You are on page 1of 194

Multiple Choice Single Answer Question MRP is based on the concept of inventory demand which is of following type Correct

Dependent and independent Answer Your Answer Dependent and independent

Multiple Choice Single Answer Question Main objective of a good plant layout is Correct Reduce material handling cost Answer Your Answer Reduce material handling cost

True/False Question

Correct Answer Your Answer False

As a general rule, the number of tail event of an activity is more than that of it's head event. False

Select The Blank Question The ________ is the probability that a good lot will be rejected by the sampling plan. Correct Producer's risk Answer Your Answer Producer's risk

Multiple Choice Multiple Answer Question Which of the following are important considerations concerning activity times? Correct Activity time should be obtained from the person responsible for the Answer completion of an activity , Activity time must be independent of any influence which the preceding or succeeding activity may have on it. , Activity time may assume that just the normal quantity of resources required to carry out the activity are available. Your Answer Activity time should be obtained from the person responsible for the completion of an activity , Activity time must be independent of any influence which the preceding or succeeding activity may have on it. , Activity time may assume that just the normal quantity of resources required to carry out the activity are available. Select The Blank Question The ________ pertain to the climatic conditions which the component , product or material should withstand. Correct Environmental specifications Answer Your Answer Environmental specifications

Multiple Choice Multiple Answer Question Following are some of the factors considered for evaluation of alternative

layouts Correct Flow of Material , Equipment utilization , Ease of supervision Answer Your Answer Flow of Material , Ease of supervision , Delivery performance

Multiple Choice Multiple Answer Question Which of the following are assignable cause? Correct Large varaitions in hardness of material , Tool wear , Errors in setting Answer Your Answer Large varaitions in hardness of material , Tool wear , Errors in setting

True/False Question

All activities must not be tied up into the network

Correct False Answer Your Answer False

Select The Blank Question In case of an OC curve, the risk of rejecting a good quality lot may vary between ________. Correct 0.01 to 10% Answer Your Answer 0.01 to 10%

True/False Question

Correct Answer Your Answer True

In case of X bar, if the process is not under control indicated by some points falling outside the control limits, such points outside the control limits are eliminated and new trial control limits for the remaining points are computed. True

Multiple Choice Single Answer Question What is the base for considering activity time as single time estimate or three time estimate? Correct Level of uncertainty Answer Your Answer Availability of labour

Select The Blank Question The ________ is the maximum percentage defective that for the purpose of sampling inspection can be considered satisfactory as a process average. Correct Acceptable quality level Answer Your Answer Acceptable quality level

Multiple Choice Single Answer Question What do you mean by lowest possible direct cost required to complete an activity within it's normal time? Correct Normal cost Answer Your Answer Normal cost

Select The Blank Question A good maintenance system is not a luxary but a ________. Correct Necessity Answer Your Answer Necessity

Select The Blank Question A ________helps to avoid crowding of jobs at a particular machine by change of route of some of the jobs or by diverting work to other machine. Correct Control board Answer Your Answer Move order

Select The Blank Question The ________ is the watch dog which ensures that every element of production and activities which could affect the quality of end product are regulated to the extent desirable. Correct Quality control Answer Your Answer Quality control

Multiple Choice Single Answer Question Any premise in which persons are employed for purpose of making any product/s is called Correct Factory Answer Your Answer Factory

Match The Following Question Emerson Efficiency Plan Craft Work Sampling Gantt Chart

Correct Answer Wage Payment Facilities Planning Machine utilization Production Scheduling

Your Answer Wage Payment Facilities Planning Machine utilization Production Scheduling

Select The Blank Question A ________ is another form of subcontracting. Correct Hiring capacity Answer Your Answer Hiring capacity

Multiple Choice Multiple Answer Question In an organization there may not be a formal PPC department if Correct Work is Answer the line Your Answer Work is the line highly repetitive in nature , Planning activities are performed by staff , Number of workmen is not very large highly repetitive in nature , Planning activities are performed by staff , Number of workmen is not very large

Multiple Choice Multiple Answer Question Which of the following cases can be treated as delay during recording of method study? Correct Operators awaiting instructions from supervisor , Worker waiting for his Answer turn at tools stores , Jobs awaiting at the machines for their turn Your Answer Operators awaiting instructions from supervisor , Worker waiting for his turn at tools stores , Jobs awaiting at the machines for their turn True/False Question

Correct Answer Your Answer False

Inspection order is must even for simple jobs which can be inspected by shop inspector with the tooling available on shop. False

Multiple Choice Multiple Answer Question Order preparation process for products manufatured to order requires following documents Correct Sales Order , Work order , Shop order Answer Your Answer Sales Order , Work order , Purchase order

Multiple Choice Single Answer Question Technique of Value Engineering can be effectively employed in design of a product to Correct To meet the intended function at lowest cost Answer Your Answer Reduce lead time

True/False Question

Correct Answer Your Answer False

Cent percent inspection is often more practical and economical than sampling inspection. False

Multiple Choice Multiple Answer Question Scale model used for layout analysis have following advantages Correct Nontechnical person finds Answer be shown , Models can be Your Answer Nontechnical person finds be shown , Models can be it easy to comprehend , Ovehead facilities can shifted easily it easy to comprehend , Ovehead facilities can shifted easily

Multiple Choice Single Answer Question Which of the following technique is event oriented ? Correct Project Evaluation & Review Technique Answer Your Answer Project Evaluation & Review Technique

Multiple Choice Single Answer Question What is the meaning of " Product features" according to J.M.Juran? Correct Quality of design Answer Your Answer Quality of design

Match The Following Question Crash cost of an activity Normal time of an activity Crash time of activity Normal cost of an activity

Correct Answer Cc Tn Tc Cn

Your Answer Cc Tn Tc Cn

Multiple Choice Multiple Answer Question What are uses of diagrams in method study? Correct Answer Study different plant layouts and select the most optimum one , Study the extent of traffic over the different routes of the plant , Identify the extent of backtracking, cross traffic and obstacles encountered during the movement of material. Your Answer Study different plant layouts and select the most optimum one , Study the extent of traffic over the different routes of the plant , Identify the extent of backtracking, cross traffic and obstacles encountered during the movement of material.

True/False Question

Correct Answer Your Answer True

A load chart specifies the work to be carried out by each person of company during shift hours. False

Multiple Choice Multiple Answer Question Route Sheet generally contains following information Correct Material Specification , Sequence of operation , Skill of Labour Answer Your Answer Material Specification , Sequence of operation , Skill of Labour

True/False Question

Cellular layout is based on the concept of Group Technology

Correct True Answer Your Answer True

Multiple Choice Single Answer Question Which varaible is taken along the abscissa or X axis? Correct Time Answer Your Answer Standard deviation

Multiple Choice Multiple Answer Question Which are the advantages of suburban location? Correct Answer Avaialability of adequate land at lower cost , Both skilled and unskilled labour can be available , Plant expansion is easier due to less or no restriction for building and construction Your Answer Avaialability of adequate land at lower cost , Both skilled and unskilled labour can be available , Plant expansion is easier due to less or no restriction for building and construction

Select The Blank Question The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking. Correct Condition monitoring Answer Your Answer Condition monitoring

Multiple Choice Multiple Answer Question Expediting function is concerned with following activities Correct Answer Progress chasing to identify delays which may hold up production , Communicating possible delays in delivery date commitment to sales department , Devising cures to keep rate of production in line with schedule Your Answer Recording progress of work , Progress chasing to identify delays which may hold up production , Communicating possible delays in delivery date commitment to sales department

Select The Blank Question Production control work is ________ in case of floor inspection as compared with the centralised inspection.

Correct easier Answer Your Answer time consuming

Select The Blank Question The easiest way to bring the delayed job within the promised delivery time by using extra shift or weekly holiday is ________. Correct Overtime working Answer Your Answer Overtime working

True/False Question

Correct Answer Your Answer True

In case of forward pass computation, the earliest event time of the first event is zero. True

Multiple Choice Single Answer Question What is represented by an arrow in a network? Correct Activity Answer Your Answer Activity

True/False Question

Correct Answer Your Answer True

As a general rule, a site five times the actual plant size is considered minimum for parking, access facilities and future expansion. True

True/False Question

Correct Answer Your Answer False

Independent float either affects the float of preceding activities or that of succeeding activities. False

Multiple Choice Single Answer Question The document raised by PPC which authorises different functions to take action as per instruction is called Correct Work Order Answer Your Answer Work Order Multiple Choice Single Answer Question A good layout makes effective use of space. Utilization of space for a department like Stores can be measured by

Correct Proportion of Cubic volume space utilized Answer Your Answer Ratio of area utilised to area available

Multiple Choice Single Answer Question The process of changing inputs into outputs thereby adding some value to entity can be defined as Correct Operation Answer Your Answer Operation

Multiple Choice Single Answer Question One of the sophisticated operations research techniques used in material planning is Correct Dynamic programming Answer Your Answer Dynamic programming True/False Question

Job life is one of the factors that influence Process Planning

Correct True Answer Your Answer True Multiple Choice Multiple Answer Question Following are some of the Principles of Management advocated by F W Taylor Correct Selection of best worker for each particular task , Division of work Answer between worker and management , Training and development of the workmen Your Answer Selection of best worker for each particular task , Division of work between worker and management , Training and development of the workmen Multiple Choice Single Answer Question Product layout is employed for manufacturing following products Correct refrigirators Answer Your Answer ships

Select The Blank Question Work study is also called ________ study Correct Time and Motion Answer Your Answer Job

Multiple Choice Multiple Answer

Which of the following situations demand the technical consideration while selecting a job for method study? Correct Jobs having inconsistent quality , Operations inviting frequent requests Answer from supervisors for relaxation in allowed time because of variations in materials and tool performance , Jobs in which too many man-hours are spend in checking and rechecking work Your Answer Jobs having inconsistent quality , Operations inviting frequent requests from supervisors for relaxation in allowed time because of variations in materials and tool performance , Jobs in which too many man-hours are spend in checking and rechecking work True/False Question

Question

Correct Answer Your Answer True

Quality control determines what, when, and how much to inspect while inspection actually conducts examination of goods. True

Select The Blank Question The ________ is the maximum percentage defective that for the purpose of sampling inspection can be considered satisfactory as a process average. Correct Acceptable quality level Answer Your Answer Producer's risk

Select The Blank Question The term ________ emplies the foregone profit due to inability of company to produce. Correct Opportunity cost Answer Your Answer Opportunity cost

True/False Question

All activities must not be tied up into the network

Correct False Answer Your Answer False

True/False Question

Correct Answer Your Answer True

F W Taylor devised a system for classifying motions into basic divisions called Therbligs False

Multiple Choice Multiple Answer Question Which of the following may be the objectives of project crashing? Correct Answer To achieve uniformity in requirement of resources , To complete the project in the least possible time , To reduce project cost below it's

normal cost Your Answer To complete the project in the least possible time , To achieve uniformity in requirement of resources , To improve the labour efficiency Multiple Choice Multiple Answer Question What is indicated by the hugging points lying close to mean of the process in X bar-R- control chart? Correct Biases in measurements , Recording done without actual measurements , Answer Improper selection of samples Your Answer Recording done without actual measurements , Improper selection of samples Multiple Choice Single Answer Question Following is one of the techniques used for Material Planning for high value material Correct MRP Answer Your Answer MRP

Select The Blank Question The ________ is the probability that a good lot will be rejected by the sampling plan. Correct Producer's risk Answer Your Answer Producer's risk

Multiple Choice Single Answer Question One of the characterstic of layout is about the flow of material / personnel. In a good layout the flow should be Correct Unidirectional Answer Your Answer Unidirectional

True/False Question

Correct Answer Your Answer False

The event numbers as far as possible reflect the logical relationships of the activities. True

Multiple Choice Multiple Answer Question Material Requirement Planning is very useful in following situations Correct Long Lead time for procurement , Several levels of assemblies in product Answer , Long manufacturing cycle Your Answer Long Lead time for procurement , Several levels of assemblies in product , Long manufacturing cycle True/False Question

Cent percent inspection is often more practical and economical than sampling inspection.

Correct False Answer Your Answer False

Select The Blank Question The ________ must ensure that the product satisfy the functional requirements of it's usage. Correct Quality of design Answer Your Answer Quality of conformance

True/False Question

Correct Answer Your Answer False

Both, preventive and breakdown maintenance work must be assigned to the same team. False

Multiple Choice Single Answer Question Following is one of the tasks of Production Control Correct Actual issue of forms and documents Answer Your Answer Actual issue of forms and documents

Multiple Choice Single Answer Question Process Engineer does not get sufficient time for designing tooling for most economic production run when Correct Delivery time is less Answer Your Answer Delivery time is less

Multiple Choice Multiple Answer Question Components of Production Management include Correct Capacity Planning , Job Design , Production Planning Answer Your Answer Capacity Planning , Production Planning , Manpower Planning

Multiple Choice Multiple Answer Question Which of the following products should be produced by using mass production? Correct Refrigerator , Tyre for automobile , Television Set Answer Your Answer Refrigerator , Tyre for automobile , Television Set

Multiple Choice Single Answer Question The process of changing inputs into outputs thereby adding some value to entity can be defined as

Correct Operation Answer Your Answer Manufacturing

Select The Blank Question A good maintenance system is not a luxary but a ________. Correct Necessity Answer Your Answer Necessity

Multiple Choice Single Answer Question What is the specific name for the Gantt chart when it shows at a glance the scheduling of various operations involved in a job? Correct Job Schedule Answer Your Answer Load Chart

Select The Blank Question A set of activities to keep an equipment in the specified condition is called as ________. Correct Maintenance Answer Your Answer Maintenance

Multiple Choice Single Answer Question What do you mean by lowest possible direct cost required to complete an activity within it's crashed time? Correct Crash cost Answer Your Answer Crash cost

Multiple Choice Multiple Answer Question Which of the following factors decide the choice between the cent percent and sampling inspection? Correct Nature of inspection , Natural tolerance versus design tolerance , Answer Vendor's quality rating Your Answer Nature of inspection , Natural tolerance versus design tolerance , Vendor's quality rating Select The Blank Question The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking. Correct Condition monitoring Answer Your Answer Condition monitoring

Multiple Choice Multiple Answer Question Which of the following are examples of attributes?

Correct Cracks , Burrs , Texture Answer Your Answer Cracks , Burrs , Texture

Multiple Choice Single Answer Question Which of the following is the criteria for the percentage defectives in the zone of the indecision? Correct Lots having the percentage defective more than AQL but less than LPTD Answer Your Answer Lots having the percentage defective more than AQL but less than LPTD

Multiple Choice Single Answer Question In mass/batch production organizations where goods are produced for stocking, Work Order is raised on the basis of Correct Sales Programme Answer Your Answer Sales Order

Match The Following Question Fixed Position Layout Product Layout Process Layout Combined Layout

Correct Answer Project Layout Line Layout Functional Layout Mixed Layout

Your Answer Functional Layout Project Layout job layout Mixed Layout

Multiple Choice Single Answer Question What do you understand by the measurement of work to establish allowed time for a job for the defined method? Correct Work measurement Answer Your Answer Work measurement

Select The Blank Question In case of an OC curve, the risk of rejecting a good quality lot may vary between ________. Correct 0.01 to 10% Answer Your Answer 0.01 to 10%

True/False Question Correct Answer

Objective of Work Study is to improve Productivity True

Your Answer False

Multiple Choice Multiple Answer Question Which are the distinct functions of scientific quality control? Correct Acceptance function , Preventive function , Assurance function Answer Your Answer Acceptance function , Feedback function , Preventive function

Match The Following Question Interruption for machine utilisation Input for scheduling Technique of scheduling Scheduling Device

Correct Answer Preventive maintenance Overlapping of operations Critical Path Analysis Strings

Your Answer Preventive maintenance Strings Critical Path Analysis Blackboard

Select The Blank Question An Ideal OC curve is ________ shaped curve that accpets all the lots with quality equal to or better than AQL . Correct Rectangular Answer Your Answer Rectangular

True/False Question

Correct Answer Your Answer True

Breakdown of machines, absenteeism of worker does not dislocate the manufacturing activity in process layout True

True/False Question

Correct Answer Your Answer True

Since value of c can never be negativee, hence" if LCLp works out to be negative, it is taken as zero." True

Multiple Choice Single Answer Question Who prepares the daily production report? Correct Shop Supervisor Answer Your Answer Worker

True/False Question

Correct Answer Your Answer True

The dispatching function is of very importance in flow and mass production units. False

Multiple Choice Multiple Answer Question Which are major benefits of identifying the critical path? Correct Answer It helps to identify the set of activities and events which are critical and as such must be carefully controlled and monitored , It identifies activities to be given preference in allocation of resources. , It helps to exercise "control by exception". Your Answer It helps to identify the set of activities and events which are critical and as such must be carefully controlled and monitored , It helps to exercise "control by exception".

True/False Question Site selection should also take into account topography and soil structure of the land. Correct True Answer Your True Answer Multiple Choice Single Answer Question Which manufacturing method is ideal for the use of air gauges as inspection device? Correct Mass Answer Your Batch Answer True/False Question Kanban system is essentially a computer based system for production scheduling and control Correct False Answer Your False Answer Multiple Choice Multiple Answer Question Which are three different bases to establish an activity time? Correct Answer Your Answer Past experience , Judgement , Historical data Past experience , Judgement , Historical data

True/False Question Inspection order is must even for simple jobs which can be inspected by shop inspector with the tooling available on shop.

Correct Answer Your Answer

False False

Multiple Choice Single Answer Question Which of the following policies is advisable in case of low product variety and large volumes? Correct Low Skilled Labour & Special Purpose Machines Answer Your Semiskilled Labour & General Purpose Machines Answer Select The Blank Question Capacity decisions have a direct influence on performance of production system in respect of ________ Correct Delivery performance Answer Your Delivery performance Answer True/False Question In case of X bar, if the process is not under control indicated by some points falling outside the control limits, such points outside the control limits are eliminated and new trial control limits for the remaining points are computed. Correct True Answer Your True Answer Select The Blank Question The ________ pertain to the climatic conditions which the component , product or material should withstand. Correct Environmental specifications Answer Your Environmental specifications Answer Select The Blank Question The ________ is necessary when the job requires detailed of one or more of the job characteristics with the help of special equipment which is not available at the producing company. Correct Inspection order Answer Your Job card Answer Match The Following Question Crash cost of an activity Normal time of an activity

Correct Answer Cc Tn

Your Answer Cc Cn

Crash time of activity Normal cost of an activity

Tc Cn

Tc Tn

True/False Question Lubrication survey should never be done for a new machine. Correct Answer Your Answer False False

Multiple Choice Single Answer Question A good plant layout helps in Correct Answer Your Answer Reducing handling costs Reducing handling costs

Multiple Choice Single Answer Question Out of two basic criteria for the selection of a manufacturing method, one is, it must be able to meet the specifications of final product and the other is, it must be Correct Cost effective method Answer Your Cost effective method Answer Multiple Choice Multiple Answer Question Which of the following is a part of preparing manufacturing order set as a primary function of dispatching? Correct Operational layouts , Move orders , Pre-filled stores issue orders Answer Your Operational layouts , Move orders , Pre-filled stores issue orders Answer Select The Blank Question A ________ is another form of subcontracting. Correct Answer Your Answer Hiring capacity Hiring capacity

Multiple Choice Multiple Answer Question Which are the major types of defects? Correct Answer Your Answer Minor , Major , Critical Minor , Critical , General

Multiple Choice Single Answer

Question Correct Answer Your Answer

Which kind of labour force is required in case of Jobbing Production? Highly Skilled Highly Skilled

Multiple Choice Multiple Answer Question Which are the sources of information to update the progress card daily? Correct Answer Your Answer Detachable ticket , Daily production report , Job Card Detachable ticket , Daily production report , Job Card

True/False Question In case of forward pass computation, the earliest event time of the first event is zero. Correct True Answer Your True Answer Multiple Choice Multiple Answer Question Which are the distinct functions of scientific quality control? Correct Answer Your Answer Acceptance function , Preventive function , Assurance function Acceptance function , Preventive function , Assurance function

Multiple Choice Multiple Answer Question Which of the following are examples of specifications? Correct Answer Your Answer Commercial standards , Assembly and testing instructions , Bill of material Production schedule , Commercial standards , Bill of material

Multiple Choice Single Answer Question Technique which can help an organization to reduce inventory is called Correct Answer Your Answer MRP MRP

Multiple Choice Single Answer Question In case of Batch Production which kind of labour is expected? Correct Answer Your Answer Skilled in one specific Manufacturing Process Semiskilled

Multiple Choice Multiple Answer

Question Correct Answer Your Answer

Major contributors in the development of Control Charts, Sampling plan are F H Dodge , H G Roming , Walter Schewhart F H Dodge , H G Roming , Walter Schewhart

Multiple Choice Single Answer Question What is represented by an arrow in a network? Correct Answer Your Answer Activity Event

True/False Question Feasibility of time schedule requires that an activity be scheduled before any of it's predecessors are scheduled. Correct False Answer Your True Answer Multiple Choice Single Answer Question Which method of critical path determination begins with the end event and moves backward to the start event of the project network? Correct Backward pass computation Answer Your Backward pass computation Answer True/False Question Operation process charts though indicates the sequence of events but do not show movements. Correct True Answer Your True Answer Multiple Choice Single Answer Question Which kind of relationship exists between those activities which can be carried out simultaneously and both activities require definite time to finish? Correct Concurrent activities Answer Your Concurrent activities Answer True/False Question One major difference between CPM and PERT is the former's adaptability for the projects where high degree of uncertainty prevails and activity times during performance are expected to vary considerably for certain activities. Correct False Answer

Your Answer

False

Multiple Choice Multiple Answer Question Following are some of the Principles of Management advocated by F W Taylor Correct Selection of best worker for each particular task , Division of work Answer between worker and management , Training and development of the workmen Your Selection of best worker for each particular task , Division of work Answer between worker and management , Training and development of the workmen Multiple Choice Single Answer Question Inadequate production capacity ultimately leads to Correct Answer Your Answer Poor Customer Service Poor Machine Utilization

Multiple Choice Multiple Answer Question Which of the following schedules are recommended to prepare and follow as a part of preventive maintenance system? Correct Preventive inspection schedule , Cleaning and upkeep schedule , Answer Lubrication schedule Your Preventive inspection schedule , Cleaning and upkeep schedule , Answer Lubrication schedule Multiple Choice Single Answer Question What is the reason of fluctuations, if the control chart evaluates that the process is in a state of statistical control? Correct Random variability Answer Your Random variability Answer True/False Question Even in a small set up wherein maintenance of a machine is looked after by a mechanic cum worker, he should report directly to the person responsible for the manufacturing operations. Correct True Answer Your True Answer Multiple Choice Single Answer Question What do you mean by the chart on which the major activities and entry points of materials are recorded to have graphic view of operations and inspections involved in the process? Correct Operation process chart Answer Your Operation process chart Answer

Multiple Choice Single Answer Question Plant Layout decisions are considered to be Correct Answer Your Answer Strategic Strategic

Multiple Choice Multiple Answer Question What are the uses of the instruction manual provided by the manufacturer of a machine? Correct It gives instructions regarding installation and operation of the equipment Answer , It contains note on common troubles with causes and remedies for troubleshooting , It enlists points, frequency and type of lubrication Your It gives instructions regarding installation and operation of the equipment Answer , It contains note on common troubles with causes and remedies for troubleshooting , It enlists points, frequency and type of lubrication Multiple Choice Single Answer Question When should operator or supervisor is supposed to sign the perforated route sheet? Correct After completion of operation Answer Your After completion of operation Answer Multiple Choice Multiple Answer Question Which of the following situations demand that the human consideration should be given preference over other considerations? Correct Inconsistent earnings where the earnings are tied to output , Poor morale Answer evidenced by petty or trivial complaints , Repeated cases of accidents and health hazards Your Excessive rejections , Poor morale evidenced by petty or trivial complaints Answer , Repeated cases of accidents and health hazards True/False Question A network can have more than one starting event but completion event must be only one. Correct False Answer Your True Answer Multiple Choice Single Answer Question Which is the ideal place to write a description of an activity in a network? Correct Answer Your Answer Above the arrow Above the arrow

Multiple Choice Multiple Answer Question Which features should be covered by the specifications of materials while defining the qualitative requirement? Correct Material composition , Dimensions , Any heat treatment if required Answer

Your Answer

Material composition , Dimensions , Any heat treatment if required

Match The Following Question When to inspect What to inspect How to inspect How much to inspect

Correct Answer Stages of inspection Specification Inspection devices Sampling or cent percent inspection

Your Answer Stages of inspection Specification Inspection devices Sampling or cent percent inspection

Multiple Choice Multiple Answer Question How the concept of float is helpful to planners? Correct Answer Your Answer To decide priorities in allocation of resources requirement of resources , To prevent peaks resources To decide priorities in allocation of resources requirement of resources , To prevent peaks resources , To minimize the and valleys in requirement of , To minimize the and valleys in requirement of

Multiple Choice Multiple Answer Question Which of the following aspects are essential to ensure quality of purchased items? Correct Defining right quality for the job , Vendor performance evaluation , Answer Making sure that suppliers understand the requirements Your Answer Defining right quality for the job , Vendor performance evaluation , Making sure that suppliers understand the requirements Select The Blank Question The ________ breakdowns usually cost more, partly due to damage done to the adjustment components and partly due to emergency actions. Correct Unexpected Answer Your Answer Unexpected True/False Question

Correct Answer Your Answer False True/False Question

After goods have been manufactured, route sheets and operation layouts should not be collected back. False

In case of centralised inspection, inspection rooms generally become bottleneck and cause delay in taking action regarding rejection or rework.

Correct True Answer Your Answer True

Multiple Choice Single Answer Question MRP is based on the concept of inventory demand which is of following type Correct Dependent and independent Answer Your Answer Dependent and independent

Multiple Choice Single Answer Question Any premise in which persons are employed for purpose of making any product/s is called Correct Factory Answer Your Answer Factory

Multiple Choice Multiple Answer Question Components of Production Management include Correct Capacity Planning , Job Design , Production Planning Answer Your Answer Capacity Planning , Job Design , Production Planning

Multiple Choice Single Answer Question Which of the following is the criteria for the percentage defectives in the zone of the indecision? Correct Lots having the percentage defective more than AQL but less than LPTD Answer Your Answer Lots having the percentage defective more than AQL but less than LPTD

Multiple Choice Multiple Answer Question Which of the following are examples of addition during recording for method study? Correct Brazing , Welding , Riveting Answer Your Answer Brazing , Welding , Riveting

Select The Blank Question The easiest way to bring the delayed job within the promised delivery time by using extra shift or weekly holiday is ________. Correct Overtime working Answer Your Answer Overtime working

Select The Blank Question An Ideal OC curve is ________ shaped curve that accpets all the lots with quality equal to or better than AQL .

