Professional Documents
Culture Documents
INTRODUCTION
LITERATURE SURVEY ORGANISATION OF THE THESIS
INTRODUCTION
Since an engineer is always concerned with the cost of products and services, the efficient optimum economic operation and planning of electric power generation system have always occupied an important position in the elctric power industry. With large interconnection of the electric networks , the energy crisis in the world and continous rise in prices , it is very essential to reduce the running charges of electric energy. A saving in the operation of the system of a small percent represents a significant reduction in operating cost as well as in the quantities of fuel consumed. The classic problem is the economic load dispatch of generating systems to achieve minimum operating cost.
CHAPTER 2
CHAPTER 3
5
3.1 INTRODUCTION:
The engineers have been very successful in increasing the efficiency of boilers, turbines and generators so continously that each new added generating plants of a system operates more efficiently than any older unit on the system. In operating the system for any load condition the contribution from each plant and from each unit within a plant must be determined so that the cost of delivered power is minimum. Any plant may contain different units such as hydro, thermal, gas etc. These plants have different characteristic which gives different generating cost of any load. So that there should be a proper scheduling of plants for minimisation of cost of operation . The cost characteristic of each generating unit is non-linear. So the problem of achieving the minimum cost becomes a non-linear problem and also difficult.
The problem of Economic Dispatch can be mathematically stated in the form of an optimization Problem with minimizing the total cost of the system as the objective function with the system limits as the constraints. The cost and the system limits can be mathematically modeled as follows.
When the cost function C can be written as sum of terms where each term depends only upon independent variable.
The inequality constraints are of two types (i) hard type and (ii) soft type. The hard type are those which are definite and specific like tapping range of an on-load tap changing transformer where as soft type are those which have some flexibility associated with them like the nodal
voltages and phase angles between the nodal voltages etc. soft inequality constraints have been very efficiently handled by penalty function methods.
i)
EQUALITY CONSTRAINTS :
From observation we can conclude that cost function is not affected by the reactive power
demand. So the full attention is given to real power balance in the system. Power balance requires that the controlled generation variables PG(i) obey the constraint equation
ii) i)
The KVA loading in a generator is given by P2 +Q2 and this should not exceed a specified value of power because of the temperature rise conditions. The maximum active power generation of a source is limited again by thermal consideration and also minimum power generation is limited by the flame instability of a boiler. If the power output of the generator for optimum operation of the system is less than a specified value Pmin, the unit is not put on the busbar because it is not possible to generate that low value of power from the unit. Hence the generator power P cannot be outside the range stated by the inequality
Pmin
P Pmax
Similarly the maximum and minimum reactive power generation of a source is limited. The maximum reactive power is limited because of overheating of rotor and the minimum is limited because of the stability limit of the machine . Hence the powers of the generators Pp cannot be outside the range stated by the inequali
Qmin
Q Qmax
ii)
Voltage constraints :
9
It is essential that the voltage magnitudes and phase angles at various nodes should vary within certain limits . The normal operating angle of transmission lies between 30 to 45 degrees for transient stability reasons. A lower limit of delta assures proper utilisation of transmission capacity.
iii)
These constraints are required to meet a) the forced outages of one or more alternators on the system and b) the unexpected load on the system The total generation should be such that in addition to meeting the load demand and losses a minimum spare capacity should be available i.e, G Pp+Pso Where G is the total generation and Pso is some pre-specified power. A well planned system is one in which this spare capacity Pso is minimum.
iv)
The flow of active and reactive power through the transmission line is limited by thermal capability of the circuit expressed as Cp Cp max Where Cp max is the maximum loading capacity of the Pth line.
