0 Letter Template EQ Prerequisite 1: Minimum IAQ Performance

Option A: For naturally or mechanically ventilated buildings capable of meeting the ASHRAE 62.1-2004 minimum requirements: (Responsible Party) Christine Beaton, LEED AP I, , declare to USGBC that the project is fully compliant with Section 4, 5, 6 and 7 of ASHRAE 62.1-2004 and all accepted Addenda AND Natural Ventilation The building is naturally ventilated and complies with ASHRAE 62-2004 Section 5.1 I have provided the following supplementary documentation to support the declaration Plans and tables to demonstrate that the ratio of operable opening area to floor area meets the required standard, and that the occupied areas are all within the allowable distance from the openings. Calculations and a spreadsheet similar to Table 2 for this credit in the LEED-CI Reference Guide.

OR

Mechanical Ventilation The building is mechanically ventilated I have provided the following supplementary documentation to support the declaration Calculations and a spreadsheet similar to Table 1 for this credit in the LEED-CI Reference Guide. When one air handler supplies a mixture of outdoor air and recirculated return air to more than one zone, I have provided its multiple zone analysis. Yes Not Applicable For multiple zone recirculating systems, the following was used to determine system ventilation efficiency: Table 6-3 of ASHRAE 62.1-2004 Appendix A of ASHRAE 62.1-2004 Not Applicable

LEED-CI 2.0 Letter Template EQ Prerequisite 1: Minimum IAQ Performance

Option B: For project areas mechanically ventilated but incapable of meeting ASHRAE 62.1-2004 (Responsible Party) Christine Beaton, LEED AP I, , declare to USGBC that the project is incapable of meeting ASHRAE 62.1-2004 but that the minimum Combined Outdoor Air Rate (per person) is 10 cfm or greater and that all other requirements of the standard are met. I have provided the following supplementary documentation to support the declaration Documentation on the determination of the minimum flow rate. Copy of the letter to the client with the supporting information (i.e., photographs, spec or cut sheet of mechanical equipment, as-built mechanical plans or single line drawing as-builts of all space constrained aspects in the system, such as vertical riser and horizontal chase space). The information required of those mechanically ventilated projects that are in compliance (the spreadsheet following the format of Table 1 for this credit in the LEED-CI Reference Guide). When one air handler supplies a mixture of outdoor air and recirculated return air to more than one zone, I have provided its multiple zone analysis. Yes Not Applicable For multiple zone recirculating systems, the following was used to determine system ventilation efficiency: Table 6-3 of ASHRAE 62.1-2004 Appendix A of ASHRAE 62.1-2004 Not Applicable

Project Name: Prerequisite:

Zhuang Lab Renovation EQ Prerequisite 1: Minimum IAQ Performance Prerequisite Documented: Yes

READY TO SAVE THIS TEMPLATE TO LEED-ONLINE? Please enter your first name, last name and today's date below, followed by your LEED-Online Username and Password associated with the Project listed above to confirm submission of this template. Christine First Name Beaton Last Name 2008-08-25 Date CB@BRPLUSA.COM Username (Email Address) Password

SAVE TEMPLATE TO LEED-ONLINE

PRINT TEMPLATE

Letter Template Version A1 . 10000325

ASHRAE 62-2004 VENTILATION CALCULATION - VENTILATION RATE PROCEDURE, CHAPTER 6.2 Harvard University - Zhuang Labs Renovation
AHU-1 & 2
RESULTS V tot V ot Actual total supply air, cfm Outdoor air intake, V ou /E v , cfm Percent outdoor air intake, V ot /V ps Ev System ventilation efficiency 4,555 Min, calculated 2,000 43.9% 0.50 Indicates where actual zone population used rather than calculated from ASHRAE max density ZONE LEVEL Az Pz Rp Ra P z *R p A z *R a Ez V oz V pztot indicates revisions to box cfms to comply w/62.1-2004 V pz Zp 100.0% Actual 4,555 100.0% 100.0% 0

Zones served by system

Zone #

Zone Name

Space type (select from pull-down list)

Zone population, People outdoor Floor area of largest # of air rate from people expected Table 6.1, zone, ft 2 to occupy zone cfm/person

Area outdoor Zone people Zone area OA air rate from OA calc (based calc (based on Table 6.1, on # of people) area ft 2) cfm/ft 2

Zone OA Zone air corrected for zone distribution air distribution effectiveness effectiveness, cfm (refer toTable (Pz*Rp + 6.2) Az*Ra)/Ez

The minimum Maximum value of the primary airflow primary airflow to to zone from air zone from air handler. In VAV handler. In CAV systems, use the systems, V pz = design value. cfm V pztot . cfm 2,150 300 40 40 160 1,950 100 50 50 50 50 340 340 340 745 650 150 40 40 160 900 100 50 50 50 50 340 340 340 745

Minimum Primary outdoor air fraction, V oz /V pz

Zone 1 Zone 2 Zone 3 Zone 4 Zone 5 Zone 6 Zone 7 Zone 8 Zone 9 Zone 10 Zone 11 Zone 12 Zone 13 Zone 14 Zone 15

Bio-Prep Lab B11 Student Desks 032A Office 032C Admin Office 032D Student Desks 032E Laboratory 034 Equipment 034C Student Desks 034F Student Desks 034G Student Desks 034H Student Desks 034I Optics 034A Optics 034E AFM/Confocal B12A Entry 032/Intereation 032B/Computer Stations 032F

Science laboratories Office space Office space Office space Office space Science laboratories Storage rooms Office space Office space Office space Office space Science laboratories Science laboratories Science laboratories Office space

