

Cleaning

Sprayable MSA-2 Insula_o n Spray _ ___ STP 621, MSA Control Room Operation STP 622, Installation End Effector Control Room Adapters MSA-2 System Insulation Preparationand Mix Spray Operations STP 634, Sprayable TP 741, MSA-2 and Removal of Robot

|
m I

ARF
SESP Robot (Safety Systems Engineering Safety Standard Requirements for Procedure) 23405,

[]

L_

Ill

Page OPS- 16

GHe Purging

of Hz Systems, Technique

Page 1 OPS-4

Technique

Prior to venting (GHe) sweep operations

a hydrogen purge

(H2) system, initiate Hr a second

initiate a gaseous GHe sweep valve purge

helium venting to evacuate valve on

to evacuate

air from the vent line. Use a flapper

After

are complete, of residual

the vent system

or check

the vent line to prevent air intrusion intermittent flow conditions.

into the line during

low or

=_-= r w

Benefits
w

Key Words

Purge,

Hydrogen,

H_, Helium,

GHe

L_.

Application Experience

National

Space

Transportation

System

(NSTS)

Technical Rationale

Use of dilution purges when is not necessarily desirable.

venting

explosive

gases

such as hydrogen

Mixtures of H2/I-Ie do not become mixture is 91% He. For "fuel rich" hydrogen/helium limit increases is obtained. with increasing

non-flammable

until the

mixtures He content,

in air, the flammability until 85% He mixture

Contact

Center

Kennedy

Space

Center

(KSC)

Page

OPS- 17

GHe Purging

of H_ Systems, Page 2 Technique OPS-4

GHe Purging Technique

of H_ Systems

Reference H. Hannah, LSOC Purge 32-30, Study, FCSS Hazardous dated September
J

OPS-4 Commodity 1991.

This technique

recommends

initiating

a GHe

sweep purge to evacuate air from a vent line prior to venting a i-i2_s-ystem. After the initial venting operation is complete, a second GHe sweep purge_should be_ conducted to ;_ evacuate the Ventsystem o_re_duaiH2. The upper _ure Figure flammability iS lower limits of a gaseous _th'no GHe_r_sen_(_g/_ or check low or valve ---:_ ....
-;2; ZZS

Ill

......

II

H2/ai r _-....
!

1). A flapper valve

used on the vent line will prevent_ air_....... intrusion into the line during intermittent flow conditions. This practice systems should _

IB

be included

in all -newand changes

i
aim

operating

procedures

initiated to applicable existing procedures. System design should be reviewed to include the following TM X-52454 as recommended (Lewis
......

by NASA Center):
i .

Research

|
m
N I m

Include a check valve/flapper valve or other suitable mechanism to exclude air from vent stacks flow conditions. Extend building vent stacks roof. use of ordinary which a H2 flame. a minimum (pulse of a 3-volume to sweep system
u

at low or intermittent

15 tL above

II

Discontinue flame arresters quenching Provide exchange prior

hydrocarbon of

are incapable

purges)

to introducing

hydrogen. to purge a vent


M m

Five to 10 volume system practice.

exchanges

is a commonly

acceptable

industry
ull

Page OPS-18

GHe Purging

of H_ Systems, Page 3 Technique OPS-4

o
w

"Iw

r_

Figure

1.

Limits

of Flammability-Mixtures

of H2and

He

Page

OPS-

19

r.
mm

Z_

I
.ram

H
g!t

DE_
I

mw

Programmable

Logic Controllers, Technique

Page I OPS-5

Technique

Use solid state Programmable system/equipment design

Logic

Controllers and monitor

(PLC's) systems

in and processes.

to control

......

.-.,.,:?_i:%qiliiiiiiiiiiSitii!!iiiiiiiiSiill /

:::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: II_!iiiii/liiliiiii/ili_i_iqiililii_iiiii/i!iiiliiil_!i_ !!i_ lil_i$!i!ii/_/i/itii i$/il!i!_/!I !!!_iiiql is!il_iiit_!_!! _!i!_i_i_$!@!i_t!li!i!!! _i !_ !!! !_! !ii! l/_ii !_!/_!i_i

iii_!iiii/i::_iiiiif/_iii::iiiii::ii_i!ii_iii."..ilili/ii
L-w

11 !!/ill liil fi//!i

._ _..'_!:_:.:_ :[:_._:.. ._:::$::::.::::_::!:!::.

::_ ?:.:::_:!,_::::_ _:_ :_i::/_::::$ :::::_:_:_,'.:_:_:i: I:::::: _:!:::_ii_: .-:::::: :::: :::_ Sj:::.'.::::.s:_: ============================================

ilili!iiiliiiiiiiiiiiiiiii!iii@iiiii!i
:::::::$ _:.". 8::= _.::::::$:::::::::::8::::: .'.'$:: $::: ::::::::::::: :_:: :::_: ::::::::::::::::::::::::::: $._$::::::::_: :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: ::::::::::::::::::::::::::::::::

##::/iiiI@#..iii#:@iiiiqiiiii@iii!@_!ii@i@it_!_ ::l!_/i/iiii/iiiiliiiii::@::::iiiiiiili_iiti _iiq!i::i!iiiii::i!i@_::_:;:;i_F:_


:_._$L_:::::::_::::.":: :::::: :::_:::i::::::: _ : :
"_f.:: $_:::.'.::!::::::::::::::::'.'..: ::::::::::::::::::::::::::::::::::::::::::$ :::

._._

:::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: :::::::::::::::::::::::::::::::::::::::::::::::

..::::

!i_@_iii_Ii_i_i_i_!_ii_ii!@i_ii_!iii@iiii!i_i_!iii_iiii@]iiiIi_ iii]!l!!i!li!i iii@ liii !i I!


e

_i!i___ i;!:!_i_!_!_::_i_q_ilili_.'.:!i_@!T'F#ii_i:_!i ............ _:"_::_!._!i_il ii_i_ii _ #_i_:;ii; i_!Y' _i_':"!!!._:':'r_:_i!i_i_ _i i!iiil_!!_!! _:'_.<_i_ili_ iiii_i_;_ili

Benefits

System/equipment design using PLC's is a prime example of the application of maintainability design objectives. PLC's are designed with ease of maintenance and troubleshooting When virtually all components are solid state, as a major function. maintenance is reduced detection to

the replacement of a modular, plug-in type component. Fault circuits and diagnostic indicators, incorporated in each major

component, can tell whether the component is working properly. With the programming tool, any programmed logic can be viewed to see if input or outputs are on or off.
w

Key Words
i

Controller,

Programmable

Application Experience
w

Space Transportation Systems.

System

(STS),

Facilities

and Ground

Support

Technical Rationale

Conventional relay-based control systems are more and cannot handle complex processing as efficiently PLC's in system design will reduce failure rates downtime, ultimately saving a program money.

subject to failure as PLC'S. Use of

and subsequent

Contact

Center

Kennedy
z

Space Center (KSC)

Page OPS-20
w

Programmable Logic Controllers, Page 2 Technique OPS-5 Programmable Logic Technique OPS-5 Controllers Table 1. Typical Programmable FeaturesBenefits .,,
High

Logic

Controller ..... Features


State Components

Benefits
I reliability

PLC'S

provide

control

capabilities

not are

Solid

possible in the past. Control incorporating programmable

systems controllers

Programmable Memory

Simplifies changes Flexible control Minimal space requirements

now able to operate machines and processes with an efficiency and accuracy never before achievable with conventional relay-based control systems. Usually, PLC architecture is modular and flexible, allowing and software elements to expand hardware as the

Small Size

Ill

Microprocessor Based

application requirements change. If an application outgrows the limitations of the PLC, the unit can easily be replaced with a unit having greater memory and input/output can be reused capacity, and the old hardware for a smaller application. PLC attributes cost effective. make Their

Communications capability Higher level of performance Higher quality products Multi-function capability Eliminate hardware Easily changed presets Reduced hardware wiring
COSts

Software Timers/Counters

Software Control Relays

installation easy and small size allows PLC'S

Reduced space requirements Modular Architecture


Installation Easily flexibility

I installed purchases
u i

II

to be located conveniently, often in less than half tt_ pace required by an equivalent relay contro: _,anel. On a small scale changeover from relays, the PLC'S' small and modular construction allows it to be mounted near the relay enclosure terminal strips. and pre-wired to existing Actual changeover can be

Hardware minimized Expandability

Variety of I/O Interfaces

Controls variety of devices Eliminates custom control

|
w

Remote I/O Stations

made quickly by simply connecting the input/output devices to the pre-wired terminal available slrips. Table 1 lists some and benefits of PLC'S. features Diagnostic Indicators

Eliminates long wiring conduit runs Reduced troubleshooting time Proper operation of signal
Neat panel Easily Easily maintained wired
i

In large installations, remote input/output stations are placed at optimum locations. The remote station is connected to the processor by a pair of twisted wires. This configuration results in a considerable reduction of material and labor cost that would multiple have been associated and conduits. and Operation of size, complexity, set of parts. others Some with running wires

Modular I/O Interface

appearance

of control

Quick I/O Disconnects

Service w/o disturbing wiring


i

All System Variables Stored in Memory

Useful management/ maintenance Data can be output the basic

PLC Components PLC'S, regardless cost, contain the parts

or of

or programs. parts supply Page OPS-21 system

Figure

1, identifies

a basic

_-I I

of the PLC.