v)
If an auto transformer is used , the minimum tap setting could be zero and the maximum one i.e, 0 t 1.0 Similarly for the two winding transformer if the tappings are provided on the secondary side, 0tn
10
CHAPTER 4
LAGRANGE METHOD
INTRODUCTION ECONOMIC LOAD DISPATCH PROBLEM (WITHOUT AND WITH LOSSES) PROBLEM FORMULATION ALGORITHM FLOW CHART
11
LAGRANGE METHOD 4.1 INTRODUCTION : In this chapter Lagrange method has been discussed and the
algorithms are developed to solve the ELD Problem with and without losses [1]. The problem formulation for economic load dispatch problem using lambda iterative method has been given. And the algorithm and flowchart to corresponding problem are presented. The economic load dispatch problem deals with the minimization of cost of generating the power at any load demand. The study of this economic dispatch can be classified into two different ways. One is economic load dispatch without the transmission line losses and other is economic load dispatch with transmission line losses. In Lambda iteration method lambda is the variable introduced in solving constraint optimization problem and is called Lagrange multiplier. Since all the inequality constraints to be satisfied in each trial the equations are solved by the iterative method
------------------------- (1)
ai bi ci are cost coefficients Pd = Given load demand Pgi= Real power generation ng = number of generation buses Pl = Transmission power loss The system losses are obtained by Krons loss formula PL = Pgi * Bij * Pgj Where, i=j=1,2ng B loss coefficient matrix.
----------------------------------- (4)
The following formulae are used to solve the ELD problem using the Lambda iterative method --------------------------------------- (5) and Pgi is given by ---------------------------------------- (6)
and
P = Pd + PL - Pgi
-----------------------------------------
(7)
Pgi =
------------------------------------- (8)
13
Else fix as following. If Pgi < Pgimin then Pgi =Pgimin If Pgi>Pgi max then Pgi =Pgimax STEP11: GOTO STEP 4. STEP12: Compute the optimal total cost from Eq.(1) STEP13:Stop
15
4.2.3 FLOW CHART FOR ELD USING LAGRANGE METHOD NEGLECTING LOSSES
Start Read the values of ai, bi, ci, , ,ITMAX,Pd
Set IT=1
Compute P given by eq 7
Pgi= Pgmin
Pgmax<Pgi<Pgmi , n
Pgi = Pgmax
Pgi
Stop
4.2.4 ALGORITHM FOR ECONOMIC LOAD DISPATCH BY LAGRANGE METHOD INCLUDING LOSSES AND CONSIDERING LIMITS:
STEP 1: Read data,namely cost coefficients, ai, bi, ci , B- coefficients, Bij, Bi0, B00 (i=1,2,.NG; j=1,2,.NG);convergence tolerance, ;step size ; and maximum allowed iterations,ITMAX,etc. STEP 2: Compute the initial values of Pgi (i=1,2,NG) and by assuming that PL =0.Then the problem can be started by Eqs.(1) and (2) and the values of and Pgi (i=1,2,,NG) can be obtained Directly using Eqs.(5) and (6) respectively. STEP 3: Assume no generator has been fixed at either lower limit or at upper limit. STEP 4: Set iteration counter,IT =1. STEP 5: Compute Pgi (i=1,2,R) of generators which are not fixed at either upper or lower limits, using Eq (8),wher R is the number of participating generators. STEP 6: Compute the transmission loss using Eq(3.14) STEP 7: Compute P=PD+PL- Pgi . i=1,2,3..NG
STEP 8: Check P, if yes then go to STEP 11.(it means the program moves Forward without obtaining required convergence.)
STEP 9: Modify new ==P,where is the step-size used to increase or decrease the value of in order to meet the STEP 7.
17
STEP 10: IT=IT+1, =new and GOTO STEP 5 and repeat. STEP11: Check the limits of generator,if no more violations then GOTO STEP13, Else fix as following. If Pgi < Pgimin then Pgi =Pgimin If Pgi>Pgi max then Pgi =Pgimax STEP12: GOTO STEP 4. STEP13:Compute the optimal total cost from (1) and transmission loss from (4) STEP14:Stop
4.2.5 FLOWCHART FOR SOLVING ELD USING LAGRANGE METHOD ( INCLUDING LOSSES)
18
Start
Set IT=1
new + *P
Pgi= Pgmax
Pgi>Pg 19
max
Pgi
Stop
CHAPTER 5
20
A VERY FAST AND EFFECTIVE NON-ITERATIVE -LOGIC BASED METHOD INTRODUCTION PROBLEM FORMULATION ALGORITHM FLOW CHART
21
5.1 INTRODUCTION : In this chapter we have solved for the problem of economic load
dispatch neglecting losses by non-iterative lambda based method. The advantage of using this method is been clearly explained and the problem formulation and algorithm and flowchart have been represented. This is a direct or non iterative method it does not demand any initial guess value of for ED of units for a given P
demand
limits at voilating units. Improper selection of initial value of may cause slow convergence or at atimes leads to divergence for conventional algorithms. Further , each specified P D the problem is to be attempted afresh with new guess value of . If the load varies from P D min to PD
max
on the plant having Kunits ,the solution time becomes significantly large for higher values of
K. Unlike to this, this proposed method always offers the solution in an non-iterative mode with very low solution time as it is computationally very fast[2]. The proposed -logic method is a new contribution in the area of economic dispatch. It has two stages at first , preprepared power demand(PPD) is to be calculated. At the second stage solution vector (P1,P2,P3PK) is calculated with very less computation as is directly calculated for specified PD without any iterative approach .
