Roof Flashing Details Index

FD01 FD02 FD03 FD04 FD05 FD06 FD07 FD08 FD09 FD10 FD11 FD12 FD13 FD14 FD15 FD16 FD17 FD18 FD19 FD20 FD21 FD22

Interior Roof Drain Detail Interior Drain with Gravel Stop Detail Scupper Roof Drain Detail Gutter Roof Drain Detail Roof-Top Equipment Curb Detail Roof-Top Metal Air Shaft Curb Detail Roof-Top Wood Air Shaft Curb Detail Roof Skylight Detail Roof-Top Chimney Pipe Detail Roof-Top Plumbing Vent Pipe Detail Sheet Metal Pipe Enclosure Detail Roof-Top Pipe Roller Support Detail Structural Roof Deck Penetration Detail Metal Covered Expansion Joint Detail Premanufactured Expansion Joint Detail Roof Area Divider Detail Raised Metal Roof Edge Detail Gravel Stop Metal Roof Edge Detail Post Supported Roof Deck Flashing Detail Wall Supported Roof Deck Flashing Detail Concrete Wall Counterflashing Detail Metal Wall Cap Flashing Detail

2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD01 Interior Roof Drain Detail


Coverboard insulation Thermal insulation A 30 sq min, 1.5 lb to 4 lb lead, or 16 oz copper flashing adhered onto finished roof with M300 RubrMastic. Prime top surface of metal flashing with M400 RubrPrime and install M60 RubrPoly flashing sheets Drain strainer M60 RubrPoly flashing sheets

Roof deck Tapered insulation Clamping ring Deck clamp Drain bowl Fields roof membrane sheets, metal flashing, & M60 RubrPoly flashing sheets all under clamping ring Fields M300 RubrMastic Fields roof membrane sheets

Side View
A 30 sq min, 1.5 lb to 4 lb lead, or 16 oz copper flashing adhered onto finished roof with M300 RubrMastic. Prime top surface of metal flashing with M400 RubrPrime and install M60 RubrPoly flashing sheets M60 RubrPoly flashing sheets Fields roof membrane sheets

Clamping ring Drain strainer

Tapered insulation

Notes
1. Metal deck sump pans are prohibited. 2. Type 1 dead level asphalt is prohibited in the drain sump area.

Fields roof membrane sheets, metal flashing, & M60 RubrPoly flashing sheets all under clamping ring Roof deck Thermal insulation Coverboard insulation Drain bowl Deck clamp

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD02 Interior Drain with Gravel Stop Detail

A 1 x 4 sheet metal gravel stop, 36 sq min adhered in place with M300 RubrMastic M60 RubrPoly flashing sheets

A 30 sq min, 1 1/2 lb to 4 lb lead, or 16 oz copper flashing adhered onto finished roof with M300 RubrMastic. Prime top surface of metal flashing with M400 RubrPrime and install M60 RubrPoly flashing sheets Drain strainer

M60 RubrPoly flashing sheets

Thermal insulation Coverboard insulation Roof deck Tapered insulation Clamping ring Deck clamp Drain bowl Fields roof membrane sheets, metal flashing, & M60 RubrPoly flashing sheets all under clamping ring M300 RubrMastic Fields roof membrane sheets
A 30 sq min, 1 1/2 lb to 4 lb lead, or 16 oz copper flashing adhered onto finished roof with M300 RubrMastic. Prime top surface of metal flashing with M400 RubrPrime and install M60 RubrPoly flashing sheets A 1 x 4 sheet metal gravel stop, 36 sq min adhered in place with M300 RubrMastic M60 RubrPoly flashing sheets

Side View

Clamping ring Drain strainer

M60 RubrPoly flashing sheets Fields roof membrane sheets

Tapered insulation

Notes
1. Metal deck sump pans are prohibited. 2. Type 1 dead level asphalt is prohibited in the drain sump area.