In addition

to a power that is

are hardware;

are software

and a housing

II

Programmable

Logic

Controllers, Technique

Page OPS-5

--[PARTS

OF A PROGRAMMABLE

CONTROLLER]--

Signals

From

Process

INPUT INTERFACE

. w

PROGRAMMING TOOL
z s

1
PROGRAMMING LANGUAGE

Signals

to Process

Figure

1. Parts

of a Programmable

Controller

appropriate environment, parts:

for the physical PLC's memory programming consist section, interface,

and electrical of the following processor programming

The Processor intelligence operating a pattern

and Memory. of the PLC.

provide

the main as

Fundamental is stored in memory into

an input

central

information

unit (CPU), language, interface. The Input the machine The principal receive

of bits that is organized

tool, and an output

working groups called words. Each word stored in memory is either an instruction or piece of data. The data may be reference data or a stored signal from the process that has been brought in through the input interface. The operation of the processor and memory fairly_simple of the PLC can be described repetitive sequence: as

Interface function

provides being

connection controlled.

to is to

or process

of the interface

and convert

field signals

into a form processing

that can be used by the central unit.

Page

OPS-22

Programmable

Logic

Controllers, Technique

Page OPS-5

Ig

Look

at the process

being

controlled.

still popular. Boolean the base

Alternative

languages control

use as

This is accomplished by examining the information from the input interface. Compare information program. 3. Decide needed. Execute the control signals action by to the output whether any control action is the information supplied with control in the

representation of the computer Tools

schemes

representation.
IB
m

The Progr.amming between concepts particular selected symbols, of electrical programmer devises program PLC. letters, signals

provide

connection The
i

by and stored

the programmer and then translates

and the PLC. control them

the necessary form required that corresponds by humans.

into the by the the pattern to the of


m m

The tool produces or numbers

in the version

Ill

transmitting interface. 5. Look again

the program

that is used

at the inputs. continually in memory refers to the

Process Improvements The use of control and monitor with the benefit ofa PLC could Increased system availability

equipment lead to:


m

The processor program concerning data. The Output stored

for instructions and for reference

its next action

Decreased downtime requirements recover from a failure Decreased hours cost in materials

to

il

Interface and translates

takes signals them control

from the that by and manI

processor

into forms actions

are appropriate to produce external devices. The Pjo_am program the PLC. the actions desired process sections and Pro_am The program output control

for installation system visibility to meet new


M

Increased Increased

Lan_age. is a representation to produce

The in of the Reference National Technology Transfer Inc. (PLC Seminar, Aurora, Colorado, 1992) flexibility requirements.

is written

by the user

and stored

that are necessary signals

for a given

condition. The program includes that d_e_t_h - bfi_nging_the - prgccss memory, making, sections and sections into decision action.

data into the controller that represent physical output that deal with converting

the decision Progi'amming

languages have many forms. Early versions were restricted to mat_ch the conventions of relay logic which that consisted of ladder closure types a _ are diagrams specified contact

and coils. This type 0fprogramconsistsgf representation of a relay logic control scheme. The relay ladder language

types

Page

OPS-23

DC Drive - Solid State Control Technique

Page 1 OPS-6

Technique

During drives,

the design of new (or upgrades to) motor generator consider the use of solid state assemblies for control

set type DC functions.

i:._:_:._::i:i:: : :_:_:.'.: _ __:-':.'.,: _._::_i:_._. _:,':.:_::..:._: _._:: :A_:_:_:_ ." _:'._,:: _:.,'_:.<:: :-'.:':_:_:.: :_ -,.'::: _i..-. _:_.:_i:-: :?.i:-_ _.,.':_:_:_._ i_ii:i:ii_i_::i:_:.::,._._ _._i_.__'i:,,.'..'i::_:::.:i.:::_-,:.'_:i.,:?:_._.,:.-.':_ _ _..': ?_::_.:: :__::_:_::_ :_.'..:::_:._: _,_i:i.,.',<_: .:.::_5::.;_ _: ._:_" _'.-_ _._:$:_::.:.::::.z_.:>..::._:_:::_:_:"_ _::_...._.._:..%%_.._.__.'.2_'__'"<'" _._::'::_'_:+:_"_'. +_':'.'._':_'-':':'-':':'::_'::_:::-_::_'. .,._.,,._:.:.li_ .:-._..:,._ _':'_':_.:::::_'_":_ _:::_ _.."._i_ _._:_:::i_::__<:_:_:i::".".:_"-':_:_::_:::::::::::::::::::::::::::::::
w

i:_.%'! ::::::_ :-:::_::: -_ll_l_l[_

=============================================================================================== :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: -':._:::-.":[:::::::-:-:::-:::_:::':::+_::'._: _''_'>'_ "',' ._i.?.'i_._ :_:._.'..:.::.:..'.::!:'_:._'_:._:_

: _,,'..::'_-:::"-:"-"-_.:'_:_ _.::.?::_:."_::::::::::::%_?-._:_:i::_:::_5_:::::_:i:_ >:'_ _:__:_:_:_::_:_-.'_::':::::::: : ::.:_:::._:_::_?_:..`.._.::_:_.z_.:._..(#.:_:::::.:'_::::::::._:_:_._%::::._:._:_:_:_::_:_:_:..._:_:_:_._:_i._::_::::_::::_:!:_:_::_:_::_:_::_:_

_i..".-"_i:'.:'_
:_:_:

_ _"_:_:_!_'::_":_i_:_:':_r_': _'"_i_':"_';_:_:_:_:;_r":i:':_:;:_':::'_:':_::::''_""e:::_: ........................ _: _"

_i-i_::i_i_ii_,_i ........ ,-.'.,-':_-':;-_._.-.'._.-'_-'-:-: ". :__:.::i_':'_:i:'.':_:'-:_:_::':i::_


_ :.:.'.:_.:.._: _:.'.: _.:._,.': k+.'::.-.:i_ ": ": ":'_:':':'>:_<':':':':':"<:::

::_,,.-.'.:: :-'.:-:-:.-,.-:.:,..:-..: :_ ::::::::::::::::::::::::::::::::::::::::: :::_.-_:::.,'z_.-. ".-.:.::_.._:_._.::_:_._:e:::::_.::_._:,_.::::-_..:.:,..'.-:..-:::.:_:.:--::.:.:.::.'-::.'._:!/_,::.-: :_::::::::::::::::::::: :_:_ .'..'.:.'._.:_::::-_.:_:,. _ :_:_ _::t.'.'_:"_:."._:_::_:_:_+::_:_:_':_:_'_ :::_._:-'. :_.-_::_:.'.:_.-'_ _:_-_._-.'_::..-.':.'.:--'._ ::_:_``._.'._.._*:_`...:_..:'.._:_:_:_:_:.:.;'._.'.:_::_.._:_.*._.`_:_:'...:.'.-r.._::_:::: :::::::::::::::::::::::::::::::::::::::::: :_::::_.:_::.-'_._:_ _,':_:-_:"-_-':"
w

: _.'..'..-':.:_:!_ " :_:_'_ "_:_-':.'_-_:!_:'.:'_:_:_,_

_,'_ :.'.:_ :e_,-_ _:_:_"':_:-'_":::':._.'::_:.<_?...'_:_:.,:._..:_:.::':..-'::_ _: _'_':._.-'._ .'.:_ :: _::::::i:_::::".:_:" :;" :_:-_ :_ ::::::::::::::::::::::::_"_:_':,' ::::::::::::::::::::::

[::._:_-":'_ _i:i:i :'"_'::_: :_: _:::': _ _:.:::<-%'::i_ _iii_-_i;_t_i!: :i!-_i!_!'_'_:::_::._:'.._.":'.':,.'_:!!;_-".:-":;_'i_.:_."_:.:_:i!ii_!: _i_: :_::_:5_;_:_:_[_::_;_:__:_:_;_;_;_;_:_:_:_:_;_;_;_;:_:_:_;_:;;_;_: i_;.'.Z:i_i_iii .:.:<.>:<.,-:.::-:.::-:.:-:.::::.:::::::::::::::::::::::::::::::::.:-::-:::..,

Benefits

Use of solid state controls system restoration detection, modular

instead

of magnetic

amplifiers

can improve

time in the event of a failure. construction, and packaging

Features such as fault can be easily employed. resolution can result can also be in improved

Diagnostics for system health status and problem readily provided. Incorporation of these features system performance and availability.