Correct Rectangular Answer Your Answer Rectangular

Multiple Choice Multiple Answer Question Which of the following causes can be responsible for derailing the production schedule in a factory? Correct Errors in drawings , Delay in receipt of material from vendor , Excessive Answer absenteeism Your Answer Errors in drawings , Delay in receipt of material from vendor , Excessive absenteeism Multiple Choice Multiple Answer Question Which of the following situations demand the economic consideration while selecting a job for method study? Correct Unorderly movement of men and materials , Excessive process defectives Answer , Too many suggestions received for improvement from a department or section Your Answer Unorderly movement of men and materials , Excessive process defectives , Inconsistent quality True/False Question

Correct Answer Your Answer False

During set up of X bar-R control chart, control limts should be practically revised from time to time as additional data is accumulated. True

Multiple Choice Multiple Answer Question Which of the following are the basic requirements of quality standard? Correct Deifinite , Undesrstandable , Economically viable Answer Your Answer Absolute uniformity , Undesrstandable , Economically viable

Match The Following Question Toung Eye Nose Ear

Correct Answer Sweet Crack Burnout Impact

Your Answer Sweet Crack Burnout Roughness

Select The Blank Question The ________ is the defect level for which lots are regarded as bad lots. Correct Answer Lot Tolerance Percentage Defective

Your Answer Acceptable quality level

True/False Question

Correct Answer Your Answer False

Floor inspection delays the identification of faults which can not be rectified immediately before large lots are spoiled. False

True/False Question

Correct Answer Your Answer True

Cent percent inspection is required on WIP prior to the key, critical or costly operation. True

Multiple Choice Single Answer Question The document which incorporates details of process planning for a job is called Correct Route Sheet Answer Your Answer Route Sheet

True/False Question

Correct Answer Your Answer True

Repetitive movements between work stations which are difficult to be traced on string diagrams can be conveniently shown on flow diagrams. False

Multiple Choice Single Answer Question Which of the following is the most popular technique for Project Production? Correct PERT & CPM Answer Your Answer PERT & CPM

Multiple Choice Single Answer Question Technique of Value Engineering can be effectively employed in design of a product to Correct To meet the intended function at lowest cost Answer Your Answer To meet the intended function at lowest cost

Multiple Choice Single Answer Question What can be the worst effect due to excessive vibration? Correct Answer Breakdown

Your Answer Breakdown

Multiple Choice Single Answer Question What is the relation between duration of an activity and length of an arrow? Correct No relation Answer Your Answer No relation

Multiple Choice Single Answer Question What is the nature of the sampling plan for critical defects? Correct Tight Answer Your Answer Tight

Select The Blank Question The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking. Correct Condition monitoring Answer Your Answer Condition monitoring

Multiple Choice Multiple Answer Question Which of the following are important considerations concerning activity times? Correct Activity time should be obtained from the person responsible for the Answer completion of an activity , Activity time must be independent of any influence which the preceding or succeeding activity may have on it. , Activity time may assume that just the normal quantity of resources required to carry out the activity are available. Your Answer Activity time should be obtained from the person responsible for the completion of an activity , Activity time must be independent of any influence which the preceding or succeeding activity may have on it. , Activity time may assume that just the normal quantity of resources required to carry out the activity are available. Multiple Choice Single Answer Question Which of the following techniques is used by industrial engineering department to obtain the utilisation index? Correct Work Sampling Studies Answer Your Answer Break Even Analysis

Multiple Choice Multiple Answer Question Which of the following factors play important role while selecting or rejecting a particular site from legislation and taxation point of view? Correct Labour laws , Building codes , Policies regarding issue of licences Answer Your Answer Labour laws , Building codes , Policies regarding issue of licences

Multiple Choice Multiple Answer Question Which of the following cases can be referred as operation in method study recording? Correct Change in physical characteristic , Consumption of physical effort , Answer Change in chemical characteristic Your Answer Change in physical characteristic , Consumption of physical effort , Movement of material True/False Question

Correct Answer Your Answer True

An activity can share the same tail event and same head event with any other activity. False

Select The Blank Question The ________ must ensure that the product satisfy the functional requirements of it's usage. Correct Quality of design Answer Your Answer Quality of design

Multiple Choice Multiple Answer Question Which of the following are examples of pure materials? Correct Bakeries , Ice factories , Woolen Answer Your Answer Bakeries , Ice factories , Woolen

Select The Blank Question The ________ are the definitions of the measurable as well as nonmeasurable characteristics of the product. Correct Specifications Answer Your Answer Specifications

Multiple Choice Single Answer Question Site factors for plant location include Correct Suitability of land Answer Your Answer Suitability of land

Select The Blank Question The ________ is the probability that a good lot will be rejected by the sampling plan. Correct Producer's risk Answer Your Answer Producer's risk

Multiple Choice Multiple Answer Question Which of the following defects can be observed during preventive inspection by using human senses? Correct Deviation from normal sound , Excessive Vibration , Leakage of a gas Answer Your Answer Deviation from normal sound , Excessive Vibration , Leakage of a gas

Select The Blank Question The ________ includes preventive maintenance activities whose needs are identified through inspection which requires stoppage of machines. Correct Shutdown Maintenance Answer Your Answer Working Maintenance

True/False Question

Correct Answer Your Answer False

Independent float either affects the float of preceding activities or that of succeeding activities. False

Multiple Choice Multiple Answer Question Lack of material planning results in the following Correct Over ordering , under ordering , stockouts Answer Your Answer Over ordering , under ordering , stockouts

True/False Question

Correct Answer Your Answer False

F W Taylor devised a system for classifying motions into basic divisions called Therbligs False

Select The Blank Question Work study is also called ________ study Correct Time and Motion Answer Your Answer Time and Motion

Match The Following Question Factor Analysis Minimization of production delays

Correct Answer Method to evaluate layouts Objective of good layout

Your Answer Technique for evolving and analysis of layouts Objective of good layout

Maximum visibility Scale model

Principles of good layout Layout analysis

Principles of good layout Method to evaluate layouts

Multiple Choice Single Answer Question Following is one of the techniques used for Material Planning for high value material Correct MRP Answer Your Answer MRP

Multiple Choice Single Answer Question What do you understand by totality of features and characteristics of a product or service that bears on it's ability to satisfy the customer? Correct Quality Answer Your Answer Quality

Select The Blank Question One detachable ticket is prepared for each ________. Correct Operation Answer Your Answer Worker

LIST OF ATTEMPTED QUESTIONS AND ANSWERS Multiple Choice Single Answer Question Which of the following technique makes three time estimates for each activity? Correct Answer Project Evaluation & Review Technique Your Answer Project Evaluation & Review Technique True/False Question Mixed layouts are generally used in case of product is to be produced in different sizes/types: contains too many components Correct Answer True Your Answer True True/False Question In case of two handed process chart, storage symbol is used when either hand is used as grip or vice to hold an object. Correct Answer True Your Answer True Match The Following Question Correct Answer Your Answer Fixation of inventory level Reorder level Reorder level

Symptom of ill planned purchasing Over ordering Over ordering Factor influencing material planning Lead time Lead time Net requirement of material under MRP Stock on hand Stock on hand

Multiple Choice Multiple Answer Question Following are the commonly used factors considered for evaluation of layout in factor analysis method Correct Answer Flow of material , Equipment utilization , Working condition Your Answer Flow of material , Equipment utilization , Working condition Multiple Choice Multiple Answer Question Which of the following are examples of pure materials? Correct Answer Bakeries , Ice factories , Woolen Your Answer Bakeries , Ice factories , Woolen Multiple Choice Multiple Answer Question Which of the following factors decide the choice between the cent percent and sampling inspection? Correct Answer Nature of inspection , Natural tolerance versus design tolerance , Vendor's quality rating Your Answer Nature of inspection , Natural tolerance versus design tolerance , Vendor's quality rating Multiple Choice Single Answer Question What do you mean by planned corrective manitenance which provides an opportunity to undertake design modifications in the equipment to eliminate or reduce frequency of breakdowns. Correct Answer Design-out Maintenance Your Answer Design-out Maintenance Multiple Choice Single Answer Question The product layout has following disadvantage Correct Answer Layout is not flexible Your Answer Layout is not flexible Multiple Choice Multiple Answer Question Which utilities are considered as infrastructural requirements? Correct Answer Disposal of waste , Power , Water Your Answer Disposal of waste , Power , Water Multiple Choice Multiple Answer Question Which are the factors on which the structure of the transportation cost depends? Correct Answer Average distance of shipment , Characteristics of the commodity , Medium of shipment Your Answer Average distance of shipment , Characteristics of the commodity , Medium of shipment

Multiple Choice Multiple Answer Question Which are the three basic types of control chart by attribute? Correct Answer p-chart , c-chart , np-chart Your Answer p-chart , c-chart , np-chart True/False Question It would not affect the project completion time if non-critical activities take little loner time than planned. Correct Answer True Your Answer True Multiple Choice Single Answer Question A good layout makes effective use of space. Utilization of space for a department like Stores can be measured by Correct Answer Proportion of Cubic volume space utilized Your Answer Proportion of Cubic volume space utilized Multiple Choice Single Answer Question Process planning is the process of Correct Answer establishing shortest and most economic path of production Your Answer establishing shortest and most economic path of production Multiple Choice Single Answer Question Who prepares the daily production report? Correct Answer Shop Supervisor Your Answer Shop Supervisor Multiple Choice Multiple Answer Question Which of the following are examples of gross materials? Correct Answer Timber , Iron ore , Sugar cane Your Answer Timber , Iron ore , Sugar cane Multiple Choice Multiple Answer Question Which of the following defects can be observed during preventive inspection by using human senses? Correct Answer Deviation from normal sound , Excessive Vibration , Leakage of a gas Your Answer Deviation from normal sound , Excessive Vibration , Leakage of a gas Multiple Choice Multiple Answer Question Which of the following are the objectives of a good maintenance system? Correct Answer Elimination of unsafe conditions , Minimisation of wear and tear of machines , Ensuring maximum plant availability Your Answer Elimination of unsafe conditions , Minimisation of wear and tear of machines , Ensuring maximum plant availability Select The Blank Question Production control work is ________ in case of floor inspection as compared with the centralised inspection. Correct Answer easier

Your Answer easier Select The Blank Question The easiest way to bring the delayed job within the promised delivery time by using extra shift or weekly holiday is ________. Correct Answer Overtime working Your Answer Overtime working True/False Question Latest starting date is the latest finishing time minus activity duration. Correct Answer True Your Answer True Select The Blank Question In case of an OC curve, the risk of rejecting a good quality lot may vary between ________. Correct Answer 0.01 to 10% Your Answer 0.01 to 10% Select The Blank Question The ________ advocates maintenance procedures whereby the condition of the plant is constantly watched through systematic inspection to unearth unhealthy conditions and preventive Correct Answer Preventive Maintenance Your Answer Preventive Maintenance Select The Blank Question The ________ breakdowns usually cost more, partly due to damage done to the adjustment components and partly due to emergency actions. Correct Answer Unexpected Your Answer Unexpected Select The Blank Question The term ________ emplies the foregone profit due to inability of company to produce. Correct Answer Opportunity cost Your Answer Opportunity cost Multiple Choice Single Answer Question Process type layout is suitable when Correct Answer there is wide variation in processing time of operations Your Answer there is wide variation in processing time of operations Select The Blank Question The ________ is the process of withdrawing the equipment from the production line, dismantling it unitwise, visualising defects, effecting adjustments, replacing worn-out parts and finally building it up to get desired accuracies. Correct Answer Reconditioning Your Answer Reconditioning

True/False Question One major difference between CPM and PERT is the former's adaptability for the projects where high degree of uncertainty prevails and activity times during performance are expected to vary considerably for certain activities. Correct Answer False Your Answer False True/False Question Kanban system is essentially a computer based system for production scheduling and control Correct Answer False Your Answer False Select The Blank Question The ________ is the defect level for which lots are regarded as bad lots. Correct Answer Lot Tolerance Percentage Defective Your Answer Lot Tolerance Percentage Defective Multiple Choice Single Answer Question How dummy activities are shown in the time chart during project scheduling? Correct Answer Vertical lines Your Answer Dotted lines Match The Following Question Correct Answer Your Answer Factor Analysis Method to evaluate layouts Method to evaluate layouts Minimization of production delays Objective of good layout Objective of good layout Maximum visibility Principles of good layout Principles of good layout Scale model Layout analysis Layout analysis

Multiple Choice Multiple Answer Question In an organization there may not be a formal PPC department if Correct Answer Work is highly repetitive in nature , Planning activities are performed by the line staff , Number of workmen is not very large Your Answer Work is highly repetitive in nature , Planning activities are performed by the line staff , Number of workmen is not very large Multiple Choice Multiple Answer Question Which three of the following are causes of continuous upward pattern of Xbar-R control chart? Correct Answer Wear of tool , Abnormal rise in temperature , Accumulation of dirt Your Answer Wear of tool , Abnormal rise in temperature , Accumulation of dirt True/False

Question A network should employ only those dummy activities which are absolutely necessary. Correct Answer True Your Answer True Select The Blank Question The ________ includes preventive maintenance activities whose needs are identified through inspection which requires stoppage of machines. Correct Answer Shutdown Maintenance Your Answer Shutdown Maintenance Multiple Choice Single Answer Question What do you understand by identification of defects in materials, components, machining processes or men to fix responsibility of defectives, thereby preventing or minimising occurance of defectives? Correct Answer Preventive function Your Answer Preventive function Select The Blank Question OC curve of ideal sampling plan suggests that all lots less than 3% defectives have the probability of acceptance of ________. Correct Answer One Your Answer One Select The Blank Question A set of activities to keep an equipment in the specified condition is called as ________. Correct Answer Maintenance Your Answer Maintenance Multiple Choice Single Answer Question One of the external factors influencing Material Planning is Correct Answer Price trends Your Answer Price trends Multiple Choice Multiple Answer Question What is indicated by the erratic pattern points falling above and below the control limits in the Xbar-R-control chart? Correct Answer Defects in materials , Poorly trained operators , Frequent adjustments of machines Your Answer Defects in materials , Poorly trained operators , Frequent adjustments of machines True/False Question Inspection should be conducted prior to an operaion, after whose completion no rework whatsoever is possible. Correct Answer True Your Answer True Multiple Choice Single Answer

Question What do you mean by CPM? Correct Answer Critical Path Method Your Answer Critical Path Method True/False Question Planned lubrication is said to be the nervous system of the equipment. Correct Answer True Your Answer True True/False Question In case of X bar-R charts,it is ensured that the assignable causes are detected before the tolerances are violated, upper and lower statistical limits are worked out and inserted into a chart. Correct Answer True Your Answer True Multiple Choice Single Answer Question Provision of drainage facilities is important for the following type of industry Correct Answer Chemical Process Your Answer Chemical Process

LIST OF ATTEMPTED QUESTIONS AND ANSWERS Select The Blank Question Production Planning is a centralised activity which includes functions such as ________ Correct Answer Scheduling Your Answer Scheduling Multiple Choice Single Answer Question In case of Batch Production which kind of labour is expected? Correct Answer Skilled in one specific Manufacturing Process Your Answer Skilled in one specific Manufacturing Process Select The Blank Question A good maintenance system is not a luxary but a ________. Correct Answer Necessity Your Answer Necessity Multiple Choice Single Answer Question A good layout makes effective use of space. Utilization of space for a department like Stores can be measured by Correct Answer Proportion of Cubic volume space utilized Your Answer No such measure in use True/False

Question One major difference between CPM and PERT is the former's adaptability for the projects where high degree of uncertainty prevails and activity times during performance are expected to vary considerably for certain activities. Correct Answer False Your Answer False Multiple Choice Multiple Answer Question In an organization there may not be a formal PPC department if Correct Answer Work is highly repetitive in nature , Planning activities are performed by the line staff , Number of workmen is not very large Your Answer Work is highly repetitive in nature , Planning activities are performed by the line staff , Number of workmen is not very large Multiple Choice Single Answer Question Which industry out of the following industries require maximum consideration for safety factor while selecting plant location? Correct Answer Nuclear power plant Your Answer Nuclear power plant Select The Blank Question The easiest way to bring the delayed job within the promised delivery time by using extra shift or weekly holiday is ________. Correct Answer Overtime working Your Answer Overtime working Select The Blank Question OC curve of ideal sampling plan suggests that all lots less than 3% defectives have the probability of acceptance of ________. Correct Answer One Your Answer One Multiple Choice Multiple Answer Question Following are some of the Principles of Management advocated by F W Taylor Correct Answer Selection of best worker for each particular task , Division of work between worker and management , Training and development of the workmen Your Answer Selection of best worker for each particular task , Division of work between worker and management , Training and development of the workmen Multiple Choice Single Answer Question Out of two basic criteria for the selection of a manufacturing method, one is, it must be able to meet the specifications of final product and the other is, it must be Correct Answer Cost effective method Your Answer Cost effective method Multiple Choice Single Answer Question What does CPA stand for? Correct Answer Critical Path Analysis Your Answer Critical Path Analysis Multiple Choice Multiple Answer

Question What is the basic minimum requirement for those who are responsible for the quality of design? Correct Answer In depth knowledge about alternative materials and manufacturing processes , access to latest technology and production process adopted by industries in the developed market , Continuous effort in product development Your Answer In depth knowledge about alternative materials and manufacturing processes , access to latest technology and production process adopted by industries in the developed market , Continuous effort in product development True/False Question A lot declared rejected in sampling inspection should not be inspected 100% in any case. Correct Answer False Your Answer False True/False Question A network should employ only those dummy activities which are absolutely necessary. Correct Answer True Your Answer True Multiple Choice Multiple Answer Question Which of the following are scheduling techniques? Correct Answer Critical Path Analysis , Index Method , Johnson's two machine algorithm Your Answer Critical Path Analysis , Index Method , Johnson's two machine algorithm True/False Question The component produced on completely automatic machines may be subjected to sampling inspection while parts produced on semi-automatic and completely manual operated machines require cent percent inspection. Correct Answer True Your Answer True Multiple Choice Single Answer Question The ratio of output to input of a production system is commonly known as Correct Answer Productivity Your Answer Productivity Multiple Choice Single Answer Question Which of the following policies is advisable in case of low product variety and large volumes? Correct Answer Low Skilled Labour & Special Purpose Machines Your Answer Low Skilled Labour & Special Purpose Machines Multiple Choice Single Answer Question Any premise in which persons are employed for purpose of making any product/s is called Correct Answer Factory Your Answer Factory

Multiple Choice Multiple Answer Question Plant layout facilitates processing of products in most effective manner through the following Correct Answer Shortest possible distance , Shortest processing time , Minimum movement Your Answer Shortest possible distance , Shortest processing time Multiple Choice Single Answer Question Site factors for plant location include Correct Answer Suitability of land Your Answer Suitability of land Multiple Choice Single Answer Question A good plant layout helps in Correct Answer Reducing handling costs Your Answer Reducing handling costs Match The Following Question Correct Answer Your Answer Combined Layout Mixed Layout Mixed Layout Fixed Position Layout Project Layout Project Layout Product Layout Line Layout Line Layout Process Layout Functional Layout Functional Layout

Multiple Choice Single Answer Question Which kind of inspection is followed in case of process layout? Correct Answer First off inspection Your Answer First off inspection True/False Question Even if any activity on the critical path is delayed, project completes on the scheduled time. Correct Answer False Your Answer False Multiple Choice Single Answer Question Inadequate production capacity ultimately leads to Correct Answer Poor Customer Service Your Answer Poor Customer Service Select The Blank Question The ________ is the probability that a bad lot will be accepted by the sampling plan. Correct Answer Consumer's risk Your Answer Consumer's risk

Multiple Choice Multiple Answer Question Which are the different methods of recording actual progress of work? Correct Answer Display boards , Progress cards , Network updating Your Answer Display boards , Progress cards , Network updating Select The Blank Question Production control work is ________ in case of floor inspection as compared with the centralised inspection. Correct Answer easier Your Answer easier Multiple Choice Single Answer Question Product layout offer following advantages Correct Answer There is economy in manufacturing time Your Answer There is economy in manufacturing time True/False Question Flow process charts do record movements as well as visual pictures. Correct Answer False Your Answer False Multiple Choice Single Answer Question Main objective of a good plant layout is Correct Answer Reduce material handling cost Your Answer Reduce material handling cost Select The Blank Question In case of an OC curve, the risk of rejecting a good quality lot may vary between ________. Correct Answer 0.01 to 10% Your Answer 0.01 to 10% Multiple Choice Multiple Answer Question Features of Cellular layout are Correct Answer It is a type of mixed layout , Uses concept of Group Technology , Facilities are grouped in to cells Your Answer It is a type of mixed layout , Uses concept of Group Technology , Facilities are grouped in to cells True/False Question Cent percent inspection is required on WIP prior to the key, critical or costly operation. Correct Answer True Your Answer True Select The Blank Question The ________ is the defect level for which lots are regarded as bad lots. Correct Answer Lot Tolerance Percentage Defective Your Answer Lot Tolerance Percentage Defective

Multiple Choice Multiple Answer Question What are the benefits of reconditioning? Correct Answer Eliminates problems and frequent breakdowns , Increases life of an equipment , It helps to plan requirement of replacement spares Your Answer Eliminates problems and frequent breakdowns , Increases life of an equipment , It helps to plan requirement of replacement spares Multiple Choice Single Answer Question What does head of an arrow represent? Correct Answer End of an activity Your Answer End of an activity Multiple Choice Single Answer Question What do you mean by planned corrective manitenance which provides an opportunity to undertake design modifications in the equipment to eliminate or reduce frequency of breakdowns. Correct Answer Design-out Maintenance Your Answer Design-out Maintenance Select The Blank Question The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking. Correct Answer Condition monitoring Your Answer Condition monitoring Multiple Choice Single Answer Question The process of changing inputs into outputs thereby adding some value to entity can be defined as Correct Answer Operation Your Answer Operation Multiple Choice Multiple Answer Question Which of the following are characteristics of an operating characteristics curve? Correct Answer Producer risk , Consumer Risk , Acceptable Quality Level Your Answer Producer risk , Consumer Risk , Acceptable Quality Level Match The Following Question Correct Answer Your Answer Toung Sweet Sweet Eye Crack Crack Nose Burnout Burnout Ear Impact Impact

Select The Blank

Question The ________ is a set of tools and techniques by which products are made to comply with the specifications at minimum cost to the firm. Correct Answer Quality control system Your Answer Quality control system Multiple Choice Multiple Answer Question Which three of the following options can be used to reduce the duration of activity during project crashing? Correct Answer Allocating more manpower and machines than originally planned for. , Working additional shifts or overtime. , Awarding work to vendors who charge extra but expedite deliveries. Your Answer Allocating more manpower and machines than originally planned for. , Working additional shifts or overtime. , Awarding work to vendors who charge extra but expedite deliveries. Select The Blank Question Goods after final inspection should accompany ________to enable dispatch department to identify and draw correct reference. Correct Answer Forwarding note Your Answer Forwarding note

LIST OF ATTEMPTED QUESTIONS AND ANSWERS Select The Blank Question An ________ history card is the record of all repairs, replacements and engineering changes carried out in the equipment during it's period of service. Correct Answer Equipment history card Your Answer Equipment history card Select The Blank Question The ________ pertain to the climatic conditions which the component , product or material should withstand. Correct Answer Environmental specifications Your Answer Environmental specifications Multiple Choice Single Answer Question The process of changing inputs into outputs thereby adding some value to entity can be defined as Correct Answer Operation Your Answer Operation Select The Blank Question The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking. Correct Answer Condition monitoring Your Answer Condition monitoring True/False

Question A lot declared rejected in sampling inspection should not be inspected 100% in any case. Correct Answer False Your Answer False Multiple Choice Single Answer Question The ratio of output to input of a production system is commonly known as Correct Answer Productivity Your Answer Productivity Multiple Choice Single Answer Question What do you mean by the graphical representation of the project which is composed as series of connected arrows and circles to describe the interrelationship of the activities involved? Correct Answer Network Your Answer Network True/False Question Since value of p can never be positive, hence" if LCLp works out to be positive, it is taken as zero." Correct Answer False Your Answer False True/False Question Kanban system is essentially a computer based system for production scheduling and control Correct Answer False Your Answer False Multiple Choice Multiple Answer Question Which of the following possibilities can be explored by using flow process chart? Correct Answer Eliminating the operations or combining the operations with another , Reducing the distance traveled by the workmen or materials , Avoiding the waiting time and thereby reduce production losses Your Answer Eliminating the operations or combining the operations with another , Reducing the distance traveled by the workmen or materials , Avoiding the waiting time and thereby reduce production losses Multiple Choice Multiple Answer Question Which are the subfactors of community facilities or social infrastructure? Correct Answer Accomodation , Educational , Entertainment Your Answer Accomodation , Educational , Entertainment True/False Question Only skilled worker can use the fixed limit gauge. Correct Answer False Your Answer False Select The Blank

Question The term ________ emplies the foregone profit due to inability of company to produce. Correct Answer Opportunity cost Your Answer Opportunity cost Multiple Choice Single Answer Question A good plant layout helps in Correct Answer Reducing handling costs Your Answer Reducing handling costs Multiple Choice Multiple Answer Question Which kind of possible defectives can be reduced due to first off inspection? Correct Answer Due to wrong machine set up , Due to mistakes in reading blue prints , Due to errors in tooling Your Answer Due to mistakes in reading blue prints , Due to errors in tooling , Due to wrong machine set up Select The Blank Question The ________ is a set of tools and techniques by which products are made to comply with the specifications at minimum cost to the firm. Correct Answer Quality control system Your Answer Quality control system Multiple Choice Single Answer Question What do you understand by identification of defects in materials, components, machining processes or men to fix responsibility of defectives, thereby preventing or minimising occurance of defectives? Correct Answer Preventive function Your Answer Preventive function Multiple Choice Multiple Answer Question Which of the following products should be produced by using mass production? Correct Answer Refrigerator , Tyre for automobile , Television Set Your Answer Refrigerator , Tyre for automobile , Television Set Select The Blank Question Work study is also called ________ study Correct Answer Time and Motion Your Answer Time and Motion Multiple Choice Single Answer Question Which kind of relationship exists between those activities which can be carried out simultaneously and both activities require definite time to finish? Correct Answer Concurrent activities Your Answer Concurrent activities Multiple Choice Multiple Answer Question Which are the sources of information to update the progress card daily? Correct Answer Detachable ticket , Daily production report , Job Card Your Answer Detachable ticket , Daily production report , Job Card

Multiple Choice Single Answer Question Out of two basic criteria for the selection of a manufacturing method, one is, it must be able to meet the specifications of final product and the other is, it must be Correct Answer Cost effective method Your Answer Cost effective method Multiple Choice Multiple Answer Question Which of the following charts are used for the recording of data during the method study? Correct Answer Operation process chart , Multiple activity chart , Flow process chart Your Answer Operation process chart , Multiple activity chart , Flow process chart Select The Blank Question The ________ is the probability that a bad lot will be accepted by the sampling plan. Correct Answer Consumer's risk Your Answer Consumer's risk True/False Question Suburban location provides the compromise netween rural and urban locations. Correct Answer True Your Answer True Multiple Choice Multiple Answer Question Which of the following method can be used to record the facts during the method study? Correct Answer Micromotion study , Cyclegraph , Chronocyclegraph Your Answer Micromotion study , Cyclegraph , Chronocyclegraph Match The Following Question Correct Answer Your Answer Combined Layout Mixed Layout Mixed Layout Fixed Position Layout Project Layout Project Layout Product Layout Line Layout Line Layout Process Layout Functional Layout Functional Layout

Multiple Choice Single Answer Question Inadequate production capacity ultimately leads to Correct Answer Poor Customer Service Your Answer Low Productivity Multiple Choice Single Answer Question Which varaible is taken along the ordinate or Y axis? Correct Answer Quality

Your Answer Quality Multiple Choice Single Answer Question Any premise in which persons are employed for purpose of making any product/s is called Correct Answer Factory Your Answer Factory Multiple Choice Multiple Answer Question Which of the following defects can be observed during preventive inspection by using human senses? Correct Answer Leakage of a gas , Deviation from normal sound , Excessive Vibration Your Answer Deviation from normal sound , Excessive Vibration , Leakage of a gas Multiple Choice Multiple Answer Question Which of the following are uses of the lubricants? Correct Answer Retard rate of wear and tear of moving parts , Protect parts from moisture and dust , Keep temperature of bearings within allowable limits Your Answer Retard rate of wear and tear of moving parts , Protect parts from moisture and dust , Keep temperature of bearings within allowable limits Multiple Choice Single Answer Question Why method study should precede work measurement? Correct Answer Time for a job can be accessed accurately only after standardizing the method Your Answer Time for a job can be accessed accurately only after standardizing the method True/False Question In case of two handed process chart, storage symbol is used when either hand is used as grip or vice to hold an object. Correct Answer True Your Answer True Multiple Choice Single Answer Question Process type layout is suitable when Correct Answer there is wide variation in processing time of operations Your Answer there is wide variation in processing time of operations Multiple Choice Single Answer Question Site factors for plant location include Correct Answer Suitability of land Your Answer Suitability of land Select The Blank Question The ________ is the probability that a good lot will be rejected by the sampling plan. Correct Answer Producer's risk Your Answer Producer's risk

Multiple Choice Single Answer Question What is the location of upper control limit in the X bar-R control chart? Correct Answer 3 standard deviations above central line Your Answer 3 standard deviations above central line Multiple Choice Single Answer Question Which of the following data is unnecessary for scheduling process? Correct Answer Cost breakup of products Your Answer Cost breakup of products Multiple Choice Multiple Answer Question Which of the following are typical examples of limit gauges? Correct Answer Snap gauge , Plug gauge , Ring gauge Your Answer Snap gauge , Plug gauge , Ring gauge True/False Question Sample sizes for the construction of p-chart are typicaly larger that for Xbar-Rcharts. Correct Answer True Your Answer True Multiple Choice Multiple Answer Question Which of the following are the basic requirements of quality standard? Correct Answer Deifinite , Undesrstandable , Economically viable Your Answer Deifinite , Undesrstandable , Economically viable Multiple Choice Multiple Answer Question Which of the following is not the characteristic of Project Production? Correct Answer Continuous flow of material , Highly mechanised material handling , Virtually zero manufacturing cycle time Your Answer Continuous flow of material , Highly mechanised material handling , Virtually zero manufacturing cycle time Match The Following Question Correct Answer Your Answer Community Facilities Educational facility Educational facility Proximity to market Fragile product Fragile product Industrial and labour attitude Productivity of labour Productivity of labour Legislation and taxation Licenses Licenses

True/False Question Breakdown of a machine is normally accompanied by added machine setup cost such as resetting of jobs or change of jobs. Correct Answer True Your Answer True

Multiple Choice Multiple Answer Question Which of the following are examples of gross materials? Correct Answer Timber , Iron ore , Sugar cane Your Answer Timber , Iron ore , Sugar cane Select The Blank Question The easiest way to bring the delayed job within the promised delivery time by using extra shift or weekly holiday is ________. Correct Answer Overtime working Your Answer Overtime working

LIST OF ATTEMPTED QUESTIONS AND ANSWERS Multiple Choice Multiple Answer Question How the concept of float is helpful to planners? Correct Answer To minimize the requirement of resources , To prevent peaks and valleys in requirement of resources , To decide priorities in allocation of resources Your Answer To decide priorities in allocation of resources , To minimize the requirement of resources , To prevent peaks and valleys in requirement of resources True/False Question Floor inspection delays the identification of faults which can not be rectified immediately before large lots are spoiled. Correct Answer False Your Answer False Multiple Choice Single Answer Question What is the location of lower control limit in the X bar-R control chart? Correct Answer 3 standard deviations below central line Your Answer 3 standard deviations below central line Multiple Choice Multiple Answer Question Which of the following variables which operate periodically are the reasons for the cyclic pattern depicting peaks and valleys during Xbar-R control chart? Correct Answer Wornout positions , Fatigue , Roller eccentricity Your Answer Wornout positions , Fatigue , Roller eccentricity Select The Blank Question The ________ pertain to the climatic conditions which the component , product or material should withstand. Correct Answer Environmental specifications Your Answer Environmental specifications Multiple Choice Multiple Answer Question Order preparation process for products manufatured to order requires following documents

Correct Answer Sales Order , Work order , Shop order Your Answer Sales Order , Work order , Shop order Multiple Choice Single Answer Question What do you understand by the measurement of work to establish allowed time for a job for the defined method? Correct Answer Work measurement Your Answer Work measurement True/False Question Suburban location provides the compromise netween rural and urban locations. Correct Answer True Your Answer True Match The Following Question Correct Answer Your Answer Scale model Layout analysis Technique for evolving and analysis of layouts Factor Analysis Method to evaluate layouts Method to evaluate layouts Minimization of production delays Objective of good layout Objective of good layout Maximum visibility Principles of good layout Principles of good layout