Fields roof membrane sheets, metal flashing, & M60 RubrPoly flashing sheets all under clamping ring Roof deck Thermal insulation Coverboard insulation Drain bowl Deck clamp

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD03 Scupper Roof Drain Detail

Bead of sealent Sheet metal scupper A .75 x 3 min L shaped gravel guard secured to the scupper flange & notched to permit drainage Sheet metal conductor head

High domed, capped, & gasketed fasteners 18 oc, depending upon wind zone and local conditions See Raised Metal Roof Edge Detail FD17 for sheet metal fascia counterflashing

4 min 4 min 2 min

Slope to the drain M60 RubrPoly flashing sheets Scupper fastened to blocking with fasteners 3 oc & staggered. Flange adhered into M300 RubrMastic & primed with M400 RubrPrime before installing M60 RubrPoly flashing sheets Fields roof membrane sheets M60 RubrPoly envelope sheet Treated wood nailers M60 RubrPoly sheet extended below blocking Coverboard insulation Thermal insulation Roof deck

Side View
See Raised Metal Edge Detail FD17 for sheet metal fascia counterflashing Scupper fastened to blocking with fasteners 3 oc & staggered. Flange adhered into M300 RubrMastic & primed with M400 RubrPrime before installing M60 RubrPoly flashing sheets

Sheet metal scupper

Notes
1. This detail shall be installed only where the deck is supported by the outside wall. 2. This detail may be adapted to roof edges as shown in Interior Roof Drain Detail FD01. 3. Roof surfaces shall be sloped for positive drainage. 4. Attach wood nailer to wall with suitable fasteners. 5. Wood blocking shall be slotted for venting wet filled decks. 6. Scupper opening through roof edge shall be 2 or less.

A .75 x 3 min L shaped gravel guard secured to the scupper flange & notched to permit drainage Sealant

M60 RubrPoly flashing sheets Fields roof membrane sheets Coverboard insulation sloped to the drain Thermal insulation Roof deck M60 RubrPoly envelope sheet

Sheet metal conductor head.

M60 RubrPoly sheet extended below blocking

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD04 Gutter Roof Drain Detail

Sheet metal edge flashing with gravel stop lip. Flange primed with M400 RubrPrime before installing M60 RubrPoly flashing sheets Fields roof membrane sheets M60 RubrPoly flashing sheets M60 RubrPoly envelope sheet

Fasteners 3 oc & staggered Gutter spacers alternately spaced from brackets

M60 RubrPoly flexible sheet closure into gutter Roof deck Wood nailers Continuous cleat Gutter brackets supported 12 to 36 oc depending upon conditions Sheet metal gutter Continuous sheet metal closure fastened 18 oc M60 RubrPoly sheet extended to overlay metal closure Turn down Flange adhered into M300 RubrMastic

Side View
M60 RubrPoly flashing sheets Sheet metal edge flashing with gravel stop lip. Flange primed with M400 RubrPrime before installing M60 RubrPoly flashing sheets Continuous cleat Gutter spacers alternately spaced from brackets Turn down M60 RubrPoly flexible sheet closure into gutter M60 RubrPoly envelope sheet Fasteners 3 oc staggered Fields roof membrane sheets

Notes
1. In climates where the winter temperature remains below freezing for extended periods of time, install Raised Metal Roof Edge Detail FD17 and interior drains, or through curb scuppers to drain the roof. 2. Gutter brackets are required to be at least one gauge heavier than gutter stock.

Sheet metal gutter

3. Attach wood nailer to wall or deck with suitable fasteners. 4. Gutter expansion joints shall be installed at appropriate intervals commensurate with the type of metal.
Gutter brackets supported 12 to 36 oc depending upon conditions Continuous sheet metal closure fastened 18 oc

Roof deck Wood nailers

M60 RubrPoly sheet extended to overlay metal closure

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD05 Roof-Top Equipment Curb Detail

Sheet metal cover with receiver for counterflashing Install bolts into sealant 10 nominal flashing height Neoprene pad Removable sheet metal counterflashing High domed, capped, & gasketed fasteners 18 oc, depending upon wind zone and local conditions Fasteners 8 oc Fields roof membrane sheets extended 2 min above top of cant Wood cant fastened to wood nailers M60 RubrPoly flashing sheets extended to a min height of 8 Wood curb Wood nailers Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck

Side View
Sheet metal cover with receiver for counterflashing High domed, capped, & gasketed fasteners 18 oc, depending upon wind zone and local conditions Removable sheet metal counterflashing Fasteners 8 oc