Key

Words

Solid State Assemblies, System Performance, Availability

Restoration,

Maintainability,

Application Experience

National Systems.

Space

Transportation

System

Shuttle

Ground

Support

Technical Rationale

-:_._:

At KSC the 175- and 250-Ton Bridge Cranes in the Vehicle Assembly Building (VAB) were using metadynes (electromechanicai rotating amplifiers) for control function. The metadyne had a long history of maintenance problems because of brush wear, contamination and corrosion. It required extensive pre-operation maintenance attention to support Shuttle processing. In addition, the metadyne units often required maintenance during processing operations impacting processing schedules. KSC replaced the metadynes with solid state controller units resulting in decreased maintenance actions including pre-operation maintenance and improved system performance and availability. Fault isolation and removal and replacement of failed components is easier and less time consuming. Since failures occur at a less frequent rate, the need for numerous operating spares is reduced. Furthermore, the "off equipment" in-shop maintenance of failed units requires much less time and money to effect a repair. Reduced maintenance and downtime allow for the crane to be ready and operating to support Shuttle processing in a more timely manner.

Contact

Center

Kennedy

Space

Center

(KSC)

Page

OPS-24

DC Drive - Solid State Control, Page 2 Technique OPS-6

I1

DC Drive Technique

- Solid 0P5-6

State

Control

acceptable were rugged satisfactory for control During became Today

response operation.

rate.

However, reliable

they

and highly

once in
m I

The use of solid State assemblies functions represents a great

improvement

the early readily

1960's the thyristor available. This device to a thyiatron the direct

or SCR is
I

over previous control methods. Historically, the first methtd-tfob_taml"_figadjustabl_ ..... speed using DC motors was the constant fie! d adjustment._, of adjustment. by the rotating potential I)(2 supply using

-gi-m_I_iribperati0h it dominates field_S_ci_ regenerate

tube. drive

current

This provided This method

a small range was followed

c_cuits enable=the SCR to and reverse readily. Larger and SCR's have extended the

less expensive

M-G system of Ward Leonard patented in the 1890's. This drive used an AC motor driving a DC generator to convert AC to DC

range to well over 1000 HP. Figure 2 illustrates a controlled rectifier drive. Note that the gateing replaced reduced Solid of rotating State control and SCR bridge have in the M-G set of Figure machinery. 1, resulting

power. The motor and generator may be combined in a single frame and use a common controlled shaft, 1). or separate The output coupled units is (See Figure DC voltage

Operation the assemblies comprising a A

by adjusting

the field excitation

Figure 3 shows

El

the DC generator. accuracy required, tachometer

Depending on the armature voltage or a signal is

solid state control system for DC drives. Single phase thyristor power conver(e-tsupplies up to 200 volts controller for armature speed control positive (speed voltage at 20 amperes closed-loop provides feedback compensation acceleration to the generator field. A

may be used as a feedback

or negative

in a closed loop system. An important aspect of this drive is that power flow reversible. driving drives power The motor the generator the AC motor as a motor, which which

regulator) with IR drop

acts as a generator, then pumps This ability,

or AC/DC

tachometer and linear A firing


U

back into the AC lines.

and deceleration.

called regenerati0n, decelerating large overhauling consideration loads. when

_isa useful feature !n inertias or holding back This is a very replacing important with a the M-G

circui t prov!des an isolated gate drive to the power converter. A bi-directional adapter used in conjunction assembly provides with the fuing bi-directional circuit current to

conventional packaged rectifier (SCR) drive. In the late 1940's, began to replace vacuum, thyratron, tubes for armature limited ratings. replace acceptance cooling and water

silicon-controlled

the field of a DC generator

for contactoriess

reversing or to regulate to zero output voltage in the presence of residual tube drives These used had magnetism circuitry of the DC generator. includes a voltage sensing Protective relay for
w m

electronic M-G drives.

excitron, or ignitron circuit control. They because 1960's requirements on larger the tubes

safety interlocking and an isolator for isolated armature current feedback. References 1. KSC Electrical Drawing for VAB 250 Ton Cranes, 250-69-K-L-11388.

of tube life limits were drives.

By the early with the solid

state thyristor

Magnetic amplifier drives were developed in the mid-1950's when silicon diodes became popular. because They were never as widely used and of difficulties of reactor design

2. KSC Electrical Drawing for VAB Ton Crane, 175-67-K-L-11348.

175
I

Page OPS-25

DC Drive - Solid State Control, Technique

Page 3 OPS-6

3-Phase AC Supply

-I-

I, x I c,cer
i I....looenora'orl I
Figure 11 Rotating M-G System

Supply
u r_ t_

SCR GATING AND POWER CIRCUITRY

DC MOTOR

Armature

Voltage

Feedback

Figure

2.

Controlled

Rectifier

Drive

Page

0PS-26

DC Drive - Solid State Control, Page 4 Technique OPS-6

I lUnum

11

+6V

-6V

SIGNAL ISOLATOR

SPEED SPEED CONTROL INTERLOCK


1

AC/DC TACH (OPTIONAL)

Figure

3. M-G

Control-Reversing

Simplified

Schematic

Motor

Generator

Page

0PS-27

AC - Variable

Frequency

Drive Systems, Page 1 Technique OPS-7

Technique

During motor variable

the design speed frequency

of new or modifications consider drive systems for motor

to existing control.

systems current

requiring (AC)

control,

the use of alternating

r::_.:'."t ............................................ _,_!_!._._._,_,__:_i_#_ _:_ __._:_:'.-.';. _:_'#_,_i_!_,_

b.'_:

_ ," :,"_:i:i_:.:_:_i:_:.':::'-'.':_i.'.:_i_::'.i_::i: :::_: :_.'.'_.:: .';:: _.:._'.'_-'.':._ :_:!:::,: _,':_ _._,'_i :-g_::!::._::`._.``.:_:__:_:`.:::_`::-_!`.`....i!`.:_:::_:_:i:i_i:_:_.. _:.:_:_ :. _'_ , ................... .......::?.., .......... > .......... .:......:._.....,:.......,. ,.....:..............................:_...,..............+

_._:_:_ _:._: _::,,_:_r.-:.,":_ :_: :i: _-:_:._: ._:_,.-'_ @'_ ___ilil_!,.:':_...,.'_ i:i_.'::_:_'.-'_ _._.::_i:_! _-:;_.,::_!'!:.-'._i _ _!,_ _'.'." _._ii_ g".'.'_b.". ___."." _:_:_" _,'_,_ _-:_ ._':._ :_!_ :::: _._.:::: _._.'-:-'; _ _:::.._: ._-':"..'.:" :- :_: ..._: ',:: ......j-, ":.:_iiii:_ :_ _!:: ':._:_ _!_i_...'_i_iiii_._
,- :._:.....,-..:.-.-...,-+:.-...-...'..-..q _ ......,.,...:.:+-.:. . .::.,.

_-:."::_:_'!.".":'_:i_ii_'i"_!i_':"""';:::'i-":-":_:"_i::..i:..::iii: :_i_:."_:: ::_::_ '.-":!:: i: :_[i_i..ii!!i: ..i ": .? _,i_


"_1_" ===================== :::::::::::::::::::::: :.q::_ :::..::.:::::: :..'::::._::..,:.'::,, _._ :::::::::::::::::::::::

_::;_,_:'.:?:._-_:_'_:':L.':_._'_r.,._ _..'.'.._ _:::::._:_:_:_.`..:.:_:::_:_:w._:.._r_.`._._.:_::::::..`..::..`._:._._i_ _,_:r_:_..,. _::,.:_ :::::._--..._.-_._::_::_.:::_:._:.`.._:..`._:.`._..:._:..``..:_:_.:_._.`_i. _!-_::::.S':.:._::._:.:,' .:_:/.':.::::::_::::::. _: .:. ' : .... : .:' : ":::_:_: i: : ?``.:`.-_.?::._::.:.:::.:[:.``._;_:.`._..:_8.::?.:...:.g.:?..`;..`.:.::.:._:_:.._.`._:[_:_(_::
":::: ::::' :.. ":::: :.:::: .:-. :...:. ::::::::::: ::: ::::: ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: _'.-_._!i_!g.'..i!,,'._i_)_._.::_i!_f_:_i'_;:."'_"_',