Multiple Choice Multiple Answer Question Plant Layout is concerned with optimum arrangement of the following Correct Answer Storage space , Machines , Material Handling Equipment Your Answer Storage space , Machines , Material Handling Equipment Multiple Choice Single Answer Question The process of changing inputs into outputs thereby adding some value to entity can be defined as Correct Answer Operation Your Answer Production True/False Question A sampling plan which perfectly discriminates will have vertical OC curve. Correct Answer True Your Answer False Multiple Choice Multiple Answer Question Which kind of possible defectives can be reduced due to first off inspection? Correct Answer Due to mistakes in reading blue prints , Due to errors in tooling , Due to wrong machine set up Your Answer Due to mistakes in reading blue prints , Due to errors in tooling , Due to wrong machine set up Multiple Choice Multiple Answer

Question Which of the following concepts must be understood for the achievement of quality? Correct Answer Quality of conformance , Purpose of product , Quality of design Your Answer Quality of conformance , Quality of design Multiple Choice Single Answer Question Site factors for plant location include Correct Answer Suitability of land Your Answer Suitability of land Multiple Choice Single Answer Question The ratio of output to input of a production system is commonly known as Correct Answer Productivity Your Answer Productivity Multiple Choice Multiple Answer Question Which of the following cases indicated that the operation has occurred? Correct Answer Movement of components to assembly section , Raw material movement , A worker's trip to grinder to sharpen the tools Your Answer Movement of components to assembly section , Raw material movement , A worker's trip to grinder to sharpen the tools Multiple Choice Single Answer Question Which kind of gauge consists of electrical contacts operating a series of colloured signal lamps which indicate whether the dimension is correct, oversize or undersize? Correct Answer Multiple gauging Your Answer Multiple gauging Select The Blank Question A ________helps to avoid crowding of jobs at a particular machine by change of route of some of the jobs or by diverting work to other machine. Correct Answer Control board Your Answer Forwarding note True/False Question Proper care and storage is not an essential part of a well planned lubrication system. Correct Answer False Your Answer False Multiple Choice Single Answer Question Any premise in which persons are employed for purpose of making any product/s is called Correct Answer Factory Your Answer Factory Multiple Choice Multiple Answer Question Major contributors in the development of Control Charts, Sampling plan are Correct Answer F H Dodge , H G Roming , Walter Schewhart Your Answer F H Dodge , Walter Schewhart , L H C Tippet

Multiple Choice Single Answer Question How to claculate the producer risk in the OC Curve? Correct Answer Probability that a good lot will be rejected by the sampling Your Answer Probability that a good lot will be rejected by the sampling Multiple Choice Single Answer Question How many types of charts are used for the purpose of method study? Correct Answer Four Your Answer Eight Multiple Choice Multiple Answer Question Which three of the following options can be used to reduce the duration of activity during project crashing? Correct Answer Allocating more manpower and machines than originally planned for. , Working additional shifts or overtime. , Awarding work to vendors who charge extra but expedite deliveries. Your Answer Allocating more manpower and machines than originally planned for. , Working additional shifts or overtime. , Awarding work to vendors who charge extra but expedite deliveries. Multiple Choice Single Answer Question What does head of an arrow represent? Correct Answer End of an activity Your Answer End of an activity Match The Following Question Correct Answer Your Answer Combined Layout Mixed Layout Project Layout Fixed Position Layout Project Layout job layout Product Layout Line Layout Mixed Layout Process Layout Functional Layout Functional Layout

Multiple Choice Single Answer Question How to reveal the capability of the sampling plan to discriminate between good lots and bad lots? Correct Answer Operating characteristics curve ( OC ) Your Answer Operating characteristics curve ( OC ) Select The Blank Question The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking. Correct Answer Condition monitoring Your Answer Condition monitoring

Select The Blank Question The ________ is the probability that a good lot will be rejected by the sampling plan. Correct Answer Producer's risk Your Answer Producer's risk Multiple Choice Multiple Answer Question Which of the following are minimum requirement for a good quality of design? Correct Answer Resonable procurement time , Resonable cost , Resonable manufacturing time Your Answer Resonable cost , Resonable procurement time , Resonable manufacturing time Select The Blank Question The ________ is a set of tools and techniques by which products are made to comply with the specifications at minimum cost to the firm. Correct Answer Quality control system Your Answer Quality control system Select The Blank Question The ________ is necessary when the job requires detailed of one or more of the job characteristics with the help of special equipment which is not available at the producing company. Correct Answer Inspection order Your Answer Inspection order True/False Question Delay in completion of projects result in unwelcome additions to the fixed manufacturing expenses. Correct Answer True Your Answer True Select The Blank Question One detachable ticket is prepared for each ________. Correct Answer Operation Your Answer Operation True/False Question Objective of Work Study is to improve Productivity Correct Answer True Your Answer False True/False Question As a general rule, the number of tail event of an activity is more than that of it's head event. Correct Answer False Your Answer False Multiple Choice Single Answer Question How critical activities are shown in the time chart during project scheduling?

Correct Answer Solid lines Your Answer Solid lines Multiple Choice Multiple Answer Question Which of the following products should be produced by using mass production? Correct Answer Refrigerator , Tyre for automobile , Television Set Your Answer Refrigerator , Tyre for automobile , Television Set Select The Blank Question Work study is also called ________ study Correct Answer Time and Motion Your Answer Time and Motion Multiple Choice Multiple Answer Question What are the benefits of reconditioning? Correct Answer Eliminates problems and frequent breakdowns , Increases life of an equipment , It helps to plan requirement of replacement spares Your Answer Eliminates problems and frequent breakdowns , Increases life of an equipment , It helps to plan requirement of replacement spares Select The Blank Question A good maintenance system is not a luxary but a ________. Correct Answer Necessity Your Answer Necessity Multiple Choice Single Answer Question Which of the following technique is event oriented ? Correct Answer Project Evaluation & Review Technique Your Answer Project Evaluation & Review Technique Multiple Choice Multiple Answer Question Which of the following is not the characteristic of Project Production? Correct Answer Continuous flow of material , Highly mechanised material handling , Virtually zero manufacturing cycle time Your Answer Continuous flow of material , Highly mechanised material handling , Virtually zero manufacturing cycle time True/False Question Breakdown of a machine is normally accompanied by added machine setup cost such as resetting of jobs or change of jobs. Correct Answer True Your Answer True True/False Question The problems of congestion, bottlenecks and backtracking can not be visualized by using templates and models. Correct Answer False Your Answer False Multiple Choice Multiple Answer

Question Which of the following are illustrations of inspection? Correct Answer Physical count of incoming material against the quantity mentioned in delivery challan , A dimensional check with measuring instrument , Visual check of burrs and finish Your Answer Physical count of incoming material against the quantity mentioned in delivery challan , Visual check of burrs and finish , Check the operator performance
True/False Question

Correct Answer Your Answer False

Floor inspection delays the identification of faults which can not be rectified immediately before large lots are spoiled. False

Multiple Choice Single Answer Question Management often fails to realize the importance of efficient layout due to following reason Correct losses resulting from poor layout are not directly shown in the financial Answer statements Your Answer losses resulting from poor layout are not directly shown in the financial statements Select The Blank Question The ________ is the defect level for which lots are regarded as bad lots. Correct Lot Tolerance Percentage Defective Answer Your Answer Lot Tolerance Percentage Defective Multiple Choice Single Answer Question Which method of critical path determination begins with the end event and moves backward to the start event of the project network? Correct Backward pass computation Answer Your Answer Backward pass computation

True/False Question

Complexity and difficulty of Planning is influenced by types of layout

Correct True Answer Your Answer False

True/False Question

Correct Answer Your Answer True

For p-chart, p bar is the ratio of total number of units inspected to the total number of units defectives. False

Multiple Choice Single Answer Question What is represented by an arrow in a network? Correct Activity Answer Your Answer Activity

Multiple Choice Multiple Answer Question MRP utilises the following information Correct Master production schedule , Product structure , Lead time for Answer procurement/manufacturing Your Answer Master production schedule , Lead time for procurement/manufacturing , list of machines Multiple Choice Single Answer Question Which is the ideal place to write a description of an activity in a network? Correct Above the arrow Answer Your Answer Above the arrow

Select The Blank Question The ________ breakdowns usually cost more, partly due to damage done to the adjustment components and partly due to emergency actions. Correct Unexpected Answer Your Answer Unexpected

Multiple Choice Single Answer Question Any premise in which persons are employed for purpose of making any product/s is called Correct Factory Answer Your Answer Factory

True/False Question

Correct Answer Your Answer True

Systematic maintenance system can completely eliminate the wear and tear of machines. False

Multiple Choice Multiple Answer Question Which of the following are types of non-destructive testing? Correct Visual Testing , Eddy current , Magnetic flow detectors Answer Your Answer Visual Testing , Eddy current , Magnetic flow detectors

Select The Blank Question Work study is also called ________ study Correct Time and Motion Answer Your Answer Time and Motion

Multiple Choice Single Answer Question Providing flexibility in plant layout means Correct Layout can be changed without much cost if required Answer Your Answer Layout can be changed without much cost if required

Multiple Choice Multiple Answer Question Which of the following aspects are essential to ensure quality of purchased items? Correct Defining right quality for the job , Vendor performance evaluation , Answer Making sure that suppliers understand the requirements Your Answer Defining right quality for the job , Vendor performance evaluation , Making sure that suppliers understand the requirements Multiple Choice Multiple Answer Question Which of the following are scheduling techniques? Correct Critical Path Analysis , Index Method , Johnson's two machine algorithm Answer Your Answer Critical Path Analysis , Index Method , Johnson's two machine algorithm

Select The Blank Question The ________ advocates maintenance procedures whereby the condition of the plant is constantly watched through systematic inspection to unearth unhealthy conditions and preventive Correct Preventive Maintenance Answer Your Answer Preventive Maintenance

True/False Question

A network should be progression of activities always moving forward.

Correct True Answer Your Answer True

Multiple Choice Multiple Answer Question In an organization there may not be a formal PPC department if Correct Work is Answer the line Your Answer Work is the line highly repetitive in nature , Planning activities are performed by staff , Number of workmen is not very large highly repetitive in nature , Planning activities are performed by staff , Number of workmen is not very large

Select The Blank Question The ________ is necessary when the job requires detailed of one or more of the job characteristics with the help of special equipment which is not available at the producing company. Correct Inspection order Answer Your Answer Inspection order

Multiple Choice Multiple Answer Question Order preparation process for products manufatured to order requires following documents Correct Sales Order , Work order , Shop order Answer Your Answer Sales Order , Work order , Shop order

Multiple Choice Single Answer Question What do you understand by the selection of the job for the method study on the basis of money saving potential of the job? Correct Economic consideration Answer Your Answer Economic consideration

Select The Blank Question Production Planning is a centralised activity which includes functions such as ________ Correct Scheduling Answer Your Answer Scheduling

Multiple Choice Multiple Answer Question Scale model used for layout analysis have following advantages Correct Nontechnical person finds Answer be shown , Models can be Your Answer Nontechnical person finds be shown , Models can be it easy to comprehend , Ovehead facilities can shifted easily it easy to comprehend , Ovehead facilities can shifted easily

Multiple Choice Single Answer Question Which is the ideal place to inspect jigs and fixtures in a mass manufacturing unit? Correct Separate inspection room Answer Your Answer Separate inspection room

Multiple Choice Single Answer Question How to reveal the capability of the sampling plan to discriminate between good lots and bad lots? Correct Operating characteristics curve ( OC ) Answer Your Answer Operating characteristics curve ( OC )

True/False Question

Correct Answer Your Answer True

It would not affect the project completion time if non-critical activities take little loner time than planned. True

Select The Blank Question The ________ includes preventive maintenance activities whose needs are identified through inspection which requires stoppage of machines. Correct Shutdown Maintenance Answer Your Answer Shutdown Maintenance

Match The Following Question Forcasting requirement for indirect material Inventory control by classification Structure of the product Material Planning for dependent demand True/False Question

Correct Answer Past consumption analysis technique ABC Analysis BOM MRP

Your Answer Past consumption analysis technique ABC Analysis BOM MRP

Correct Answer Your Answer True

The dispatching function is of very importance in flow and mass production units. False

Multiple Choice Multiple Answer Question Which features should be covered by the specifications of materials while defining the qualitative requirement? Correct Material composition , Dimensions , Any heat treatment if required Answer Your Answer Material composition , Dimensions , Cost of material

Select The Blank Question The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking. Correct Condition monitoring Answer Your Answer Condition monitoring

Select The Blank

Question

One detachable ticket is prepared for each ________.

Correct Operation Answer Your Answer Operation

Multiple Choice Single Answer Question Which of the following is the most popular technique for Project Production? Correct PERT & CPM Answer Your Answer PERT & CPM

Select The Blank Question A good maintenance system is not a luxary but a ________. Correct Necessity Answer Your Answer Necessity

Multiple Choice Single Answer Question The process of changing inputs into outputs thereby adding some value to entity can be defined as Correct Operation Answer Your Answer Operation

True/False Question

Correct Answer Your Answer False

An activity should represent an operation or set of operations which can be performed using a particular kind of equipment or a special skill. True

Multiple Choice Multiple Answer Question Which of the following are types of sampling plan? Correct Single sampling plan , Double sampling plan , Multiple sampling plan Answer Your Answer Single sampling plan , Double sampling plan , Multiple sampling plan

True/False Question

Correct Answer Your Answer False

In case of forward pass computation, the earliest event time of a plain event equals the earliest event time of the preceding event plus duration of activity emanating from the preceding event. True

Multiple Choice Multiple Answer

Question

Which of the following are ideal situations for the preventive inspection?

Correct Weekly off and holidays , Non-production hours , Stand-up equipment Answer Your Answer Weekly off and holidays , Non-production hours , Stand-up equipment

Multiple Choice Single Answer Question What do you mean by the chart on which the major activities and entry points of materials are recorded to have graphic view of operations and inspections involved in the process? Correct Operation process chart Answer Your Answer Flow Process chart

Match The Following Question Fixation of inventory level Symptom of ill planned purchasing Factor influencing material planning

Correct Answer Reorder level Over ordering Lead time

Your Answer Reorder level Over ordering Lead time Stock on hand

Net requirement of material Stock on hand under MRP

Multiple Choice Single Answer Question Taxes / duties levied is one of the important determinant for location decision as taxes/duties substantially influence Correct Product cost Answer Your Answer Product cost

Multiple Choice Single Answer Question Which kind of gauge consists of electrical contacts operating a series of colloured signal lamps which indicate whether the dimension is correct, oversize or undersize? Correct Multiple gauging Answer Your Answer Multiple gauging

Multiple Choice Multiple Answer Question Which of the following are minimum requirement for a good quality of design? Correct Resonable cost , Resonable procurement time , Resonable manufacturing Answer time Your Answer Resonable cost , Resonable procurement time , Resonable manufacturing time Select The Blank

Question

Correct Answer Your Answer One

OC curve of ideal sampling plan suggests that all lots less than 3% defectives have the probability of acceptance of ________. One

True/False Question Correct Answer Your Answer

Cent percent inspection is required on WIP prior to the key, critical or costly operatio True True

Multiple Choice Multiple Answer Question Which of the following aspects are essential to ensure quality of purchased items? Correct Answer Your Answer

Defining right quality for the job , Vendor performance evaluation , Making sure that suppliers understand the requirements Vendor performance evaluation , Making sure that suppliers understand the requirem , Defining right quality for the job

Multiple Choice Single Answer Question Any premise in which persons are employed for purpose of making any product/s is called Correct Answer Factory Your Answer Factory

Multiple Choice Single Answer Question Which of the following technique is event oriented ? Correct Answer Your Answer Project Evaluation & Review Technique Project Evaluation & Review Technique

Select The Blank Question Work study is also called ________ study Correct Answer Your Answer Time and Motion Time and Motion

Multiple Choice Multiple Answer Question Which of the following concepts must be understood for the achievement of quality? Correct Answer Your Answer Quality of conformance , Purpose of product , Quality of design Quality of conformance , Quality of design

Multiple Choice Multiple Answer Question Following are some of the factors considered for evaluation of alternative layouts

Correct Answer Your Answer

Flow of Material , Equipment utilization , Ease of supervision Flow of Material , Equipment utilization , Ease of supervision

Match The Following Question Toung Eye Nose Ear

Correct Answer Sweet Crack Burnout Impact

Your Answer Sweet Crack Burnout Impact

Multiple Choice Multiple Answer Question Which of the following are important considerations concerning activity times? Correct Answer

Your Answer

Activity time should be obtained from the person responsible for the completion of a activity , Activity time must be independent of any influence which the preceding or succeeding activity may have on it. , Activity time may assume that just the normal quantity of resources required to carry out the activity are available. Activity time should be obtained from the person responsible for the completion of a activity , Activity time must be independent of any influence which the preceding or succeeding activity may have on it. , Activity time may assume that just the normal quantity of resources required to carry out the activity are available.

Multiple Choice Multiple Answer Question Which are the subtasks of the maintenance phase of the method study? Correct Answer Your Answer Monitoring and control , Performance appraisal , Audit on savings Monitoring and control , Performance appraisal , Audit on savings

Multiple Choice Multiple Answer Question Which of the following are characteristics of an operating characteristics curve? Correct Answer Your Answer Producer risk , Consumer Risk , Acceptable Quality Level Producer risk , Consumer Risk , Acceptable Quality Level

Select The Blank Question The ________ breakdowns usually cost more, partly due to damage done to the adjustment components and partly due to emergency actions. Correct Answer Unexpected Your Answer Partial

Multiple Choice Single Answer Question Why stores issue order should not be issued as soon as it is prepared? Correct Answer Material may or may not be available at the time of preparation

Your Answer

Inventory investment will increase

Multiple Choice Single Answer Question What is the nature of the sampling plan for critical defects? Correct Answer Your Answer Tight Tight

Select The Blank Question In case of an OC curve, the risk of rejecting a good quality lot may vary between ________. Correct Answer 0.01 to 10% Your Answer 0.01 to 10%

Multiple Choice Multiple Answer Question Plant layout facilitates processing of products in most effective manner through the following Correct Answer Shortest possible distance , Shortest processing time , Minimum movement Your Answer Shortest possible distance , Shortest processing time , Minimum movement

True/False Question Correct Answer Your Answer

After goods have been manufactured, route sheets and operation layouts should not collected back. False False

Multiple Choice Single Answer Question Process planning is the process of Correct Answer Your Answer establishing shortest and most economic path of production establishing shortest and most economic path of production

Multiple Choice Single Answer Question The process of changing inputs into outputs thereby adding some value to entity can defined as Correct Answer Operation Your Answer Operation

Select The Blank Question The ________ is specified to indicate the maximum permissible variability in the dimensions product or parts. Correct Answer Tolerance Your Answer Tolerance

Select The Blank Question Goods after final inspection should accompany ________to enable dispatch departm to identify and draw correct reference. Correct Answer Forwarding note Your Answer Forwarding note

Select The Blank Question The ________ includes preventive maintenance activities whose needs are identified through inspection which requires stoppage of machines. Correct Answer Shutdown Maintenance Your Answer Shutdown Maintenance

True/False Question Correct Answer Your Answer

A load chart specifies the work to be carried out by each person of company during s hours. False True

Select The Blank Question The easiest way to bring the delayed job within the promised delivery time by using shift or weekly holiday is ________. Correct Answer Overtime working Your Answer Overtime working

True/False Question Correct Answer Your Answer

Under MRP system for common items order for procurement is placed based on requirement for each product False True

Multiple Choice Single Answer Question What do you understand by the extent the products manufactured conforms to the la down design? Correct Answer Quality of conformance Your Answer Quality of conformance

Select The Blank Question The ________ is necessary when the job requires detailed of one or more of the job characteristics with the help of special equipment which is not available at the produ company. Correct Answer Inspection order Your Answer Job card

Multiple Choice Multiple Answer Question Which of the following are the basic requirements of quality standard? Correct Answer Your Answer Deifinite , Undesrstandable , Economically viable Deifinite , Undesrstandable , Economically viable

True/False Question Correct Answer Your Answer

In case of forward pass computation, the earliest event time of the first event is zero True True

Multiple Choice Multiple Answer Question Which kind of possible defectives can be reduced due to first off inspection? Correct Answer Your Answer

Due to mistakes in reading blue prints , Due to errors in tooling , Due to wrong mach set up Due to mistakes in reading blue prints , Due to errors in tooling , Due to wrong mach set up , Due to purposely done mistakes by unsatisfied worker

True/False Question Correct Answer Your Answer

A sampling plan which perfectly discriminates will have vertical OC curve. True True

Multiple Choice Multiple Answer Question Which of the following is a part of preparing manufacturing order set as a primary function of dispatching? Correct Answer Operational layouts , Move orders , Pre-filled stores issue orders Your Answer Operational layouts , Rejection reports , Move orders , Pre-filled stores issue orders

Select The Blank Question An ________ history card is the record of all repairs, replacements and engineering changes carried out in the equipment during it's period of service. Correct Answer Equipment history card Your Answer Equipment history card

True/False Question Correct Answer Your Answer

Specifications is the basic tool of inspection. True True

Match The Following

Question

Correct Answer

Your Answer Economic order quantity ABC Analysis BOM MRP

Forcasting requirement for indirect Past consumption analysis material technique Inventory control by classification Structure of the product Material Planning for dependent demand ABC Analysis BOM MRP

Multiple Choice Single Answer Question The document raised by PPC which authorises different functions to take action as pe instruction is called Correct Answer Work Order Your Answer Job Instructions

Multiple Choice Single Answer Question Who prepares the daily production report? Correct Answer Your Answer Shop Supervisor Shop Supervisor

True/False Question Correct Answer Your Answer

A lot declared rejected in sampling inspection should not be inspected 100% in any c False True

Multiple Choice Single Answer Question How is the probability of acceptance in case of Acceptable Quality Level (AQL )? Correct Answer Your Answer Very high Average

Multiple Choice Multiple Answer Question Which are the different methods of recording actual progress of work? Correct Answer Your Answer Display boards , Progress cards , Network updating Display boards , Progress cards , Network updating

True/False Question Correct Answer

The dispatching function is of very importance in flow and mass production units. False

Your Answer

True

True/False Question Correct Answer Your Answer

Proper care and storage is not an essential part of a well planned lubrication system. False False

Select The Blank Question The ________ pertain to the climatic conditions which the component , product or material should withstand. Correct Answer Environmental specifications Your Answer Environmental specifications

Multiple Choice Single Answer Question Which of the following is the most popular technique for Project Production? Correct Answer Your Answer PERT & CPM PERT & CPM

Select The Blank Question Production Planning is a centralised activity which includes functions such as ______ Correct Answer Your Answer Scheduling Scheduling

Multiple Choice Single Answer Question Which rule is used for numbering of events? Correct Answer Your Answer Fulkerson's Rule Fulkerson's Rule

Multiple Choice Multiple Answer Question Material Requirement Planning is very useful in following situations Correct Answer Long Lead time for procurement , Several levels of assemblies in product , Long manufacturing cycle Your Answer Long Lead time for procurement , Several levels of assemblies in product , Long manufacturing cycle Select The Blank Question The ________ is specified to indicate the maximum permissible variability in the dimensions product or parts. Correct Answer Tolerance

Your Answer

Standard

Select The Blank Question An ________ history card is the record of all repairs, replacements and engineering changes carried out in the equipment during it's period of service. Correct Answer Equipment history card Your Answer Equipment history card

Multiple Choice Single Answer Question What can be the worst effect due to excessive vibration? Correct Answer Breakdown Your Answer Breakdown

Multiple Choice Single Answer Question Any premise in which persons are employed for purpose of making any product/s is called Correct Answer Factory Your Answer Factory

Multiple Choice Single Answer Question How dummy activities are shown in the time chart during project scheduling? Correct Answer Vertical lines Your Answer Vertical lines

Multiple Choice Single Answer Question Which of the following technique makes three time estimates for each activity? Correct Answer Project Evaluation & Review Technique Your Answer Project Evaluation & Review Technique

True/False Question

Expediting action is necessary if the delays and interruptions are abnormal and hence any subsequent delay is bound to extend the promised delivery date. Correct Answer True Your Answer True

Multiple Choice Multiple Answer Question Which features should be covered by the specifications of materials while defining the qualitative requirement? Correct Answer Material composition , Dimensions , Any heat treatment if required Your Answer Material composition , Dimensions , Any heat treatment if required

True/False Question

Limit gauges are not useful when it is necessary to measure the exact amount of variation. Correct Answer True Your Answer False

Select The Blank Question The ________ is the defect level for which lots are regarded as bad lots. Correct Answer Lot Tolerance Percentage Defective Your Answer Lot Tolerance Percentage Defective

Multiple Choice Single Answer Question Technique of Value Engineering can be effectively employed in design of a product to Correct Answer To meet the intended function at lowest cost Your Answer Increase resourse utilization

Multiple Choice Single Answer Question What do you mean by the preventive maintenance by using five human senses? Correct Answer Preventive inspection Your Answer Sensitive inspection

Multiple Choice Multiple Answer Question Which of the following are typical examples of limit gauges? Correct Answer Snap gauge , Plug gauge , Ring gauge Your Answer Snap gauge , Plug gauge , Ring gauge

Multiple Choice Multiple Answer Question Which are the major types of defects? Correct Answer Minor , Major , Critical Your Answer Major , Critical

Match The Following Question Emerson Efficiency Plan Craft Work Sampling

Correct Answer Wage Payment Facilities Planning Machine utilization

Your Answer Facilities Planning Production Scheduling Sampling Inspection

Gantt Chart

Production Scheduling

Charting technique

Select The Blank Question The ________ is the maximum percentage defective that for the purpose of sampling inspection can be considered satisfactory as a process average. Correct Answer Acceptable quality level Your Answer Acceptable quality level

Multiple Choice Single Answer Question A good plant layout helps in Correct Answer Reducing handling costs Your Answer Reducing handling costs

Multiple Choice Multiple Answer Question Which of the following charts are used for the recording of data during the method study? Correct Answer Operation process chart , Multiple activity chart , Flow process chart Your Answer Operation process chart , Multiple activity chart , Flow process chart

Multiple Choice Single Answer Question What do you mean by the selection of the job for the method study on the basis of manufacturing difficulties? Correct Answer Technical consideration Your Answer Human consideration

True/False Question

An activity can share the same tail event and same head event with any other activity. Correct Answer False Your Answer False

Select The Blank Question The ________ is the probability that a good lot will be rejected by the sampling plan. Correct Answer Producer's risk Your Answer Producer's risk

Multiple Choice Single Answer Question Inadequate production capacity ultimately leads to Correct Answer Poor Customer Service Your Answer Poor Customer Service

True/False Question

All activities must not be tied up into the network

Correct Answer False Your Answer True

Multiple Choice Single Answer Question Technique which can help an organization to reduce inventory is called Correct Answer MRP Your Answer CPM

True/False Question

Dust gets mixed with lubricants, forms an abrasive substance and causes premature failure of machinery. Correct Answer True Your Answer True

Multiple Choice Multiple Answer Question Which of the following situations demand the technical consideration while selecting a job for method study? Correct Answer Jobs having inconsistent quality , Operations inviting frequent requests from supervisors for relaxation in allowed time because of variations in materials and tool performance , Jobs in which too many man-hours are spend in checking and rechecking work Your Answer Jobs having inconsistent quality , Operations inviting frequent requests from supervisors for relaxation in allowed time because of variations in materials and tool performance , Jobs in which too many man-hours are spend in checking and rechecking work Multiple Choice Multiple Answer Question Which of the following are examples of attributes? Correct Answer Cracks , Burrs , Texture Your Answer Cracks , Hardness , Burrs

Select The Blank Question In case of an OC curve, the risk of rejecting a good quality lot may vary between ________. Correct Answer 0.01 to 10% Your Answer 0.01 to 10%

Select The Blank Question The ________ must ensure that the product satisfy the functional requirements of it's usage. Correct Answer Quality of design

Your Answer

Quality of inspection

True/False Question

Delay in completion of projects result in unwelcome additions to the fixed manufacturing expenses. Correct Answer True Your Answer True

Multiple Choice Multiple Answer Question Which of the following activities are used while recording for method study? Correct Answer Delay , Operation , Inspection Your Answer Delay , Operation , Inspection

True/False Question

Root cause of most of the breakdowns is failure of the lubrication system.

Correct Answer True Your Answer True

Select The Blank Question The term ________ emplies the foregone profit due to inability of company to produce. Correct Answer Opportunity cost Your Answer Opportunity cost

True/False Question

Latest finishing date is the latest event time of the tail event.