Install bolts into sealant Noeprene pad

Notes
1. This detail allows for roof maintenance around supported equipment. The continuous support design shall be installed in light weight structural systems so as to distribute the equipment weight across two or more structural support members. A min of 2 of horizontal clearance shall be provided for removal and replacement of roofing and flashing between parallel supports. A min of 3 of vertical clearance from roof surface to bottom of supported equipment shall be provided. 2. Attach wood nailer to deck with suitable fasteners.
10 nominal flashing height

Fields roof membrane sheets extended 2 min above top of cant M60 RubrPoly flashing sheets extended to a min height of 8

Wood curb Wood nailers Wood cant fastened to wood nailers

Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD06 Roof-Top Metal Air Shaft Curb Detail

Equipment mounting curb Sealing material


10 nominal flashing height

Sheet metal flashing receiver Min of 2 high domed, capped, & gasketed fasteners 18 oc per side, depending upon wind zone and local conditions

Wood nailer

Removable sheet metal counterflashing Fasteners 8 oc Fields roof membrane sheets extended 2 min above top of cant Alternate curb bearing location for heavy weight loading conditions
Equipment Base of unit shall extend .5 min beyond top of curb Sealing material shall be continous on top of the curb 1 min below top of curb Flashing receiver Fasteners Wood nailer Counterflashing M60 RubrPoly flashing sheets Equipment mounting curb Insulation Equipment mounting curb Sealing material Wood nailer

M60 RubrPoly flashing sheets extended to a min height of 8 Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck
Sheet metal flashing receiver Install a min of 2 high domed, capped, & gasketed fasteners 18 oc per side, depending upon wind zone and local conditions Removable sheet metal counterflashing Fasteners 8 oc Fields roof membrane sheets extended a min of 2 above top of cant: Not shown for clarity M60 RubrPoly flashing sheets extended to a min height of 8

Side View

Notes
1. The top wood nailer of the curb & the seal strip shall be supplied by the curb manufacturer. 2. Attach the treated wood nailer to deck with suitable fasteners. 3. Mechanical units shall be installed after the roof membrane and flashings have been installed.
Alternate curb bearing location for heavy weight loading conditions

10 nominal flashing height

Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD07 Roof-Top Wood Air Shaft Curb Detail

Sealing material Wood curb


10 nominal flashing height

Sheet metal flashing receiver Min of 2 high domed, capped, & gasketed fasteners 18 oc per side, depending upon wind zone and local conditions

Removable sheet metal counterflashing Wood nailers Wood cant to brace curb Fasteners 8 oc Fields roof membrane sheets extended 2 min above top of cant M60 RubrPoly flashing sheets extended to a min height of 8 Fields roof membrane sheets Coverboard insulation
Equipment Base of unit shall extend .5 min beyond top of curb Sealing material shall be continous on top of curb 1 min below top of curb Flashing receiver Fasteners Wood nailer Counterflashing M60 RubrPoly flashing sheets 10 nominal flashing height

Thermal insulation Roof deck

Side View
Sealing material Sheet metal flashing receiver Min of 2 high domed, capped, & gasketed fasteners 18 oc per side, depending upon wind zone and local conditions Removable sheet metal counterflashing Fasteners 8 oc Fields roof membrane sheets extended a min of 2 above top of cant: Not shown for clarity M60 RubrPoly flashing sheets extended to a min height of 8

Notes
1. Attach wood nailer to the deck with suitable fasteners. 2. The equipment shall be set after the roof membrane and flashings have been installed.
Wood cant to brace curb Wood nailers Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD08 Roof Skylight Detail


Double dome skylight installed by others Skylight frame with weep holes Min of 2 high domed, capped, & gasketed fasteners 18 oc per side, depending upon wind zone and local conditions Removable sheet metal counterflashing

10 nominal flashing height

Fasteners 8 oc Fields roof membrane sheets extended 2 min above top of cant M60 RubrPoly flashing sheets to a min height of 8 Fields roof membrane sheets Coverboard insulation Wood nailers and curb Wood cant to brace curb Thermal insulation Roof deck

Side View
Double dome skylight installed by others Skylight frame with weep holes Min of 2 high domed, capped, & gasketed fasteners 18 oc per side, depending upon wind zone and local condition Removable sheet metal counterflashing Fasteners 8 oc 10 nominal flashing height Fields roof membrane sheets extended a min of 2 above top of cant M60 RubrPoly flashing sheets extended to a min height of 8 Fields roof membrane sheets Coverboard insulation

Note
1. Attach treated wood nailer to deck with suitable fasteners.

