Professional Documents
Culture Documents
Owner
The reproduction, transmission or use of this document or its contents is not permitted without express written authority. Offenders will be liable for damages. All rights, including rights created by patent grant or registration of a utility model or design, are reserved.
D C B A
Revised to reflect to site preparation. Revised as Siemens Comment. Revised as Siemens Comment. First Issue
Anderungshinweis / Details of Revision
Inkor Engineering Pvt. Ltd. This document is the property of INKOR, and is to be used only for the purpose of the agreement with INKOR pursuant to which it is furnished
IKR-PROC-001
Ursprung/ Original Urspaung-Nr./Original No. Urspr-PKZ-Nr. Orig.-PC
Projekt/project
PKZ/PC
IND696
A4
UA/DCC Type Infalrskennzeichen Contents Code
DH01
HA
Zahl-Nr.
Abtlg Dept.
Reg.No.
223104
Version
SIEMENS
Erstellt mit / designed with: Intergraph
E932
458077234
Ang-VR./Offer-Var. Var./Opt. Ersatz fur Supersedes
Index/Rev.
D
Blatt-Nr./Page-No.
IND696-DH01-HA-223104
23
The primary purpose of this procedure is to provide a good quality of performance of HRSG before chemical cleaning and commissioning operation. And also to find a fault in site welding parts and to repair it. 1.2 a) b) c) 1.3 a) b) c) Applicable Code and Reference Data for Hydrostatic Test ASME Boiler and Pressure Vessel Code Sect. I ANSI B31.1 (for external piping) IBR1950 Responsibility Erector is responsible for confirming and controlling the hydrostatic test job is being carried out according to the prescribed procedure. The manager in charge of hydrostatic test for HRSG must follow the procedure as requested, review and manage in accordance with the prescribed procedure. Temporary control office should be placed around the pressurization pump. The communication system for pressurization and depressurization shall be carried out by means of walkie-talkie.
Before starting to fill the boiler make sure all drums and headers are cleared of foreign material. Close all drains. Open all vents normally used when filling the HRSG (such as superheater link vents, economizer link vents, drum vents). 2.2 Hydrostatic Test Pressure and Water Volume
System HP (F.W) HP (SH,Eva,Eco) IP (F.W,Eco) IP (SH,Eva) RH (RH,HP Bypass Outlet) LP (F.W) LP & LBG Deae. To Cond. Sys Deaerator CPH HP Bypass Cooling water Total
Remarks (Test Circuits Color / P&ID No.) Dark Blue (IND696-XG02-HAD10-220011) Purple (IND696-XG02-HAD10-220011) Blue (IND696-XG02-HAD50-220051 / 220052) Mauve (IND696-XG02-HAD50-220051) Mauve (IND696-XG02-HAD50-220052 / HAD10-220011) Light Blue (IND696-XG02-HAD80-220081) Orange (IND696-XG02-HAD80-220081 / LAA20-412001 / LBG10-421111) Brown (IND696-XG02-LAA20-412001) Deep Purple (IND696-XG02-LAA20 / 412001) Light Green (IND696-XG02-LCA30-413032) Gray (IND696-XG02-HAD10-220011)
2.3
Treated Water Requirement 1) Superheater and Reheater Type Temperature Contents : : : Demineralized water 21 C to 49 C Ammonia 10ppm solution Hydrazine 200ppm solution
NOTE : Demineralized or Condensate quality water is defined as containing no more than 1 ppm (1 /) of identifiable solids and essentially a zero concentration (or lowest detective level ) of organic material. CAUTION : The use of fill water, treated with solid chemicals, should be avoided. Deposits of solid materials in superheaters can be detrimental from heat transfer and corrosion standpoints. Superheaters containing stainless steel tubing are particularly vulnerable to stress corrosion cracking in the presence of such chemicals as caustic and chlorides. 2) Remainder of HRSG unit: Fill with treated condensate or treated demineralized water, or, if not available, with a clean source of filtered water with 10 ppm (10 cm3/m3) of ammonia and 200 ppm (200 cm3/m3) of hydrazine The water conditions as stated above can be adjusted by pouring chemicals, Ammonia in the temporary storage tank i.e. condensate storage tank. The water can be treated with only ammonia. This will however reduce the period of time that this water can be left in the system.
3.
All safety valves will be checked for having the Hydro Plug inserted if applicable. The Compression screw on the Safety Valve must be turned clockwise until the locknut makes up on the Yoke. 3.2 Test Gauges Only recently calibrated test gauges are to be used. Dial pressure gauges used in the testing shall preferably have dials graduated over their entire range of about double the intended maximum test pressure, but in no case shall the
Description D.M Pump Filling Water Pump Pressurizing pump Temporary Water Tank Air Compressor Fire Hose High Pressure Hose Temporary Piping
Capacity
Qty 1
Remarks Water filling for Temp. Tank Water filling for System Pressurizing Pressurizing
1 1 1 1 5 Multitude
3.4
Communication
All communication between the boiler control station and the Hydro-Pump station will be with Radios. Back-up radios are to be readily available at each control station. Radio : More than 4 walkie-talkie Location : Control center (filling water pump or pressurization pump area) Top (pressure gauge, thermometer and vent area) Inspector Inspector and recorder must be placed in a convenient area to communicate for the pressure gauge, inspection of thermometer and control center. 3.5 Advance Material Readiness
4.