Correct Answer False Your Answer False

Multiple Choice Multiple Answer Question What is the basic minimum requirement for those who are responsible for the quality of design? Correct Answer In depth knowledge about alternative materials and manufacturing processes , access to latest technology and production process adopted by industries in the developed market , Continuous effort in product development Your Answer In depth knowledge about alternative materials and manufacturing processes , access to latest technology and production process adopted by industries in the developed market , Continuous effort in product development True/False Question

If the firm has adopted elaborate planned maintenance system, there is no chance of any unplanned maintenance work. Correct Answer False

Your Answer

False

Multiple Choice Multiple Answer Question Which of the following is not the characteristic of Project Production? Correct Answer Continuous flow of material , Highly mechanised material handling , Virtually zero manufacturing cycle time Your Answer Continuous flow of material , Highly mechanised material handling , Virtually zero manufacturing cycle time Multiple Choice Single Answer Question Which document is used for returning the surplus material? Correct Answer Stores Return Note Your Answer Stores Return Note

Select The Blank Question Work study is also called ________ study Correct Answer Time and Motion Your Answer Time and Motion

Match The Following Question Factor Analysis Minimization of production delays Maximum visibility Scale model

Correct Answer Method to evaluate layouts Objective of good layout Principles of good layout Layout analysis

Your Answer Method to evaluate layouts Objective of good layout Principles of good layout Layout analysis

Multiple Choice Single Answer Question The process of changing inputs into outputs thereby adding some value to entity can be defined as Correct Answer Operation Your Answer Operation

Multiple Choice Single Answer Question What does the additional cost incurred to reduce the duration of an activity by one unit of time represent? Correct Answer Activity cost slope Your Answer Activity time slope

Select The Blank

Question

Production control work is ________ in case of floor inspection as compared with the centralised inspection. Correct Answer easier Your Answer easier

Select The Blank Question One detachable ticket is prepared for each ________. Correct Answer Operation Your Answer Operation

Multiple Choice Single Answer Question The ratio of output to input of a production system is commonly known as Correct Answer Productivity Your Answer Productivity

Multiple Choice Single Answer Question Which of the following policies is advisable in case of low product variety and large volumes? Correct Answer Low Skilled Labour & Special Purpose Machines Your Answer Low Skilled Labour & Special Purpose Machines

Select The Blank Question The ________ must ensure that the product satisfy the functional requirements of it's usage. Correct Answer Quality of design Your Answer Quality of design

Multiple Choice Multiple Answer Question Which of the following information is available in summary of part in a chart during methods study? Correct Answer Frequency of each symbol , Total time for each symbol , Total distance travelled by the object Your Answer Frequency of each symbol , Total time for each symbol True/False Question

The event numbers as far as possible reflect the logical relationships of the activities. Correct Answer True Your Answer False

Multiple Choice Single Answer Question Which varaible is taken along the ordinate or Y axis? Correct Answer Quality Your Answer Quality

Multiple Choice Multiple Answer Question Which of the following schedules are recommended to prepare and follow as a part of preventive maintenance system? Correct Answer Preventive inspection schedule , Cleaning and upkeep schedule , Lubrication schedule Your Answer Preventive inspection schedule , Cleaning and upkeep schedule , Lubrication schedule Multiple Choice Single Answer Question Which kind of preventive inspection detects some maintenance related characteristics by making use of human senses, when equipment is in operation? Correct Answer Extrernal inspection Your Answer Extrernal inspection

Multiple Choice Multiple Answer Question Which are different ways to show critical path in a network? Correct Answer Thick Line , Red Line , Double Line Your Answer Thick Line , Red Line , Double Line

Multiple Choice Multiple Answer Question What are the benefits of overhauling? Correct Answer It increases useful life of an equipment and it's parts , Advance planning allows to attend equipment without disturbing the production programme , Advance planning allows to prepare and keep ready the list of replacement spares Your Answer It increases useful life of an equipment and it's parts , Advance planning allows to attend equipment without disturbing the production programme , Advance planning allows to prepare and keep ready the list of replacement spares Match The Following Question Combined Layout Fixed Position Layout Product Layout

Correct Answer Mixed Layout Project Layout Line Layout

Your Answer Mixed Layout Line Layout Shop layout

Process Layout

Functional Layout

Functional Layout

Multiple Choice Multiple Answer Question Which of the following factors play important role while selecting or rejecting a particular site from legislation and taxation point of view? Correct Answer Labour laws , Building codes , Policies regarding issue of licences Your Answer Labour laws , Building codes , Policies regarding issue of licences

Select The Blank Question The ________ is the maximum percentage defective that for the purpose of sampling inspection can be considered satisfactory as a process average. Correct Answer Acceptable quality level Your Answer Acceptable quality level

Multiple Choice Multiple Answer Question Major contributors in the development of Control Charts, Sampling plan are Correct Answer F H Dodge , H G Roming , Walter Schewhart Your Answer True/False Question F H Dodge , H G Roming , Walter Schewhart

Skill of labour force in a product type layout is usually higher than in the process type of layout Correct Answer False Your Answer True

True/False Question

Repetitive movements between work stations which are difficult to be traced on string diagrams can be conveniently shown on flow diagrams. Correct Answer False Your Answer True

Select The Blank Question The ________ is necessary when the job requires detailed of one or more of the job characteristics with the help of special equipment which is not available at the producing company. Correct Answer Inspection order Your Answer Job card

Multiple Choice Multiple Answer

Question

Which of the following cases can be referred as operation in method study recording? Correct Answer Change in physical characteristic , Consumption of physical effort , Change in chemical characteristic Your Answer Change in physical characteristic , Consumption of physical effort , Change in chemical characteristic Select The Blank Question The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking. Correct Answer Condition monitoring Your Answer True/False Question Overhauling

All activities lying on the non-critical paths must have total float and free float. Correct Answer False Your Answer False

Select The Blank Question Work study is also called ________ study Correct Answer Time and Motion Your Answer Method

Match The Following Question Crash cost of an activity Normal time of an activity Crash time of activity Normal cost of an activity

Correct Answer Cc Tn Tc Cn

Your Answer Cc Tn Tc Cn

Multiple Choice Multiple Answer Question Which are the advantages of suburban location? Correct Answer Avaialability of adequate land at lower cost , Both skilled and unskilled labour can be available , Plant expansion is easier due to less or no restriction for building and construction Your Answer Avaialability of adequate land at lower cost , Both skilled and unskilled labour can be available , Plant expansion is easier due to less or no restriction for building and construction

True/False Question

In case of X bar-R charts,it is ensured that the assignable causes are detected before the tolerances are violated, upper and lower statistical limits are worked out and inserted into a chart. Correct Answer True Your Answer False

Multiple Choice Single Answer Question Which of the following is the criteria for the percentage defectives in the zone of the indecision? Correct Answer Lots having the percentage defective more than AQL but less than LPTD Your Answer Lots having the percentage defective less than AQL but more than LPTD Select The Blank Question The easiest way to bring the delayed job within the promised delivery time by using extra shift or weekly holiday is ________. Correct Answer Overtime working Your Answer Overtime working

Multiple Choice Single Answer Question What do you mean by lowest possible direct cost required to complete an activity within it's crashed time? Correct Answer Crash cost Your Answer Crash cost

Multiple Choice Single Answer Question In case of Batch Production which kind of labour is expected? Correct Answer Skilled in one specific Manufacturing Process Your Answer Semiskilled

Multiple Choice Multiple Answer Question Which three of the following are causes of continuous upward pattern of Xbar-R control chart? Correct Answer Wear of tool , Abnormal rise in temperature , Accumulation of dirt Your Answer True/False Question Wear of tool , Abnormal rise in temperature , Accumulation of dirt

Root cause of most of the breakdowns is failure of the lubrication system. Correct Answer True

Your Answer True/False Question

True

It is not necessary to know spare time available on the non-critical path to allow a little delay for noncritical activity. Correct Answer False Your Answer False

True/False Question

MRP software generates time periodwise requiremetn of subassemblies Correct Answer True Your Answer True

True/False Question

In case of two handed process chart, the simultaneous activities of both hands are recorded opposite to each other on the chart. Correct Answer True Your Answer True

Multiple Choice Single Answer Question What do you mean by CPM? Correct Answer Critical Path Method Your Answer Critical Path Method

Multiple Choice Multiple Answer Question Which of the following are major inputs to scheduling? Correct Answer Overlapping of operations , Effective Capacity per work centre , Performance standards Your Answer Overlapping of operations , Effective Capacity per work centre , Performance standards Multiple Choice Multiple Answer Question Lack of material planning results in the following Correct Answer Over ordering , under ordering , stockouts Your Answer Over ordering , under ordering , stockouts

Multiple Choice Single Answer Question What do you mean by the verification of object against predetermined standards of quality or quantity or both? Correct Answer Inspection

Your Answer

Inspection

Multiple Choice Multiple Answer Question What are the advantages of templates over diagrams? Correct Answer Can be conveniently moved on the graph paper , Less laborious , Saves time Your Answer Can be conveniently moved on the graph paper , Less laborious , Unskilled person can do and analyze it True/False Question

It would not affect the project completion time if non-critical activities take little loner time than planned. Correct Answer True Your Answer True

Select The Blank Question The ________ is the probability that a good lot will be rejected by the sampling plan. Correct Answer Producer's risk Your Answer Producer's risk

Multiple Choice Single Answer Question Any premise in which persons are employed for purpose of making any product/s is called Correct Answer Factory Your Answer Factory

Select The Blank Question An Ideal OC curve is ________ shaped curve that accpets all the lots with quality equal to or better than AQL . Correct Answer Rectangular Your Answer Bell

Multiple Choice Single Answer Question Which is the right time to prepare stores issue order? Correct Answer When route sheet is ready Your Answer When route sheet is ready

Multiple Choice Single Answer Question Which element of a network represents a task which has got a definite beginning and definite end? Correct Answer Activity

Your Answer

Activity

Multiple Choice Single Answer Question Which kind of preventive inspection detects some defects in moving parts, internal cracks, and others , when machine is under preplanned shutdown? Correct Answer Internal inspection Your Answer Internal inspection

Select The Blank Question Production Planning is a centralised activity which includes functions such as ________ Correct Answer Scheduling Your Answer Dispatching

Select The Blank Question The ________ is the watch dog which ensures that every element of production and activities which could affect the quality of end product are regulated to the extent desirable. Correct Answer Quality control Your Answer Quality control

Select The Blank Question Goods after final inspection should accompany ________to enable dispatch department to identify and draw correct reference. Correct Answer Forwarding note Your Answer Forwarding note

Multiple Choice Single Answer Question Who has introduced the useful concept of control chart in 1931? Correct Answer Walter Shewhart Your Answer Walter Shewhart

LIST OF ATTEMPTED QUESTIONS AND ANSWERS Multiple Choice Multiple Answer Question Why graphical method of recording is preferred over the descriptive method during method study? Correct Answer It segregates effective part form ineffective parts , It reduces effort involved in writing , Critical examinations easier and more effective Your Answer Critical examinations easier and more effective , It segregates effective part form ineffective parts , It reduces effort involved in writing

Multiple Choice Multiple Answer Question Which are the subfactors of community facilities or social infrastructure? Correct Answer Accomodation , Educational , Entertainment Your Answer Accomodation , Educational , Entertainment Select The Blank Question The ________ is the probability that a bad lot will be accepted by the sampling plan. Correct Answer Consumer's risk Your Answer Consumer's risk Multiple Choice Multiple Answer Question Which of the following are examples of consumption of physical effort during recording for method study? Correct Answer Bending , Positioning , Unloading Your Answer Bending , Positioning , Unloading Multiple Choice Single Answer Question How to claculate the producer risk in the OC Curve? Correct Answer Probability that a good lot will be rejected by the sampling Your Answer Probability that a good lot will be rejected by the sampling Select The Blank Question The ________ are the definitions of the measurable as well as nonmeasurable characteristics of the product. Correct Answer Specifications Your Answer Specifications Select The Blank Question The ________ is the watch dog which ensures that every element of production and activities which could affect the quality of end product are regulated to the extent desirable. Correct Answer Quality control Your Answer Quality control True/False Question Expediting action is necessary if the delays and interruptions are abnormal and hence any subsequent delay is bound to extend the promised delivery date. Correct Answer True Your Answer True Multiple Choice Single Answer Question Process Engineer does not get sufficient time for designing tooling for most economic production run when Correct Answer Delivery time is less Your Answer Delivery time is less Select The Blank

Question The ________ includes preventive maintenance activities whose needs are identified through inspection which requires stoppage of machines. Correct Answer Shutdown Maintenance Your Answer Shutdown Maintenance True/False Question Breakdown of machines, absenteeism of worker does not dislocate the manufacturing activity in process layout Correct Answer True Your Answer True Select The Blank Question The ________ is the maximum percentage defective that for the purpose of sampling inspection can be considered satisfactory as a process average. Correct Answer Acceptable quality level Your Answer Acceptable quality level Multiple Choice Single Answer Question What do you mean by lowest possible direct cost required to complete an activity within it's crashed time? Correct Answer Crash cost Your Answer Crash cost Multiple Choice Multiple Answer Question Which are the first three steps of Critical Path Analysis technique? Correct Answer Activity relationships , Activity identification , Network construction Your Answer Activity relationships , Activity identification , Network construction True/False Question Dust gets mixed with lubricants, forms an abrasive substance and causes premature failure of machinery. Correct Answer True Your Answer True Multiple Choice Multiple Answer Question Which of the following can be subtypes of corrective maintenance? Correct Answer Shutdown Maintenance , Design-out Maintenance , Design-in Maintenance Your Answer Shutdown Maintenance , Design-out Maintenance , Design-in Maintenance Select The Blank Question The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking. Correct Answer Condition monitoring Your Answer Condition monitoring Multiple Choice Single Answer Question The process of changing inputs into outputs thereby adding some value to entity can be defined as Correct Answer Operation

Your Answer Production Match The Following Question Correct Answer Your Answer Toung Sweet Sweet Eye Crack Crack Nose Burnout Burnout Ear Impact Impact

Select The Blank Question The ________ is a set of tools and techniques by which products are made to comply with the specifications at minimum cost to the firm. Correct Answer Quality control system Your Answer Quality control system Multiple Choice Single Answer Question What is the meaning of " Product features" according to J.M.Juran? Correct Answer Quality of design Your Answer Quality of design Multiple Choice Multiple Answer Question Which of the following method can be used to record the facts during the method study? Correct Answer Micromotion study , Cyclegraph , Chronocyclegraph Your Answer Micromotion study , Photograph , Cyclegraph , Chronocyclegraph True/False Question All activities must not be tied up into the network Correct Answer False Your Answer False Multiple Choice Multiple Answer Question Which of the following are types of sampling plan? Correct Answer Single sampling plan , Double sampling plan , Multiple sampling plan Your Answer Single sampling plan , Double sampling plan , Multiple sampling plan Multiple Choice Multiple Answer Question How many of the following are types of specification? Correct Answer Material specifications , Dimensional specifications , Performance specifications Your Answer Material specifications , Dimensional specifications , Performance specifications Multiple Choice Multiple Answer

Question Plant layout facilitates processing of products in most effective manner through the following Correct Answer Shortest possible distance , Shortest processing time , Minimum movement Your Answer Shortest possible distance , Minimum movement Select The Blank Question Work study is also called ________ study Correct Answer Time and Motion Your Answer Time and Motion True/False Question Operation Process Chart provides information on time and distances Correct Answer False Your Answer False Multiple Choice Multiple Answer Question Plant Layout is concerned with optimum arrangement of the following Correct Answer Storage space , Machines , Material Handling Equipment Your Answer Storage space , Machines , Sequence of operation Multiple Choice Single Answer Question Management often fails to realize the importance of efficient layout due to following reason Correct Answer losses resulting from poor layout are not directly shown in the financial statements Your Answer losses resulting from poor layout are not directly shown in the financial statements True/False Question Inspection order is must even for simple jobs which can be inspected by shop inspector with the tooling available on shop. Correct Answer False Your Answer True True/False Question Feasibility of time schedule requires that an activity be scheduled before any of it's predecessors are scheduled. Correct Answer False Your Answer True Multiple Choice Single Answer Question Any premise in which persons are employed for purpose of making any product/s is called Correct Answer Factory Your Answer Factory True/False Question Planned lubrication is said to be the nervous system of the equipment. Correct Answer True

Your Answer True Multiple Choice Single Answer Question What is the basic philosophy of statistical process control? Correct Answer Prevention is better than cure Your Answer Prevention is better than cure Multiple Choice Single Answer Question How does the control chart of statistical quality control helps the operating personnel? Correct Answer Identify the presence of an assignable cause before it develops Your Answer Identify the presence of an assignable cause before it develops Multiple Choice Single Answer Question Where does the central line is located in case of p-chart? Correct Answer at p bar Your Answer at p bar Multiple Choice Multiple Answer Question Which of the following may be the objectives of project crashing? Correct Answer To complete the project in the least possible time , To reduce project cost below it's normal cost , To achieve uniformity in requirement of resources Your Answer To complete the project in the least possible time , To reduce project cost below it's normal cost , To achieve uniformity in requirement of resources Select The Blank Question The ________ advocates maintenance procedures whereby the condition of the plant is constantly watched through systematic inspection to unearth unhealthy conditions and preventive Correct Answer Preventive Maintenance Your Answer Preventive Maintenance True/False Question A network should be progression of activities always moving forward. Correct Answer True Your Answer True Multiple Choice Single Answer Question Which is the ideal place to write a description of an activity in a network? Correct Answer Above the arrow Your Answer Above the arrow Select The Blank Question In case of an OC curve, the risk of rejecting a good quality lot may vary between ________. Correct Answer 0.01 to 10% Your Answer 0.01 to 10% True/False

Question For p-chart, the central line of fraction defectives is determined by average percentage defectives. Correct Answer True Your Answer True Multiple Choice Single Answer Question Which phase of method study is concerned with analyzing the facts critically, generating alternatives which form the basis for selection and development of improved methods? Correct Answer Critical examination Your Answer Critical examination Multiple Choice Single Answer Question Which of the following policies is advisable in case of low product variety and large volumes? Correct Answer Low Skilled Labour & Special Purpose Machines Your Answer Low Skilled Labour & Special Purpose Machines Multiple Choice Single Answer Question Which kind of inspection is followed in case of product layout? Correct Answer Pilot inspection Your Answer Pilot inspection Match The Following Question Correct Answer Your Answer Emerson Efficiency Plan Wage Payment Wage Payment Craft Facilities Planning Facilities Planning Work Sampling Machine utilization Sampling Inspection Gantt Chart Production Scheduling Production Scheduling

Select The Blank Question Correct Answer Your Answer

The ________ must ensure that the product satisfy the functional requirements it's usage. Quality of design Quality of design

Multiple Choice Multiple Answer Question Which of the following information is available in summary of part in a chart duri methods study? Correct Answer Frequency of each symbol , Total time for each symbol , Total distance travelled the object Your Answer Frequency of each symbol , Total time for each symbol

True/False Question Correct Answer Your Answer

The event numbers as far as possible reflect the logical relationships of the activ True False

Multiple Choice Single Answer Question Which varaible is taken along the ordinate or Y axis? Correct Answer Your Answer Quality Quality

Multiple Choice Multiple Answer Question Which of the following schedules are recommended to prepare and follow as a pa of preventive maintenance system? Correct Answer Preventive inspection schedule , Cleaning and upkeep schedule , Lubrication schedule Your Answer Preventive inspection schedule , Cleaning and upkeep schedule , Lubrication schedule

Multiple Choice Single Answer Question Which kind of preventive inspection detects some maintenance related characteristics by making use of human senses, when equipment is in operation? Correct Answer Extrernal inspection Your Answer Extrernal inspection

Multiple Choice Multiple Answer Question Which are different ways to show critical path in a network? Correct Answer Your Answer Thick Line , Red Line , Double Line Thick Line , Red Line , Double Line

Multiple Choice Multiple Answer Question What are the benefits of overhauling? Correct Answer Your Answer

It increases useful life of an equipment and it's parts , Advance planning allows t attend equipment without disturbing the production programme , Advance plann allows to prepare and keep ready the list of replacement spares It increases useful life of an equipment and it's parts , Advance planning allows t attend equipment without disturbing the production programme , Advance plann allows to prepare and keep ready the list of replacement spares

Match The Following Question Combined Layout

Correct Answer Mixed Layout

Your Answer Mixed Layout

Fixed Position Layout Product Layout Process Layout

Project Layout Line Layout Functional Layout

Line Layout Shop layout Functional Layout

Multiple Choice Multiple Answer Question Which of the following factors play important role while selecting or rejecting a particular site from legislation and taxation point of view? Correct Answer Labour laws , Building codes , Policies regarding issue of licences Your Answer Labour laws , Building codes , Policies regarding issue of licences

Select The Blank Question Correct Answer Your Answer

The ________ is the maximum percentage defective that for the purpose of sampling inspection can be considered satisfactory as a process average. Acceptable quality level Acceptable quality level

Multiple Choice Multiple Answer Question Major contributors in the development of Control Charts, Sampling plan are Correct Answer Your Answer F H Dodge , H G Roming , Walter Schewhart F H Dodge , H G Roming , Walter Schewhart

True/False Question Correct Answer Your Answer

Skill of labour force in a product type layout is usually higher than in the process type of layout False True

True/False Question Correct Answer Your Answer

Repetitive movements between work stations which are difficult to be traced on string diagrams can be conveniently shown on flow diagrams. False True

Select The Blank Question Correct Answer Your Answer

The ________ is necessary when the job requires detailed of one or more of the characteristics with the help of special equipment which is not available at the producing company. Inspection order Job card

Multiple Choice Multiple Answer

Question Correct Answer Your Answer

Which of the following cases can be referred as operation in method study recording? Change in physical characteristic , Consumption of physical effort , Change in chemical characteristic Change in physical characteristic , Consumption of physical effort , Change in chemical characteristic

Select The Blank Question Correct Answer Your Answer

The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking. Condition monitoring Overhauling

True/False Question Correct Answer Your Answer

All activities lying on the non-critical paths must have total float and free float. False False

Select The Blank Question Correct Answer Your Answer

Work study is also called ________ study Time and Motion Method

Match The Following Question Crash cost of an activity Normal time of an activity Crash time of activity Normal cost of an activity

Correct Answer Cc Tn Tc Cn

Your Answer Cc Tn Tc Cn

Multiple Choice Multiple Answer Question Which are the advantages of suburban location? Correct Answer Your Answer

Avaialability of adequate land at lower cost , Both skilled and unskilled labour ca available , Plant expansion is easier due to less or no restriction for building and construction Avaialability of adequate land at lower cost , Both skilled and unskilled labour ca available , Plant expansion is easier due to less or no restriction for building and construction

True/False Question

In case of X bar-R charts,it is ensured that the assignable causes are detected before the tolerances are violated, upper and lower statistical limits are worked o

and inserted into a chart. Correct Answer Your Answer True False

Multiple Choice Single Answer Question Which of the following is the criteria for the percentage defectives in the zone of indecision? Correct Answer Lots having the percentage defective more than AQL but less than LPTD Your Answer Lots having the percentage defective less than AQL but more than LPTD

Select The Blank Question Correct Answer Your Answer

The easiest way to bring the delayed job within the promised delivery time by us extra shift or weekly holiday is ________. Overtime working Overtime working

Multiple Choice Single Answer Question What do you mean by lowest possible direct cost required to complete an activity within it's crashed time? Correct Answer Crash cost Your Answer Crash cost

Multiple Choice Single Answer Question In case of Batch Production which kind of labour is expected? Correct Answer Your Answer Skilled in one specific Manufacturing Process Semiskilled

Multiple Choice Multiple Answer Question Which three of the following are causes of continuous upward pattern of Xbar-R control chart? Correct Answer Wear of tool , Abnormal rise in temperature , Accumulation of dirt Your Answer Wear of tool , Abnormal rise in temperature , Accumulation of dirt

True/False Question Correct Answer Your Answer

Root cause of most of the breakdowns is failure of the lubrication system. True True

True/False Question

It is not necessary to know spare time available on the non-critical path to allow little delay for noncritical activity.

Correct Answer Your Answer

False False

True/False Question Correct Answer Your Answer

MRP software generates time periodwise requiremetn of subassemblies True True

True/False Question Correct Answer Your Answer

In case of two handed process chart, the simultaneous activities of both hands a recorded opposite to each other on the chart. True True

Multiple Choice Single Answer Question What do you mean by CPM? Correct Answer Your Answer Critical Path Method Critical Path Method

Multiple Choice Multiple Answer Question Which of the following are major inputs to scheduling? Correct Answer Your Answer Overlapping of operations , Effective Capacity per work centre , Performance standards Overlapping of operations , Effective Capacity per work centre , Performance standards

Multiple Choice Multiple Answer Question Lack of material planning results in the following Correct Answer Your Answer Over ordering , under ordering , stockouts Over ordering , under ordering , stockouts

Multiple Choice Single Answer Question What do you mean by the verification of object against predetermined standards quality or quantity or both? Correct Answer Inspection Your Answer Inspection

Multiple Choice Multiple Answer Question What are the advantages of templates over diagrams? Correct Answer Can be conveniently moved on the graph paper , Less laborious , Saves time

Your Answer

Can be conveniently moved on the graph paper , Less laborious , Unskilled perso can do and analyze it

True/False Question Correct Answer Your Answer

It would not affect the project completion time if non-critical activities take little loner time than planned. True True

Select The Blank Question Correct Answer Your Answer

The ________ is the probability that a good lot will be rejected by the sampling plan. Producer's risk Producer's risk

Multiple Choice Single Answer Question Any premise in which persons are employed for purpose of making any product/ called Correct Answer Factory Your Answer Factory

Select The Blank Question Correct Answer Your Answer

An Ideal OC curve is ________ shaped curve that accpets all the lots with qualit equal to or better than AQL . Rectangular Bell

Multiple Choice Single Answer Question Which is the right time to prepare stores issue order? Correct Answer Your Answer When route sheet is ready When route sheet is ready

Multiple Choice Single Answer Question Which element of a network represents a task which has got a definite beginning and definite end? Correct Answer Activity Your Answer Activity

Multiple Choice Single Answer Question Which kind of preventive inspection detects some defects in moving parts, intern cracks, and others , when machine is under preplanned shutdown? Correct Answer Internal inspection Your Answer Internal inspection

Select The Blank Question Correct Answer Your Answer

Production Planning is a centralised activity which includes functions such as ________ Scheduling Dispatching

Select The Blank Question Correct Answer Your Answer

The ________ is the watch dog which ensures that every element of production activities which could affect the quality of end product are regulated to the exten desirable. Quality control Quality control

Select The Blank Question Correct Answer Your Answer

Goods after final inspection should accompany ________to enable dispatch department to identify and draw correct reference. Forwarding note Forwarding note

Multiple Choice Single Answer Question Who has introduced the useful concept of control chart in 1931? Correct Answer Your Answer Walter Shewhart Walter Shewhart

Multiple Choice Single Answer Question MRP is based on the concept of inventory demand which is of following type Correct Dependent and independent Answer Your Dependent and independent Answer Multiple Choice Single Answer Question Main objective of a good plant layout is Correct Answer Your Answer Reduce material handling cost Reduce material handling cost

True/False Question As a general rule, the number of tail event of an activity is more than that of it's head event. Correct False Answer

Your Answer

False

Select The Blank Question The ________ is the probability that a good lot will be rejected by the sampling plan. Correct Producer's risk Answer Your Producer's risk Answer Multiple Choice Multiple Answer Question Which of the following are important considerations concerning activity times? Correct Activity time should be obtained from the person responsible for the Answer completion of an activity , Activity time must be independent of any influence which the preceding or succeeding activity may have on it. , Activity time may assume that just the normal quantity of resources required to carry out the activity are available. Your Activity time should be obtained from the person responsible for the Answer completion of an activity , Activity time must be independent of any influence which the preceding or succeeding activity may have on it. , Activity time may assume that just the normal quantity of resources required to carry out the activity are available. Select The Blank Question The ________ pertain to the climatic conditions which the component , product or material should withstand. Correct Environmental specifications Answer Your Environmental specifications Answer Multiple Choice Multiple Answer Question Following are some of the factors considered for evaluation of alternative layouts Correct Flow of Material , Equipment utilization , Ease of supervision Answer Your Flow of Material , Ease of supervision , Delivery performance Answer Multiple Choice Multiple Answer Question Which of the following are assignable cause? Correct Answer Your Answer Large varaitions in hardness of material , Tool wear , Errors in setting Large varaitions in hardness of material , Tool wear , Errors in setting

True/False Question All activities must not be tied up into the network Correct Answer Your False False

Answer

Select The Blank Question In case of an OC curve, the risk of rejecting a good quality lot may vary between ________. Correct 0.01 to 10% Answer Your 0.01 to 10% Answer True/False Question In case of X bar, if the process is not under control indicated by some points falling outside the control limits, such points outside the control limits are eliminated and new trial control limits for the remaining points are computed. Correct True Answer Your True Answer Multiple Choice Single Answer Question What is the base for considering activity time as single time estimate or three time estimate? Correct Level of uncertainty Answer Your Availability of labour Answer Select The Blank Question The ________ is the maximum percentage defective that for the purpose of sampling inspection can be considered satisfactory as a process average. Correct Acceptable quality level Answer Your Acceptable quality level Answer Multiple Choice Single Answer Question What do you mean by lowest possible direct cost required to complete an activity within it's normal time? Correct Normal cost Answer Your Normal cost Answer Select The Blank Question A good maintenance system is not a luxary but a ________. Correct Answer Your Answer Necessity Necessity

Select The Blank

Question Correct Answer Your Answer

A ________helps to avoid crowding of jobs at a particular machine by change of route of some of the jobs or by diverting work to other machine. Control board Move order

Select The Blank Question The ________ is the watch dog which ensures that every element of production and activities which could affect the quality of end product are regulated to the extent desirable. Correct Quality control Answer Your Quality control Answer Multiple Choice Single Answer Question Any premise in which persons are employed for purpose of making any product/s is called Correct Factory Answer Your Factory Answer Match The Following Question Emerson Efficiency Plan Craft Work Sampling Gantt Chart

Correct Answer Wage Payment Facilities Planning Machine utilization Production Scheduling

Your Answer Wage Payment Facilities Planning Machine utilization Production Scheduling

Select The Blank Question A ________ is another form of subcontracting. Correct Answer Your Answer Hiring capacity Hiring capacity

Multiple Choice Multiple Answer Question In an organization there may not be a formal PPC department if Correct Answer Your Answer Work is the line Work is the line highly repetitive in nature , Planning activities are performed by staff , Number of workmen is not very large highly repetitive in nature , Planning activities are performed by staff , Number of workmen is not very large

Multiple Choice Multiple Answer

Question Correct Answer Your Answer

Which of the following cases can be treated as delay during recording of method study? Operators awaiting instructions from supervisor , Worker waiting for his turn at tools stores , Jobs awaiting at the machines for their turn Operators awaiting instructions from supervisor , Worker waiting for his turn at tools stores , Jobs awaiting at the machines for their turn

True/False Question Inspection order is must even for simple jobs which can be inspected by shop inspector with the tooling available on shop. Correct False Answer Your False Answer Multiple Choice Multiple Answer Question Order preparation process for products manufatured to order requires following documents Correct Sales Order , Work order , Shop order Answer Your Sales Order , Work order , Purchase order Answer Multiple Choice Single Answer Question Technique of Value Engineering can be effectively employed in design of a product to Correct To meet the intended function at lowest cost Answer Your Reduce lead time Answer True/False Question Cent percent inspection is often more practical and economical than sampling inspection. Correct False Answer Your False Answer Multiple Choice Multiple Answer Question Scale model used for layout analysis have following advantages Correct Answer Your Answer Nontechnical person finds be shown , Models can be Nontechnical person finds be shown , Models can be it easy to comprehend , Ovehead facilities can shifted easily it easy to comprehend , Ovehead facilities can shifted easily

Multiple Choice Single Answer Question Which of the following technique is event oriented ? Correct Answer Your Answer Project Evaluation & Review Technique Project Evaluation & Review Technique

Multiple Choice Single Answer Question What is the meaning of " Product features" according to J.M.Juran? Correct Answer Your Answer Quality of design Quality of design

Match The Following Question Crash cost of an activity Normal time of an activity Crash time of activity Normal cost of an activity

Correct Answer Cc Tn Tc Cn

Your Answer Cc Tn Tc Cn

Multiple Choice Multiple Answer Question What are uses of diagrams in method study? Correct Answer Your Answer Study different plant layouts and select the most optimum one , Study the extent of traffic over the different routes of the plant , Identify the extent of backtracking, cross traffic and obstacles encountered during the movement of material. Study different plant layouts and select the most optimum one , Study the extent of traffic over the different routes of the plant , Identify the extent of backtracking, cross traffic and obstacles encountered during the movement of material.

