AHMEDABAD MUNICIPAL CORPORATION - ENGINEERING DEPARTMENT SPECIFICATIONS OF ROAD WORK UP TO GROUTING LEVEL

This section gives detail specifications for mainly used materials, for other materials refer Building Specifications. For materials relevant IS code shall apply. TECHNICAL SPECIFICATIONS Item No.01 : Box cutting the road surface in all sorts of soil, murrum to proper lope & camber for making a base for road work including removing the excavated stuff & depositing on the road side as directed up to 50.00 mt. Lead. Any soil which generally yields to the application of pickaxes and shovels, spades, rakes or any such ordinary excavating implement or organic soil, gravel, silt, sand turf loam, clay, peat etc. falls under this category. For materials and workmanship for earthwork and excavation, relevant specification IS: 3764 & IS 1200 (Part I) shall be followed. To protect persons from injury and to avoid damage to property, adequate barricades, construction signs, red lanterns and guards as required shall be placed and maintained during the progress of the construction work and until it is safe for the traffic to use the roadways. The relevant Indian standards and the rules and regulations of local authorities in regards to safety provisions shall be observed. The depth of the excavation shall be as required. The site shall be cleared and all obstructions, loose stones, materials and rubbish of all kind, bush; wood and all type trees shall be removed, as directed. The materials so obtained shall be the property of AMC and shall be conveyed and stacked as directed, within 50-m. lead. The roots of the trees coming in the sides of the trenches shall be cut and coated with hot Bitumen. All types of trees, woods etc. which requires prior permission of Govt./ Forest Authority / Municipal Commissioner, before cutting shall be cut after obtaining such permission from them. The rate of site clearance is deemed to be included in the rate of earthwork. The excavation shall be carried out in true line and level and having width and depth, as shown in the drawings or as directed. The Contractor shall do the necessary shoring and strutting or shall provide necessary slopes to a safe angle or steps, as required or directed, at his own cost. No extra payment shall be made for such precautionary measures, taken. The bottom of the excavated area shall be leveled both longitudinally and transversely, as directed, by removing excess soil and watering, as required. No earth filling will be allowed for bringing it to level, if by mistake or any other reason, excavation is made deeper or wider than shown on the drawings or as directed. The extra depth or width shall be made up with sand filling, as specified for the bottom level of the subsequent finishing at the cost of the Contractor or as directed by Engineer-In-Charge. The Contractor shall at his own expense and without extra charge make provision of supporting all utility services, lighting the excavated areas, separating and stacking serviceable materials neatly, shoring, timbering, strutting, bailing out water either sub-soil or rainwater, including pumping at any stage of the work. Excavated areas shall be kept free of water while masonry or concrete or relevant base works are in progress and till the Engineer-in-charge considers it necessary. Contractor shall have to take levels before and after excavation. Contractor shall have to provide level and leveling staff and shall take levels with his own engineers in presence of AMC staff. Measurement shall be given by level results. Disposal of the Excavated Stuff: The excavated stuff of the selected type shall be used in backfilling the excavated areas wherever required in layers, including ramming and watering, ensuring proper compaction etc. complete up to lead of 50mt. The Contractor shall remove the balance of the excavated quantity from the site of work, to a place, as directed by engineer in charge. The lead is the shortest practical route and not necessarily the route actually taken. The decision of Engineer-In-charge shall be final in this regard. The measurement of excavation of excavated area shall be made according to the sections shown on the drawing or as per sections given by the Engineer-in-charge. The rate shall include for clearing the site, surface dressing, and making layout for road. The rate shall be for a unit of one Cubic meter. Item No. 02: Conveyance charge for surplus excavated earth, lime, murrum, building rubbish, manure, garbage, sludge, excavated rock, fly ash, aggregates of any kind including spreading & leveling etc. complete. (iii) Lead up to 3 Km. All the surplus earth/excavated material etc. shall be carried away immediately from the site of work to a place within distance specified in the relevant item or as directed and ordered by the Engineer, so as not to cause any inconvenience to the public traffic. If the instructions are not complied within 7