i_

''.'':''_ :::::::::::::::::::::::::::::::::::::::::::::: :._:::->._::_'"-"":":'_'_:':'_:':':':':':_::'_::'_:':',_':::':::: ," :',.:_ .':."._: ::':_':::': ::::::::::::::::::::::::::::::: _-_.:_ >::::!._:_..-.,'._:I _ _:._:::_:_..'.!:.,.':_::_:_:._ _._:._i:i._r.._ .'._-_:._:_:_:_.:._:!:_:_:::_._:_ __:, _.`.:```_.::`.:`<_:.`...._:_._._;_..._:.._;.._.``:_:_.``:_::```::;:.< __::::-'.:::-:_" " "_""::_::_:_:' _:_:_'_"::_:_:":_'_:":'_,_'_:,,..:_ :_":_:_._.,.,-:: i._:-.-.'_ _._:_-_ _:: _.,<'::_:_:_,'.':'._:_ _,,.'_:'::'_,--.':_--.'._._ _(,_._..':_.::_'_;_:'., __ _._.._.:._.._._._._._._._._:_?_:`_..`.._.._._:_ :._..'.:':_.:,:i _.._.i_ ...,.._._:-_ _;_._ _:_ _._:,.::_.,'. _'_l _-."..: :_:-.::_.:__'_._ :_$-::::_::._.,-.::::b.-:::.:._::::_:.'...::._:_._ :_:'_._::.::_.:,._:_ _':.'_:::::_:: _:_:_:i_._:: :':'::,--,_._ i:.:._::.h:"-'.:i:_"':_:" ::::::::::::::::::::::::::::: :_ :_ _:_:_:: _<:::_::': :'_:_ _:'4"::f_: :::':'_ '_#.' ::::::::-.'::: :.,.:::::::-'.:_:_:.,.:?:.:_:'_:<..'::_: _ :_:.':.:.:- -:::+ -:-- - -::-."-:-_ <.::_," +:':::.::':-:-:-:-:':':':::':-.':_'.'.::-':':'.':_:'_: :_:: -':::_ _:: _:::_::_>__: :_ :_ _:::__:. ::-::::::'::-:_-_:__`_._`<:.:_:_._:_:_:._:::_>..::._``_:.`_:i_._::::.:_i_``_``_:_::.:_:_.`_.!_::_::.(_._::_:_:._:<:::_<_:_:_::::::_:_:_:_:_:_:_::_: ':_:.::_.:.,::_._+:.-'-'_::::::_:_.':_::-'.:_.,'_:'::::::-_:_-::'_i:::: _::._.'::_-'. _._i_ _.i_ _!_'_ _., _-_ "" :`..::::_:::._::..:.:::):.:.::_:.::._.``;_?...`.....:::::_:_(:._:.::_:_._:_

::: ::.:.-.::!::._:_'4:_:_.::')_:'.':_:::_:.,":_:_.'.<'_:_: _-.'_ _:_._:).-": .:_ _:_ _:".,.'_:.-.:-:ii

-.'-_'- :- _. :'-'--'-:_ _'--'-...:"-...':..

,:.:.g<:_._':':-:':'_

_i!.:::-_'::':.:. _._

:_:-::_!?'_:_:_:_:_.".:.,_:.,':'..::_-_.:':_._!_'_ !!_i:_::.r.-.'::i_._:..::,"_:_i_[:_i

l_

:I

:_:;_:_b:'_ _._?_,'.!_:'_.,%.:'_._:!!_._I_._,.'::_ __:_:::::..:..:_.:.:_:_.,.:_:_:.<._.-"_:::: ............... -.:.:.-:._ ............ _:_.,--,,.',,::.:_._.._,_:.'. ................... _._ ......... .`._.:._.:::_:._._::_._.::..:::.`_.:_:::_:_:_:_`_.`_._:_:.<z.:_!_ ...:......,...-,.....-.. :-:,:..:...7:-:<..:+:-:..._,,..,..:..'....,.,..-4_...._..._(_.,':,,:,,:_::_.. , _:_....`....:_:.``._.:_:..-..::.._:>::_..`:?._:._!:_:!:._:!.-.......:_:!:!_:..-.._:.:_`_._:_:_:..`._:i:_.`..:_:_:_::_:_q_:_[._:_`_:_:_:i.-..:_i:_:.:::`:...`..:._:i._:_``:-:_!_.:_:.._i::.`..::.::`._:_:_:_::<:_._:_::-:_:i:.:_:i_<:i_:i:i_)i:i:i:_i:::_:_:_:_g_:__ .:4:.:.:.:::.:::.:.:.:.:.:::.:_:::.:.:_..g_%:::::_.`::::::::::::..:::::::g::::::::::_._.:.:_:.:_..:::_:.:._:_:_.:< _._:+:+:.:+:+'-'-_:_<.:<._:+_:_-:_::-:-_:-:-:.:+:-:-:-:.:_:.'.:.._._. :.::..'-:::..:...:-.':-._:.:-.-:::.:.:.:.,:': .....:-," .."._:_:_<:".%,. :'-!:.::_:_;_:'._:_,%'_:_::: _:::.'::,"::::::::::::::::::::::::::::::: :: ._...,..._:': ............................................................................................... :.......

,.f.:,..:..:..._ ........... ::>.., . ..:::..:.-... ::::....::._.::[_,_.:_.:.:.:::.-:_.:.:.....,:,::.:::, _..::_ ,:.:....:_:......-:::.,_. ':.,.::_:- ::::_.: _:--:-.-..--. -....-..-,....-_:.-..-.'..':.'-'_:::::::,._-.,%........._. ,'_ _.-_-,.,-.....,._,..._..-:::_:k::i::.:>.., ._.:-.'.:.:.:_:.-..:.:.:.:..-:._._.:.:.:-:-:.:::-.:+-:--_:._:::---:.---+,--: ..:. '..,.-:-.'.:<-'...-'-.--...--:.., :.:'-'_..:.::::::.'_.::..-.._.,,......:.-.-_.,....,.,'..::::._._ _...-

Benefits

AC variable several control.

frequency devices

drive systems (clutches enhance

for motor

speed

control

offer coupled speed in:

advantages These Improved Reduction Increased Reduced Reduced

over systems

that use DC or AC motors and pulleys) system to achieve maintainability reliability,

with mechanical

motor

advantages system

resulting

maintainability,

and performance. (manhours devices.

of preventive system

and corrective

maintenance

and materials) Self-contained

by elimination availability. diagnostic costs.

of mechanical

test capability. complexity.

size and mechanical life cycle

i..;

iJ

Key Words

AC Variable

Frequency

Drive,

System

Performance,

Availability

Application Experience
I I

Launch

Complex

39A & B, Main

Propulsion

System,

Liquid

Oxygen

Subsystem

Technical Rationale
r

Variable at KSC. propulsion the motor

frequency The system system clutch

drive systems allows liquid system, oxygen

are installed pump

at the Shuttle between motor.

launch the main

pads

for a direct coupling and drive item,

This eliminates nitrogen

a high maintenance system.

and gaseous

lines used to purge

the clutch

Contact Center

Kennedy

Space Center (KSC)

Page
w

OPS-28

AC - Variable

Frequency

Drive Systems, Page 2 Technique OPS-7

AC - Variable Technique

Frequency

Drive

Systems

The control

circuitry

in the drive turns

the

OPS-7 frequency efficiency drive for motor

SCR's on 60 times per second to obtain the desired current flow. Each time a new SCR is gated, off. it then forces a previous one to shut
I

The use of A/C variable systems provides greater

If it is necessary

to turn off all the

speed control than mechanical devices with DC or AC motors. AC variable frequency drive systems allow for direct coupling and eliminates the need for mechanical devices= such as clutches these mechanical maintenance Adjustable advantages simplicRy, maintenance motors. adverse explosive locations. speed and pulleys. Elimination of devices results in decreased and repair because costs. of i AC drives also offer many andi0w 7

SCR's, all gate signals are removed and the SCR's then turned off naturally when the AC input
7=

voltage

is reversed. is so called the inverter Electronically that filters and provides because and it is an of
i

The DC link module a device converter inductor u_f0rm module. a constant that connects modules. or choke module

it is

downtime

the output

over DC drives high-speed requirements

the converter

a more

capability,

of induction

flow Of current to the inverter Since the inductor tries to maintain flow of current through it, this
I

These motors are suitable for conditions such as dirty air, atmospheres, and inaccessible

allows the=voltage source converter to function as a current source to the inverter module. The inverter module Here takes the filtered and converts are gated, the SCR's DC it one

Components Typically, an adjustable system consist module,

frequency

drive

from the DC link module back to AC. after the other, steering

for an AC induction motor will of a converter module, DC link and inverter The module. configuration The following frequency shown and the of an adjustable

this DC into and out the

is a description drive system.

of each of three input lines to the motor. The faster the SCR's are fired, the faster motor turns. Since

the AC line is not present


= =

the type of control scheme used classify drive as a current source inverter type. Figure 1 illustrates three fundamental used in converting the AC input variable AC output. The converter programmable module into a

here, external commutating capacitors are used to ensure that each time a new SCR is fired, an old or previously shut off. Drive Operation The following paragraphs some of the characteristics a. Output voltage conducting one is

steps

can be thought source

of as a the

DC voltage

where

briefly discuss of the drive: normally

three AC input lines are rectified by silicon controlled rectifiers (SCR's) to provide a variable DC output. An SCR can be thought of as a controlled rectifier or switch that lets current gated again flow in the forward or opened. Then until the flow reverses the SCR regains capability until gated direction or ceases. its forward again. when At it cannot shut off

and current

delivered to a motor are both sinusoidal. operating inverter the motor (see Figure

from the AC input line This is not true when from a current voltage The source 1). The