True/False Question A load chart specifies the work to be carried out by each person of company during shift hours. Correct False Answer Your True Answer Multiple Choice Multiple Answer Question Route Sheet generally contains following information Correct Answer Your Answer Material Specification , Sequence of operation , Skill of Labour Material Specification , Sequence of operation , Skill of Labour

True/False Question Cellular layout is based on the concept of Group Technology Correct Answer Your Answer True True

Multiple Choice Single Answer Question Which varaible is taken along the abscissa or X axis? Correct Answer Your Answer Time Standard deviation

Multiple Choice Multiple Answer Question Which are the advantages of suburban location? Correct Answer Your Answer Avaialability of adequate land at lower cost , Both skilled and unskilled labour can be available , Plant expansion is easier due to less or no restriction for building and construction Avaialability of adequate land at lower cost , Both skilled and unskilled labour can be available , Plant expansion is easier due to less or no restriction for building and construction

Select The Blank Question The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking. Correct Condition monitoring Answer Your Condition monitoring Answer Multiple Choice Multiple Answer Question Expediting function is concerned with following activities Correct Answer Your Answer Progress chasing to identify delays which may hold up production , Communicating possible delays in delivery date commitment to sales department , Devising cures to keep rate of production in line with schedule Recording progress of work , Progress chasing to identify delays which may hold up production , Communicating possible delays in delivery date commitment to sales department

Select The Blank Question Production control work is ________ in case of floor inspection as compared with the centralised inspection. Correct easier Answer Your time consuming Answer Select The Blank Question The easiest way to bring the delayed job within the promised delivery time by using extra shift or weekly holiday is ________. Correct Overtime working Answer Your Overtime working Answer True/False

Question Correct Answer Your Answer

In case of forward pass computation, the earliest event time of the first event is zero. True True

Multiple Choice Single Answer Question What is represented by an arrow in a network? Correct Answer Your Answer Activity Activity

True/False Question As a general rule, a site five times the actual plant size is considered minimum for parking, access facilities and future expansion. Correct True Answer Your True Answer True/False Question Independent float either affects the float of preceding activities or that of succeeding activities. Correct False Answer Your False Answer Multiple Choice Single Answer Question The document raised by PPC which authorises different functions to take action as per instruction is called Correct Work Order Answer Your Work Order Answer Multiple Choice Single Answer Question A good layout makes effective use of space. Utilization of space for a department like Stores can be measured by Correct Proportion of Cubic volume space utilized Answer Your Ratio of area utilised to area available Answer Multiple Choice Single Answer Question The process of changing inputs into outputs thereby adding some value to entity can be defined as Correct Operation Answer Your Operation Answer

LIST OF ATTEMPTED QUESTIONS AND ANSWERS Multiple Choice Single Answer Question MRP is based on the concept of inventory demand which is of following type Correct Answer Dependent and independent Your Answer Dependent and independent

Multiple Choice Single Answer Question Main objective of a good plant layout is Correct Answer Reduce material handling cost Your Answer Reduce material handling cost

True/False Question

As a general rule, the number of tail event of an activity is more than that of it's head event. Correct Answer False Your Answer False

Select The Blank Question The ________ is the probability that a good lot will be rejected by the sampling plan. Correct Answer Producer's risk Your Answer Producer's risk

Multiple Choice Multiple Answer Question Which of the following are important considerations concerning activity times? Correct Answer Activity time should be obtained from the person responsible for the completion of an activity , Activity time must be independent of any influence which the preceding or succeeding activity may have on it. , Activity time may assume that just the normal quantity of resources required to carry out the activity are available. Your Answer Activity time should be obtained from the person responsible for the completion of an activity , Activity time must be independent of any influence which the preceding or succeeding activity may have on it. , Activity time may assume that just the normal quantity of resources required to carry out the activity are available. Select The Blank Question The ________ pertain to the climatic conditions which the component , product or material should withstand. Correct Answer Environmental specifications Your Answer Environmental specifications

Multiple Choice Multiple Answer Question Following are some of the factors considered for evaluation of alternative layouts Correct Answer Flow of Material , Equipment utilization , Ease of supervision Your Answer Flow of Material , Ease of supervision , Delivery performance

Multiple Choice Multiple Answer Question Which of the following are assignable cause? Correct Answer Large varaitions in hardness of material , Tool wear , Errors in setting Your Answer Large varaitions in hardness of material , Tool wear , Errors in setting True/False Question

All activities must not be tied up into the network

Correct Answer False Your Answer False

Select The Blank Question In case of an OC curve, the risk of rejecting a good quality lot may vary between ________. Correct Answer 0.01 to 10% Your Answer 0.01 to 10%

True/False Question

In case of X bar, if the process is not under control indicated by some points falling outside the control limits, such points outside the control limits are eliminated and new trial control limits for the remaining points are computed. Correct Answer True Your Answer True

Multiple Choice Single Answer Question What is the base for considering activity time as single time estimate or three time estimate? Correct Answer Level of uncertainty Your Answer Availability of labour

Select The Blank Question The ________ is the maximum percentage defective that for the purpose of sampling inspection can be considered satisfactory as a process average. Correct Answer Acceptable quality level

Your Answer

Acceptable quality level

Multiple Choice Single Answer Question What do you mean by lowest possible direct cost required to complete an activity within it's normal time? Correct Answer Normal cost Your Answer Normal cost

Select The Blank Question A good maintenance system is not a luxary but a ________. Correct Answer Necessity Your Answer Necessity

Select The Blank Question A ________helps to avoid crowding of jobs at a particular machine by change of route of some of the jobs or by diverting work to other machine. Correct Answer Control board Your Answer Move order

Select The Blank Question The ________ is the watch dog which ensures that every element of production and activities which could affect the quality of end product are regulated to the extent desirable. Correct Answer Quality control Your Answer Quality control

Multiple Choice Single Answer Question Any premise in which persons are employed for purpose of making any product/s is called Correct Answer Factory Your Answer Factory

Match The Following Question Emerson Efficiency Plan Craft Work Sampling Gantt Chart

Correct Answer Wage Payment Facilities Planning Machine utilization Production Scheduling

Your Answer Wage Payment Facilities Planning Machine utilization Production Scheduling

Select The Blank Question A ________ is another form of subcontracting. Correct Answer Hiring capacity Your Answer Hiring capacity

Multiple Choice Multiple Answer Question In an organization there may not be a formal PPC department if Correct Answer Work is highly repetitive in nature , Planning activities are performed by the line staff , Number of workmen is not very large Your Answer Work is highly repetitive in nature , Planning activities are performed by the line staff , Number of workmen is not very large Multiple Choice Multiple Answer Question Which of the following cases can be treated as delay during recording of method study? Correct Answer Operators awaiting instructions from supervisor , Worker waiting for his turn at tools stores , Jobs awaiting at the machines for their turn Your Answer Operators awaiting instructions from supervisor , Worker waiting for his turn at tools stores , Jobs awaiting at the machines for their turn True/False Question

Inspection order is must even for simple jobs which can be inspected by shop inspector with the tooling available on shop. Correct Answer False Your Answer False

Multiple Choice Multiple Answer Question Order preparation process for products manufatured to order requires following documents Correct Answer Sales Order , Work order , Shop order Your Answer Sales Order , Work order , Purchase order

Multiple Choice Single Answer Question Technique of Value Engineering can be effectively employed in design of a product to Correct Answer To meet the intended function at lowest cost Your Answer Reduce lead time

True/False Question

Cent percent inspection is often more practical and economical than sampling inspection. Correct Answer False Your Answer False

Multiple Choice Multiple Answer Question Scale model used for layout analysis have following advantages Correct Answer Nontechnical person finds it easy to comprehend , Ovehead facilities can be shown , Models can be shifted easily Your Answer Nontechnical person finds it easy to comprehend , Ovehead facilities can be shown , Models can be shifted easily Multiple Choice Single Answer Question Which of the following technique is event oriented ? Correct Answer Project Evaluation & Review Technique Your Answer Project Evaluation & Review Technique

Multiple Choice Single Answer Question What is the meaning of " Product features" according to J.M.Juran? Correct Answer Quality of design Your Answer Quality of design

Match The Following Question Crash cost of an activity Normal time of an activity Crash time of activity Normal cost of an activity

Correct Answer Cc Tn Tc Cn

Your Answer Cc Tn Tc Cn

Multiple Choice Multiple Answer Question What are uses of diagrams in method study? Correct Answer Study different plant layouts and select the most optimum one , Study the extent of traffic over the different routes of the plant , Identify the extent of backtracking, cross traffic and obstacles encountered during the movement of material. Your Answer Study different plant layouts and select the most optimum one , Study the extent of traffic over the different routes of the plant , Identify the extent of backtracking, cross traffic and obstacles encountered during the movement of material. True/False Question

A load chart specifies the work to be carried out by each person of company during shift hours. Correct Answer False Your Answer True

Multiple Choice Multiple Answer Question Route Sheet generally contains following information Correct Answer Material Specification , Sequence of operation , Skill of Labour Your Answer Material Specification , Sequence of operation , Skill of Labour

True/False Question

Cellular layout is based on the concept of Group Technology

Correct Answer True Your Answer True

Multiple Choice Single Answer Question Which varaible is taken along the abscissa or X axis? Correct Answer Time Your Answer Standard deviation

Multiple Choice Multiple Answer Question Which are the advantages of suburban location? Correct Answer Avaialability of adequate land at lower cost , Both skilled and unskilled labour can be available , Plant expansion is easier due to less or no restriction for building and construction Your Answer Avaialability of adequate land at lower cost , Both skilled and unskilled labour can be available , Plant expansion is easier due to less or no restriction for building and construction Select The Blank Question The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking. Correct Answer Condition monitoring Your Answer Condition monitoring

Multiple Choice Multiple Answer Question Expediting function is concerned with following activities Correct Answer Progress chasing to identify delays which may hold up production , Communicating possible delays in delivery date commitment to sales department , Devising cures to keep rate of production in line with schedule Your Answer Recording progress of work , Progress chasing to identify delays which may hold up production , Communicating possible delays in delivery date commitment to sales department Select The Blank Question Production control work is ________ in case of floor inspection as compared with the centralised inspection.

Correct Answer easier Your Answer time consuming

Select The Blank Question The easiest way to bring the delayed job within the promised delivery time by using extra shift or weekly holiday is ________. Correct Answer Overtime working Your Answer Overtime working

True/False Question

In case of forward pass computation, the earliest event time of the first event is zero. Correct Answer True Your Answer True

Multiple Choice Single Answer Question What is represented by an arrow in a network? Correct Answer Activity Your Answer Activity

True/False Question

As a general rule, a site five times the actual plant size is considered minimum for parking, access facilities and future expansion. Correct Answer True Your Answer True

True/False Question

Independent float either affects the float of preceding activities or that of succeeding activities. Correct Answer False Your Answer False

Multiple Choice Single Answer Question The document raised by PPC which authorises different functions to take action as per instruction is called Correct Answer Work Order Your Answer Work Order

Multiple Choice Single Answer Question A good layout makes effective use of space. Utilization of space for a department like Stores can be measured by Correct Answer Proportion of Cubic volume space utilized

Your Answer

Ratio of area utilised to area available

Multiple Choice Single Answer Question The process of changing inputs into outputs thereby adding some value to entity can be defined as Correct Answer Operation Your Answer Operation

Multiple Choice Single Answer Question MRP is based on the concept of inventory demand which is of following type Correct Answer Dependent and independent Your Answer Dependent and independent

Multiple Choice Single Answer Question Main objective of a good plant layout is Correct Answer Reduce material handling cost Your Answer Reduce material handling cost

True/False Question

As a general rule, the number of tail event of an activity is more than that of it's head event. Correct Answer False Your Answer False

Select The Blank Question The ________ is the probability that a good lot will be rejected by the sampling plan. Correct Answer Producer's risk Your Answer Producer's risk

Multiple Choice Multiple Answer Question Which of the following are important considerations concerning activity times? Correct Answer Activity time should be obtained from the person responsible for the completion of an activity , Activity time must be independent of any influence which the preceding or succeeding activity may have on it. , Activity time may assume that just the normal quantity of resources required to carry out the activity are available. Your Answer Activity time should be obtained from the person responsible for the completion of an activity , Activity time must be independent of any influence which the preceding or succeeding activity may have on it. , Activity time may assume that just the normal quantity of resources required to carry out the activity are

available.

Select The Blank Question The ________ pertain to the climatic conditions which the component , product or material should withstand. Correct Answer Environmental specifications Your Answer Environmental specifications

Multiple Choice Multiple Answer Question Following are some of the factors considered for evaluation of alternative layouts Correct Answer Flow of Material , Equipment utilization , Ease of supervision Your Answer Flow of Material , Ease of supervision , Delivery performance

Multiple Choice Multiple Answer Question Which of the following are assignable cause? Correct Answer Large varaitions in hardness of material , Tool wear , Errors in setting Your Answer Large varaitions in hardness of material , Tool wear , Errors in setting

True/False Question

All activities must not be tied up into the network

Correct Answer False Your Answer False

Select The Blank Question In case of an OC curve, the risk of rejecting a good quality lot may vary between ________. Correct Answer 0.01 to 10% Your Answer 0.01 to 10%

True/False Question

In case of X bar, if the process is not under control indicated by some points falling outside the control limits, such points outside the control limits are eliminated and new trial control limits for the remaining points are computed. Correct Answer True Your Answer True

Multiple Choice Single Answer Question What is the base for considering activity time as single time estimate or three time estimate? Correct Answer Level of uncertainty

Your Answer

Availability of labour

Select The Blank Question The ________ is the maximum percentage defective that for the purpose of sampling inspection can be considered satisfactory as a process average. Correct Answer Acceptable quality level Your Answer Acceptable quality level

Multiple Choice Single Answer Question What do you mean by lowest possible direct cost required to complete an activity within it's normal time? Correct Answer Normal cost Your Answer Normal cost

Select The Blank Question A good maintenance system is not a luxary but a ________. Correct Answer Necessity Your Answer Necessity

Select The Blank Question A ________helps to avoid crowding of jobs at a particular machine by change of route of some of the jobs or by diverting work to other machine. Correct Answer Control board Your Answer Move order

Select The Blank Question The ________ is the watch dog which ensures that every element of production and activities which could affect the quality of end product are regulated to the extent desirable. Correct Answer Quality control Your Answer Quality control

Multiple Choice Single Answer Question Any premise in which persons are employed for purpose of making any product/s is called Correct Answer Factory Your Answer Factory

Match The Following Question Emerson Efficiency Plan

Correct Answer Wage Payment

Your Answer Wage Payment

Craft Work Sampling Gantt Chart

Facilities Planning Machine utilization Production Scheduling

Facilities Planning Machine utilization Production Scheduling

Select The Blank Question A ________ is another form of subcontracting. Correct Answer Hiring capacity Your Answer Hiring capacity

Multiple Choice Multiple Answer Question In an organization there may not be a formal PPC department if Correct Answer Work is highly repetitive in nature , Planning activities are performed by the line staff , Number of workmen is not very large Your Answer Work is highly repetitive in nature , Planning activities are performed by the line staff , Number of workmen is not very large Multiple Choice Multiple Answer Question Which of the following cases can be treated as delay during recording of method study? Correct Answer Operators awaiting instructions from supervisor , Worker waiting for his turn at tools stores , Jobs awaiting at the machines for their turn Your Answer Operators awaiting instructions from supervisor , Worker waiting for his turn at tools stores , Jobs awaiting at the machines for their turn True/False Question

Inspection order is must even for simple jobs which can be inspected by shop inspector with the tooling available on shop. Correct Answer False Your Answer False

Multiple Choice Multiple Answer Question Order preparation process for products manufatured to order requires following documents Correct Answer Sales Order , Work order , Shop order Your Answer Sales Order , Work order , Purchase order

Multiple Choice Single Answer Question Technique of Value Engineering can be effectively employed in design of a product to Correct Answer To meet the intended function at lowest cost Your Answer Reduce lead time

True/False

Question

Cent percent inspection is often more practical and economical than sampling inspection. Correct Answer False Your Answer False

Multiple Choice Multiple Answer Question Scale model used for layout analysis have following advantages Correct Answer Nontechnical person finds it easy to comprehend , Ovehead facilities can be shown , Models can be shifted easily Your Answer Nontechnical person finds it easy to comprehend , Ovehead facilities can be shown , Models can be shifted easily Multiple Choice Single Answer Question Which of the following technique is event oriented ? Correct Answer Project Evaluation & Review Technique Your Answer Project Evaluation & Review Technique

Multiple Choice Single Answer Question What is the meaning of " Product features" according to J.M.Juran? Correct Answer Quality of design Your Answer Quality of design

Match The Following Question Crash cost of an activity Normal time of an activity Crash time of activity Normal cost of an activity

Correct Answer Cc Tn Tc Cn

Your Answer Cc Tn Tc Cn

Multiple Choice Multiple Answer Question What are uses of diagrams in method study? Correct Answer Study different plant layouts and select the most optimum one , Study the extent of traffic over the different routes of the plant , Identify the extent of backtracking, cross traffic and obstacles encountered during the movement of material. Your Answer Study different plant layouts and select the most optimum one , Study the extent of traffic over the different routes of the plant , Identify the extent of backtracking, cross traffic and obstacles encountered during the movement of material. True/False

Question

A load chart specifies the work to be carried out by each person of company during shift hours. Correct Answer False Your Answer True

Multiple Choice Multiple Answer Question Route Sheet generally contains following information Correct Answer Material Specification , Sequence of operation , Skill of Labour Your Answer Material Specification , Sequence of operation , Skill of Labour

True/False Question

Cellular layout is based on the concept of Group Technology

Correct Answer True Your Answer True

Multiple Choice Single Answer Question Which varaible is taken along the abscissa or X axis? Correct Answer Time Your Answer Standard deviation

Multiple Choice Multiple Answer Question Which are the advantages of suburban location? Correct Answer Avaialability of adequate land at lower cost , Both skilled and unskilled labour can be available , Plant expansion is easier due to less or no restriction for building and construction Your Answer Avaialability of adequate land at lower cost , Both skilled and unskilled labour can be available , Plant expansion is easier due to less or no restriction for building and construction Select The Blank Question The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking. Correct Answer Condition monitoring Your Answer Condition monitoring

Multiple Choice Multiple Answer Question Expediting function is concerned with following activities Correct Answer Progress chasing to identify delays which may hold up production , Communicating possible delays in delivery date commitment to sales department , Devising cures to keep rate of production in line with schedule Your Answer Recording progress of work , Progress chasing to identify delays which may hold up production , Communicating possible delays in delivery date commitment to sales department

Select The Blank Question Production control work is ________ in case of floor inspection as compared with the centralised inspection. Correct Answer easier Your Answer time consuming

Select The Blank Question The easiest way to bring the delayed job within the promised delivery time by using extra shift or weekly holiday is ________. Correct Answer Overtime working Your Answer Overtime working

True/False Question

In case of forward pass computation, the earliest event time of the first event is zero. Correct Answer True Your Answer True

Multiple Choice Single Answer Question What is represented by an arrow in a network? Correct Answer Activity Your Answer Activity

True/False Question

As a general rule, a site five times the actual plant size is considered minimum for parking, access facilities and future expansion. Correct Answer True Your Answer True

True/False Question

Independent float either affects the float of preceding activities or that of succeeding activities. Correct Answer False Your Answer False

Multiple Choice Single Answer Question The document raised by PPC which authorises different functions to take action as per instruction is called Correct Answer Work Order Your Answer Work Order

Multiple Choice Single Answer

Question

A good layout makes effective use of space. Utilization of space for a department like Stores can be measured by Correct Answer Proportion of Cubic volume space utilized Your Answer Ratio of area utilised to area available

Multiple Choice Single Answer Question The process of changing inputs into outputs thereby adding some value to entity can be defined as Correct Answer Operation Your Answer Operation

True/False Question Correct Answer Your Answer

Flow process charts do record movements as well as visual pictures. False False

True/False Question Correct Answer Your Answer

The OC curve is based on the assumption that if the lot is large in comparison to the sample, the probabilities of the OC curve will follow a poisson distribution. False True

Multiple Choice Single Answer Question The ratio of output to input of a production system is commonly known as Correct Productivity Answer Your Answer Productivity Multiple Choice Multiple Answer Question Order preparation process for products manufatured to order requires following documents Correct Sales Order , Work order , Shop order Answer Your Answer Work order , Purchase order

Select The Blank Question The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking. Correct Condition monitoring Answer Your Answer Preventive maintenance

Match The Following Question Scheduling of interrelated activities of small projects with consideration of uncertainty of duration of activities.

Correct Answer Critical Path Analysis

Your Answer Critical Path Analysis

Two machines & processing Johnson's Two Machine time depends on sequence Algorithm of job loading Sufficient orders and resonable choice of machines Time relationship between when a product is required and when it can be made available Index Method

Johnson's Two Machine Algorithm Index Method

Critical Ratio Scheduling

Time series

Select The Blank Question Production control work is ________ in case of floor inspection as compared with the centralised inspection. Correct easier Answer Your Answer easier

Match The Following Question When to inspect What to inspect How to inspect How much to inspect

Correct Answer Stages of inspection Specification Inspection devices Sampling or cent percent inspection

Your Answer Specification Standard Tools & Jigs Stages of inspection

Multiple Choice Single Answer Question Material Planning is an integral part of Correct Answer Your Answer Production Planning Process Planning

Select The Blank Question An Ideal OC curve is ________ shaped curve that accpets all the lots with quality equal to or better than AQL . Correct Rectangular Answer

Your Answer

Rectangular

Multiple Choice Single Answer Question Technique of Value Engineering can be effectively employed in design of a product to Correct To meet the intended function at lowest cost Answer Your Answer Reduce lead time

Multiple Choice Single Answer Question Material control function of PPC is concerned with Correct Answer Your Answer Preparation of material estimates Preparation of material estimates

Multiple Choice Single Answer Question Main objective of a good plant layout is Correct Answer Your Answer Reduce material handling cost Reduce material handling cost

True/False Question Correct Answer Your Answer

In case of X bar-R charts, statistical limits are calculated from averages of samples of n (4,5,) instead of single sample of large size to reduce the spread of natural variability. True True

Multiple Choice Multiple Answer Question Which of the following is not the characteristic of Project Production? Correct Answer Your Answer Continuous flow of material , Highly mechanised material handling , Virtually zero manufacturing cycle time Fixed position layout , Virtually zero manufacturing cycle time

Multiple Choice Single Answer Question A good plant layout helps in Correct Answer Your Answer Reducing handling costs Reducing handling costs

Multiple Choice Single Answer Question Inadequate production capacity ultimately leads to Correct Answer Poor Customer Service

Your Answer

Low Productivity

Select The Blank Question Production Planning is a centralised activity which includes functions such as ________ Correct Scheduling Answer Your Answer Scheduling

Multiple Choice Single Answer Question Any premise in which persons are employed for purpose of making any product/s is called Correct Factory Answer Your Answer Factory

Multiple Choice Multiple Answer Question What are the uses of the instruction manual provided by the manufacturer of a machine? Correct It gives instructions regarding installation and operation of the Answer equipment , It contains note on common troubles with causes and remedies for troubleshooting , It enlists points, frequency and type of lubrication Your Answer It gives instructions regarding installation and operation of the equipment , It contains note on common troubles with causes and remedies for troubleshooting Multiple Choice Multiple Answer Question MRP utilises the following information Correct Answer Your Answer Master production schedule , Product structure , Lead time for procurement/manufacturing Master production schedule , Product structure , Lead time for procurement/manufacturing

Select The Blank Question A good maintenance system is not a luxary but a ________. Correct Answer Your Answer Necessity Necessity

True/False Question Correct Answer Your Answer

Shape od an OC curve is a function of sample size and the acceptance number. True False

Multiple Choice Multiple Answer

Question Correct Answer Your Answer

Which of the following can be subtypes of corrective maintenance? Shutdown Maintenance , Design-out Maintenance , Design-in Maintenance Predictive Maintenance , Shutdown Maintenance

True/False Question Correct Answer Your Answer

For p-chart, "Inspection by variables" is much faster than "Inspection by attributes" False True

Multiple Choice Single Answer Question Site factors for plant location include Correct Answer Your Answer Suitability of land Suitability of land

Select The Blank Question The ________ breakdowns usually cost more, partly due to damage done to the adjustment components and partly due to emergency actions. Correct Unexpected Answer Your Answer Partial

True/False Question Correct Answer Your Answer

Cent percent inspection is a must if the inspection is of destructive nature. False False

True/False Question Correct Answer Your Answer

Since value of p can never be positive, hence" if LCLp works out to be positive, it is taken as zero." False True

Multiple Choice Single Answer Question Which varaible is taken along the abscissa or X axis? Correct Answer Your Answer Time Standard deviation

Multiple Choice Multiple Answer

Question Correct Answer Your Answer

Which of the following are examples of specifications? Commercial standards , Assembly and testing instructions , Bill of material Production schedule , Commercial standards , Assembly and testing instructions

Multiple Choice Multiple Answer Question Which of the following products should be produced by using mass production? Correct Refrigerator , Tyre for automobile , Television Set Answer Your Answer Refrigerator , Tyre for automobile , Television Set

Multiple Choice Single Answer Question Which of the following techniques is used by industrial engineering department to obtain the utilisation index? Correct Work Sampling Studies Answer Your Answer Method Study

True/False Question Correct Answer Your Answer

An ideal OC curve is never possible only with cent percent inspection. False False

Select The Blank Question The ________ is the probability that a bad lot will be accepted by the sampling plan. Correct Consumer's risk Answer Your Answer Producer's risk

Select The Blank Question The easiest way to bring the delayed job within the promised delivery time by using extra shift or weekly holiday is ________. Correct Overtime working Answer Your Answer Overtime working

True/False Question Correct Answer Your Answer

The operator should not stop production if first piece is not approved by the inspector. False False

Multiple Choice Single Answer

Question Correct Answer Your Answer

The process of changing inputs into outputs thereby adding some value to entity can be defined as Operation Conversion

Multiple Choice Single Answer Question Which kind of relationship exists between those activities which can be carried out simultaneously and both activities require definite time to finish? Correct Concurrent activities Answer Your Answer Concurrent activities

Multiple Choice Multiple Answer Question Which are different ways to show critical path in a network? Correct Answer Your Answer Thick Line , Red Line , Double Line Dotted line

Select The Blank Question A ________helps to avoid crowding of jobs at a particular machine by change of route of some of the jobs or by diverting work to other machine. Correct Control board Answer Your Answer Control board

Multiple Choice Single Answer Question What do you understand by PERT ? Correct Answer Your Answer Project Evaluation & Review Technique Project Evaluation & Review Technique

Multiple Choice Multiple Answer Question Which of the following factors play important role while selecting or rejecting a particular site from legislation and taxation point of view? Correct Labour laws , Building codes , Policies regarding issue of licences Answer Your Answer Labour laws , Policies regarding issue of licences

Multiple Choice Multiple Answer Question Which of the following concepts must be understood for the achievement of quality? Correct Quality of conformance , Purpose of product , Quality of design Answer Your Answer Purpose of product , Process specifications , Quality of design

Select The Blank Question The ________ is the probability that a good lot will be rejected by the sampling plan. Correct Producer's risk Answer Your Answer Producer's risk

Multiple Choice Single Answer Question What do you mean by the project duration for which the total cost is minimum? Correct Optimum duration Answer Your Answer Optimum duration

True/False Question Correct Answer Your Answer

Originating process of raw material influence Process Planning True True

Multiple Choice Multiple Answer Question Which of the following products should be produced by using mass production? Correct Answer Refrigerator , Tyre for automobile , Television Set Your Answer Refrigerator , Tyre for automobile , Television Set Multiple Choice Multiple Answer Question What are the benefits of reconditioning? Correct Answer Eliminates problems and frequent breakdowns , Increases life of an equipment , It helps to plan requirement of replacement spares Your Answer Eliminates problems and frequent breakdowns , Increases life of an equipment , It helps to plan requirement of replacement spares Multiple Choice Multiple Answer Question Which kind of natural delays and interruptions are considered during estimation of activity time? Correct Answer Shop efficiency , Breakdowns , Absenteeism Your Answer Breakdowns , Absenteeism , Delay due to shortage of resources Multiple Choice Multiple Answer Question How to exercise control over quality? Correct Answer Periodical analysis of inspecting reports to establish causes of rejections , Preperation of quality standard and specifications , Exercising control over inputs

POM assgn : Sushant

Your Answer Periodical analysis of inspecting reports to establish causes of rejections , Preperation of quality standard and specifications , Replacing existing measuring instruments by those having smaller least count. , Exercising control over inputs True/False Question In case of forward pass computation, the earliest event time of a plain event equals the earliest event time of the preceding event plus duration of activity emanating from the preceding event. Correct Answer True Your Answer True True/False Question Any proposed change must not be intimated to workers in advance. Correct Answer False Your Answer False Select The Blank Question The ________ are the definitions of the measurable as well as nonmeasurable characteristics of the product. Correct Answer Specifications Your Answer Standards Multiple Choice Multiple Answer Question How many of the following are types of specification? Correct Answer Material specifications , Dimensional specifications , Performance specifications Your Answer Material specifications , Dimensional specifications , Performance specifications Select The Blank Question A ________ is another form of subcontracting. Correct Answer Hiring capacity Your Answer Collaboration Select The Blank Question The ________ advocates maintenance procedures whereby the condition of the plant is constantly watched through systematic inspection to unearth unhealthy conditions and preventive Correct Answer Preventive Maintenance Your Answer Preventive Maintenance Multiple Choice Single Answer Question Which phase of method study is concerned with analyzing the facts critically, generating alternatives which form the basis for selection and development of improved methods?