Thermal insulation Roof deck Wood cant to brace curb Wood nailers and curb

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD09 Roof-Top Chimney Pipe Detail


Temperature appropriate elastomeric sealer Drawband or weld umbrella to stack Insulate void for cold stack Min of 2 high domed, capped, & gasketed fasteners 18 oc per side, depending upon wind zone and local condition
10 nominal flashing height

Removable sheet metal counterflashing Fasteners 8 oc

Metal or gypsum liner Varies Wood nailers and curb Wood cant to brace curb

Fields roof membrane sheets extended 2 min above top of cant M60 RubrPoly flashing sheets extended to a min height of 8 Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck

Side View
Temperature appropriate elastomeric sealer Drawband or welded umbrella to stack Metal or gypsum liner is required Insulate void for cold stack Min of 2 high domed, capped, & gasketed fasteners 18 oc per side, depending upon wind zone and local conditions Removable sheet metal counterflashing Fasteners 8 oc

1. This detail allows the opening to be completed before the stack is placed. 2. The clearance necessary between the gypsum or metal liner and the stack, and the need for insulation, will depend on the temperature of the material emited through the stack.

10 nominal flashing height

Notes

Fields roof membrane sheets extended a min of 2 above top of cant M60 RubrPoly flashing sheets extended to a min height of 8

Fields roof membrane sheets

3. Attach treated nailer to the deck with suitable fasteners.

Wood nailers & curb Wood cant to brace curb

Coverboard insulation Thermal insulation

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD10 Roof-Top Plumbing Vent Pipe Detail


Form top of flashing 1 down into pipe Soft metal pipe flashing Plumbing vent stack Apply M300 RubrMastic at juncture of pipe penetration through roof membrane

6 min flange 4 min 4 min

M60 RubrPoly flashing sheets Fields roof membrane sheets Coverboard insulation Thermal insulation Adhere flange with M300 RubrMastic. Prime top of flange with M400 RubrPrime before flashing with M60 RubrPoly Roof deck

Side View
Form top of flashing 1 down Plumbing vent stack Soft metal pipe flashing Apply M300 RubrMastic at juncture of pipe penetration through roof membrane

Notes
1. Soft metal pipe flashing: Minimum sheet lead of 2.25 lb per sq ft or Minimum sheet copper of 16 oz per sq ft
n mi mi n

Adhere flange with M300 RubrMastic. Prime top of flange with M400 RubrPrime before flashing with M60 RubrPoly sheets M60 RubrPoly flashing sheets

lan

ge

2. If using copper flashing over an iron or steel pipe, insert a separator sheet wrapped around pipe, to separate the copper flashing from direct contact with pipe so as to reduce galvanic reaction. 3. Vent stacks and other pipes shall have a min of 12 clearance on all sides from walls, curbs, and other projections to facilitate correct flashing & maintenance.

mi

nf

Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD11 Sheet Metal Pipe Enclosure Detail


Slope sheet metal enclosure for drainage Insulate void to prevent condensation Sheet metal or flex tube collar
10 nominal flashing height

Slope pipes down and away from hood Install sheet metal flashing receiver Min of 2 high domed, capped, & gasketed fasteners 18 oc per side, depending upon wind zone and local conditions Removable sheet metal counterflashing Fasteners 8 oc

Wood cant to brace curb Wood nailers and curb Min 4 clearance from pipe to top of curb & min 2 between pipes

Fields roof membrane sheets extended 2 min above top of cant M60 RubrPoly flashing sheets extended to a min height of 8 Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck

Side View
Slope sheet metal enclosure for drainage Insulate void to prevent condensation Sheet metal or flex tube collar Slope pipes down and away from hood Min 4 clearance from pipe to top of curb & Min 2 between pipes Sheet metal flashing receiver Min of 2 high domed, capped, & gasketed fasteners 18 oc per side, depending upon wind zone and local conditions Removable sheet metal counterflashing Fasteners 8 oc

10 nominal flashing height

Fields roof membrane sheets extended a min of 2 above top of cant M60 RubrPoly flashing sheets to a min height of 8 Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck Wood cant to brace curb

Notes
1. This detail eliminates pitch pockets for piping penetrations through the roof. Pitch pocket installations are prohibited. 2. Attach treated wood nailer to deck with suitable fasteners.