1,055 80 315 145 340 995 200 145 145 145 80 160 185 200 500

15 2 2 1 8 25 0 4 4 4 2 4 5 5 12

10.0 5.0 5.0 5.0 5.0 10.0 0.0 5.0 5.0 5.0 5.0 10.0 10.0 10.0 5.0

0.18 0.06 0.06 0.06 0.06 0.18 0.12 0.06 0.06 0.06 0.06 0.18 0.18 0.18 0.06

150 10 10 5 40 250 0 20 20 20 10 40 50 50 60

189.90 4.80 18.90 8.70 20.40 179.10 24.00 8.70 8.70 8.70 4.80 28.80 33.30 36.00 30.00

1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00

340 15 29 14 60 429 24 29 29 29 15 69 83 86 90

0.52 0.10 0.72 0.34 0.38 0.48 0.24 0.57 0.57 0.57 0.30 0.20 0.25 0.25 0.12

TOTAL

3,635

78

4,555

3,355

8/25/2008, 4:49 PM

Page 1 of 2

J:\Jobs\2715000.SW\HVAC\LEED\Credits & Prereqs\EQp1\Zhuang LEED 62 compliance 2-20-08.xls, Existing AHUs

ASHRAE 62-2004 VENTILATION CALCULATION - VENTILATION RATE PROCEDURE, CHAPTER 6.2 Harvard University - Zhuang Labs Renovation
AHU-1 & 2
RESULTS V tot V ot Actual total supply air, cfm Outdoor air intake, V ou /E v , cfm Percent outdoor air intake, V ot /V ps Ev System ventilation efficiency 4,555 Min, calculated 2,000 43.9% 0.50 Indicates where actual zone population used rather than calculated from ASHRAE max density ZONE LEVEL Az Pz Rp Ra P z *R p A z *R a Ez V oz V pztot indicates revisions to box cfms to comply w/62.1-2004 V pz Zp 100.0% Actual 4,555 100.0% 100.0% 0

Zones served by system

Zone #

Zone Name

Space type (select from pull-down list)

Zone population, People outdoor Floor area of largest # of air rate from people expected Table 6.1, zone, ft 2 to occupy zone cfm/person

Area outdoor Zone people Zone area OA air rate from OA calc (based calc (based on Table 6.1, on # of people) area ft 2) cfm/ft 2

Zone OA Zone air corrected for zone distribution air distribution effectiveness effectiveness, cfm (refer toTable (Pz*Rp + 6.2) Az*Ra)/Ez

The minimum Maximum value of the primary airflow primary airflow to to zone from air zone from air handler. In VAV handler. In CAV systems, use the systems, V pz = design value. cfm V pztot . cfm

Minimum Primary outdoor air fraction, V oz /V pz

SYSTEM LEVEL Ps D System population, maximum simultaneous # of occupants of space served by system Occupant diversity, ratio of system peak occupancy to sum of space peak occupancies, = P s /SP z Uncorrected outdoor air intake, = D *SR p *P z +SR a *A z , cfm Actual total supply air, cfm Mixing ratio at primary air handler of uncorrected outdoor air intake to system primary flow, = V ou /V ps 78 1.00

V ou Vtot Xs

1,000 4,555 0.22 Not used in calculation

SYSTEM EFFICIENCY Max Z p Ev V ot Maximum Z p of all zones System ventilation efficiency (from Table 6.3) based on Max Z p Calculated minimum outdoor air intake, V ou /E v , cfm Percent outdoor air intake = V ot /SVpztot 0.72 0.50 2,000

43.9%

8/25/2008, 4:49 PM

Page 2 of 2

J:\Jobs\2715000.SW\HVAC\LEED\Credits & Prereqs\EQp1\Zhuang LEED 62 compliance 2-20-08.xls, Existing AHUs

Harvard University Zhuang Laboratory Renovation HVAC Narrative: This project is a renovation to the Basement & Ground Floor of the Naito Chemistry Building. The scope of work includes new optics laboratories, an equipment room, interaction area, and offices. The HVAC plans and specifications indicate the necessary system components to provide heating, ventilation, and air conditioning for the addition. The new HVAC components are extensions of the existing all air and hot water systems in the existing Naito Chemistry Building. An existing 100% outside air, variable volume air handling unit, will provide conditioned fresh air to variable volume terminal boxes, fan coil units, and recirculating air handling units. The recirculating air handling units have variable volume control via EC motors. The fan coil units and recirculating air handling units have both hot water heating and chilled water coiling coils. Perimeter heating is provided via fin tube radiation and radiant panels. Hot water and chilled water for heating, reheating, radiation, and cooling are provided by the building hot water and chilled water loops, supplied by the Harvard Campus Central Plant. The existing laboratory exhaust system consisting of variable volume exhaust fans, located in the penthouse, will provide exhaust for the variable volume lab fume hoods and general exhaust via exhaust air terminals. Laboratory fume hoods and general exhaust are arranged in a ganged exhaust system and exhausted to the roof. Design Criteria/Conditions: Exterior Winter Design Temperature: 0 F. Exterior Summer Design Temperature: 91 F dry bulb/73 F wet bulb Interior Winter Design Temperature: 72 2 F Interior Summer Design Temperature: 75 2 F System capacities: Refer to drawings and equipment schedules. Testing requirements/criteria acceptance: Refer to Section 15990 of specifications. Operation and maintenance manuals: Refer to Section 15050 of specifications. Record and Control documents: Refer to Section 15050 of specifications.

BARD, RAO + ATHANAS CONSULTING ENGINEERS, LLC

September 8, 2008

Drawings included in this projects original LEED submittal are on file with the Harvard Office for Sustainability.