Correct Answer Critical examination Your Answer Development and selection Multiple Choice Single Answer Question In exponential smoothing method,for a stable demand pattern and better smoothing effect, value of fraction( Alpha) selected is Correct Answer 0.05 to 0.10 Your Answer 0.20 to 0.25 Multiple Choice Single Answer Question Technique of Value Engineering can be effectively employed in design of a product to Correct Answer To meet the intended function at lowest cost Your Answer Reduce process rejections Select The Blank Question The ________ is the probability that a bad lot will be accepted by the sampling plan. Correct Answer Consumer's risk Your Answer Acceptable quality level Multiple Choice Multiple Answer Question Which of the following observations are expected from the preventive maintenance person? Correct Answer Wrong allignments , Overheating defects , Excessive play Your Answer Wrong allignments , Overheating defects , Excessive play Multiple Choice Single Answer Question When should operator or supervisor is supposed to sign the perforated route sheet? Correct Answer After completion of operation Your Answer After completion of operation Select The Blank Question The ________ must ensure that the product satisfy the functional requirements of it's usage. Correct Answer Quality of design Your Answer Quality of conformance Multiple Choice Single Answer Question What do you understand by the properties which are difficult to measure quantitatively but usually measured by the comarision and then classification into acceptable or unacceptable? Correct Answer Attributes Your Answer Attributes

Multiple Choice Multiple Answer Question Which of the following may be the objectives of project crashing? Correct Answer To complete the project in the least possible time , To reduce project cost below it's normal cost , To achieve uniformity in requirement of resources Your Answer To complete the project in the least possible time , To reduce project cost below it's normal cost , To achieve uniformity in requirement of resources , To improve the labour efficiency True/False Question Since recording by descriptive method has it's limitations, it is not recommended for use in method study. Correct Answer True Your Answer True Multiple Choice Single Answer Question What do you mean by the selection of the job for the method study on the basis of manufacturing difficulties? Correct Answer Technical consideration Your Answer Economic consideration Multiple Choice Single Answer Question One of the external factors influencing Material Planning is Correct Answer Price trends Your Answer Price trends Select The Blank Question The ________ is the maximum percentage defective that for the purpose of sampling inspection can be considered satisfactory as a process average. Correct Answer Acceptable quality level Your Answer Lot Tolerance Percentage Defective True/False Question Cent percent inspection is a must if the inspection is of destructive nature. Correct Answer False Your Answer True Select The Blank Question Capacity decisions have a direct influence on performance of production system in respect of ________ Correct Answer Delivery performance Your Answer Delivery performance Multiple Choice Multiple Answer

Question Which of the following factors related to the labour and wages are considered while deciding the plant location? Correct Answer Prevailing wage pattern , Productivity of labour , Industrial relations Your Answer Prevailing wage pattern , Productivity of labour , Industrial relations Multiple Choice Single Answer Question Which is the ideal place to write a description of an activity in a network? Correct Answer Above the arrow Your Answer Above the arrow True/False Question If the firm has adopted elaborate planned maintenance system, there is no chance of any unplanned maintenance work. Correct Answer False Your Answer False Match The Following Question Correct Answer Your Answer Change in chemical characteristic Chemical reaction Chemical reaction Consumption of effort Posting a ledger Giving directions or instructions Information given Giving directions or instructions Posting a ledger Subtraction Removal of worn-out part from a machine Removal of wornout part from a machine Select The Blank Question OC curve of ideal sampling plan suggests that all lots less than 3% defectives have the probability of acceptance of ________. Correct Answer One Your Answer One Select The Blank Question A set of activities to keep an equipment in the specified condition is called as ________. Correct Answer Maintenance Your Answer Maintenance Multiple Choice Single Answer Question Site factors for plant location include Correct Answer Suitability of land

Your Answer

Suitability of land

True/False Question Both, preventive and breakdown maintenance work must be assigned to the same team. Correct Answer False Your Answer False Multiple Choice Single Answer Question Product layout is employed for manufacturing following products Correct Answer refrigirators Your Answer automobile components Multiple Choice Single Answer Question What can be the worst effect due to excessive vibration? Correct Answer Breakdown Your Answer Breakdown Multiple Choice Multiple Answer Question What is indicated by the erratic pattern points falling above and below the control limits in the Xbar-R-control chart? Correct Answer Defects in materials , Poorly trained operators , Frequent adjustments of machines Your Answer Defects in materials , Poorly trained operators , Frequent adjustments of machines True/False Question In case of two handed process chart, inspection symbol is used when check by touch or feel is involved. Correct Answer True Your Answer True True/False Question Site selection should also take into account topography and soil structure of the land. Correct Answer True Your Answer False Multiple Choice Single Answer Question The ratio of output to input of a production system is commonly known as Correct Answer Productivity Your Answer Effectiveness Select The Blank

Question A ________helps to avoid crowding of jobs at a particular machine by change of route of some of the jobs or by diverting work to other machine. Correct Answer Control board Your Answer Control board Match The Following Question Correct Answer Your Answer Emerson Efficiency Plan Wage Payment Sampling Inspection Craft Facilities Planning Facilities Planning Work Sampling Machine utilization Production Scheduling Gantt Chart Production Scheduling Charting technique True/False Question Only skilled worker can use the fixed limit gauge. Correct Answer False Your Answer False Multiple Choice Multiple Answer Question Which are the different methods to record details of the existing method during method study? Correct Answer Charts , Diagrams , Templates or models Your Answer Charts , Diagrams Multiple Choice Single Answer Question Which photographic technique is used to record path of motions of the members of the body during method study? Correct Answer Cyclograph Your Answer Flowgraph Select The Blank Question The ________ is the watch dog which ensures that every element of production and activities which could affect the quality of end product are regulated to the extent desirable. Correct Answer Quality control Your Answer Inspection True/False Question In case of centralised inspection, inspection rooms generally become bottleneck and cause delay in taking action regarding rejection or rework. Correct Answer True

Your Answer

True

Multiple Choice Multiple Answer Question Which of the following are minimum requirement for a good quality of design? Correct Answer Resonable cost , Resonable procurement time , Resonable manufacturing time Your Answer Resonable cost , Resonable procurement time , Resonable manufacturing time

LIST OF ATTEMPTED QUESTIONS AND ANSWERS Select The Blank Question Material flow in process layout is ________. Correct Answer Discontinuous Your Answer Discontinuous

Multiple Choice Multiple Answer Question Which details are recorded in columns when each square of progress card is split up into columns? Correct Answer Date , Shift , Quantity produced Your Answer Shift , Quantity produced , Date

Multiple Choice Multiple Answer Question Which of the following cases can be referred as operation in method study recording? Correct Answer Change in physical characteristic , Consumption of physical effort , Change in chemical characteristic Your Answer Change in physical characteristic , Consumption of physical effort , Change in chemical characteristic Multiple Choice Single Answer Question Process type layout is suitable when Correct Answer there is wide variation in processing time of operations Your Answer there is wide variation in processing time of operations

Multiple Choice Multiple Answer Question Scale model used for layout analysis have following advantages Correct Answer Nontechnical person finds it easy to comprehend , Ovehead facilities can be shown , Models can be shifted easily Your Answer Nontechnical person finds it easy to comprehend , Ovehead facilities can be shown , Models can be shifted easily True/False

Question

The operator should not stop production if first piece is not approved by the inspector. Correct Answer False Your Answer False

True/False Question

Kanban system is essentially a computer based system for production scheduling and control Correct Answer False Your Answer False

True/False Question

MRP software generates time periodwise requiremetn of subassemblies Correct Answer True Your Answer True

Multiple Choice Single Answer Question Following is one of the tasks of Production Control Correct Answer Actual issue of forms and documents Your Answer Actual issue of forms and documents

Multiple Choice Single Answer Question Which of the following policies is advisable in case of low product variety and large volumes? Correct Answer Low Skilled Labour & Special Purpose Machines Your Answer Low Skilled Labour & Special Purpose Machines

Multiple Choice Multiple Answer Question Which of the following observations are expected from the preventive maintenance person? Correct Answer Wrong allignments , Overheating defects , Excessive play Your Answer Wrong allignments , Overheating defects , Excessive play

Select The Blank Question The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking. Correct Answer Condition monitoring Your Answer Condition monitoring

Match The Following

Question Emerson Efficiency Plan Craft Work Sampling Gantt Chart

Correct Answer Wage Payment Facilities Planning Machine utilization Production Scheduling

Your Answer Wage Payment Facilities Planning Machine utilization Production Scheduling

Multiple Choice Single Answer Question Out of two basic criteria for the selection of a manufacturing method, one is, it must be able to meet the specifications of final product and the other is, it must be Correct Answer Cost effective method Your Answer Cost effective method

Multiple Choice Multiple Answer Question Which of the following variables which operate periodically are the reasons for the cyclic pattern depicting peaks and valleys during Xbar-R control chart? Correct Answer Wornout positions , Fatigue , Roller eccentricity Your Answer Fatigue , Roller eccentricity , Wornout positions

Multiple Choice Multiple Answer Question Which are the three distinct parts of the chart? Correct Answer Summary , Introduction , Body Your Answer Summary , Introduction , Body

Multiple Choice Single Answer Question Main objective of a good plant layout is Correct Answer Reduce material handling cost Your Answer Reduce material handling cost

Multiple Choice Multiple Answer Question Which of the following charts are used for the recording of data during the method study? Correct Answer Operation process chart , Multiple activity chart , Flow process chart Your Answer Operation process chart , Multiple activity chart , Flow process chart

Multiple Choice Multiple Answer Question What are the benefits of overhauling?

Correct Answer It increases useful life of an equipment and it's parts , Advance planning allows to attend equipment without disturbing the production programme , Advance planning allows to prepare and keep ready the list of replacement spares Your Answer It increases useful life of an equipment and it's parts , Advance planning allows to attend equipment without disturbing the production programme , Advance planning allows to prepare and keep ready the list of replacement spares True/False Question

The chances that pessimistic time could even be longer should be one in hundred or less. Correct Answer True Your Answer True

Multiple Choice Multiple Answer Question What are uses of diagrams in method study? Correct Answer Study different plant layouts and select the most optimum one , Study the extent of traffic over the different routes of the plant , Identify the extent of backtracking, cross traffic and obstacles encountered during the movement of material. Your Answer Study different plant layouts and select the most optimum one , Study the extent of traffic over the different routes of the plant , Identify the extent of backtracking, cross traffic and obstacles encountered during the movement of material. Select The Blank Question A ________ is the systematic recording and critical examination of existing and proposed ways of doing work, as a means of developing and applying easier and more effective methods and reducing costs. Correct Answer Method study Your Answer Method study

True/False Question

F W Taylor devised a system for classifying motions into basic divisions called Therbligs Correct Answer False Your Answer False

Select The Blank Question The ________ is the probability that a bad lot will be accepted by the sampling plan. Correct Answer Consumer's risk Your Answer Consumer's risk

True/False

Question

Fixed cost is lower in case of continuous production than intermittent production. Correct Answer False Your Answer False

Multiple Choice Single Answer Question Site factors for plant location include Correct Answer Suitability of land Your Answer Suitability of land

Multiple Choice Single Answer Question What do you understand by the selection of the job for the method study on the basis of money saving potential of the job? Correct Answer Economic consideration Your Answer Economic consideration

Select The Blank Question In case of normal distribution curve, the distribution is dependent on only two parameters, mean and ________. Correct Answer Standard deviation Your Answer Standard deviation

Select The Blank Question In case of an OC curve, the risk of rejecting a good quality lot may vary between ________. Correct Answer 0.01 to 10% Your Answer 0.01 to 10%

True/False Question

Floor inspection promotes tendency of machines to drift out of limits and produce defectives. Correct Answer False Your Answer False

Multiple Choice Single Answer Question In case of Batch Production which kind of labour is expected? Correct Answer Skilled in one specific Manufacturing Process Your Answer Skilled in one specific Manufacturing Process

True/False Question

Every network does not necessarily have a critical path.

Correct Answer False Your Answer False

Multiple Choice Single Answer Question How total floats on non-critical activities are shown in the time chart during project scheduling? Correct Answer Dotted lines Your Answer Dotted lines

Select The Blank Question An ________ history card is the record of all repairs, replacements and engineering changes carried out in the equipment during it's period of service. Correct Answer Equipment history card Your Answer Equipment history card

True/False Question

Objective of Work Study is to improve Productivity

Correct Answer True Your Answer True

Multiple Choice Single Answer Question Production Planning includes Correct Answer Predetermination of manufacturing requirements Your Answer Predetermination of manufacturing requirements

True/False Question

While numbering as per Fulkerson's rule, arrows emerging from the initial event are deleted so as to create one or more initial events. Correct Answer True Your Answer True

Multiple Choice Single Answer Question Who has introduced the useful concept of control chart in 1931? Correct Answer Walter Shewhart Your Answer Walter Shewhart

Multiple Choice Multiple Answer Question Major contributors in the development of Control Charts, Sampling plan are

Correct Answer F H Dodge , H G Roming , Walter Schewhart Your Answer F H Dodge , H G Roming , Walter Schewhart

True/False Question

In case of X bar, if the process is not under control indicated by some points falling outside the control limits, such points outside the control limits are eliminated and new trial control limits for the remaining points are computed. Correct Answer True Your Answer True

Multiple Choice Multiple Answer Question What are the advantages of templates over diagrams? Correct Answer Can be conveniently moved on the graph paper , Less laborious , Saves time Your Answer Can be conveniently moved on the graph paper , Less laborious , Saves time Multiple Choice Multiple Answer Question Which are the different types of flow process charts used for method study? Correct Answer Equipment type , Man type , Material type Your Answer Equipment type , Man type , Material type

Multiple Choice Multiple Answer Question What is indicated by the hugging points lying close to mean of the process in X bar-R- control chart? Correct Answer Biases in measurements , Recording done without actual measurements , Improper selection of samples Your Answer Biases in measurements , Recording done without actual measurements , Improper selection of samples Select The Blank Question The ________ must ensure that the product satisfy the functional requirements of it's usage. Correct Answer Quality of design Your Answer Quality of conformance

Select The Blank Question The ________ refers to the number of samples to be collected to construct a control chart. Correct Answer Sample population Your Answer Sample population

Match The Following

Question Scale model Factor Analysis

Correct Answer Layout analysis

Your Answer Technique for evolving and analysis of layouts

Method to evaluate layouts Method to evaluate layouts Objective of good layout Principles of good layout

Minimization of production Objective of good layout delays Maximum visibility Principles of good layout

Multiple Choice Single Answer Question Product layout is suitable when Correct Answer Products have reasonable stable demand Your Answer Products have reasonable stable demand

Multiple Choice Multiple Answer Question Which are the distinct functions of scientific quality control? Correct Answer Acceptance function , Preventive function , Assurance function Your Answer Assurance function , Acceptance function , Preventive function

True/False Question

F W Taylor devised a system for classifying motions into basic divisions called Therbligs Correct Answer False Your Answer True

Multiple Choice Multiple Answer Question Which are the general principles underlying probability aspects of project planning? Correct Answer Statistically three time estimate of an activity conform to Beta distribution. , Expected time divides the area under the curve into two equal parts. , Expected time of an activity is located at one third of the distance between "m" and mid-range { (a+b)/2 } away from the most likely time. Your Answer Statistically three time estimate of an activity conform to Beta distribution. , Expected time divides the area under the curve into two equal parts. , Expected time of an activity is located at one third of the distance between "m" and mid-range { (a+b)/2 } away from the most likely time. Multiple Choice Multiple Answer Question Which of the following cases can be referred as operation in method study recording? Correct Answer Change in physical characteristic , Consumption of physical effort , Change in chemical characteristic

Your Answer

Change in physical characteristic , Consumption of physical effort , Change in chemical characteristic

True/False Question

Activities whose earliest finish times and latest finish times are not equal constitutes the critical path. Correct Answer False Your Answer False

Multiple Choice Single Answer Question Which phase of method study is concerned with analyzing the facts critically, generating alternatives which form the basis for selection and development of improved methods? Correct Answer Critical examination Your Answer Critical examination

Multiple Choice Multiple Answer Question Which are the subtasks of the maintenance phase of the method study? Correct Answer Monitoring and control , Performance appraisal , Audit on savings Your Answer Monitoring and control , Performance appraisal , Audit on savings

Select The Blank Question REL chart exhibits relationship between ________ of departments in terms of degree of closeness desired. Correct Answer Pairs Your Answer Pairs

Multiple Choice Multiple Answer Question Which of the following method can be adopted to overcome the problem of rushing up a job for it's timely completion? Correct Answer Use of optimum speeds and feeds , Subcontracting , Job splitting Your Answer Use of optimum speeds and feeds , Subcontracting , Job splitting

Select The Blank Question We can say that ________ occurs when there is a distinct change in the physical or chemical characteristic of an object. Correct Answer Operation Your Answer Manufacturing

Multiple Choice Single Answer Question What is represented by an arrow in a network? Correct Answer Activity

Your Answer

Activity

True/False Question

For p-chart, fraction defective units in each sample is calculated by dividing number of defectives by the number of pieces in the sample. Correct Answer True Your Answer True

True/False Question

Objective of Work Study is to improve Productivity

Correct Answer True Your Answer True

Multiple Choice Multiple Answer Question Which of the following are steps to identify the critical path in a small network? Correct Answer Enumerate all paths in the network and list down activities on each path. , Compare the durations of all paths to identify the longest path. , Sum up the durations of activities along each path. Your Answer Compare the durations of all paths to identify the longest path. , Sum up the durations of activities along each path. , Enumerate all paths in the network and list down activities on each path. True/False Question

A sampling plan which perfectly discriminates will have vertical OC curve.

Correct Answer True Your Answer True

Multiple Choice Single Answer Question How to calculate float? Correct Answer Parallel critical path time minus Non-critical path time Your Answer Parallel critical path time minus Non-critical path time

Select The Blank Question Delay is indicated by ________ during recording for method study. Correct Answer Letter Dee Your Answer Letter Dee

Multiple Choice Single Answer Question One of the sophisticated operations research techniques used in material planning is Correct Answer Dynamic programming

Your Answer

Dynamic programming

True/False Question

Kanban system is essentially a computer based system for production scheduling and control Correct Answer False Your Answer True

Multiple Choice Multiple Answer Question Which of the following three methods used to select the qualified supplier? Correct Answer By vendor plant surveys , By reputation , By experience Your Answer By vendor plant surveys , By reputation , By experience

Multiple Choice Multiple Answer Question Which of the following are examples of incentives offered by the Central and State Governments for setting up industries in particular locations? Correct Answer Exemption from excise duty , Soft loans , Subsidy in electrical charges Your Answer Exemption from excise duty , Soft loans , Subsidy in electrical charges

Multiple Choice Single Answer Question Which kind of labour force is required in case of Jobbing Production? Correct Answer Highly Skilled Your Answer Highly Skilled

Multiple Choice Single Answer Question Which of the following policies is advisable in case of low product variety and large volumes? Correct Answer Low Skilled Labour & Special Purpose Machines Your Answer Low Skilled Labour & Special Purpose Machines

Select The Blank Question In ________ technique activity time are related to costs. Correct Answer Critical Path Method Your Answer Critical Path Method

Multiple Choice Single Answer Question What is the location of upper control limit in the X bar-R control chart? Correct Answer 3 standard deviations above central line Your Answer 3 standard deviations above central line

True/False Question

An activity should represent an operation or set of operations which can be performed using a particular kind of equipment or a special skill. Correct Answer True Your Answer False

Multiple Choice Multiple Answer Question Which of the following are examples of gross materials? Correct Answer Timber , Iron ore , Sugar cane Your Answer Timber , Iron ore , Sugar cane

Select The Blank Question A ________ is another typical chart which is used to record frequency of movements between work centers. Correct Answer Travel chart Your Answer Travel chart

Multiple Choice Single Answer Question What do you mean by CPM? Correct Answer Critical Path Method Your Answer Critical Path Method

Multiple Choice Single Answer Question What do you mean by a single event which represents the joint start of more than one activities? Correct Answer Burst event Your Answer Burst event

Select The Blank Question Any incentive scheme must achieve the ________ of the organisation. Correct Answer Objectives Your Answer Objectives

Select The Blank Question In cellular layout the facilities are grouped together in cell which are able to perform ________ type of operation for a group of products Correct Answer Similar Your Answer Similar

Multiple Choice Multiple Answer

Question

Which of the following symbols are used in flow process chart but not used in operation process chart? Correct Answer Storage , Delay , Transport Your Answer Storage , Delay , Inspection

Select The Blank Question The ________ is the process of withdrawing the equipment from the production line, dismantling it unitwise, visualising defects, effecting adjustments, replacing worn-out parts and finally building it up to get desired accuracies. Correct Answer Reconditioning Your Answer Reconditioning

True/False Question

In case of backward pass computation method, the latest event time represents the latest occurrence time of the event. Correct Answer True Your Answer True

True/False Question

Three time estimates are transformed into expected time before using it into a network. Correct Answer True Your Answer True

Match The Following Question Release of manufacturing orders Shop interdepartmental transport Issue of tools for production Return of surplus material

Correct Answer Job card Move order Tool order Stores return note

Your Answer Job card Move order Tool order Stores return note

Multiple Choice Single Answer Question Why stores issue order should not be issued as soon as it is prepared? Correct Answer Material may or may not be available at the time of preparation Your Answer Material may or may not be available at the time of preparation

Multiple Choice Single Answer Question Which kind of labour force is required in case of Jobbing Production?

Correct Answer Highly Skilled Your Answer Highly Skilled

Multiple Choice Multiple Answer Question Plant Layout is concerned with optimum arrangement of the following Correct Answer Storage space , Machines , Material Handling Equipment Your Answer Storage space , Machines , Material Handling Equipment

Select The Blank Question Inspection is represented by ________ during recording for method study. Correct Answer Square Your Answer Square

True/False Question

In case of backward pass computation, the latest event time of the burst event equals the smallest of the difference between the latest event time of the head event less duration of the activity converging on the head event. Correct Answer True Your Answer True

Match The Following Question When to inspect What to inspect How to inspect How much to inspect

Correct Answer Stages of inspection Specification Inspection devices Sampling or cent percent inspection

Your Answer Stages of inspection Specification Inspection devices Sampling or cent percent inspection

Multiple Choice Single Answer Question How should a dummy activity be represented in a network? Correct Answer By dotted line Your Answer By dotted line

Multiple Choice Multiple Answer Question Which three of the following options can be used to reduce the duration of activity during project crashing? Correct Answer Allocating more manpower and machines than originally planned for. , Working additional shifts or overtime. , Awarding work to vendors who charge extra but expedite deliveries.

Your Answer

Allocating more manpower and machines than originally planned for. , Working additional shifts or overtime. , Awarding work to vendors who charge extra but expedite deliveries.

True/False Question

In case of forward pass computation, the earliest event time of a plain event equals the earliest event time of the preceding event plus duration of activity emanating from the preceding event. Correct Answer True Your Answer True

Multiple Choice Single Answer Question Which of the following technique is event oriented ? Correct Answer Project Evaluation & Review Technique Your Answer Project Evaluation & Review Technique

ASSIGNMENT
Q.1) What is Operations Management? What are the objectives of Operations Management? Enlist key elements of Operations Management.

Answer.1) An operation may be defined as the process of changing inputs into outputs thereby adding value to some entity.Right quality, right quantity, right time and right price are the four basic requirements of the customers and as such they determine the extent of customer satisfaction. And if these can be provided at a minimum cost, then the value of goods produced or services rendered increases. Thus the objectives of production management are to produce goods and services of the right quality, in the right quantities, according to the time schedule and a minimum cost. Objectives of production management may be amplified as under: Producing the right kind of goods and services that satisfy customers needs (effectiveness objective). Maximizing output of goods and services with minimum resource inputs (efficiency objective). Ensuring that goods and services produced conform to pre-set quality specifications (quality objective). Minimizing throughput-time- the time that elapses in the conversion process- by reducing delays, waiting time and idle time (lead time objective). Maximizing utilization of manpower, machines, etc. (Capacity utilization objective). Minimizing cost of producing goods or rendering a service (Cost objective).

Key elements of Operations Management

1. Product selection and design The right kind of products and good designs of the products are crucial for the success of an organizing. A wrong selection of the product and/or poor design of the products can render the companys operation ineffective and non-competitive. Products/services, therefore, must be chosen after detailed evaluation of the product/services alternatives in conformity with the organizations objectives. Techniques like value engineering may be employed in creating alternate designs, which are free from unnecessary features and meet the intended functions at the lowest cost. 2. Process selection and planning Selection of the optimal conversion system is as important as choice of products/services and their design. Process selection decisions include decisions concerning choice of technology, Equipment, machines, material handling systems, mechanization and automation. Process planning involves detailing of processes if resource conversion required and their sequence. 3 Facilities (Plant) location Plant location decisions are strategic decisions and once plant is set up at a location, it is comparatively immobile and can be shifted later only at a considerable cost and interruption of production. Although problem of location choice does not fall within preview the production function and it occurs infrequently, yet it is of crucial importance because of its major effect on the performance of every department including production. Therefore, it is important to choose the right location, which will minimize total delivered customer cost (Production and distribution cost). Locational decisions involve evaluation of locational alternatives against multiplicity of relevant factors considering their relative importance to the organization and selecting those, which are operationally advantageous to the organization. 4. Facilities (Plant) layout and materials handling Plant layout is concerned with relative location of one department (Work centre) with another in order to facilitate material flow and processing of a product in the most efficient manner through the shortest possible time. A good layout reduces material handling cost, eliminates delays and congestion, improves co-ordination, provide good housekeeping etc. while a poor layout results in congestion, waste, frustration, inefficiency and loss of profit. 5. Capacity Planning Capacity planning concerns determination and acquisition of productive resource to ensure that their availability matches the demand. Capacity decisions have a direct Influence on performance of production system in respect of both resource productivity and customer service (i.e. delivery performance). Excess capacity results in low resource productivity while inadequate capacity leads to poor customer service. Capacity planning decisions can be short-term decisions. Long-term capacity planning decisions concern expansion/contraction of major facilities required in the conversion process, economics of multiple shift operation, development of vendors for major components etc. Short term capacity planning decisions concern issues like overtime working, sub-contracting, shift adjustments etc. Break even analysis is a valuable tool for capacity planning. 6. Production Planning and Control (PPC)

Production planning is the system for specifying the production procedure to obtain the desired output in a given time at optimum cost in conformance with specified standard of quality, and control is essential to ensure that manufacturing takes place in the manner stated in the plan. 7. Inventory control

Inventory control deals with determination of optimal inventory levels of raw materials, components, parts, tools; finished goods, spares and supplies to ensure their availability with minimum capital lock up. Material requirement planning (MRP) and just-in-Time (JIT) are the latest techniques that can help the firm to reduce inventory.

8. Quality assurance and control Quality is an important aspect of production system and it must ensure that services and products produced by the company conform to the declared quality standards at the minimum cost A total quality assurance system includes such aspects as setting standards of quality, inspection of purchased and sub-contracted parts, control of quality during manufacture and inspection of finished product including performance testing etc. 9. Work study and job design Work-study, also called time and motion study, is concerned with improvement of productivity in the existing jobs and the maximization of productivity in the design of new jobs. Two principal component of work-study are: (i) (ii) Method study Work measurement

Method study has been defined (BS 3138) as the systematic recording and critical examination of the existing and proposed ways of doing work, as a means of developing and applying easier and more effective methods and reducing costs. Method study when applied to production methods yields one or more of the following benefits: Improved work environment Improved facility layout Better utilization of facilities Greater safety Lesser materials handling Smooth production flow Lower work-in-process Higher earnings for the workmen

10. Maintenance and replacement Maintenance and replacement involve selection of optimal maintenance Preventive and/or breakdown) policy to ensure higher equipment availability at minimum maintenance and repair cost. Preventive maintenance, which includes preventive inspection, planned lubrication, periodic cleaning and upkeep, planned replacement of parts, condition monitoring of the equipment and machines, etc. is most appropriate for critical machines.

11. Cost reduction and cost control Effective production management must ensure minimum cost of production and in this context cost reduction and cost control acquires significant importance. There are large number of tools and techniques available that can help to make a heavy dent on the production cost.