22
and
-------------------------------------------------------------
(2) (3)
For given power demand, Pd P= Pd - PPD Then find new = slope*(P) + i --------------------------------(5)
Step4:Now calculate total power demand at each of ED condition. (i) min(i) then P(i) =Pmin(i)
Step5:Calculate slope between any two intervals of power demand and Step6: Calculate P1,P2.Pk = new new = slope (P)+ j Step7:Repeat the same process for different power demands. Step8:Stop. for specified pd using equation 1 where
vector.
5.2.3 FLOWCHART FOR SOLVING ELD PROBLEM USING NONi gi ITERATIVE LAMBDA BASED METHOD i=1,2ng
Read
F (P ),
Pd
I=
Start
Calculate min=dFi /dPgi at Pi=Pmin(i) max= dFi /dPg(i) at Pi =Pmax(i) Arrange lambda vector in ascending order If jmin(i Pi =Pmax(i)
)
Pi=Pmin(i)
j>max(
i)
Pi =[-bi ]/[2*ai ]
25
of power each j as
slope
from
P=Pdnew
PPDj,
Pi = Pmin(i)
and Pd=PPDi
stop
26
CHAPTER 6
27
28
The first one is the best solution (fitness) it has achieved so far.(The fitness value is also stored.) This value is called pbest. Another best value that is tracked by the particle swarm optimizer is the best value, obtained so far by any particle in the population. This best value is a global best and called g-best. When a particle takes part of the population as its topological neighbors, the Best value is a local best and is called p-best. After finding the two best values, the particle updates its velocity and positions with following equation.
In the above equation, The term rand()*(pbest i -Pi(u)) is called particle memory influence. The term rand()*( gbesti -Pi(u)) is called swarm influence. Vi(u) which is the velocity of ith particle at iterations u must lie in the range Vmin Vi(u) Vmax The parameter Vmax determines the resolution, or fitness, with which regions The are to be searched between the present position and the target position. If Vmax is too high, particles may fly past good solutions. If Vmin is too small, particles may not explore sufficiently. In many experiences with PSO, Vmax was often set at 10-20% of the dynamic range on each dimension. The constants C1 and C2 pull each particle towards pbest and gbest positions.
Low values allow particles to roam far from the target regions before being tugged back. On the other hand, high values result in abrupt movement towards, or past, target regions. The acceleration constant C1 and C2 are often set to be 2.0 according to past experiences.
29
Suitable selection of inertia weight provides a balance between global and local explorations, thus requiring less iteration on average to find a sufficiently optimal solution.
In general,the inertia weight w is set according to the following equation, Where w -is the inertia weighting factor Wmax - maximum value of weighting factor Wmin - minimum value of weighting factor ITERmax - maximum number of iteration ITER - current number of iteration
Where Ft = ai + biPi + ciPi2 $/hr The ELD problem is subjected to the following constraints, ----------------(1)
30
gi
= Pd+ Pl
------------------- (2)
In addition, power output of each generator has to fall with in the operation limits of the Generator Pgimin Pgi Pgimax for i=1,2n Constraints Satisfaction Technique: To satisfy the equality constraint of equation (3), a loading of any one of the units is selected as the dependent loading Pd and its present value is replaced by the value calculated according to the following equation,
Pd=Pd+Pl-
Where Pd can be calculated directly from the equation (5.a) with the known power demand P D and the known values of remaining loading of the generators. Therefore the dispatch solution will always satisfy the power balance constraint provided that P d also satisfies the operation limit constraint as given in equation (5). An infeasible solution is omitted and above procedure is repeated until Pd satisfies its operation limit. Because Pl also depends on Pd, we can substitute an expression for Pl in terms of P1,P2Pd..Pn and Bmn coefficients. After substituting it in the equation (5.a), separate the independent and dependent generator terms to obtain a quadratic equation for Pd. Solving the quadratic equation for Pd, the power balance equality condition is exactly satisfied.