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD12 Roof-Top Pipe Roller Support Detail

Adjust vertically and horizontally

10 nominal flashing height

See Roof-Top Equipment Curb Detail FD05 for curb construction Install bolts in sealant

Notes
1. It is required that pipes & conduits be installed in other locations other than on the roof. However, where pipes and conduits are absolutely necessary on the roof, a pipe roller support is required. 2. This detail is designed to eliminate roof damage due to expansion and contraction of pipes & conduits.
Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD13 Structural Roof Deck Penetration Detail


Structural member Insulate void to prevent condensation Welded plate sealed watertight Min of 2 fasteners 18 oc per side, depending upon wind zone and local conditions 10 nominal flashing height Removable sheet metal counterflashing.

Fasteners 8 oc

Fields roof membrane sheets extended a min of 2 above top of cant. M60 RubrPoly flashing sheets extended to a min height of 8. Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck Wood cant to brace curb Wood nailers and curb
Structural member Insulate void to prevent condensation Welded plate sealed watertight Min of 2 high domed, capped, & gasketed fasteners 18 oc per side, depending upon wind zone and local conditions Removable sheet metal counterflashing

Side View

Notes
10 nominal flashing height

Fasteners 8 oc Fields roof membrane sheets extended a min of 2 above top of cant M60 RubrPoly flashing sheets to a min height of 8 Fields roof membrane sheets

1. This detail eliminates pitch pockets for structural penetrations through the roof. Pitch pockets are prohibited. 2. This curbed system allows for movement in the structural member without damaging the roof system membrane. 3. Attach treated wood nailer to deck with suitable fasteners.

Coverboard insulation Thermal insulation Roof deck Wood cant to brace curb

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD14 Metal Covered Expansion Joint Detail


Flexible vapor retarder to serve as insulation retainer attached to top of curb Install compressible insulation Sheet metal expansion joint cover Drive cleat or standing seam joint Extend M60 RubrPoly flashing sheets Install flexible waterproof membrane closure 10 nominal flashing height

Min of 2 high domed, capped, & gasketed fasteners 18 oc per side, depending upon wind zone and local conditions Fasteners 8 oc Bevel top of both wood curbs to drain to one side Fields roof membrane sheets extended 2 min above top of cant M60 RubrPoly flashing sheets extended to a min height of 8 Fields roof membrane sheets Coverboard insulation Thermal insulation

Side View
Sheet metal expansion joint cover Flexible waterproof membrane closure Bevel top of both wood curbs to drain to one side

Wood nailers and curb Wood cant to brace curb

Roof deck

M60 RubrPoly flashing not shown for clarity Flexible vapor retarder to serve as insulation retainer attached to top of curb

Fasteners 8 oc Min of 2 high domed, capped, & gasketed fasteners 18 oc per side, depending upon wind zone and local conditions Fields roof membrane sheets extended a min of 2 above top of cant M60 RubrPoly flashing sheets to a min height of 8 Compressible insulation Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck Wood cant to brace curb

Notes
1. This detail allows for building movement in both directions. 2. Flashing requirements are the same for both sides of expansion joint. 3. Attach treated wood nailer to deck with suitable fasteners.