days from the date of order to cart the surplus materials and clear the site, the said work shall be carried out by the Municipal Corporation at the risk and cost of the contractor and no claim or dispute shall be entertained in this respect. The rate of carting including carting of brick bats, metal, rubble vegetable and garbage, if necessary to clear the road surface. Carting of payment shall be given as per excavation without any bulkage. The rate shall be for a unit of one cubic meter. Item No.03 : Supplying of graded hand broken stone aggregate of 90 to 127 mm size at site (Spouls) The stone for rubble soling to be supplied by the contractor and shall be of good quality and size 90 mm to 127 mm. The stone shall be quarried and shall be sound, angular, durable and free form flaws and decay and shall be approved by the Engineer in charge. The material shall conform to standard tests as required by AMC. The stone shall be stacked on neat and uniform ground at roadsides, stack shall be of the regular/ geometric shape, and stack shall be measured in volume. The material shall be stacked in such a way that there shall be minimum voids. The rate includes quarrying blasting, hand breaking collection transporting, to the site and stacking in measurable stacks at site. Inferior quality of material brought on site shall be immediately removed from the site without any extra cost. The rubble or spouls shall be spread after measurements are recorded and orders are obtained from the Engineer in charge. Mode of Payment The rate shall be paid on cubic meter basis. Item No.04 : Labour charges for spreading the spouls 127 mm thickness Layer earth filling correcting the grade and camber comp. with watering, rolling, including preparing the surface by brushing for removing all loose or dirt etc. completed. The item relates to labour work of soling. The spouls stacked at any lead from the filling area should be used good earth obtained from outside only after Engineer in charge approved. The spouls shall be sorted out from stacks. Extra earth, debris, shall be removed and the spouls shall be placed in position over the earth level formed to give a suitable soling formation by packing voids, no hollow space is left. The soling shall be filled up with the same material of finer size, interlock the small cavities between the soling and the whole soiling shall be made a compact, solid and continues level which shall not be disturbed while rolling. The entire surface shall be well watered and rolled with a heavy roller weight not less than 8 ton capacity as directed by engineer in charge. The gaps formed shall be packed again by the same process. Spouls shall be laid on herringbone bond to required grade and camber. Contractor shall provide required number of labour at time of rolling to rectify undulation and depression without any extra payment. The contractor shall have to prepare the surface true in accordance to camber & gradient of the road. If any extra depth of soling is required in the process that will not be paid for separately. The measurement will be on square meter basis of the actual area of soling surface prepared. Item No.05 : Supply of graded machine cut black trap stone aggregate of Sevaliya/Timba or equivalent quality. Metal of size 25 mm to 40 mm. The Aggregates shall consist of Black trap machine crushed stone only, obtained from quarries situated in Sevaliya /Timba or equivalent. It shall remain visibly black on immersion in water. They shall be clean, strong, durable of fairly cubical shape and free from disintegrated pieces, organic or other deleterious matters and adherent coating. They shall be free from elongated and flaky piece also. The size of the aggregate shall be as per standard required by AMC . For stacking relevant Specification of Item No. A-3 shall be apply. The rate shall be paid on cubic meter basis. Item No.06 : Labour work for spreading the metal in total 100mm th. in two uniform layers each of 50 mm thick, including providing and applying bitumen for semi grouting 1.5 kg/sq.mt. for each layer (in both layer) & providing and spreading the key black trap aggregate of Sevaliya/Timba or equivalent quality on top (second) layer at the rate of 0.013 cmt per sq.mt. of size 18 mm passing & 9.5 mm retained. Rolling with 10 T.roller etc. complete as directed. The metal shall be screened of any rubbish, dust or grass. Then metal shall be laid uniformly in two layers of 50 mm each, to the required grade and camber as directed by the Engineer in charge. Laying of metal shall be started after the consolidating soling layers prepared perfectly to the proper line level and camber. Where camber of soling is found doubtful it shall be corrected prior to spreading metal. Metal filled in the basket shall be spread evenly in required number of layers as directed. Metal shall be spread in proper grade and camber if required using camber boards, so as to ensure the corrected

surface. The surface shall be checked at every 15 mts. by means of template and string for correctness of the camber. The consolidation of metal shall be done by the contractor with a minimum 8 to 10 T roller. The contractor shall provide required number of labors at the time of rolling to rectify the undulation that might have occurred during rolling. To carryout grouting of the above said 50 mm thick metalling coat the contractor shall bring all the required equipment and materials as directed. Bitumen of 80/100 grade penetration of approved quality heated to a temperature of about 150 C. and shall be applied hot by means of a sprayer uniformly over the surface at the rate of 1.5 kg./sq. mt. up to the satisfaction of Engineer in charge. Immediately following the application of bitumen and while it is still hot second layer of metal shall be spread in proper thickness and again application of bitumen at the rate of 1.5 kg./sq. mt. as above for second layer shall be done. Key aggregate of as specified in below table and of approved quality shall be evenly spread out at rate of 0.013 cum. per sq. mt. After spreading the chipping the whole area shall be rolled over thoroughly with a 8 T to 10 T. roller It is important that the rolling should be done while the bitumen is still soft and it should be continued until the road sets and there is no settlement under the roller. During the period between the initial compaction of coarse aggregate and compaction of the surface course shall be protected form all traffic other than essential to its construction, till the final compaction level is attained. All above operation shall be carried by the contractor using his equipments and material including fuel or wood required for burning etc. and as directed up to the entire satisfaction of Engineer in charge . Vehicles tube tire burning shall not be allowed. As shown in the TABLE-500-7 I.S. Sieve (mm) Per cent by weight passing the sieve Key Aggregate 53 26.5 22.4 13.2 5.6 2.8

100 40-75 0-20 0-5