[]
lid

this point blocking

waveform is closely sinusoidal with disturbances called commutation spikes. output current is a high quality quasi-square

m_ wml

Page OPS-29

II

m
g

AC - Variable

Frequency

Drive Systems, Technique

Page 3 OPS-7

ConveNer

D.C. Link t_t'yy_ i i


or

Inverter

Inductor
or

DC Choke L AC Line Reactor _. -Typical SCR

=_ r_

diJdt Reactors & Resistors


L--_

Typical Commutation

Spike

Figure

1. Simplified

Adjustable

Speed

Drive

waveform. makes output simply motor

The current voltage.

source

inverter of the is of voltage

b. Crowbar: conditions large of stored happens current,

Since which

during implies

normal a large

operating is carrying amount what to the a

no attempt a result

to define

the shape

the DC link or choke energy, should it is worth the input

The output

of the current

and rotation

discussing

the motor. waveform or decreased


L_

The shape of the current is def'med and its level is increased to obtain the required voltage.

or output

drive be suddenly disconnected. The inductor would normally develop whatever voltage is needed to maintain the constant flow of DC. To mitigate damaging voltage levels, are incorporated are based within a path for this DC. the danger of these protective circuits the drive to provide schemes

Stated more simply, the control circuitry contains an inner current regulator loop with an outer supplied voltage regulator current loop that ensures are that the proper and voltage

to the motor.

The protective

on the capability

of both the

Page OPS-30

A C - Variable

Frequency

Drive Systems, Page 4 Technique OPS- 7

inverterandconvertermodulesto providea pathfor this currentby firing two series SCR'sin the converterandinvertermodules, thusgenerating a directshortcircuit path throughwhich the currenttrappedin the inductormayflow. The process of firing theseSCR'sto providea currentpathis called"crowbar." c. Outputclamp: With anabmpt lossof load,the protectivemechanism operates as follows. The inverteroutputleadsto the motor areequippedwith a devicecalledan "outputclamp." If the motoris abruptly disconnected, the outputcurrentfrom the inverterwill transferto this clampcircuit until its level hits 950volts DC. At this point, thecontrolcirc_uitrywflIforcea"crowbar"andshut off the converter
module. performed. d. Commutation: by which conducting types power Commutation is a process Two in the This prevents any further increase is in output voltage; an orderly shutdown

very low speeds, in discrete two-pole complete reduced connected disappears References 1. KSC Electrical Drawing steps machine rotation depending load. At a frequency

the motor rather of 1 Hertz, would

appears

to move rotate. a

[]

than smoothly for example, perform one steps

in six distinct per second. The visual above on the inertia effect

at a is
i

rate of six steps

This effect of the

completely
I

at speeds

a few Hertz.

Advanced

Schematic

79K06382. Advanced Schematic


B

2. KSC Electrical Drawing 79K40029.

[] i

an SCR is forced state by reverse natural

out of a biasing. occur

of commutation circuit,

normally and forced.

e. Regeneration: two-quadrant

The SCR converter device capable

is a it to

of accepting
-'-=_ i

power from the DC bus and returning the line when the DC bus potential is

negative. This capability makes the current source inverter one of the few inverter types that are inherently excessive circuit regenerative complication.
7

without

am

f. Low speed in the inverter

cogging: module

Each causes

commutation the current stopped in


H

flow to the motor

to be abruptly

one phase and started in another. forces the motor to turn one-sixth rotation 4-pole on a 2-pole machine, etc. machine, This explains

This action of a on a why, at

one-half

[]

Page OPS-31

[]
2

Fiber Optic Systems, Page 1 Technique OPS-8

Technique

During consider systems.

new design

or upgrades

to existing systems

transmission of metallic

systems, cable

the use of fiber optic

in place

:!'_.':.'." !:!?.!._:_:_ i:!:_:'.:."_:::i/::_: ::'.::: .'.':: _::.".':i: _!_:! _ !_i ::__.._-._.-....:..::_ . _ ......... ::_.:: _......_ 4...:::... ".:/_::::_ _::":::_:."._:..: _::::')_-'.'::::!:!_:.::::::::::::::::::::::::::::::: _:_.'." _:_.".'._ __i:_:_.'.'::_::':""" """":::::,_ ::_ ::_::.'." _:._ .'._: :."J: :_:_::

================================

: ._:_ ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: _ :::: :::::::::::::::::::::::::::::::::::::::::::: ::::::::::::::::::::::: : _ .5_.'..':_:_.'.:_.'.::':.':: _::_:.:'..,:._::: .:::::_:_._::. :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: _:!:!:i:!:!:i:!:!:'_:!:':_:!:i_ [_:_: .'._::::_: :_: :.'._:::::: :.',:::__ :::::: ::: ?._.<:::: :_: ::_:?.:.'.':_:: ::,: :._ :::::::: _:_ :_:_:::::::: :_-'.':: ::::: :_:::::::: :_:::: :::::: _::_,'::') _:_:._:_:[: _!:_?.':_:_:!:i:i:!:!:3:i:_:i:i:i:'::!::::': _:::_ _:_ ?:::' "._ :.)!:i:?.!:i:_i:i_:!:i:!:i:!!i:!_?..!_:_!_:_!_!_..`._?.._:_i[_i_!_!-...:ii_:_:i_ii:_i_i_i_:_:_:_:_:_:_:::_:_:_:_:_::_:_:::_:_:_:_:_[_::_:_:_:_:_:i_i:_:!:!_:'..i:_:_.:_!:_:_:!:_:_::......:[:.::_:.::_:_:[:_:_:.``_:_..`..:_i.`..:[:!.`..:i:i:_:::_:_
::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::

"._ :::::::::::::::::::::::::::::::::::::::::::::::::::: _!:!:_::_:_::_.`..:.)_:_:_:_:_:_:i:i_:_:_:_:i:_:_:_:_:_!_:_:_:._ ii i!_!_i!!i! :_:,'_:::_:_:_:::_::_:_:_:_::[::.,.':::_ ::::_ .:: ::::_::._::: .......... :.:::_ 4_ ._,_.,. _......:_ ........ _....... :: ,:..'.:. :_::_.:::: .:::,._,._..:...._ ....... :_.:._:. ,:_..:.::_.:.:.:+:.:.,.:.:.:..:. _._ .,.._....... :_.:_:::::.::::.:'::::'.::.:::_:: _:..'.::_:_::::_::: :_::._:_:::::_.'.':::::::::

,: ======================== ", ii:", :"":!i!:i:':_:!:::_! :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: "!i:::" '!i:::..'.::::: i _::_:i:::_:::_:::"._ _:_:::_:::::_ ' !:::::i:_::?" ::::::::::::::::::::: "!:::::_::"!:::".i:" ':::::::i .".::::_" !:.".'" '" "i ":'::i:::_ ._[__ i _i_.".. _ ...... :.....:...,.._... . . ;_:_.:::: ..,_ .:. :-.., ..:.....-::.... ,.: :::::_:;:,_!. !:: ..... :::i: _:?-_::::: ":

._............_..._

:`.i:!_!:!:_:!:!:i:..`._:_:!:_:_:i:._:.._..i:_:_i?:_i:_:_:!:::::::::::::::::::::::::::::::::_::::_:_:_!:!:::!:!:_:_:._'.!_:!:_:_:!:.::_:.:_:_:!:_:!:_:_:_>..:_i:i:i_:i:._i:i:.:i:i:i:i:_:!_i:_:?.!_:!:!:_:_:_.`..:_:_:_:_:_:_:i:_:_.`_:_:i>..:_:._5!_!:i:!:i:!
t.....

Benefits

Properly periods reduced

designed maintenance

fiber optic downtime

transmission and repair

systems maintenance costs.

will last for long and can offer Well-built optical

of time without

any preventive

transmission interference,
-i,

lines and couplers are relatively immune to electromagnetic adverse temperature, and moisture conditions and can be cable. control An optic fiber can be 20 times electrical isolation lighter energy. for safety and smaller than copper wire and still carry far more provides

used Using

for underwater fiber optic

five times
r

circuits

in hazardous environments. Because optical they are safe to use in explosive environments of short circuits in metal wires and cables.

cables carry no current and eliminate the hazards

Key

Words

Fiber

Optics,

Maintainability

Application Experience
w

Kennedy Processing

Space

Center

Ground

Support

Systems

(e.g.,

Launch

System,

Ground

Communications

System).