Q.2) What is batch Production? What are its key characteristics? Compare these characteristics with those of project production. Answer.2) Batch production is characterized by the manufacture of a limited number of a product (but many such quantities of different products) produced at periodic intervals and stocked in warehouses as finished goods (or finished parts) awaiting sales (or withdrawal for assembly). Typical examples of batch production are: process industries such as pharmaceuticals, paints, chemicals; medium and heavy engineering industry engaged in the manufacture of electric motors, switch gears, heavy motor vehicles, internal combustion engines; manufacture of ready made garments; manufacture of assembly shops such as machine tools; sub contractors which take on machining of batches of components to the drawings of a large manufacture etc. Characteristics of batch production (a) Short runs: Short production runs and frequent changes of set also characterize batch production up. The equipment and the assembly set up is used for a limited number of parts or assemblies and is then changed to make a different product. The production is generally made to stock. (b) Skilled labour in specific trades: The labour force is expected to posses skill in one specific manufacturing process, Turning, milling, drilling, welding, grinding, hobbing, fitting etc. The operator may perform simpler machine set-ups but the separate machine tool setter performs those involving complex operations. (c) Supervision to possess knowledge of a specific process The supervision has considerable knowledge of a specific process. Supervisor in the grinding section for example, may not expert in turning and drilling work but s expected to possess a find of knowledge of different types of grinding operations. Similarly a supervisor in the gear shop is expected to have sound knowledge in working of different types of gear cutting machines. (d) Limited span of control: The amount of supervision required in batch production is lower than that of jobbing production. The ration of direct workmen to supervisors is more or less a function of batch size. The smaller the batches, the lower are the ratio of direct workers to supervisors, and vice versa. This is because smaller lots require each supervisor to spend a great deal of his time in allocating new work, giving instructions, follow up on the shop floor for proper movement of materials from and to the machines, identifying delays and interruptions, and arranging, in consultation with planning, work load in his section to keep his men busy. (e) General purpose machines and process type of layout Plant and equipment is procured and arranged to obtain maximum flexibility. General purpose machines and handling equipment capable of performing variety of operations with minimum set up times are installed in lieu of variety of products. The machines are arranged to give process layout-layout by function. Similar machines capable of doing similar types of operations are grouped together and kept at one place. Presses for example, are put together and kept at one place milling machines are placed together at another place, drilling machines are kept at the third place, gear cutting machines are located at the fourth place and so on. Each Group of machines is usually designated as a work centre or a section or a shop.

(f) Manual materials handling: Materials handling in batch production as compared to jobbing production are small. Individual components and parts are placed in trolleys and trays and are transported as unit loads. Materials handling may be mechanized by deploying power driven trucks. (g) Manufacturing cycle time affected due to queues: The manufacture cycle time is comparatively smaller than jobbing production but is much more than mass and flow production. The batches of work tend to queue up at different machines due to differing cycles times, batch sizes and sequence of operations. (h) Large work-in-progress: Work in progress is comparatively large due to varying work content of different components, imbalance in manufacturing times, formation of queues between the machines. (i) Flexibility of production schedules: Disruptions due to machine breakdown or absenteeism do not seriously affect production as job can be shifted to another machine or another operator from another machine can be shifted. (j) Need to have production planning and control: Functions of production planning and control in a batch production unit are more complex than those in jobbing production or mass and flow production: Materials control and tools control functions are important. Some kind of replenishment system needs to be used to ensure routine replenishment Detailed operational layout and route sheets are prepared for each part of the product. Loading and scheduling needs to be more detailed and more sophisticated since every machine requires to be individually scheduled. Progressing function is very important to collect information on progress of work. A separate progress card needs to be maintained to record progress of each component. Expediting is generally necessary since quite often jobs, due to imbalances in work content, tend to lag behind

Q.3) (a) Why are locational decisions important? What factors should be taken into account while deciding location of a unit to manufacture washing machines? Answer.3a) Locational decisions generally arise when: A new manufacturing (or servicing) unit is to be set up. Existing plant operations are difficult to expand due to poor selection of site earlier. The growth of the business makes it advisable to establish additional facilities in new territories. There is emergence of new social (chronic labour problems) political (political instability or economic conditions that suggest a change in the location of the existing plant. The product development has over weighted the advantages of the existing plant. The changes in the industrial Policy of the Government, favoring decentralizing and dispersal of industries to achieve overall development of the country, do not permit expansion of the existing plant

FACTORS GOVERNING PLANT LOCATION Plant location studies are conducted in three phases: (i) (ii) (iii) 1. General territory selection Community selection, and Site selection

Proximity to market:

Every company is in business to market and it can survive only if their product reaches the consumers on time and at the competitive price. The ratio of selling costs to sales generally increases with distance. Therefore, in the choice of location o the plant, the factor of proximity to the market is given the highest priority. Locating a plant nearer to the market is preferred if: The product is fragile. The product is susceptible to spoilage. The promptness of service is required. The product is relatively inexpensive and transportation costs add significantly to the cost.

Bread, soap factories, etc. require the market to be nearby. If factory cannot be started in Bombay, it may be started in Thane, Kalyan or Poona. If the product is exported, location near ports is desirable. This is particularly important for producers who sell bulky commodities, which incur high transportation costs

Nearness to market not only lowers transportation costs but also gives many other benefits namely:

A good many administrative problems, which cause perpetual headaches and add to costs, are avoided. Liaison with dealers or whole sellers can be maintained economically and easily Other costs such as commission to middlemen, which at times run as high as 20 to 50 percent can be reduced significantly. Customers accounts do not remain outstanding for settlement. This recovery is easy and less time saving which itself reduces selling costs.

2. Proximity to source of raw materials: Since raw materials usually constitute 50 to 60 percent of the total product cost, it is important that the firm gets its requirements of raw materials at the right time and at the reasonable price for which the plant must be located in the neighborhood of some source which can meet the raw materials requirement of the unit Proximity to supply of raw materials factor assumes still greater importance if raw materials are of perishable nature or if they are expensive to transport, or if their weight is substantially reduced by processing. Proximity to sources of raw materials is equally important for small units. This is because usually small units are not considered important customers. They get least priority and in the event of scarcity are the one to be struck off first from the list. The availability of materials to small units to a large extent thus depends on their follow up and personal visits to the suppliers plant which is possible only if the buyers plant is close by. 3. Infrastructural facilities: Infrastructural facilities consider availability of utilities like power water, disposal of waste etc. These form the life-blood of many types of industries without which there facilities may come to a stand still. Underestimating the need of any one of the utilities can be extremely costly and inconvenient. Certain industries, for example, aluminium, steel, etc are power intensive and must be located close to the sites of power generation failing which the shortage of, or increase in cost of generating power may spell problems for their survival. Similarly, chemical process industries like paper and pulp, cement, steel, sugar laundries, metal plating, food preparation etc. requires perennial source of water. Mineral content of water may also be an important factor. Treatment of water is an expense to be considered while comparing economics of different locations. Drainage facilities are important for process industries otherwise disposal of process waster can create lot of difficulties. 4. Transport facilities: Transportation cost to the value added is a key determinant of the plant location. The structure of the transportation cost depends on (i) Characteristics of the commodity (ii) average distance of shipment (iii) medium of shipment: rail, road, and air sea. The need for transport arises because raw materials and fuel are to be moved to factory site and finished goods are to be transported from factory to markets. Other things being equal since transport cost has a major effect on product cost, the regions well served by transport facilities are most suitable for industrial locations. 5. Labour and wages:

Plant location should be such that required labour is easily available in the neighbourhood. Importing labour from outside is usually costly and it causes lot of administrative problems. Availability of required labour locally is better since problem of arranging accommodation and other related problems do not arise. Since normally workers with specific skills are required, some sort of training facility should also be available in the neighborhood. Skilled employees are easily available if ITIs, or Engineering colleges are there in the neighbourhood. 6. Legislation and taxation: The policies of the state Government and Local Bodies relating to issue of licenses, building codes, labour laws, etc. are the factors in selecting/rejecting a particular community/site. In order to disperse industries and ensure balanced economic growth, both Central and State government offer a package of incentives for setting up industries in particular locations. Exemption from excise duty, sales tax and octroi, soft loans from financial institutions, subsidy in electricity charges, etc. are some of the incentives offered. Since taxes and duties levied by the State Government and Local bodies substantially influence product cost, the incidence of such taxes/levies must be taken into account while selecting a community/site. 7. Climatic conditions: Climatic factors may not have a major influence these days because of modern air conditioning facilities available today. However, it may be important factor for certain industries like textile mills, which require high humidity. 8. Industrial and labour attitudes: Community attitudes towards supporting hostile trade union activities are an important factor. Locating facilities in a certain region/community may not be desirable as frequent labour problems and interruptions are harmful to the plant in the long run. Political situation in the state and attitude of the government towards labour activities also influences selection of the site for the plant. 9. Safety requirement: Safety factor may be important for certain industries such as: Nuclear power plants Explosive factories Location of such industries close to border areas is undesirable.

10. Community facilities (or social infrastructure): Community facilities imply accommodation, educational, entertainment and transport facilities. Accommodation is needed unless the employees are local residents. Accommodation should be easily available, comparatively cheap and near some public transport stop. The locational area should be fully developed, be accessible by road and should have a convenient and efficient public transport system operating between the area and the township to enable employees, officials, customers and suppliers to make easy trips for their work

11. Community attitudes: Community attitudes towards work (i.e. whether the people in the location are hard working or otherwise) as well as their attitudes towards the incoming entrepreneurs (helpful and cooperative or otherwise) can make or mar an industry. Locational decisions, therefore, must take such factors also into account particularly while setting up labour intensive units.

12. Supporting industries and services: Locational factors should also include proximity of services needed by the firm. A firm desirous of getting some or all parts made from outside or some of the operations done from outside must see that such sub-contractors are located in the neighbourhood. Getting a job done from units located at far off places will mean not only additional transportation cost but also time consuming and costly. Also if units are too far off, the control on quality of work done by them cannot be exercised. 13. Suitability of the land: Site selection should also take into account topography and soil structure of the land. The soil structure must be capable of bearing loads of foundations. Though modern building techniques can overcome the limitations of the soil, but if considerable improvement is required then selection of a low cost and may ultimately turn out to be expensive.

14. Availability and cost of the land: Site size (Plot size) must be large enough to accommodate the present production facilities, parking and access facilities but also leave sufficient room for future expansion. As a general rule, a site five times the actual plant size is considered minimum for all these things including future expansion.

ECONOMY SURVEY OF THE SITE SELECTION: An ideal location is one where the cost of obtaining materials and processing them into finished product plus the cost of distributing the finished product to customers is minimum. One of the most commonly used approaches consists of following steps: Step 1: Step 2: Prepare a list of all relevant factors. Estimate expenses on materials, transport, wages, power etc for each location on each of the above factors.

Step 3: Collect data on intangible factors like community facilities, community attitudes etc.

Step 4: Step 5: Step 6:

Analyse the tangible data for each location and calculate rate of return on investment. Select provisionally a locational based on financial data. Compare the intangible data for the different locations and select the optimal location considering intangible data.

Q.3) (b) What are objectives of a good layout? Discuss any six principles of a good layout? Answer.3)(b) OBJECTIVE OF A GOOD PLANT LAYOUT Only through an efficient layout, the organization can attain the following objectives: (i) (ii) (iii) (iv) (v) (vi) (vii) Economy in handling of materials, work-in-process and finished goods. Minimization of product delays. Lesser work-in-progress and minimum manufacturing cycle time. Efficient utilization of available space. Easy supervision and better production control. Greater flexibility for changes in product design and for future expansion. Better working conditions by eliminating causes of excessive noise, objectionable odor smoke etc.

PRINCIPLES OF A GOOD LAYOUT (i) Overall integration of factors: A good layout is one that integrates men, materials, machines and supporting activities and others in a way that the best compromise is obtained No layout can satisfy each and every principle of a good layout. Some criterion may conflict with some other criterion and as a result no layout can be ideal it has to integrate all factors into the best possible compromise. (ii) Minimum movement: A good layout is one that permits the minimum movement between the operations. The plant and machinery in case of product layout and departments in case of process layout should be arranged as per sequence of operations of most of the products. Since straight line is the shortest distance between any two points, men and materials as far as possible should be made to move along the straight path

A door may be made in a wall or a hole may be drilled in a ceiling if that eliminates or reduces material handling in place of stairs or a distant door.

(iii)

Uni-direction flow: A good layout is one that makes the materials move only in the forward direction, towards stage of completion, with any backtracking. Since straight line is the shortest distance between any two, points, materials as far as possible should be made to move on the principle of straight line

flow. And when straight line flow is not possible, other flows like U-shaped flow, circular flow or zig zag flow may be adopted, but the layout may ensure that materials move in the forward direction (Fig 4.1) (iv) To ensure forward flow, equipment if necessary may be duplicated.

Effective use of available space: A good layout is one that makes effective use of available space both horizontal and vertical Backtracking and duplicated movements consume more time, involve un-necessary materials handling, add to cost and lead to inefficiency. Raw materials, work-in-progress and finished goods should be piled vertically one above another rather than being strewn on the floor. Pallets or equivalents should be made use of to pile up several layers one above another Area below the work tables or in the cupboards built into the wall are welcome since they reduce requirement of space

(v)

Maximum visibility: A good layout is one that makes men, machines and materials ready observable at all times. All departments should be smoothly integrated, convenient to service and easy to supervise Every piece of positioning or screening or partitioning should be scrutinized and carefully planned. Special cupboards, enclosures, offices, partitions etc. should be avoided except when their utility is established beyond doubt. Maximum accessibility: A good layout is one that makes all servicing and maintenance point readily accessible. Machines should be kept sufficiently apart and with reasonable clearance from The wall so that lubrication, adjustment and replacement of belts, removal of parts at the time of repairs etc can be done conveniently by the maintenance staff. Area in front of electrical panels and fire extinguishers should be kept free from obstructions.

(vi)

Q.4) How does production planning differ from production control? What are the key functions of production planning and control? Answer.4) Production planning versus production control. Planning (Planning the work) Planning involves collection and maintenance of data regarding time standards, materials and their specifications, machines and their quantities, tools and their process capabilities, drawings and operational layouts etc. Control (Working the Plan) Control involves dissemination of data preparation of reports regarding output, machine and labour efficiency, percent defectives etc.

Planning is seeing that requirements tool, machines, men, instructions, authorization and the like-will be available at the right time and Control is seeing the requirements are actually in the right quantities and are of proper quality. made available at the right place and in the right quantities. Planning involves preparations of load charts and fitting various work orders into uncommitted time available on the companys facilities (men or machines). Control involves actual seeing that the jobs are started and completed as per schedule prepared Planning involves preparation of all necessary by the scheduling cell of the PPC. forms and paper work. Control involves actual issue of forms and Planning involves designing suitable feed back paper work. as to what may happen. Control involves keeping track of what is happening and collecting information as to Planning involves forwarding thinking what has happened. regarding the remedial action to be taken if the job falls behind schedule. Control involves suggesting remedial action when the job is falling behind schedule. Planning therefore is a centralized Activity (in the office) and includes such Control is thus a diffused activity (in the shops) functions as materials control, tools control, and includes functions such as dispatching, process planning and scheduling. progressing and expediting.

FUNCTIONS OF PRODUCTION PLANNING AND CONTROL:

Production planning and control is normally assigned two sets of functions: (I)Regular functions and (ii) Optional functions. (i) Regular functions are those, which are generally assigned to PPC in most of the organizations through the importance of the function, may vary from industry to industry. Optional functions are those, which may be assigned to PPC depending upon policy of the management of the firm.

(ii)

Common (or Regular Functions) Order Preparation includes activities like making of work orders, converting work orders to shop orders, preparing auxiliary orders and releasing such orders to those concerned to authorize their activities

Optional Functions Cost Estimation concerns preparations of Preproduction cost estimates to be used by sales department for quotation purposes (Alternatively this may be assigned to Costing Department Or Industrial Engineering Department)

Materials control concerns preparations of materials estimates, indenting non-stock materials, ascertaining availability of materials purchased to stock, continual follow-up with purchase and stores for timely receipt of materials, and advising stores to allocate required quantities or available materials (alternatively on their receipt) against specific shop orders.

Process planning or Routing concerns fixation of method of manufacture: operations and their sequence, machine tool for each operation, jigs and fixtures, measuring instruments and gauges etc. to enable shops to produce goods of the right quality at the lowest cost. Tools control concerns preparations of estimates of cutting tools (Standards as week As non-standards tools), gauges and measuring instruments, jigs and fixtures etc indenting nonstick tooling: follow up with tool room for timely manufacture of jigs and fixtures; periodical replenishment of worn-out-nonconsumable tooling (e.g. work arbors, collets, copying masters, Allen keys, spanners, etc.

Work measurement concern fixation of time to be allowed to a qualified workman to carry out a specific task, under specified conditions and at the defined level of performance. Work measurement employs scientific, well-known techniques like time study, work sampling standard data, production study, analytical estimating etc. (Alternatively, work measurement function may be assigned to Industrial Engineering department. Sub-Contract concerns offloading of certain work on outside vendors for economic reasons or to augment the existing manufacturing facilities (Sub-contract work alternatively) be handled by Materials/purchase Department)

Capacity planning concerns estimation of requirements of men and machines as the basis of decision making to meet the firms increased volume of business (Some companies prefer to assign this function to Engineering department.

Scheduling concerns preparation of machine loads, fixation of calendar dates of various operations to be performed on a job, coordination with sales to confirm delivery dates of new items and periodical preparation

Demand forecasting concerns making projection of companys product market. Though, long term forecasts are given by Sales Department but short term forecasts required for materials planning, machine loading, sub

of dispatch schedules of regular items.

contracting etc may be prepared by PPC department

Dispatching concerns preparation and distribution of shop orders and manufacturing instructions to the concerned department as their authority to perform the work according to the predetermined schedule. Progressing concerns collection of data from manufacturing shops, recording of progress of work, and comparing progress against the plan. Expediting concerns intensive progress chasing to identify delays and interruptions which may hold up production, devising cures from time to time to keep rate of production in line with the schedule, communicating possible failure in delivery commitments to Sales Department.

Q.12 (a) What is critical path? What does it signify? How is it identified? Answer.2)(a) Critical path analysis, an important aid to planning, scheduling and coordinating the activities if large scale projects. Is a synthesis of two independent techniques: Programme Evaluation and Review Technique (PERT) and Critical Path Method (CPM). Though the two techniques were developed independently, they are only superficially different. The two method have many features in common and are now combined into a technique called Critical Path Analysis (CPA) or Network Analysis. There are three basic different between a PERT network and CPM network: PERT is event oriented while CPM is activity oriented (i.e. PERT prepares network from events while CPM builds if from activities) PERT provides for an allowance for uncertainty while CPM does not (i.e. PERT makes three time estimates for each activity while CPM makes one time estimate) Activity time in CPM technique are related to costs while it is not so in PERT since it is event oriented

Significance of critical path Critical path analysis offers several advantages. It (i) Forces through pre-planning. Each and every activity compromising the project is identified and recorded. Nothing is left to memory or chance which prevents crises in scheduling Increases coordination of tasks as technological relationship between the activities suggests which activities can run simultaneously and which should succeed others. Helps computations of different project durations for different level of resources and thereby select a plan that minimizes total project cost. Indicates optimal start and finish times of each activity of the project. Defines areas of responsibility of different departmental heads for timely execution of the project. Facilitates progress reporting and limits unnecessary discussion at the progress meetings. Identifies troubles spot often in advance and apply remedial measures. Enables the plan to be revised in accordance with changes/changing circumstances. Helps to exercise control by exception and prevents cost overruns.

(ii) (iii) (iv) (v) (vi) (vii) (viii) (ix)

A Project comprises a series of activities and the identification of the individual activities requires knowledge and experience of the men responsible for the planning of the project. Even the preliminaries-mere listing of the activities-make the operating personnel: Think of details about the project well in advance. Observe critically the way in which the various activities interact or compete for scarce resources Improve upon the original plans even before network is formally drawn and analyzed.

A project, therefore, must be torn into a set of identifiable activities. There are no set rules but general guidelines are as under:

An activity should represent the smallest unit of the operation or set of operations over which management desires control. An activity should represent an operation or set of operations, which can be performed using a particular kind of equipment or a special skill. For example in construction project, plumbing is considered as one activity while wiring can be considered as another activity since the first activity requires plumbers and the second activity needs electricians.

Q.12) (b) Activity 1-2 1-3 1-4 Optimistic 02 02 02 Most Likely 03 04 06 Pessimistic 10 06 10

2-5 3-5 4-5 4-6 5-6

01 04 02 02 03

01 05 03 05 05

01 12 04 08 13

Answer: (a) Expected time of an activity can be obtained from the three time estimates using the formula: te = a + 4m +b 6 where a m b a m b te = = = = = = = Optimistic time most likely time pessimistic time 2 3 10

For activity (1-2)

2 + 4 x 3 + 10 6 24 6 = 4

te

Expected times of all activities of the network, calculated on above lines, are tabulated below. Activity 1-2 1-3 1-4 2-5 3-5 4-5 4-6 5-6 Three time estimates 02-03-10 02-04-06 02-06-10 01-01-01 04-05-12 02-03-04 02-05-08 03-05-13 Expected time 4 4 6 1 6 3 5 6

4
6 3

Critical path is 1-3,3-5,5-6 and the duration for the project is 16 weeks (4+6+6) Variance is Vi = (b a) X (b a) 6 6 4 9 16 9 25 9

V1-3

V3-5

V5-6

V V

= =

V1-3 + V3-5 + V5-6 5 = T - Tcp 19 -16 5 3 2.236 1.34

Standard deviation Z

The approximate probability value when Z = 1.34 is 0.9099 The probability of completion of critical path by the schedule time of 19 weeks = 91%

Q.5) What is preventive maintenance? Why it is better than Breakdown Maintenance? What are the key activities of Preventive Maintenance? Answer.5) Preventive maintenance anticipates failures and adopts necessary actions to check failures before they occur. It includes activities like inspection, lubrication cleaning and unkeeps, minor adjustments and replacements found necessary at the time of inspection etc. Preventive maintenance can be either: running maintenance or shut down maintenance. Running maintenance includes maintenance activities (e.g. minor adjustments In machines revealed through inspections, lubrication, cleaning and unkeep etc.) Which are carried out when the machine is still running. Shutdown maintenance includes preventive maintenance activities such as minor component replacement whose needs are identified through inspections, which require stoppage of Machines. Preventive inspection is one of the key activities of preventive maintenance which is usually performed by making use of human senses watch) eye), listen (ear), Touch (hand, leg, body) smell (nose) and taste (tongue) but the trend is Changing towards use of condition monitoring instruments. Such maintenance. Practice is known as predictive maintenance or condition based maintenance.

Q.10) (a) What are X-R Charts? How are they made and used in controlling a process? Answer.10) X-R chart is a pair of chart consisting of a average (called X chart) and a range Chart (called R chart) placed one below another on a piece of graph paper. The X chart is used to control the mean value of the characteristic an R-chart is used to restrict the range of variations in the values. X-R charts are drawn when the characteristics are measurable. Each chart consists of three values: a central line, upper control limit and lower control limit. The central line represents the arithmetic average of the sample means which equals the mean of the population, u. The upper and lower control limits are located at three standard deviation on either side of the central line. Samples of fixed size are drawn at regular intervals and measurements are taken. The samples wise values of the mean and range are plotted in their respective X and R charts. The spread of sample points in the charts is studied to decide the remedial action (if any) to be taken. The X chart analyses whether or not the mean of the quality Characteristics is within control while Rchart analyses whether or not the variability is within control. STEPS TO PREPARE X-R CHART A pre-requisite to the preparation of the chart is the decision on the following aspects: Quality Characteristics refer to the property of the product, which is to be assessed. The quality characteristics must be capable of being measured. In case of more than quality characteristics, separate chart is made for each quality characteristic. Sample size refers to number of pieces comprising each sample. Sample size is an important decision. It is a common practice to use sample of n = 4 or 5 to have low appraisal cost. Large samples such as n = 15 or 20 are used if the process standard deviation is large. Sample Population refers to the number of samples to be collected to construct a control chart. The number of samples must be sufficient. Usually, 20 samples each of size 4 or 5 are enough to have good estimates of the process average (X) and dispersion (R). Time Interval measures the time gap between consecutive samples. Time interval, as a genera rule, should be proportional to the average frequency of out-of-control conditions. It is a fairly complex decision since a number of factors such as cost economy, susceptibility of the process to disturbances; convenience of the inspector etc. requires to be considered.

The making of X-R Charts involves the following Steps: Step 1: (a) (b) (c) Step 2: A Collect Data Collect sufficient samples spread over a reasonable period. Each sample must be of equal size. Measure each component comprising the sample for the given quality characteristic Record individual measurements on a work data sheet. Calculate mean (X) and Range (R) of each sample The mean which is written as X (X bar) is average of each sample and is Obtained by totaling the individual measurements of the units comprising the sample and dividing the total by the sample size (number of units in each sample) The range, which is written as R, is obtained as the difference between the highest and the lowest measurement of a sample. The values of X and R are recorded sample wise either on the extreme right of the individual measurements on the data sheet or in a separate table.

B C

Step 3: A

Calculate grand Average (X) and mean Range (R) The grand average, which is written as, X (X double bar) is the average of the sample averages and is obtained by dividing the total of the averages of all the samples by the total number of samples. The mean range, which is written as, R (R bar) is the average of the ranges and is obtained by dividing the total of the ranges of the samples by the total number of samples.

Step 4: A

Set up Control chart for the average Set up a control chart with the central line drawn at X (X double bar), upper control limit located X + A2R (R bar) and the lower control limit set up at X-A2R. Plot the averages to see whether the process was under control when samples were drawn. If all points fall within the control limits, the process is said to be under control If process is not under control (indicated by some points falling outside the control limits), eliminate points outside the control limits and compute new trial control limits for the remaining points. Repeat step 4 (d) until all points fall within the control limits Control limits in a particular situation should be revised from time to time as additional data is accumulated.

B C D

E F

Step 5: Calculate control limits of the range chart A The control chart for range chart is set up with central line as R, upper control limit (UCLR) located at D4R above the central line and lower control limit (LCL) at D3R below the central line Plot the value of the range of each sample. If all points fall within the control limits no modification is necessary unless it is desired to reduce the process dispersion if range chart exhibits lack of control indicated by some points falling outside the control limits, eliminate those points out of control and compute new trial control limits Repeat step 5 (d) until all points fall within the control limits. Control limits in a practical situation should be revised time to time as additional data is accumulated.

B C D

E F

Step 6: Use control chart A B Collect samples of fixed size at specified intervals of time. Measure each unit of the sample for the quality characteristics, calculate mean and the range of each sample. Plot the values of X and R of each sample in their respective charts Study the trend of the points to interpret and suggest remedial action

C D

Q10 (b) ABC company produces a solvent, which must contain 3 percent of alcohol. It tries to maintain the actual percentage at 3 + 0.3 percent. It tests hourly in samples of five. The following table shows the results of last five samples. Set up a control chart for mean and examine whether the process is under control. A) Solution: (i) Collect data (ii) Calculate mean (X bar) and range(R bar) Sample No. 1 2 3 4 5 (iii) Arithmetic Mean (X bar) 2.92 2.98 3.06 3 3 Range(R) 0.3 0.1 0.1 0 0.2

Calculate grand average and the mean range X(X bar) = 2.92 + 2.98 + 3.06 + 3 + 3 5 2.992 0.3 + 0.1 + 0.1 + 0 + 0.2 5 0.14

= R =

(iv)

Set Up control chart for the average Central Line = CLx = X(X bar) Upper Control Limit = = = = Lower Control Limit = 2.992 UCLx = X (X bar) + A2.R(R bar) 2.992 + 0.5768 x 0.14 3.476 UCLx = X (X bar) - A2.R(R bar)

= =

2.992 - 0.5768 x 0.14 2.507

(v)

Set up a range chart Central line CLR Lower control limit = = = = Lower control limit = = = R(R bar) LCLR = 0 x 0.14 0 UCLR = 2.114 x 0.14 0.29596 D4.R (R bar) = 0.14

D3.R (R bar)

Q.6) What is method study? Describe the procedural steps to develop easier and effective methods. Answer.6) Method study is the systematic recording and critical examination of existing and proposed ways of doing work, as a means of developing and applying easier and more effective methods and reducing costs. Method study is an organized approach and its investigation rests on the following six basic steps outlined in the block diagram Select the work to be analyzed. Record all facts relating to the existing method. Examine the recorded facts critically but impartially. Develop the most economical method commensurate with plant Requirements Install the new method as standard practice. Maintain the new method.

Selection of the job Selections of the jobs to be studied for methods improvement by the method study practioner is a managerial responsibility and it (selection) may be based on economic technical or human consideration. Economic consideration justifies selection based on the economic worth (i.e. money saving potential) of the job. Technical consideration identifies jobs, which require studies to overcome manufacturing difficulties (excessive rejection, relaxation in prefixed performance standards, inability if the shops to stick to specified machining parameters such as speeds, feeds, depth of cut etc., inconsistent quality etc.) Human consideration in job selection is usually given weightage while introducing method study practices for the first time. Recording of facts Systematic recording is the most crucial step in method improvement. Since recording by long hand (or by descriptive method) has its limitations, it is not recommended for use in method study. Instead, five symbols and eight charting conventions are used to record facts relating to the job under study. Five typical symbols are O, ||, , D and V and eight charting conventions concern composition of the chart, reject, rework, repletion, change of state, introducing of new material, combined events and numbering of events. The document on which details of the process are recorded by the above referred symbols and conventions is called chart. There are four basic types of chart: (i) operation process chart (ii) Flow process chart (iii) multiple activity charts and (iv) two handed process chart. Besides charts, two types of diagrams-flow diagram and string diagram are drawn when recording details of an existing layout. Travel chart is another typical chart, which is used to record frequency of movements (weight x distance) between work centres/departments.

Repetitive short cycle operation which involves quick hand/feel motions (i.e. microscopic motions) may be studied with micro motion study. Glibreth, founder father of micro motion

study, also developed photographic techniques called cyclograph and chronocylegraph to record path of the motions of the members of the body. Critical examination Critical examination aims to analyze the facts critically and thereby give rise to alternatives, which form the basis of selection and development of easier, and effective methods. Critical examination is conducted through a systematic and methodical questioning process. Each activity recorded on the chart, whether it relates to processing or inspection, or material handling, or to any other aspect, is picked up one at a time and is examined minutely. The questioning process is considered under five major heads, namely the purpose, the place, the sequence, the person and the means. These five aspects in critical examination are referred to as five governing considerations. Development and selection: Development and selection stage concerns short listing of ideas generated at the critical examination stage, testing each short listed idea for its technical and economic feasibility, and making selection among the alternatives wherever choice exists. To develop ideas and to ascertain their technical and economical feasibility, the method study practioner needs to solicit the cooperation of personnel from different departments of the company. Various techniques available for the development and selection purpose are: cost benefit analysis, break even analysis, investment analysis and critical path analysis. Installation Installation (or implementation) of the proposed method involves preparation of project report on recommendations making oral presentation to the top management, securing approval of the decision maker, assisting line management during implementation, arranging training of workmen, and getting jobs (operations) retime after implementation, arranging training of workmen, and getting jobs (operations) retimed after implementation. Maintenance Maintenance phase is the follow up phase after implementation, which serves as a monitoring and control mechanism. It helps to ensure that the revised methods are set into concrete and workmen do not revert back to old methods. It also provides an opportunity to the practitioner to assess the effectiveness of the approach followed by him and makes changes in the methodology (if required).

