ReplacementofRawMill4DedustingCyclones Scopeofwork

TheScopeofwork: 1. ErectinganyrequiredscaffoldingfortheCyclonesinletandoutlet ducts. 2. Dismantlingofanyducts,platformorladdersthatmaydistractthe job. 3. Dismantlingofalltheexpansionjoints. 4. Dismantling,makinganyrequiredrepairs,andreinstallingthe outletducts. 5. DismantlingthetoppartsofcyclonesCN301andCN321and makingthemreadyforDensittobeinstalled. 6. Dismantlingalltheaccessdoorsandmanholesfromthecyclones bodyanderectingthemonthenewcyclones. 7. Dismantlingthe4oldcyclonesandsendingthemtothe determinedscraparea. 8. Dismantlingthe2elbowsattheoutletductsofthecyclones. 9. Dismantlingtherotarysluicesunderthe4cyclonesandinstalling thembackafterassemblingthecyclones. 10. Liftingtotheirpositionsandassemblingallthepartsofthe4new cycloneswithDensitinstalled. 11. AssemblingthetoppartsCyclonesCN301andCN321after installationofDensit. 12. Replacingthe2elbowsofoutletductsofthecycloneswith2new elbows. 13. Makinganyrequiredrepairsattheductsbelowthe2elbows. EquipmentName:RawMillDedustingCyclones. EquipmentNo.:R1.321.CN301 JobDescription:ReplacementofRawMill4DedustingCyclones Duration:13days(2shifts)

14. Assemblingofalltheexpansionjoints. 15. ReerectinganyDucts,platformsorladdersthatremovedduring dismantling. 16. Dismantlingthescaffoldsafterfinishingwork 17. Inspectionoftheinletductsofthecyclonesandmakingany requiredrepairs.

18. Installinginsulationforthetoppartsandoutletductsand elbows. 19. Housekeepingfortheworkareaafterfinishingthejobincluding transportinganyscrapestodeterminedarea. ContractorObligations:


1. Acompletesitesurveyingtoknowthesitefacilities,trafficfor easymovingaroundthesite. 2. AfocusedsurveyingontheRawMillarea(placeofwork)to knowtheaccesspointsandladdersfortheDedustingCyclones. 3. Requiredliftingequipmentswithasuitablecapacitysuchas cranes,forklifts,chainblocks.etc.tobeavailableinsitetwo daysbeforestartingworkandshouldbeprovidedforallperiod ofworkwithoutanyadditionalcharge. 4. Requiredscaffoldingmaterialtobepreparedandreadyatthe workplaceonedaybeforestartingwork. 5. Providetherequiredhandtoolsandequipments(welding machines,oxygenacetylenecylindersetc)inadditiontothe consumableslikegrindingdisks,weldingelectrodesetc). 6. Providethesafetytoolsequipmentsneededaccordingto NLSupervisionsafetypolicy.

7. Providethesuitableskilledwelltrainedmanpowerwithworking licenseaccordingtoEgyptslaw,tocover2shiftsperday(12 hrs/each),forallperiodofwork.(Underageworkerswillbe rejected). 8. Providetheaccommodation,transportationsandmealsforhis staff. 9. Providetherequiredinsurancesforhisstaff. 10.Contractormustprovideacompletejobplan[MSProject]witha deadline,criticalpathandtimeperiodsforthewholejobandfor eachprojectoperationwiththemanpowerdescriptionand numbersonit. 11.Thecontractorisobligatedtodothehousekeepingforthework areaafterfinishingthejobincludingtransportinganyscrapesto determinedareaifany. 12. FollowuperectioninstructionsanddrawingsofFLSmidthwhich willbeprovidedbyNLSoneweekbeforestartingthejob. 13.TheContractorisobligatedtogetacquaintedwiththecondition onsitebeforesigningthecontract.

NLSupervisionObligations:
1. Providethecontractorwithallthenewparts(newCyclones, expansionjoints,bolts,etc.). 2. Provideallpowerandsafelightsources. 3. Providethecontractorwiththerequireddrawingsandmanuals oneweekbeforestartingwork. 4. ProvidethecontractorwithNLSupervisionsafetypolicyand safetytrainingforthewholeworkgroup.