Technical Rationale

Fiber

optics

can enhance

the transmission

quality,

capacity,

and safety

environment of the system. The system designer should carefully weight the pros and cons of fiber optics vs. copper, microwave, or satellite installed system repair for the transmission properly, availability, costs. Reliability medium. Optical without cable fiber, if cabled any preventive and will enhance and reduce and will last for years of optical minimize

maintenance.

is very good, for maintenance,

downtime

Contact

Center

Kennedy

Space

Center

(KSC)

Page

OPS-32

Fiber Optic Systems, Technique

Page 2 OPS-8

m Z

Fiber Optic Systems Technique OPS-#

cable expands temperature,

and Shrinks with changes it does not affect

in

the fiber as
l

much. A fiber has a lower temperature coefficient th_most cable elements, Components and Operation found in fiber optic flf_er 0_ti_cable, Figure 1 illustrates ' This construction provides impac-t reS_s_anCeihowever, protect better crush and it does not of meaning that it expands and contracts directly less. appfied The basic elements receiver, The tight buffer has a plastic

" S),stems-_area tr_Smitter, and connectors.

over thefiberc0ating

|
i

the main parts of a fibe r optic system. The following is a brief description of these' elements and their function: The Transmitter signal consists equipment converts _ electrical The transmitter The circuit

the fiber as well from stresses

temperature variations. Because the plastic expands and contracts at a different rate than the fiber, contractions temperature microbends. caused by variations in can result in loss-producing Tight buffers are more flexible tight

l
i

to a light signal. of a driver being

and a source.

input to the driver

is the signal from the served. The driver

chang_es=the input signal int_a'form required to operate the source. The source, either a light-emitting diode (LED) or laser diode, does the actual conversion. The Fiber Optic Cable is the medium for

and allow tighter turn radii. Therefore; tube i:;u-ffers are useful for indoor applications where temperature variations to make are minimal and the capability turns inside walls is desired. Strength members to the fiber cable. strength steel, members and fiberglass

| |
m

tight

carrying the light signal. The main parts of a fiber cable are the optical fiber, cladding, buffer parts fiber jacket, buffer, Figure two strength 2 illustrates concentric part. The members, the main The optical layers called The inner core surrounding and jacket. contains

add mechanical strength The most common are Kevlar epoxy Aramid yarn, and rods. During

[]
m

of a single fiber cable. and the cladding.

after installation, the strength members handle the tensile stresses applied to the cable Kevlar so that the fiber is not damaged. is most commonly fibers are placed used when within their own find better

[]

the core cladding refractive reflection cladding.

is the light-carrying

individual

provides the difference in index that allows tOtal internal of light through the core. coating The applied to the

jackets. Steel and fiberglass members use in multi-fiber cables. Steel offers strength cable. than fiberglass, for maintaining also attracts Steel best choice

but may not be the an all dielectric


i

buffer is the plastic

lighting,

whereas

fiber does not. Cable buffers are one of two types, loose or tight. The loose buffer uses a hard plastic tube having an inside diameter that of the fiber. One or more within the buffer forces tube. acting fiber from mechanical becomes the rest of the cable the load bearing several times fibers lie the and the The Receiver converts

The jacket-like protection oil, ozone,

wire from the acids, alkali, material required


i i

insulation provides effects of abrasion, solvents, etc.

The choice

of jacket

The tube isolates on_it_ -The buffer member.

depends on the degree for different influences accepts

of resistance and costs.

the light signal and signal. The

As the

it back to an electrical

Page OPS-33
=== :

Fiber Optic Systems, Page 3 Technique OPS-8 receiver an output contains section. a detector, The amplifier, and with conventional hauls current, control of less than necessary. components electronics. are reduced of fiber
w

systems

and for short are of electrical system's life of the and the costs costs

amplifier

enhances

10 km, no repeaters

the attenuated

signal

from the detector. many of the clock level (TTL,

In the absence equals

The output section functions such as: and data, shitting ECL, etc.) pulse to ensure

performs separation compatibility

the life of a fiber optic the useful system, the light source,

reshaping

and timing,

Maintenance dramatically. cables

and repair Installation

and gain control. and splices, which link the A

optic

are lower

than metal

Connectors various

components

of a fiber optic

cables because the shipping and handling costs are about one-fourth and labor costs one-half that of current metal cables.

system, are vital to system performance. connector is defined as a disconnectable device detector,
w

used to connect or another

a fiber to a source, It is designed to

References

fiber.

be easily connected and disconnected many times. A splice is a device used to connect one fiber to another permanently. and connectors to power Connection couples another by splices

1.

RADC-TR-88-124, on System June

Impact and 1988. Failure October Guide

of Fiber

Optics

Reliability

Maintainability, 2. Fiber

light from one component with as little loss of optical is precise alignment

RADC-TR-80-322, Optic Assemblies,

Rates 1980.

for

as possible. connection mated fibers)

The key to a fiber optic of the (or spots in single-mode all the light is coupled 3. AWP, Technician's Optics, 1987. for Fiber

fiber cores

so that nearly

from one fiber across the junction to the other fiber. Contact between the fibers is not required. precise
w

However,

the demands

of a

alignment

on small fibers create of the connector

challenge or splice. Maintainability addressed systems built-in

to the designer

design provide modular

features

that should

be

in the design should

for fiber optic for fault localization replacement, capability. and

and isolation,

test and check-out

Improvements Fiber optics systems offer many benefits. In sensing systems, sensitive electronics can be isolated
_z

L F_

from shock,

vibration,

and harsh

environments,

resulting

in more economical

packaging. The number of repeaters required for low attenuation cable is less than

Page

OPS-34

Fiber Optic Systems, Technique

Page 4 OPS-8

--

t - - -- __em..,_r....
I SIGNAL IN I I I , i = I DR_VER I--I = SOURCE I---II I I [ I

',
SOURCE I -TOF_BER I--I 'OP _CALI-[ I FIBER / -[ CONNECTION I I

_,
=

.....
I" ....................

R_Zve7 - I

I
I1[ OUTPUT . I ........
I _.,,I KI_U

i
[ [ I-.,,--I AMPLIFIER [ I I--IDETECTORI--I I [ FIBER TO DETECTOR

" i
[]

_.

S,GmAL, I
OUT I

I/

I i
m m m m m _ m

I I
m m m m m _

I
m

I CONNECTION
=1
m

,
_

,
i

Figure 1. Basic Fiber Optic Link

8LACK

POLVU_Er.ANt OUTEa.JACCEV _
STRENGTH x MEM /

\ \ -S,UCON(COAT,NO \ \ CL_,.a IS,.,CAJ ] \ coRE m,w.A_ _Op,,CAL,,SEA

Figure 2. Parts of a Fiber Optic Cable


I

Page

0PS-35

Pneumatic

Systems

-- Pilot-Controlled

Pressure

Regulator

Loadingo Technique

Page 1 OPS-9

_m_

Technique

Use a separate, pneumatic controlled practices. specifications,

hand-operated, designs regulators.

spring-loaded, reference Specify documents,

vented

regulator

in

system pressure

to provide

pressures

for pilot and

application and design

in system/equipment policies

requirements

mm_.m

Benefits
r . z tl

Design

of a pneumatic

systems

using vented advantages:

pressure

regulators

offers circuit is

the following Requirement eliminated. Logistics decreased System components Elimination reliability.

maintainability for a separate support availability

relief valve in the pilot-loading (materials, parts, tools) are

requirements is increased

by elimination

of additional

relief valves. of additional requirements. and increases and

by elimination

and their maintenance/downtime of components enhances

maintainability

Overall life cycle costs downtime requirements,

are improved by decreased maintenance and increased system availability.

Key Words
r _

Pneumatic,

Regulator,

Pressure

Application Experience

Apollo, Ground

National Support

Space Systems

Transportation

System

(STS),

Pneumatic

Technical Rationale

When pressure

pneumatic regulators, pressure

system

requirements

mandate pressure

the use of pilot operated regulators the system to supply component

the use of vented is mandatory. logistics

reference count

This reduces requirements.

and associated

Contact

Center

Kennedy

Space

Center

(KSC)

Page
w

OPS-36

Pneumatic

Systems

-- Pilot-Controlled

Pressure

Regulator

Loadinb Technique

Page 2 OPS-9

Pneumatic Pressure Technique

Systems Regulator OPS-9

- Pilot-Controlled Loading

Pressure in Pneumatic systems must be controlled. Primary points of control are downstream the pressure of the source (compressor) :_2on_trol of downstream of the _ _ :: : -: :: .... ::_:i -::,:_ :: _ and
I

system_eceive_ank). is required

"

_=_

= ........

compressor downstream

for system safety and ................... of the receiver to m_aintai_na _-_ .... _--:: :: _: ::: source for efficient operation .....

steady pressure

of other system components. Pneumatic : ....... systems use pressure regulators to provide this control. For those systems using ::

standard dome-loaded (pilot-operated) regulators, this practice requires use of separate regulator A venting pressure upstream event vented system type regulator regulators. regulator for loading Figure the pilot operated 1 shows

:: ..... ::::=: : :::: ....... -

-_ -_-_:/- -:: :

with separate

relief valves.

limits downstream than that of the It also acts as in the _ _ This method Figure system 1 also which

to a level lower (receiver)

pressure. build up.

a relief valve for its leg of the circuit of pressure eliminates the need for a separate circuit.

relief valve

in the dome-loading

shows an example of a vented illustrates this method.