10 nominal flashing height

Wood nailers & curb

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD15 Premanufactured Expansion Joint Detail


Extend M60 RubrPoly flashing sheets Premanufactured expansion joint cover Flexible waterproof membrane closure Flexible vapor retarder to serve as insulation retainer Min of 2 high domed, capped, & gasketed fasteners 18 oc per side, depending upon wind zone and local conditions Fasteners 8 oc Bevel top of both wood curbs to drain to outside. Fields roof membrane sheets extended 2 min above top of cant. M60 RubrPoly flashing sheets extended to a min height of 8 Install compressible insulation Fields roof membrane sheets Coverboard insulation Thermal insulation Wood nailers and curb Wood cant to brace curb Roof deck

10 nominal flashing height

Side View
Premanufactured expansion joint cover Flexible waterproof membrane closure

M60 RubrPoly flashing sheets not shown for clarity Flexible vapor retarder to serve as insulation retainer attached to top of curb

Bevel top of both wood curbs to drain to outside Fasteners 8 oc Min of 2 high domed, capped, & gasketed fasteners 18 oc per side, depending upon wind zone and local conditions Fields roof membrane sheets extended a min of 2 above top of cant Compressible insulation M60 RubrPoly flashing sheets extended to a min height of 8 Fields roof membrane sheets Coverboard insulation Thermal insulation

Notes
1. This detail allows for building movement in both directions. 2. Flashing requirements are the same for both sides of expansion joint. 3. Attach treated wood nailer to deck with suitable fasteners.

10 nominal flashing height

Roof deck Wood cant to brace curb Wood nailers & curb

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD16 Roof Area Divider Detail


Sheet metal area divider cover Min of 2 high domed, capped, & gasketed fasteners 18 oc per side, depending upon wind zone and local conditions

10 nominal flashing height

Fasteners 8 oc

Bevel top of both wood curbs to drain to outside Fields roof membrane sheets extended 2 min above top of cant.

M60 RubrPoly flashing sheets to a min height of 8 Fields roof membrane sheets Wood nailers and curb Wood cant to brace curb Coverboard insulation Thermal insulation Roof deck

Side View
Install sheet metal area divider cover Bevel top of both wood curbs to drain to outside

Notes
1. An area divider shall be designed as a raised double wood member attached to a securely fastened wood base plate that is anchored to the roof deck. Area dividers shall be located between the roof s expansion joints at about 150 to 200 intervals, depending upon climatic conditions. Area dividers are prohibited from restricting the flow of water. 2. The flashing requirements are the same for both sides of the area divider. 3. Attach the treated wood nailer to the deck with suitable fasteners.
10 nominal flashing height

Fasteners 8 oc Min of 2 high domed, capped, & gasketed fasteners 18 oc per side, depending upon wind zone and local conditions Fields roof membrane sheets extended a min of 2 above top of cant M60 RubrPoly flashing sheets extended to a min height of 8 Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck Wood cant to brace curb Wood nailers & curb

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD17 Raised Metal Roof Edge Detail


f ho t g len al ch met a e r eet g x fo er sh shin a t fla m e 12 erim nter p ou c
Fasten M60 RubrPoly flashing sheets 8 oc Fasten wood cant to blocking Sheet metal counter flashing 1/2 gap Min of 2 high domed, capped, & gasketed fasteners 18 oc per side, depending upon wind zone and local conditions

Sheet metal joint cover plate in 2 beads of sealant

4 mi n

M60 RubrPoly flashing sheets extended a min of 4 beyond base of cant

M60 RubrPoly flashing sheets 1 min below blocking First M60 RubrPoly flashing sheet extended below the blocking Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck Treated wood nailers Continuous cleat

Side View
Sheet metal counter flashing First M60 RubrPoly flashing sheet extended below the blocking Fasten M60 RubrPoly flashing sheets layer a min of 8 oc Min of 2 high domed, capped, & gasketed fasteners 18 oc per side, depending upon wind zone and local conditions M60 RubrPoly flashing sheets 4 minimum 1 minimum below blocking M60 RubrPoly flashing sheets extended a min of 4 beyond base of cant Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck Wood cant to blocking Treated wood nailers Continuous cleat

Notes
1. Attach the treated wood nailers to the wall or deck with suitable fasteners. 2. Wood blocking shall be slotted for venting wet filled decks. 3. This detail shall be installed only where the deck is supported by the outside wall.