31
Where 1=1,2,n
d=1,2,..m
STEP 6: Check the velocity components constraint occurring in the limits from the following conditions, If V id (u+1) > Vdmax then Vid (u+1)=Vdmax If V id (u+1) > Vdmin then Vid (u+1)=Vdmin Where Vd min = -0.5 Pgmin
32
STEP 8: If the evaluation value of each individual is better than previous pbest, the current value is set to be pbest. If the best pbest is better than gbest, the value is set to be gbest. STEP 9: If the number of iterations reaches the maximum, then go to step10. Otherwise, go to step2 . STEP 10: The individual that generates the latest gbest is the optimal generation power of each unit with the minimum total generation cost.
33
6.2.3 FLOWCHART FOR SOLVING ELD PROBLEM USING PARTICLE SWARM OPTIMIZATION TECHNIQUE
Start Initialize the particles with random position and velocity vectors
For each particle position (p)evaluate the fitness If fitness (p) is better than fitness of pbest then
Stop
34
CHAPTER 7
35
7.1 ECONOMIC LOAD DISPATCH OF THREE UNIT SYSTEM 7.1.1 LAMBDA ITERATIVE METHOD (WITH LOSSES)
In this method initial value of lambda is guessed in the feasible region that can be calculated from derivative of cost function. For the convergence of the problem the delta lambda should be selected small. Here delta lambda is selected 0.0001 and the value of lambda must be chosen near the optimum point. S.NO Power demand (MW) 450 585 700 800 900 P1(MW) P2(MW) P3(MW) Loss(MW) Cost Time (Rs/Hr) (sec) 4665.1 5844.7 6872.2 7783.3 8711.8 10.52 6.67 7.06 7.71 5.07
1 2 3 4 5
36
TABLE 7.1 : RESULTS OBTAINED FOR LAMBDA ITERATIVE METHOD (WITH LOSSES) 7.1.2 PARTICLE SWARM OPTIMIZATION METHOD In this method the initial particles are randomly generated within the feasible range. The parameters c1 and c2 and inertia weight are selected for best convergence characteristics. Here c1=2 and c2=2. Here maximum value of is chosen 0.9 and minimum value is 0.4. The velocity limits are selected as Vmax=0.5*Pmax and minimum velocity is selected as Vmin= -0.5*Pmin. There are ten number of particles selected in the population. Power demand (MW) 450 585 700 800 900
S.NO
P1(MW)
P2(MW)
P3(MW)
Loss(MW)
Cost Time (Rs/Hr) (sec) 4664.1 5842.7 6868.9 7779.3 8705.8 12.58 6.31 8.06 8.81 6.30
1 2 3 4 5
37
7.1.3 COMPARISION OF RESULTS OBTAINED IN LAGRANGE METHOD AND PSO METHOD ( WITH LOSSES)
It has been observed that when transmission line losses are included the minimum cost was found in PSO method and the execution time is minimum for Lagrange method. Power demand (MW) 450
Method PSO
LAGRANGE 450
TABLE 7.3 : RESULTS OBTAINED IN LAGRANGE METHOD AND PSO METHOD ( WITH LOSSES) FOR Pd= 450
TABLE 7.4 : RESULTS OBTAINED IN LAGRANGE METHOD AND PSO METHOD ( WITH LOSSES) FOR Pd= 900
38
7.2 ECONOMIC LOAD DISPATCH OF SIX UNIT SYSTEM 7.2.1 LAMBDA ITETARIVE METHOD (WITH LOSSES)
The initial value of lambda is guessed in the feasible region that can be calculated from the derivative of cost function. For the convergence of the problem must be selected small. The convergence is largely affected by the selection of lambda value. The time taken for convergence increases than the three unit system. It is also observed that the time taken for convergence of six unit with losses case is more than without losses case.