References 1. KSC-SD-Z-0005A, Ground Standard Support for Design

of Pneumatic 2.

Equipment. 0225-

Parker-Hannifin Power.

Corp., Bulletin

B 1, Fluid

Page

OPS-37

Pneumatic Systems-

Pilot-Controlled Pressure Regulator Loadinb Page 3 Technique OPS-9

NON-VENTING

REGULATOR (NON-VENTING) SPRING LOADED ---_ RELIEF VALVE

(VENT)
PNEU. INPUT __ REGULATED

[ : w

LT_IJ
PILOT OPERATED (DOME LOADED) REGULATOR

:>OUTPUT

REGULATOR (VENTING) SPRING LOADED

VENTINGPNEU. INPUT _
t

[VENT) _ "

J I> ;:> OUTPUT

PILOT OPERATED (DOME LOADED) REGULATOR

=--

THIS APPLICATION ELIMINATES THE RELIEF VALVE

= I.,,#

Figure 1. Examples

of Non-Vented

and Vented Regulator

Systems

(Schematics)

Page

OPS-3 8

r._

ii
m

BB

L m

Ul
N m

BB

.m m
m

m i ND

L_J

iil

L=

IB

r_

H mm

Modular

Automated

Power

Switching

Device,

Page

Technique OPS-IO

Technique

Incorporate system equipment

modular, specifications,

fault tolerant upgrades. requirements

power

switching

devices

in new policies

designs

and system

Specify

application

in system/

documents,

and design

and practices.

a_

Benefits

Miniaturizing

of conventional

electronic

components

and assembling

them in convenient groupings provides the following benefits: More efficient base of maintenance can be achieved. Logistics stocking Keeping support modules modules requirements as opposed at lowest (materials, to piece parts. level of maintenance for sophisticated in improved (throw-away) will and highly the test equipment parts, etc.) are reduced by

minimize the requirements skilled technicians. Modular problem Module Sealed


_'_=_

design design modules

will result

fault detection various

by isolating loads.

at the module provide

level instead increased

of at the piece environmental

part level. protection.

can be sized to accommodate

Key Words

Power,

Switching,

Modular

Application Experience

National

Space

Transportation

System

Technical Rationale
!

Incorporation

of the technique

will achieve

the goal of avoiding

high

maintenance costs from premature or sand intrusion and other severe program device operations has been detrimental around extremely reliable

failure of hardware due to moisture environmental conditions. Shuttle have shown that this switchover that are even under equipment. conditions

the world

normally

to electrical

Contact

Center

Kennedy

Space

Center

(KSC)

Page

OPS-39

ModularAutomated

Power Switching Device, Page 2 Technique OPS- IO

Modular Device Technique

Automated OPS-I O

Power

Switching:

This technique modular, _/witching maintenance Application The design

recommends tolerant,

providing p0Wer ease of restoration. _:= _ ::_:_ that .... : :El

single-fault devices

that e_ance

and expedite

system

i
ii

of lighted

visual Landing

Aids

presently install_ at sever_-SpaceShu/tie landing sites around the world specified

the Ball/Bar lights for the Inner Glideslope ....must be powered by a p_rim_ary/rod 5acku_ _ power source with automatic source switchover failure. Engineers The had to fail in the event of primary

R.eliability/Maintainability

ensure the system would not prematurely and that the switchover mechanism was relatively effort, inexpensive, self-contained, automated 1). could instead. to Shuttle and power and easy to install/maintain. the modularized device (see Figure switching implemented Failure Transfer Ball/Bar As a result of this

was developed

to utilize Switches

this technique are utilized is critical These prior Failure

result The

Ill

in excessive

cost if commercial

Automatic
g

light system

landing operations. up and operational Commit could Shuttle decision. program.

systems prior

must be

to a Launch to launch delay to the


W

result in a very costly

References 1. NSTS Flight 07700, Vol. X, Space System Shuttle R.ev.

& Ground

Specification,

J, June 14, 1990. 2. KSC Transfer BallBar Dra_ng Switch Lights.


g

No. 80K52361, Wiring Diagram

Au!omatic for

Page OPS_0

Modular Automated

Power Switching Device, Page 3 Technique OPS-IO

LI

L2

L1

L2

START SWITCH

K2A

--

--K1A

KIB

--

sl I- !
T

K1 AUX

-_-

7'

L_

_LT1

=4

, ,' oo, o,
L1 L2

MODULE

ENCLOSURE

IF K1A OR KIB FAILS OPEN - K2 DROPS OUT CAUSING SUPPLY TO COME ON LINE.

THE BACK-UP

POWER

IF THE PRIMARY POWER SUPPLY FAILS - K2 DROPS OUT CAUSING POWER SUPPLY TO COME ON LINE.

THE BACK-UP

S1 IS USED TO SUPPLY THE PRIMARY LINES AND IS ALSO USED TO BY-PASS K2A & K1 AUX TO ACTIVATE AND LOCK ON K1.

Figure

1. Modularized

Automatic

Power

Source

Switching

Device

Page OPS-41

_m
IB

IB

I_

ii
u_B g

II

m_ r m

i um

I m

m m

Pneumatic

System

Contamination

Protection,

Page 1

Technique OPS-11

Technique

Install filters immediately upstream of all interfaces systems to control dirt and water contamination.

in pneumatic

ii_iiiiiiili tiiii_i/iii_iii_ii_i_iiilitit_!i!lii_
::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: :::_. ::':::_.:::::::::::::::::::::::::::: _:: .'.':_:_::::::: _ _:_:._ _:?-:: .'.'_.::: _ :..'._:: :_::_::: :i:i:_:_: :_:_:_:_ _:i:_:_:i:i:i:i:i:_:_:_:i_:_:i:i:_:?..:_:_:i:_:i:i:i:i:i:_::: :i:i:i:!:i:::i:!:::i:i_: ::::i:_i_;::i: :!:': :: :i:_:: _:_: :..'.:,_:: ,_:_: _: ::: :::: _:.'...':::_::: :i_'_::

..%.._._.::_-_ _ __
+._- ..... _..,: _: _:.::_:: ::,

_ _:.:! i_ _ ! !.,:._ :,.:..,: _


: : :_ _:: :: :_.::::.:::: :: :::::::::::::::::::::::

.............. ..................................................... ................... :,,.......................................... ........................................ ............................


:::_::_:.::.:_.:..:_:_,_::.'.. _ +..._.+..+_:::...+...._._.... ...... <._<..._._.,...._.-.._ .,,_....., ......._ _......_:_.::..,._ ....... _._......_ ............. ....... _::_:_._:_._:_:_:_:_:_:_:_:.:_:_+:_:_:_:+:_:_:_.:. +..._.....,.. ........ ._........ ::::::_::::_ _ : : .. _._::._._ :: :...,..::.'.::..._+:::._..: ::_:!:.:_:::::_:_::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::_:._i:::_:`.::::::._:::`._:::::.`.:_::_:i:_ :::_:'_._::::_:::: _:_ ::_ ::::::'.::::::_ :_!:::_ ::::::::: _-'.':_ !i_i:iiii_!."-'_:_i_i_:i_._i _ ..... _ ..".' ._'." _' ._....._...,_._.. _:.i_i _ i?...'!_i ::::::::::::::::::::::::::::::::::::::: :::: _ :::::: :_ _:: :: ::: ::: _._.: ::: t: _.::._._: : _:_:t:: _:.__:_ _::: _..'.: _: : :: ::: ::_'._:::?,.'.'.': _ : :: _:_:_:_:_:_$_:_:..`._:_:_:_:._:_:::_:.:_:_:_:_:i:_:_:_:_:_::`._:i:i:_:_:i:i:::i:i:_.._:i:_:i:i:_:_:_:i:_:[: :!:_:_:!:i:". _::."._:_._'._::_ ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: :: :::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::

:::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: :_:.". _: _..'..:'._: : ::::::_.:::_. :_::'__:: .":::::: : :_ : ::'.-"::::::: :: : :: :_:::."..'.'_:::: ::: ::: :_:::: : _:::: : : :.:: :i::::: ::: ::: :_ _: :: : ::: :::: :_.":_:_:.:_:: :_i: :i:i:!:_:i_._:_:i:_:_:_:_: "_::. _::" ::_:::: :_.:'_:::::-_ :'_._: _::: : ::'):: ::: ::: :::-'.':.::::-:: ::::::,'.'::::_:'::_:_: :::_.'.':_:::_:?.: _: :_::_: ::::i_::::::i::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: :._:: ::::.':::::: _:._:: : :::._:_ _:l_:_._,_ ............................... _:_,..:::._.:.:._

,_i_,.": _ i i i ! ! :::::::::::::::::::::::::::::::::::::::: .............. -..:::::_:::::_: :_ ::::._

_:_'_

::::::::::::::::::::::::::::::::::::

j"

...