4.1
The metal temperature of all components to be Hydro-Tested must be at least 21 C (70 F) before applying the Hydro Test pressure but shall not exceed 48.8 C(120F) 4.2 Sectional Testing of the HRSG Systems
When Hydrostatic Testing is to be done on a section of the system which is not directly linked to a lower than test pressure designed system, but segregated by the test boundary isolation, all vent valves in the lower pressure designed system must be open to avoid over pressurization of the same. 4.3 Double Valve Arrangements All components tested will be as indicated on the flow chart or P&ID for the specific test. Always open the root valve fully and throttle with the down stream valve when depressurizing or draining a system. 4.4 Communication
All communication / Co-ordination concerning the Hydro-Test has to be addressed through designated personnel.
5.
5.1.1 Check for any foreign materials of tools, clothes and other things inside manifolds etc. and then close the manholes and all holes of the pressure.
5.1.2 The pressure gauge to be used for Hydro-Test should exactly be calibrated. In addition to this, the filling piping and pressurization shall be checked. 5.1.3 It is very important to check whether the instruments and the temporary construction piping
5.2.1 Water filling In case of non availability of condensate transfer pump, which are to fill the water, filling of water shall be done by temporary filling water pump shall be installed in each system as paragraph 5.2.1.2. 5.2.1.1 In advance, in the close condition of the specified valve, it has to be checked then the signature on the control list is requested under the open condition of top air vent valve. If the above condition is pleased it may be filled for water washing. 5.2.1.2 It is a fundamental rule to fill the inside of HRSG through specified valves for each system(HP, IP, LP, CPH and Deaerator). 5.2.1.3 If water is seen being filling from bottom valve, each air vent valve shall be closed on sequentially till top air vent valve at that time a full filling should be confirmed at top air vent valve. 5.2.2 Pressurization 5.2.2.1 HP F.W. Section a) The pressure should be increased by 3~5 kg/cm^2/min. up to Max. allowable working pressure(design pressure 257barg). b) Observe test section for any obvious leaks. c) Then the pressure should be increased by 2~3 kg/cm^2/min till the hydro-test
6.
INSPECTION AND TEST 6.1 All welding points, valves and hangers which were welded on pipe must be inspected during the hydrostatic test. During the inspection if there is an abnormal condition the inspection should be stopped and a repair work should be done. 6.2 The test data should be recorded at an interval of 5 minutes but not less than 5 measuring data in each case during hold time and during subsequent inspection, and the basis of the pressure is the pressure gauge installed at the highest point of the system, and temperature should be recorded from the temporary temperature gauge installed near the pressure gauge. 6.3 The inspection must be witnessed as per the inspection points in hydro test inspection table. NOTE : Hydrostatic test pressure should not be applied to the boiler of the metal temperature of the pressure parts is below 70 F ( 21 C ). Since there is generally some time delay between the hydrostatic test and the initial boiling out and cleaning for the boiler the unit should remain full of water, air should not be allowed to enter.
7.
Post Hydrostatic Test Procedures 7.1 Hydrostatic test water will be left in the system for preservation. Pressure approximately 3 to 5 psig (21 to 34 kPa) to be maintained, checked and recorded on a regular basis. 7.2 Remove all hydrostatic test plugs and gags from the safety valves prior to starting up the unit. NOTE: Since there is generally some time delay between the hydrostatic test and the initial boiling out and acid cleaning of the HRSG, it should remain full of water; air should not be allowed to enter.
8.
ATTACHMENT 8.1 The pressure curve of hydrostatic test for HRSG A. HP F.W Section pressure curve (Typical) B. HP Section pressure curve (Typical) C. LP Section Pressure Curve(Typical) D. LP F.W Section Pressure Curve (Typical E. CPH Section pressure curve (Typical) F. IP & RH Section Pressure Curve (Typical) G. IP F.W Section Pressure Curve (Typical) H. Deaerator Section Pressure Curve (Typical) I. 8.2 HP Bypass Cooling Water Section Pressure Curve (Typical)
Pressure Test Circuit ------- 1 Set Red Color Marking(golden joint) means pipe will be blanked before hydrostatic test and RT will be done for weld joint after Hydrostatic test.
400
350
300
Pressure [barg]
250
200
150
100
50
300
250
200
Pressure [barg]
150
100
50
Time [min]
Pressure Up Pressure Down
24
20
Min. 30 Minutes At 16.5 barg(16.8 /) (Hydrostatic Test Pressure)
Pressure [barg]
16
Inspection Time
12
0 0 20 40 60 80 100 120
Time [Min]
Pressure Up Pressure Down
Pressure [barg]
60
45
30
15
0 0 20 40 60 80 100
Time [Min]
Pressure Pressure Down
Pressure [barg]
60
45
30
15
0 0 20 40 60 80 100 120
Time [Min]
Pressure Pressure Down
60
50
Inspection Time 40
Pressure [barg]
30
20
10
0 0 20 40 60 80 100
Time [Min]
Pressure Up Pressure Down
175
150
Pressure [barg]
Inspection Time
125
100
75
50
25
Time [min]
Pressure Up Pressure Down
Min. 30 Minutes
12
10
Inspection Time At 8 barg (8.2 /) (Design Pressure)
Pressure [barg]
0 0
15
30
45
60
75
Time [Min]
Pressure Up Pressure Down
I.
90
75 Inspection Time
Pressure [barg]
60
45
30
15
0 0 20 40 60 80 100
Time [Min]
Pressure Pressure Down