P1 (MW)
P2 (MW)
P3 (MW)
P4 (MW)
P5 (MW)
P6 (MW)
Loss (MW)
Cost (Rs/Hr)
Time (sec)
39
10 10 10.8 10 24.40
7.30 8.70
7.2.3 COMPARISION OF RESULTS OBTAINED IN LAGRANGE METHOD AND PSO METHOD ( WITH LOSSES)
It has been observed that when transmission line losses are included the minimum cost was found in PSO method compared to conventional method. The performance depends on randomly generated particle in PSO
40
Method
P2 P3 (MW (MW)
)
PSO LAGRANG E
10 10
95.70 95.62
TABLE 7.7: RESULTS OBTAINED IN LAGRANGE METHOD AND PSO METHOD ( WITH LOSSES) FOR Pd= 600 For Power Demand of 950MW Method P1 (MW) 39.0 5 39.03 P2 (MW) 24.40 23.97 P3 (MW) 191.8 0 175.30 P4 (MW) 172. 56 161.95 P5 (MW) 294.5 0 297.57 P6 (MW) 262. 40 287.77 Loss (MW) 34.9 0 35.64 Cost (Rs/Hr) 49681. 38 49683.10 Time (sec) 9.40 9.9
PSO
LAGRANGE
TABLE 7.8: RESULTS OBTAINED IN LAGRANGE METHOD AND PSO METHOD ( WITH LOSSES) FOR Pd= 950
41
7.3 ECONOMIC LOAD DISPATCH OF THREE UNIT SYSTEM 7.3.1 LAMBDA ITERATIVE METHOD (NEGLECTING LOSSES)
The initial value of lambda is guessed in the feasible region that can be calculated from the derivative of cost function. For the convergence of the problem must be selected small. The convergence is largely affected by the selection of lambda value.
S.NO
P1(MW)
P2(MW)
P3(MW)
1 2 3
voilating units. Improper selection of initial value of may cause slow convergence or at atimes leads to divergence for conventional algorithms
42
S.NO
P1(MW)
P2(MW)
P3(MW)
1 2 3
7.3.3 COMPARISION OF RESULTS OBTAINED IN LAGRANGE METHOD AND NON ITERATIVE METHOD ( NEGLECTING LOSSES)
It has been observed that when transmission line losses are not included the minimum cost was found in lambda based method when compared to non-iterative lambda based method but the time of execution is minimum for non iterative method. Power demand (MW)
Method
43
TABLE 7.11: RESULTS OBTAINED IN LAGRANGE METHOD AND NON ITERATIVE METHOD (NEGLECTING LOSSES) FOR Pd= 600
Method
TABLE 7.12 : RESULTS OBTAINED IN LAGRANGE METHOD AND NON ITERATIVE METHOD (NEGLECTING LOSSES) FOR Pd= 950
7.4 ECONOMIC LOAD DISPATCH OF SIX UNIT SYSTEM 7.4.1 LAMBDA ITERATIVE METHOD (NEGLECTING LOSSES)
The initial value of lambda is guessed in the feasible region that can be calculated from the derivative of cost function. For the convergence of the problem must be selected small. The convergence is largely affected by the selection of lambda value.
P1(MW)
P2(MW)
P3(MW)
P4(MW)
P5(MW)
P6(MW)
Cost (Rs/Hr)
Time (sec)
voilating units. Improper selection of initial value of may cause slow convergence or at atimes leads to divergence for conventional algorithms
Power P1(MW) demand (MW) P2(MW) P3(MW) P4(MW) P5(MW) P6(MW) Cost (Rs/Hr) Time (sec)
7.4.3 COMPARISION OF RESULTS OBTAINED IN LAGRANGE METHOD AND NON ITERATIVE METHOD ( NEGLECTING LOSSES)
It has been observed that when transmission line losses are not included the minimum cost was found in lambda based method when compared to non-iterative lambda based method but the time of execution is minimum for non iterative method.