::

.': :_.:::..:::.:.:.:.:.:.:.:.,.::." _.....:.._+..:_ .... :..::_:.._..::: ,..:..::::_:........:...; ....... :..:....:..:.....:. : .,.: ..... :_..:_ ........ ::...: ....... :::::::::::::::::::::::::: ....: ...-.. :.....:.. :.......: .:..,.:.....::::...,.:.. :.:::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: : ._:::::_::::: :::::::::::::::::::::::::::::::::::::::::::::::::::::::: __:it_: .:'_'"_ ........ __'"' "_'_ ......... ".":_ _ ':" "'_'"" _"":':: """'" '_'_i!i_ "" """"_" """:+"<""""":':_:::":_:'_:_':''_"_"" "" "_" " "" "" ".......... _'" " "_"'_"' "" _'_ _'............... "_'"" _'" _"" __:::_..:!2{ '_ ....... :::::_:::::_:::' _:._::.::::. _:::::'.'::::' ............ _::: _:_ :::: _::_ ............. .'.::::::_ _......... :_ _:::::_ ::._ ........... ::::_._:_::: : ::..-: ::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::::: :::_: _::_._ I_ : _.,. _:: .,.': _ i:_i_:L.'.,_..'._:_:.::..'i

:::::::::::::::::::::::::: L_ w

.: : :,_...,_.:,,..::....... :.:.+...+:

:,,...:.:

_:,:::_.:::.:,:.:_ _:_ ::_ _:::: ::_ :::::_:::::_i_.::.::::

Benefits

Proper

use of filters,

prevents

contaminated provides caused

gas from interfacing the following by contamination. system/equipment benefits:

with

component
E

and system component

operation, failure means

Decreased Efficient

and effective

of servicing

by

filter cleaning

or replacement. availability due to reduction in system

Increased system maintenance.

Key Words

Pneumatic,

Protection,

Contamination

Application
iml

Apollo, Support

National Systems

Space

Transportation

System,

Pneumatic

Ground

Experience

Technical Rationale
-:!

System system. interfere

gas must be conditioned Installing filters and also reduces

before

it is allowed upstream operation.

to enter

a new achieves that can

immediately and system

of interfaces contamination

this objective

dirt and water

with component

Contact

Center

Kennedy

Space

Center

(KSC)

Page

OPS-42

Pneumatic

System

Contamination

Protection, Page 2 Technique OPS-I1

Pneumatic Protection Technique No how matter

System OPS-11

Contamination

and element design Providing

clogged

to its maximum

iii

capability).
=,_

unconditioned will have

gas in a pneumatic effects: because of

how well a system with component

is designed

or gas

system

the following performance

expensive,

particulate-contaminated and system

interferes

operation. System gas must be conditioned; it must be decontarninated before it is =-:_:_::_ allowed KSC defines Filters upstream particulate appropriate particulate Selection analysis protection minimal drop). Filter housings and elements shall be constructed of 300 series stainless steel to reduce particulate contamination due to corrosion. Seal materials shall conform to manufacturer's requirements construction recommendations specified herein. should be welded and the The element instead of to enter a pneumatic system. The systems for filters:

Degraded System contamination. _ _ Increased to recover -

maintenance from

cost and downtime induced by

design

standard

for pneumatic requirements

problems

the following

contamination.
I

shall be installed of all interfaces matter points

immediately where control to control of and at other

Decreased References

system

availability.

is critical as required

migration. of filters of overall shall be made system only after

1. KSC-SD-Z-0005A, of Pneumatic performance maximum and (pressure Ground

Standard Support Corp.,

for Design Equipment. 0225-B 1,

requirements.

This ensures of critical penalty

2. Parker-Hannifin Fluid Power.

Bulletin

components

l i

performance

soldered whenever possible to simplify cleaning. Where 300 series stainless steel is specified, type 303 and other austenitic stainless possible corrosion should steels because cracking. be the deciding should be avoided However, factor. filtering in any way system flow rate whenever to stress of susceptibility

overall

cost

Filter elements when subjected

shall maintain to worst-case

quality and not be damaged conditions (i.e., maximum

design

Page

OPS-43
=

Q8-1@-1995

15:14

P.@2

""

F_.

App+ow_

REPORT DOCUMENTATION
Dlriloforlll for Infm, mut}an C _lrltllml ind Papm'tw. I | 1 li J/|flrlMI DIVII Mlgrlwly,

PAGE
UiJI_i 1 ;[_, AfllrloTorl+ YA Z++u;I-6.3uz, Erie

oMlNo,
118 lirlW _ilTItgl UI[ IMlrlalilmmln[

Public mportl_+; b_+--_o_ thll collection of Informetlqn le o_Jfn, I t_l to mverfg9 I ho'ar Fm.rrmupnn.H, I.,,alud!nll _ t.kl_ f_ revle.wlng Ingtm_/onm, _,L_I+n__ IXll_k'lU dl_.l SOUPINg0glt._ll IrlE .nd r_..mlntalnlns the alike nomclml, el+_l oompllUl'_l ins rlv+lWll_ _ .oo_i+i.._:lOnIs T M11.o,rm, ITlOfi, .Imlna ol._rmlnll mjlmmmg 'mew burd,n **tim,t, or ,my omit iipem of _1, oollemlon _ Inform,tiroL In .dudln _ luOgp_nn+ f,r ,_ly.m,g Im.*..numpntp .w_l_*_nm0_n .m.,uq_ul_e_, u e_r__1. _. NK_01t. P+l_vMk 1. AOENCYUiEON_ Rodu_Jo | PrOJl(X (0704_1U). _ b_n_ WNhlngton, DATE December 4.7_LEANDSUBTffLE 1994 DC 20503, 2. RI_ORT TYPE AND DATE8 COVERED Technical Memorandum 8, FUNDIN tu NUM|ERE

|.REPO_

_.AUTHO_(B)

NASA Reliability

and Maintainability

Steering

Committee

7. PERFORMiNeOR_ANRA_ONNAMEL|IANDADDREiIIEil NASA Office of Safety and Mission Management Division

REPORT NUMBER Assurance, Safety and Risk

I. sPoNSOmNO_ONITONNGASENCTNAME(DIANDADDREES{ES) National Aezonautice and 5pace A_inistratio_ Washington+ DC 20546

10, 8PONSOR_OIMONITOP_NO AGENCY REPORT NU_qBER NASA TM-4628

1 I. SUPPLEMENTARY NOTE8

Iaa. DISTNBUTION_VAI_LITYETATEM_T

Igb. DISTNBU_ON

CODE

Unlas_ified

Unlimited

Subject 13, ABSTRACT (MaximUm 200 wwdal This manual presents operational effeetlvness of tools that minimizes It Restoring conducting Sustaining a

Category

38

series of recommended techniques of both flight and ground based risk associated wi_h; fllgh_ the of an

that NASA

can increase systems.

It

overall provides

set

failed functions (both ground and co_plex a_d highly vlsiblemaintenance a technical capability to support or facilities program Rangement key elements

based) operations NASA mission effective

using

agin_ effort;

e_uipment considers (i)

main_alnability

{2) design and developmen_ - techniques that have benefited previous programs; (3) analysis and teS_ - qu_tltative _d qualitative analysis processes and testing techniques; and (4) operations and operational design techniques that address NASA field experience. This d_cument is a valuable resource for continuous improvement ideas in executing _he systems development process in accordance with the NASA "better, faster, ,_aller, end cheeper" goal without +om_omlalng _afety.

14. su_Ec'r_[_| maintainability, yet_me engineering, space effectiveness, ground-based cost 7. SECUR_r_ CLASSIFICATION OF REPORT Unclassified NON 7540-01,2E0_51S00
I1.

maintenance, eystem design, systems, flight

design operational systems,

and

test, life-cycle

1 E, NUMBER OF PAGES

104
10, PNCE CODE

A05
IiCuRrrf CLAEEIFICA'rlON

OF THIS PAeE

1III. IECURITY CLASIIFICATION OF ABSTRACT Unclassified

20.

LIMITATION

OF

ABE'TRACT

Uncleselfled

ndard Form 20E (Flev. 2-SQI eiribd by _d_ll_Ind. Z31-_il


:IIII-102

You might also like