Q.9) (a) What desirable conditions need to be present to be present to guarantee success of an incentive scheme? Answer.9) A good wage incentive plan should have the following characteristics. Administrative simplicity: The incentive system should be simple and must be easily understood by the workers and their representatives. An incentives scheme, which can be understood, only by engineers and mathematicians or a scheme which involves the use of complex formulate or references and crossreferences is sure to fail. The incentive scheme should be such that workmen can calculate their own earnings easily and quickly. Minimum clerical work: The system should fit into existing system of production and cost control. It should not involve any significant addition to the clerical work. Maximum coverage: The system should cover as many workmen as possible. A scheme if applied to a few workmen creates a demoralizing effect on the morale of those not covered by the scheme. Direct Incentive payments should increase at least in direct proportion to the increase in output by the operator. There are two reasons: Firstly because it is more difficult to producer extra units and secondly because saving in the overheads are far greater at higher levels of production. Period of Payment The period of payment should be as short as possible Adequate guaranteed minimum hourly rate The scheme must ensure adequate guaranteed minimum hourly rate to all incentive workers regardless of their output. Such an hourly guaranteed rate is normally referred to as the guaranteed base rate. The guaranteed base rate must be realistic and should be at least equal to the hourly rate payable to a non-incentive worker doing similar job in the industry. Incentive earnings of the workers should never be regarded as a substitute for poor wages. Accurate and yet attainable performance standards Performance standards should be set through systematic work measurement studies. The experts to that there is no dispute or malpractice and yet the standards are attainable so that a worker working at normal pace can attain them should base the standards of measurement on the assessment.

Further the incentive plan should be such that it provides an opportunity to all average workers to earn reasonable earnings.

Consistency of the standards Standards once fixed should not be changed unless there is a permanent change in methods, or change in equipment, or change in material and plan should provide for the provisions to modify the performance standards. Inbuilt check on process rejections A good incentive scheme should exercise a check on the operator against achieving higher bonus by poor workmanship. Payment should be made only for pieces declared acceptable by the inspection department and a workman constantly producing substandard pieces should be liable for disciplinary action. Payment of partially completed jobs The problem of payment for the incomplete work arises only in case of long cycle jobs. Situations do arise when the jobs are of very long cycle duration and cannot be finished within the bonus period. Similarly, a semi-finished job may require to be handed over by one operator to another at the end of shift, or prior to having a holiday. The scheme should clearly spell out as how assessment of work done by the workmen on the same job will be carried out and how disputes arising out of such assessment would be resolved. Payment of Idle Time Adequate safeguards must be provided to compensate the operator for the time lost due to reasons beyond his control. A good incentive scheme should ensure that an operator does not suffer financial loss for reasons attributable to the managerial weakness, e.g.: lack of material due to bad buying, breakdowns of the machines due to poor maintenance practices, non-availability of work etc. Thus an operator rendered idle because of factors attributable to the management should be given a lieu bonus. Safeguards The scheme should be fair not only to the employees but also to the employer. Safeguarding clauses as under should be incorporated to protect. a. Managements right to change a standard when there are changes in methods. Materials and machines b. Managements right to withdraw or discontinue temporarily a scheme during bad period. c. Managements right to initiate disciplinary action against operators who continually produce sub-standard articles. d. Managements right to initiate disciplinary action against employees who, time and again, do not achieve minimum standard of production even in the presence of fair and accurate standards. e. Managements right to initiate disciplinary action against employees who, time and again are found using speeds and feeds higher than those recommended in the process sheet (or operational layouts) Maximum ceiling on the earnings The system should have built-in-control against higher earnings beyond a certain limit. Firstly, the system should discourage workers to work beyond a certain limit otherwise too attractive an incentive scheme may induce the worker to work more and more and thereby adversely affect his health. Secondly, the system should ensure that in case of loose standards the company does not lose financially. Consistency of Plan The plan should be consistent over a period of time. Frequent changes in the plan make its functioning difficult. Faith in plan is lost if there are frequent revisions.

Acceptance of Labour Body The scheme should finally have acceptance of the labour body. The body of workers representatives to prevent any misunderstanding and ill-feeling later on must accept the basic incentive plan and its provisions. Continuous Use The scheme should be in continuous use. The temporary use of the scheme in good times and its discontinuation in bad times makes its functioning difficult. Define End Results The plan must result in reduction in per unit labor cost.

Q 13) Answer 13) i) Average Cycle time = 0.22 + 0.24 + 0.28 + 0.26 + 0.25 5 0.25

Normal Time

Observed time x Rating 100 0.25 x 80 100 0.2

Similarly, average cycle time and normal time for all the elements are calculated and tabulated as below Element A B C D E Avg. cycle time 0.25 0.15 0.35 0.102 0.12 Rating 80 100 120 90 100 Normal time 0.2 0.15 0.42 0.0918 0.12

Total Normal time Total Normal time

= =

0.2 + 0.15 + 0.42 + 0.0918 + 0.12 0.9818

ii)

Relaxation Allowance =

15 100 =

0.9818

0.1473 x 0.9818

Contingency Allowance = Standard time

5 100 =

0.0491

Normal time + Relaxation Allowance + Contingency Allowance = Standard time = 1.1782 0.9818 + 0.1473 + 0.0491

Multiple Choice Multiple Answer Question Which of the following are minimum requirement for a good quality of design? Correct Answer Resonable cost , Resonable procurement time , Resonable manufacturing time Your Answer Resonable manufacturing time , Resonable cost , Resonable procurement time Multiple Choice Single Answer Question Where does the central line is located in case of p-chart? Correct Answer at p bar

Your Answer

at median

Multiple Choice Single Answer Question Any premise in which persons are employed for purpose of making any product/s is called Correct Answer Factory Your Answer Factory

Multiple Choice Single Answer Question Technique of Value Engineering can be effectively employed in design of a product to Correct Answer To meet the intended function at lowest cost Your Answer To meet the intended function at lowest cost

Select The Blank Question The ________ is the probability that a good lot will be rejected by the sampling plan. Correct Answer Producer's risk Your Answer Producer's risk

Multiple Choice Multiple Answer Question Material Requirement Planning is very useful in following situations Correct Answer Your Answer Long Lead time for procurement , Several levels of assemblies in product , Long manufacturing cycle Long Lead time for procurement , Long manufacturing cycle , Demand for the product is not known

Select The Blank Question The ________ is the watch dog which ensures that every element of production and activities which could affect the quality of end product are regulated to the extent desirable. Correct Answer Quality control Your Answer Quality control

Select The Blank Question The ________ is the process of withdrawing the equipment from the production line, dismantling it unitwise, visualising defects, effecting adjustments, replacing worn-out parts and finally building it up to get desired accuracies. Correct Answer Reconditioning Your Answer Overhauling

Multiple Choice Single Answer Question The ratio of output to input of a production system is commonly known as

Correct Answer Your Answer

Productivity Productivity

True/False Question Correct Answer Your Answer

In case of two handed process chart, the simultaneous activities of both hands are recorded opposite to each other on the chart. True True

Match The Following Question Emerson Efficiency Plan Craft Work Sampling Gantt Chart

Correct Answer Wage Payment Facilities Planning Machine utilization Production Scheduling

Your Answer Wage Payment Facilities Planning Machine utilization Production Scheduling

Multiple Choice Multiple Answer Question Which of the following factors play important role while selecting or rejecting a particular site from legislation and taxation point of view? Correct Answer Labour laws , Building codes , Policies regarding issue of licences Your Answer Labour laws , Building codes , Policies regarding issue of licences

Multiple Choice Single Answer Question What do you mean by the study of repetitive short cycle operations which involve quick hand / feet motions? Correct Answer Micromotion study Your Answer Macromotion study

True/False Question Correct Answer Your Answer

An activity should represent an operation or set of operations which can be performed using a particular kind of equipment or a special skill. True True

Multiple Choice Multiple Answer Question Which of the following products should be produced by using mass production? Correct Answer Refrigerator , Tyre for automobile , Television Set

Your Answer

Refrigerator , Tyre for automobile , Television Set

True/False Question

Correct Answer Your Answer

In case of X bar, if the process is not under control indicated by some points falling outside the control limits, such points outside the control limits are eliminated and new trial control limits for the remaining points are computed. True True

True/False Question Correct Answer Your Answer

After goods have been manufactured, route sheets and operation layouts should not be collected back. False False

True/False Question Correct Answer Your Answer

Planned lubrication is said to be the nervous system of the equipment. True True

Multiple Choice Single Answer Question What does the points falling outside the control limits indicate? Correct Answer Your Answer Presence of assignable causes Mean = Standard deviation

Multiple Choice Single Answer Question Which industry out of the following industries require maximum consideration for safety factor while selecting plant location? Correct Answer Nuclear power plant Your Answer Nuclear power plant

Multiple Choice Multiple Answer Question Which of the following are assignable cause? Correct Answer Your Answer Large varaitions in hardness of material , Tool wear , Errors in setting Large varaitions in hardness of material , Play in guide rods , Errors in setting

Multiple Choice Single Answer Question A good plant layout helps in Correct Answer Reducing handling costs

Your Answer

Reducing handling costs

Multiple Choice Multiple Answer Question Which of the following are examples of addition during recording for method study? Correct Answer Brazing , Welding , Riveting Your Answer Brazing , Welding , Riveting

True/False Question Correct Answer Your Answer

An activity can share the same tail event and same head event with any other activity. False True

Select The Blank Question Work study is also called ________ study Correct Answer Your Answer Time and Motion Time and Motion

Multiple Choice Single Answer Question Which kind of gauge consists of electrical contacts operating a series of colloured signal lamps which indicate whether the dimension is correct, oversize or undersize? Correct Answer Multiple gauging Your Answer Multiple gauging

Multiple Choice Multiple Answer Question Components of Production Management include Correct Answer Your Answer Capacity Planning , Job Design , Production Planning Capacity Planning , Job Design , Production Planning

True/False Question Correct Answer Your Answer

Only skilled worker can use the fixed limit gauge. False False

Multiple Choice Multiple Answer Question Which are major benefits of identifying the critical path? Correct Answer It helps to identify the set of activities and events which are critical and as such must be carefully controlled and monitored , It identifies activities to be given preference in allocation of resources. , It helps

to exercise "control by exception". Your Answer It helps to identify the set of activities and events which are critical and as such must be carefully controlled and monitored , It reduces the paperwork , It identifies activities to be given preference in allocation of resources.

Multiple Choice Multiple Answer Question Which are reason due to which the progress of work is rarely in line with it's plan? Correct Answer Absenteeism , Machine breakdowns , Substandard performance against prefixed production standards Your Answer Absenteeism , Machine breakdowns , Substandard performance against prefixed production standards Select The Blank Question The ________ is necessary when the job requires detailed of one or more of the job characteristics with the help of special equipment which is not available at the producing company. Correct Answer Inspection order Your Answer Inspection order

Multiple Choice Multiple Answer Question Which of the following are important considerations concerning activity times? Correct Answer Activity time should be obtained from the person responsible for the completion of an activity , Activity time must be independent of any influence which the preceding or succeeding activity may have on it. , Activity time may assume that just the normal quantity of resources required to carry out the activity are available. Your Answer Activity time should be obtained from the person responsible for the completion of an activity , Activity time must be independent of any influence which the preceding or succeeding activity may have on it. , Activity time may assume that just the normal quantity of resources required to carry out the activity are available. Select The Blank Question Capacity decisions have a direct influence on performance of production system in respect of ________ Correct Answer Delivery performance Your Answer Delivery performance

True/False Question Correct Answer Your Answer

Breakdown of machines, absenteeism of worker does not dislocate the manufacturing activity in process layout True True

Multiple Choice Single Answer Question The process of changing inputs into outputs thereby adding some value to entity can be defined as

Correct Answer Your Answer

Operation Operation

Multiple Choice Multiple Answer Question Which of the following possibilities can be explored by using flow process chart? Correct Answer Eliminating the operations or combining the operations with another , Reducing the distance traveled by the workmen or materials , Avoiding the waiting time and thereby reduce production losses Your Answer Eliminating the operations or combining the operations with another , Reducing the distance traveled by the workmen or materials , Avoiding the waiting time and thereby reduce production losses Multiple Choice Single Answer Question The document raised by PPC which authorises different functions to take action as per instruction is called Correct Answer Work Order Your Answer Work Order

True/False Question Correct Answer Your Answer

Dust gets mixed with lubricants, forms an abrasive substance and causes pre-mature failure of machinery. True True

Match The Following Question Draining and refilling of oil reserviors of plunger pump Parts lubricated with oil nipple Tools and slideways Table lubrication

Correct Answer Yearly Daily two to three times a day Weekly

Your Answer Yearly Daily two to three times a day Weekly

Select The Blank Question Production control work is ________ in case of floor inspection as compared with the centralised inspection. Correct Answer easier Your Answer easier

True/False Question

Operation process charts though indicates the sequence of events but do not show movements.

Correct Answer Your Answer

True True

Select The Blank Question The ________ is the probability that a bad lot will be accepted by the sampling plan. Correct Answer Consumer's risk Your Answer Consumer's risk

Select The Blank Question A ________ is another form of subcontracting. Correct Answer Your Answer Hiring capacity Hiring capacity

Select The Blank Question The ________ breakdowns usually cost more, partly due to damage done to the adjustment components and partly due to emergency actions. Correct Answer Unexpected Your Answer Unexpected

Select The Blank Question Production Planning is a centralised activity which includes functions such as ________ Correct Answer Scheduling Your Answer Scheduling

Multiple Choice Single Answer Question Which is the zone beyond LTPD in case of Oc curve of a general plan? Correct Answer Zone of rejection Your Answer Zone of rejection

Multiple Choice Single Answer Question Where the ignorance towards the degradation of machine leads to? Correct Answer Your Answer Eventual breakdown Eventual breakdown

True/False Question

The problems of congestion, bottlenecks and backtracking can not be visualized by using templates and models.

Correct False Answer Your Answer False

Multiple Choice Multiple Answer Question Following are some of the factors which influence process planning Correct Order Quantity , Process capability of machine , Delivery Dates Answer Your Answer Process capability of machine , Delivery Dates , Order Quantity

Multiple Choice Single Answer Question Gross requirement of products is determined on the basis of Correct Both forecast and pending orders Answer Your Answer Both forecast and pending orders

True/False Question

Correct Answer Your Answer True

Skill of labour force in a product type layout is usually higher than in the process type of layout False

Multiple Choice Single Answer Question In exponential smoothing method,for a stable demand pattern and better smoothing effect, value of fraction( Alpha) selected is Correct 0.05 to 0.10 Answer Your Answer 0.05 to 0.10

True/False Question

Correct Answer Your Answer True

Recording of movement is not necessary in case of method study in any form. False

Multiple Choice Multiple Answer Question Which of the following may be the objectives of project crashing? Correct Answer To complete the project in the least possible time , To reduce project cost below it's normal cost , To achieve uniformity in requirement of resources Your Answer To complete the project in the least possible time , To reduce project cost below it's normal cost , To achieve uniformity in requirement of resources

Multiple Choice Single Answer

Question

Correct Answer Your Answer Total Quality management

Which is the next stage to the inspection based quality control in the historical development of quality management. Quality assurance

Select The Blank Question The ________ includes preventive maintenance activities whose needs are identified through inspection which requires stoppage of machines. Correct Shutdown Maintenance Answer Your Answer Shutdown Maintenance

Multiple Choice Single Answer Question Inadequate production capacity ultimately leads to Correct Poor Customer Service Answer Your Answer Low Productivity

Select The Blank Question The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking. Correct Condition monitoring Answer Your Answer Condition monitoring

True/False Question

Correct Answer Your Answer True

Inspection should be conducted on all incoming materials, semifinished items, bought out components, subcontract items prior to any operation, assembly. True

Select The Blank Question The ________ is the maximum percentage defective that for the purpose of sampling inspection can be considered satisfactory as a process average. Correct Acceptable quality level Answer Your Answer Acceptable quality level

Multiple Choice Single Answer Question Production Planning includes Correct Predetermination of manufacturing requirements Answer Your Answer Predetermination of manufacturing requirements

Multiple Choice Multiple Answer Question Expediting function is concerned with following activities Correct Answer Progress chasing to identify delays which may hold up production , Communicating possible delays in delivery date commitment to sales department , Devising cures to keep rate of production in line with schedule Your Answer Progress chasing to identify delays which may hold up production , Communicating possible delays in delivery date commitment to sales department , Devising cures to keep rate of production in line with schedule

Select The Blank Question The ________ is the watch dog which ensures that every element of production and activities which could affect the quality of end product are regulated to the extent desirable. Correct Quality control Answer Your Answer Quality control

True/False Question

Correct Answer Your Answer False

A load chart specifies the work to be carried out by each person of company during shift hours. False

Match The Following Question Pessimistic time Expected time Optimistic time Most likely time

Correct Answer b Te a m

Your Answer b Te a m

True/False Question

Breakdown is inversly proportional to the investment in W.I.P.

Correct False Answer Your Answer True

Select The Blank Question Production Planning is a centralised activity which includes functions such as ________ Correct Scheduling Answer Your Answer Scheduling

Select The Blank Question A set of activities to keep an equipment in the specified condition is called as ________. Correct Maintenance Answer Your Answer Maintenance

Multiple Choice Single Answer Question A good plant layout helps in Correct Reducing handling costs Answer Your Answer Reducing handling costs

Select The Blank Question The ________ is the probability that a good lot will be rejected by the sampling plan. Correct Producer's risk Answer Your Answer Producer's risk

Multiple Choice Multiple Answer Question Components of Production Management include Correct Capacity Planning , Job Design , Production Planning Answer Your Answer Capacity Planning , Job Design , Production Planning

Multiple Choice Single Answer Question Technique of Value Engineering can be effectively employed in design of a product to Correct To meet the intended function at lowest cost Answer Your Answer To meet the intended function at lowest cost

Multiple Choice Multiple Answer Question Which are the subtasks of the maintenance phase of the method study? Correct Monitoring and control , Performance appraisal , Audit on savings Answer Your Answer Monitoring and control , Performance appraisal , Audit on savings

True/False Question

short cycle job should be studied for macroscopic motions.

Correct False Answer Your Answer True

Select The Blank Question The ________ is a set of tools and techniques by which products are made to comply with the specifications at minimum cost to the firm. Correct Quality control system Answer Your Answer Quality control system

True/False Question

Inspection Order can be a verbal order

Correct True Answer Your Answer False

Multiple Choice Single Answer Question Need for change in layout can occur due to following reason Correct introduction of new product Answer Your Answer improve quality

Select The Blank Question Goods after final inspection should accompany ________to enable dispatch department to identify and draw correct reference. Correct Forwarding note Answer Your Answer Forwarding note

Multiple Choice Multiple Answer Question Which are the different methods of recording actual progress of work? Correct Display boards , Progress cards , Network updating Answer Your Answer Display boards , Progress cards , Network updating

Select The Blank Question The term ________ emplies the foregone profit due to inability of company to produce. Correct Opportunity cost Answer Your Answer Opportunity cost

Multiple Choice Single Answer Question What do you mean by lowest possible direct cost required to complete an activity within it's crashed time? Correct Crash cost Answer Your Answer Normal cost

Multiple Choice Single Answer

Question

Correct Answer Your Answer Factory

Any premise in which persons are employed for purpose of making any product/s is called Factory

Multiple Choice Single Answer Question The process of changing inputs into outputs thereby adding some value to entity can be defined as Correct Operation Answer Your Answer Operation

Multiple Choice Single Answer Question What do you mean by the selection of the job for the method study on the basis of manufacturing difficulties? Correct Technical consideration Answer Your Answer Economic consideration

True/False Question

Correct Answer Your Answer True

In case of backward pass computation, the latest event time of the end event equals to the earliest event time minus duration of that activity. False

Match The Following Question Emerson Efficiency Plan Craft Work Sampling Gantt Chart

Correct Answer Wage Payment Facilities Planning Machine utilization Production Scheduling

Your Answer Wage Payment Facilities Planning Machine utilization Production Scheduling

Multiple Choice Multiple Answer Question Which of the following are examples of addition during recording for method study? Correct Brazing , Welding , Riveting Answer Your Answer Brazing , Welding , Riveting

Multiple Choice Single Answer Question The ratio of output to input of a production system is commonly known as

Correct Productivity Answer Your Answer Productivity

Multiple Choice Single Answer Question In case of Batch Production which kind of labour is expected? Correct Skilled in one specific Manufacturing Process Answer Your Answer Skilled in all Manufacturing Processes

Select The Blank Question The ________ is necessary when the job requires detailed of one or more of the job characteristics with the help of special equipment which is not available at the producing company. Correct Inspection order Answer Your Answer Inspection order

Multiple Choice Multiple Answer Question Which are the factors on which the structure of the transportation cost depends? Correct Average distance of shipment , Characteristics of the commodity , Answer Medium of shipment Your Answer Average distance of shipment , Characteristics of the commodity , Medium of shipment Multiple Choice Single Answer Question Which is the ideal place to inspect jigs and fixtures in a mass manufacturing unit? Correct Separate inspection room Answer Your Answer Separate inspection room

True/False Question

Correct Answer Your Answer True

In Gantt Chart, the horizontal lines devide vertical lines into sections which represents either operations or work centres. True

Multiple Choice Single Answer Question Which phase of method study is concerned with analyzing the facts critically, generating alternatives which form the basis for selection and development of improved methods? Correct Answer Critical examination Your Answer Select The Blank Development and selection

Question Correct Answer Your Answer

The ________ advocates maintenance procedures whereby the condition of the plant is constantly watched through systematic inspection to unearth unhealthy conditions and preventive Preventive Maintenance Design-in Maintenance

Select The Blank Question The term ________ emplies the foregone profit due to inability of company to produce. Correct Answer Opportunity cost Your Answer True/False Question Correct Answer Your Answer Down time cost

A network should employ only those dummy activities which are absolutely necessary. True True

Select The Blank Question A set of activities to keep an equipment in the specified condition is called as ________. Correct Answer Maintenance Your Answer True/False Question Correct Answer Your Answer Maintenance

While making X bar-R-chart, values of X bar and R are recoded samplewise either on the extreme right of the individual measurements on the data sheet or in a separate sheet. True False

Select The Blank Question The ________ must ensure that the product satisfy the functional requirements of it's usage. Correct Answer Quality of design Your Answer True/False Question Correct Answer Your Answer Quality of inspection

Even if any activity on the critical path is delayed, project completes on the scheduled time. False False

Multiple Choice Single Answer

Question Correct Answer Your Answer

Which is the alternative way of indicating the load other than numerical way, in case of Gantt chart ? Graphical approach Symbolic pproach

Multiple Choice Multiple Answer Question Which of the following are types of sampling plan? Correct Answer Your Answer Single sampling plan , Double sampling plan , Multiple sampling plan Single sampling plan , Double sampling plan , Multiple sampling plan

Multiple Choice Multiple Answer Question Which of the following are major inputs to scheduling? Correct Answer Your Answer Overlapping of operations , Effective Capacity per work centre , Performance standards Overlapping of operations , Effective Capacity per work centre , Performance standards

Select The Blank Question The ________ is necessary when the job requires detailed of one or more of the job characteristics with the help of special equipment which is not available at the producing company. Correct Answer Inspection order Your Answer Stores issue order

Select The Blank Question The ________ is the maintenance work initiated on a result of knowledge of the condition of an item from routine or continuous checking. Correct Answer Condition monitoring Your Answer True/False Question Correct Answer Your Answer Condition monitoring

Diversified labour is adequately available in rural area as compared to urban area. False False

Multiple Choice Multiple Answer Question Which of the following cases indicated that the operation has occurred? Correct Answer Movement of components to assembly section , Raw material movement , A worker's trip to grinder to sharpen the tools Your Answer Movement of components to assembly section , A worker's trip to grinder to sharpen the tools , Tools kept in rack of tool crib Multiple Choice Single Answer

Question Correct Answer Your Answer

What is the reason of fluctuations, if the control chart evaluates that the process is in a state of statistical control? Random variability Set up variability

Select The Blank Question The ________ is the maximum percentage defective that for the purpose of sampling inspection can be considered satisfactory as a process average. Correct Answer Acceptable quality level Your Answer Acceptable quality level

Multiple Choice Single Answer Question Product layout is suitable when Correct Answer Your Answer Products have reasonable stable demand Products are not required in large quantities

Multiple Choice Multiple Answer Question Which of the following charts are used for the recording of data during the method study? Correct Answer Operation process chart , Multiple activity chart , Flow process chart Your Answer True/False Question Correct Answer Your Answer Operation process chart , Multiple activity chart , Flow process chart

The operator should not stop production if first piece is not approved by the inspector. False False

Multiple Choice Single Answer Question Need for change in layout can occur due to following reason Correct Answer Your Answer introduction of new product introduction of new product

Multiple Choice Single Answer Question What do you mean by a single event which represents the joint completion of more than one activities? Correct Answer Merge event Your Answer True/False Question Merge event

The control chart for number of defectives is more convenient to make than control chart for fraction defectives sincethe fugure of

Correct Answer Your Answer

number of defectives units can be directly taken from the inspection report. True True

Multiple Choice Single Answer Question Which rule is used for numbering of events? Correct Answer Your Answer True/False Question Correct Answer Your Answer True/False Question Correct Answer Your Answer Fulkerson's Rule Juran's Rule

In case of two handed process chart, the simultaneous activities of both hands are recorded opposite to each other on the chart. True True

All activities lying on the non-critical paths must have total float and free float. False True

Multiple Choice Multiple Answer Question Which of the following is not the characteristic of Project Production? Correct Answer Your Answer Continuous flow of material , Highly mechanised material handling , Virtually zero manufacturing cycle time Continuous flow of material , Highly mechanised material handling , Virtually zero manufacturing cycle time

Multiple Choice Multiple Answer Question Which of the following is not the characteristic of Project Production? Correct Answer Your Answer Continuous flow of material , Highly mechanised material handling , Virtually zero manufacturing cycle time Fixed position layout

Select The Blank Question The ________ are the definitions of the measurable as well as nonmeasurable characteristics of the product. Correct Answer Specifications Your Answer Specifications

Multiple Choice Single Answer Question How industry has responded to the fact of existence of inherant variability of the manufacturing process?

Correct Answer Your Answer

Inclusion of certain tolerance on the basic dimensions in the drawing Inclusion of certain tolerance on the basic dimensions in the drawing

Select The Blank Question Work study is also called ________ study Correct Answer Your Answer Time and Motion Time and Motion

Multiple Choice Multiple Answer Question Which are the different methods of recording actual progress of work? Correct Answer Display boards , Progress cards , Network updating Your Answer True/False Question Correct Answer Your Answer Job cards , Progress cards , Network updating

In case of backward pass computation, the latest event time of the end event equals to the earliest event time minus duration of that activity. False True

Multiple Choice Multiple Answer Question Which of the following products should be produced by using mass production? Correct Answer Refrigerator , Tyre for automobile , Television Set Your Answer Refrigerator , Tyre for automobile , Television Set

Multiple Choice Multiple Answer Question Which of the following are examples of attributes? Correct Answer Your Answer Cracks , Burrs , Texture Cracks , Burrs , Texture

Match The Following Question Scheduling Device Interruption for machine utilisation Input for scheduling Technique of scheduling

Correct Answer Strings Preventive maintenance Overlapping of operations Critical Path Analysis

Your Answer Strings Preventive maintenance Critical Path Analysis JIT

Multiple Choice Multiple Answer Question Which are the three distinct parts of the chart? Correct Answer Your Answer Summary , Introduction , Body Summary , Introduction , Analysis

Match The Following Question Combined Layout Fixed Position Layout Product Layout Process Layout

Correct Answer Mixed Layout Project Layout Line Layout Functional Layout

Your Answer Mixed Layout Project Layout Line Layout Functional Layout

Multiple Choice Multiple Answer Question Following are the commonly used factors considered for evaluation of layout in factor analysis method Correct Answer Flow of material , Equipment utilization , Working condition Your Answer Flow of material , Equipment utilization , Working condition

Multiple Choice Single Answer Question Fixed position layout is adopted when Correct Answer Your Answer product is very heavy involving assembly of large number of parts product is very heavy involving assembly of large number of parts

Select The Blank Question The ________ is the defect level for which lots are regarded as bad lots. Correct Answer Lot Tolerance Percentage Defective Your Answer Acceptable quality level

Multiple Choice Multiple Answer Question Which of the following are examples of specifications? Correct Answer Your Answer Commercial standards , Assembly and testing instructions , Bill of material Commercial standards , Assembly and testing instructions , Bill of material

Multiple Choice Single Answer Question Process Engineer does not get sufficient time for designing tooling for most economic production run when Correct Answer Delivery time is less

Your Answer

Delivery time is less

Multiple Choice Single Answer Question What do you mean by the graphical representation of the project which is composed as series of connected arrows and circles to describe the interrelationship of the activities involved? Correct Answer Network Your Answer True/False Question Correct Answer Your Answer Flow chart

Latest finishing date is the latest event time of the tail event. False True

Multiple Choice Single Answer Question Any premise in which persons are employed for purpose of making any product/s is called Correct Answer Factory Your Answer Factory

Select The Blank Question The ________ is the probability that a bad lot will be accepted by the sampling plan. Correct Answer Consumer's risk Your Answer Consumer's risk

You might also like