45
Method
P1 (MW)
P2 (MW)
P3 (MW)
P4 (MW)
P5 (MW)
P6 (MW)
Cost (Rs/Hr)
Time (sec)
LAGRANGE
550
NON ITERATIVE
109.56 103.46
150 173.49
78.96 74.57
66.67 62.97
130 130
125 125
8056.7 8171.2
0.1870 0.1720
550
TABLE 7.15 : RESULTS OBTAINED IN LAGRANGE METHOD AND NON ITERATIVE METHOD (NEGLECTING LOSSES) FOR Pd= 550
Method
P1 (MW)
P2 (MW)
P3 (MW)
P4 (MW)
P5 (MW)
P6 (MW)
Cost (Rs/Hr)
Time (sec)
LAGRANGE
700 700
125.00 135.62
150 227.41
100.49 97.75
84.85 82.53
130 130
125 125
9079.5 10503.2
0.2030 0.1410
NON ITERATIVE
TABLE 7.16 : RESULTS OBTAINED IN LAGRANGE METHOD AND NON ITERATIVE METHOD (NEGLECTING LOSSES) FOR Pd=700
46
CHAPTER 8
47
CONCLUSION
In both study cases of three generating and six generating systems considering losses, PSO method gives the better cost than Lambda iterative method. In Lambda iterative method the number of iterations to converge increases. But in PSO method the no of iterations are not affected. In PSO method the selection of parameters c1,c2 and w are very important in the convergence of the system. And for the case of neglecting losses though Lambda iterative method gives the best result but the non-iterative method provides the result in less execution time.
48
REFERENCES/ BIBILOGRAPHY
[1] D.P.Kothari , J.S.Dhillon Power System Optimization Published by Prentice Hall of India Pvt.Ltd , NewDelhi. [2] D.P.Kothari , I.J.Nagrath Modern Power System Analysis Published by Mc.Graw-Hill [3] Dr.Maheswarapu Sydulu A Very Fast And Effective Non-Iterative -Logic Based Algorithm For Economic Dispatch Of Thermal Units 1999 IEEE TENCON [4] [5] [6] [7] [8] [9] M.Sudhakaran , P.Ajay-D-Vimal Raj and T.G.Palanivelu Application Of Particle Swarm Optimization For Economic Load Dispatch Problems S.S.Rao Power System Optimization D.C.Waltersw and G.B.Scheble , Genetic Algorithm Solution of Economic Dispatch with valve point loading, IEEE Trans. Power system J.Tippayachai, W.Ongsakul and I.Ngamroo, Parallel micro genetic algorithm for constrained economic dispatch IEEE Trans Power system. N.Sinha, R.Chakrabarthi and P.K.Chattopadhyay, Evolutionary programming techniques for economic load dispatch IEEE Evol. Comput.,7(February(1))( 2003). H.T.Yang, P.C.Yang and C.L.Huang, evolutionary programming based economic dispatch For units with nonsmooth fuel cost functions,IEEE trans.power system. [10] A.J.Wood and B.F.Wollenberg, Power Generation, Operation, and Control (2nd ed.), Wiley, New York(1996). [11] W.M.Lin,F.S.Cheng and M.T.Tsay, An improved Tabu search for economic dispatch with multiple minima, IEEE Trans , Power systems [12] A.J. Wood and B.F. Wollenberg, Power Generation, Operation, and and Sons., New York (1984). [13] P. Aravindhababu and K.R. Nayar, Economic dispatch based on optimal lambda using
49
radial basis function network, Elect. Power Energy Syst,. 24 (2002), pp. 551556. [14] IEEE Committee Report, Present practices in the economic operation IEEE Trans. Power Appa. Syst., PAS-90 (1971) 17681775. of power systems,
APPENDIX- I
CASE STUDY-1: THREE UNIT SYSTEM
The three generation units considered are having different characteristics. Their cost function characteristics are given by the following equations F1=0.00156P12+7.92P1+561 Rs/Hr F2=0.00194P22+7.85P2+310 Rs/Hr F3=0.00482P32+7.97P3+78 Rs/Hr According to the constraints considered in this work among inequality constraints only active power constraints are considered. Their operating limits of maximum and minimum power are also different. The unit operating ranges are 100MWP1600MW 100MWP2400MW 50MWP3200MW The transmission line losses can be calculated by knowing the loss coefficient. The B mn loss coefficient matrix is given by Bmn = 0.000075 0.000005 0.0000075 0.001940 0.000015 0.0000100
50
51
CASE STUDY-3: THREE UNIT SYSTEM ( NON- ITERATIVE LAMBDA BASED METHOD)
The cost function of three units are F1=0.00142P12+7.20P1+510 Rs/Hr F2=0.00194P22+7.85P2+310 Rs/Hr F3=0.00482P32+7.97P3+78 Rs/Hr According to the constraints considered in this work among inequality constraints only active power constraints are considered. Their operating limits of maximum and minimum power are also different. The unit operating ranges are 150MWP1600MW 100MWP2400MW 50MWP3200MW
52
53