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD18 Gravel Stop Metal Roof Edge Detail


Sheet metal joint cover plate a minimum 6 wide installed in 2 beads of sealant Flange 4 min width 3 min width 3 min width

of th g n h le tal eac et me r e fo ax ter sh shing m a e 12 erim ter fl p oun c

1/2 gap

Fasteners 3 oc & staggered

mi

When installing a mineral sheet as the reflective surfacing, install metal flange and associated M60 RubrPoly sheets beneath the mineral cap Sheet metal gravel stop adhered in M300 RubrMastic. Prime flange with M400 RubrPrime before installing M60 RubrPoly sheets M60 RubrPoly envelope sheet Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck

1 min below blocking

Treated wood nailers One M60 RubrPoly sheet extended below blocking Continuous cleat

Side View
Sheet metal gravel stop, installed in M300 RubrMastic. Prime flange with M400 RubrPrime before installing M60 RubrPoly flashing sheets M60 RubrPoly envelope sheet

Notes
1. Rigid metal flanges are prohibited from being installed between the roofing sheets. See Raised Metal Roof Edge Detail FD17 for perimeter construction. 2. This detail shall be installed only where the deck is supported by the outside wall. 3. Attach treated wood nailer to the wall with suitable fasteners. 4. Wood blocking shall be slotted for venting wet filled decks. 5. Frequent nailing of sheet metal flange is required to minimize thermal movement.

Fasteners 3 oc staggered When installing a mineral sheet as the surfacing, install metal flange and associated M60 RubrPoly flashing sheets beneath the mineral cap Fields roof membrane sheets 1 min below blocking Tapered coverboard insulation edge Coverboard insulation Thermal insulation Roof deck One M60 RubrPoly sheet below the blocking Continuous cleat

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD19 Post Supported Roof Deck Flashing Detail


Continuous through wall flashing installed by others Weep holes installed by others Tooled polyurethane sealant installed by others Fasteners 24 oc Sheet metal reglet Lap 3 with bead of sealant Lap 3 at joints Removable sheet metal counterflashing Secure & adhere M60 RubrPoly sheet closure to wall 2 wide clip 30 oc M60 RubrPoly flashing sheets extended Fasteners 8 oc Fields roof membrane sheets extended a min of 2 above top of cant Flexible vapor retarder with compressible insulation M60 RubrPoly flashing sheets extended to a min height of 8: Cover top of flashing sheets with M60 RubrPoly vapor retarder Treated wood cant to brace curb Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck
Continuous through wall flashing installed by others Tooled polyurethane sealant installed by others Sheet metal reglet Fasteners 24 oc Removable sheet metal counterflashing Secure & adhere M60 RubrPoly sheet closure to wall M60 RubrPoly flashing sheets extended

Side View

Notes
1. This detail should be installed where there is any possibility that differential movement will occur between the deck and a vertical surface. The wood members should not be fastened to the wall. 2. The joints in the sheet metal counterflashing shall not be soldered. 3. Attach treated wood nailer to deck with suitable fasteners. 4. This detail is not for use with lightweight fills.

2 wide clip 30 oc Fasteners 8 oc Fields roof membrane sheets extended a min of 2 above top of cant M60 RubrPoly flashing sheets extended to a min height of 8: Cover top of flashing sheets with M60 RubrPoly vapor retarder Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck Install treated wood cant to brace curb Flexible vapor retarder with compressible insulation

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD20 Wall Supported Roof Deck Flashing Detail


Continuous through wall flashing installed by others Weep holes installed by others Tooled polyurethane sealant installed by others Fasteners 24 oc Sheet metal reglet Lap 3 with bead of sealant Lap 3 at joints 2 wide clip 30 oc Seal top of flashing with a 3 layer application: 2 layers of M300 RubrMastic and 1 layer of P74 PolyWeb Fasteners 8 oc M60 RubrPoly flashing sheets extended Prime masonry with M400 RubrPrime Fields roof membrane sheets extended a min of 2 above top of cant M60 RubrPoly flashing sheets extended to a min height of 8 Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck Fasten treated wood cant to nailers

Side View
Continuous through wall flashing installed by others Tooled polyurethane sealant installed by others Sheet metal reglet Fasteners 24 oc Removable sheet metal counterflashing Seal top of flashing with a 3 layer application: 2 layers of M300 RubrMastic and 1 layer of P74 PolyWeb Fasteners 8 oc 2 wide clip approx. 30 oc

Notes
1. This detail shall be installed where the deck is supported by the wall. 2. The joints in the sheet metal counterflashing shall not be soldered. 3. A fiber cant may be adhered in ambient or hot asphalt in place of wood cants.

Fields roof membrane sheets extended a min of 2 above top of cant M60 RubrPoly flashing sheets to a min height of 8

Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck Wood cant to nailers

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD21 Concrete Wall Counterflashing Detail


Exposed smooth concrete surface shall be waterproofed by others Sealant at wall joints installed by others shall be compatible with counterflashing sealant Apply polyurethane sealant & tool to facilitate water run off Expanding shank fasteners a min of 12 oc depending upon wind zone & local conditions Lap 3 at joints Sheet metal counterflashing Compressible elastomeric tape to span irregularities 2 wide clip a min of 30 oc Seal top of flashing with a 3 layer application: 2 layers of M300 RubrMastic and 1 layer of P74 PolyWeb Prime concrete with M400 RubrPrime above wood nailer and below top of counterflashing Fasteners 8 oc Bevel cut top of wood curb to drain Fields roof membrane sheets extended a min of 2 above top of cant Fasten wood cant to nailers M60 RubrPoly flashing sheets to a min height of 8 Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck Wood nailers

Side View
Exposed smooth concrete surface shall be waterproofed by others Apply polyurethane sealant & tool to facilitate water run off Expanding shank fasteners a min of 12 oc, depending upon wind zone & local conditions Compressible elastomeric tape to span irregularities Seal top of flashing with a 3 layer application: 2 layers of M300 RubrMastic and 1 layer of P74 PolyWeb

Notes
1. This detail shall be installed where the deck is supported by the wall. 2. Attach the treated wood nailer to the deck with suitable fasteners. 3. A fiber cant may be adhered in ambient or hot asphalt in place of wood cants. 4. Counterflashing detail shall be a 2 piece reglet and counterflashing.

Sheet metal counterflashing Fasteners 8 oc 2 wide clip approx. 30 oc Fields roof membrane sheets extended a min of 2 above top of cant M60 RubrPoly flashing sheets to a min height of 8 Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck Fastened wood cant to nailers Bevel cut top of wood curb to drain

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com

FD22 Metal Wall Cap Flashing Detail


Sheet metal joint cover plate min 6 wide set in 2 beads of sealant Sheet metal parapet cap High domed, capped, & gasketed fasteners 18 oc, depending on wind zone and local conditions

f ho ngt ap e l ch lc r ea meta o f t x ma shee 12 rapet pa

.5 gap

Continuous membrane liner Extend M60 RubrPoly flashing sheets Seal top of flashing with a 3 layer application: 2 layers of M300 RubrMastic and 1 layer of P74 PolyWeb Install fasteners 8 oc Install continuous beveled cedar siding tapered shim Install treated wood nailers Prime concrete with M400 RubrPrime Extend Fields roof membrane sheets a min of 2 above top of cant Install M60 RubrPoly flashing sheets between 8 min to 14 max height Fields roof membrane sheets Coverboard insulation Thermal insulation Wood cant fastened to nailers Roof deck
Sheet metal parapet cap 1/2 gap Continuous membrane liner Continuous beveled cedar siding tapered shim M60 RubrPoly flashing sheets

1 min below blocking

Side View

Notes
1. This detail shall be installed when the roof deck is supported by the wall. See Post Supported Roof Deck Flashing Detail FD19. 2. Attach treated wood nailer to deck with suitable fasteners. 3. A fiber cant may be adhered in ambient or hot asphalt in place of wood cants.

1 min below blocking

High domed, capped, & gasketed fasteners 18 oc depending on wind zone and local conditions Fasteners 8 oc Fields roof membrane sheets extended a min of 2 above top of cant M60 RubrPoly flashing sheets to a min height of 8 Fields roof membrane sheets Coverboard insulation Thermal insulation Roof deck Wood cant fastened to nailers Continuous cleat

Fields Roof Systems Manual (253) or (800) 627-4098 www.fieldscorp.com