Professional Documents
Culture Documents
IVT
18th Annual Validation Week October, 2012
Presented By:
Agenda
Equipment Qualification Terminology Intended Use - User Requirements Maintaining the Qualified State Interactive Exercise Bonus Material
Terminology
Terminology (cont.)
Factory Acceptance Test (FAT) The purpose of FAT is to establish confidence that the equipment or system is tested to the extent possible at the manufacturers facility and that it is ready for shipment and installation at the operational site. The extent of testing is agreed with the manufacturer in advance and is documented in a test plan or protocol. FAT activities may include: Verification that the equipment or system has been constructed in conformance with the Purchase Order and other Engineering specifications. Safety issues and concerns have been addressed if applicable (e.g. Safety Assessment). Any software associated with the equipment or system has been verified for proper installation and security. The equipment will perform the specified operations as designed and documented Any issues or concerns are addressed by the vendor prior to shipment and acceptance by the customer. All required drawings, documents, cut-sheets, sequence of operations, etc. are properly documented and delivered by the vendor. Reference to documented results in the FAT may be appropriate for subsequent qualification activities if it was planned, executed, and documented to a sufficient level to do so.
Terminology (cont.)
The purpose of SAT is to establish confidence that the equipment or system has been built to design specifications, assembled, and debugged by the manufacturer at the operational site, and that it is ready for turnover to the customer for acceptance. The extent of testing is agreed with the manufacturer in advance and is documented in a test plan or protocol. Once the SAT is approved the customer owns the equipment. Typically the SAT is a repeat* of the FAT along with testing for anything that was discovered, repaired, redesigned, etc. during or after the FAT. SAT activities may include: Visual and or other inspections to ensure no damage occurred during shipment. Reassembly if the equipment had to be shipped in pieces due to size or other issues Verification that the equipment or system has been constructed in conformance with the Purchase Order and other Engineering specifications. Any software associated with the equipment or system has been verified for proper installation and security. Start up and running with the site utilities to ensure the equipment operates the same as at the FAT All required drawings, documents, cut sheets, sequence of operations are complete and appropriate from the vendor.
*Reference to documented results in the SAT may be appropriate for subsequent qualification activities if it was planned, executed, and documented to a sufficient level to do so. IVT Validation Week - October, 2012 5
Terminology (cont.)
Whats the difference between Validation and Qualification? Validation means confirmation by examination and provision of objective evidence that specified requirements have been fulfilled. (CFR 21 Part 820.3 (z)) Qualification Not defined by FDA Subset of validation Provides documented evidence that the subject
equipment has been installed per specification (manufacturer's recommendations) and will attain and maintain critical process parameters repeatedly and reliably. Typically done as part of a larger validation effort. May support multiple validation efforts. (see slide #26)
IVT Validation Week - October, 2012 7
Getting Started
Validation Team The Project Leader is responsible to form a multi-functional team to plan and oversee the validation activities. A team approach assures that the validation processes are well thought out, the protocols are comprehensive, and that the final packages are well documented and easy to follow. Members of the validation team could include representatives from or personnel with expertise in: Quality Assurance (must be a member of all validation teams) Engineering
Manufacturing Others depending on facility organization and equipment/product types: o Laboratory o Technical Services o Research & Development o Regulatory Affairs
IVT Validation Week - October, 2012
Getting Started
For all phases described, the Project Team must: Determine what, how and when to verify/measure. Determine how many to verify/measure, i.e. statistical significance. Define acceptance/rejection criteria. Identify required documentation.
The division of responsibilities and activities must be determined by the Project Team based on the Risk Assessment to provide a high degree of assurance that the equipment under test is suitable for its intended purpose.
Intended Use
User Requirements - A stand alone document that is common for computer systems. For equipment User Requirements come from many sources. Commercial Off The Shelf (COTS) equipment, they usually take the form of Owners Manual or Users Guides. Maybe a Request for Quote (RFI) if the equipment is custom. Other sources: Set up sheets
Design of Experiment Parameter Limit Values Environmental requirements and/or constraints Manufacturers installation guide Regardless of their origin they form the basis for your Risk Assessments and Acceptance criteria
IVT Validation Week - October, 2011 10
Risk Assessment
CONDUCTING RISK ASSESSMENT
A risk assessment must be performed for all validations and determines the documentation deliverables. The risk assessment will determine the validation parameters of the overall equipment or system and the required functions. The assessment must also analyze the potential failure and fault modes of the equipment or system to determine if the design is appropriate and to gauge the
relative level of validation testing and need for external safeguards. Risk assessment must be conducted using methods appropriate to the scope and nature of the validation project. The conclusions of the risk assessment process may be included in a project Validation Plan, in individual protocols, or in a separate document.
IVT Validation Week - October, 2012 11
12
All equipment systems must be assessed for their impact to patient safety, product quality and data integrity. This assessment will be accomplished by following SOP-MD-2010411, GXP Assessment System Categorization.
13
All equipment systems determined as GxP related are categorized as Non-configured, Configured, or Custom.
14
Non-Configured
Configured
Custom
Internally and externally developed IT applications o Internally and externally developed process control applications Custom ladder logic o
Life cycle approach Risk-based approach to supplier assessment Demonstrate supplier has an adequate Quality Management System o Some life cycle documentation (DS) retained by supplier. o Installation Qualification against Design Qualification o Operational Qualification against Functional Specification o Performance Qualification against . o Version control o Risk-based testing to demonstrate application works as designed. o Verify procedures are in place for maintaining compliance and fitness for intended use Same as for configurable, plus: oMore rigorous supplier assessment. oPossible supplier audit oPossession of full life cycle documentation oDesign and source code review
15
16
Installation Qualification
Purpose Scope Equipment description o Boundaries ancillary equipment Environment Critical Utilities Drawings
Preventive Maintenance o Spare Parts Product Contact o Cleaning procedures o Materials of construction Product Contact
IVT Validation Week - October, 2012 17
Utilities Construction, Installation and Requirements Supporting Documentation Maintenance Programs Spare/Change Parts Drawings
18
19
Environment
Valves
Lubricants
Safety Devices
Alarms Instrumentation
Verify all instruments installed on the equipment/system are labeled appropriately and any instruments deemed to require calibration or routine certification are within calibration and have been entered into the calibration program Compressed gas connections Sample ports (if required), labeling and sizes
Utilities
20
21
22
Equipment/System Description Operational Qualification Pre-requisites Test Equipment Calibration Verification Standard Operating Procedures Alarm/Control Challenges
Notes: Software parameters must also be considered; separate computer validation protocol can be used to address this
Provide rationale for: Qualification approach taken Sample size rationale Selected test conditions Critical parameters Define the test range for each critical process parameter for verification o The testing range typically brackets the operating range to ensure equipment is qualified with extra security; e.g., if temperature operating range is 50C to 100C, then the test range should be 40C to 110C The process will be challenged at the extremes of the critical process parameters wherever possible. The number of test runs needs to be statistically justified and it may be depending on the complexity of the equipment
Summarize test results and confirms the acceptance criteria Discuss and justifies discrepancies Summarize equipment OQ results and provide a conclusion on whether the equipment operation is acceptable
23
24
Training Preventive Maintenance o Spare Parts List Calibration Change Control Re-Qualification
25
Re-Qualification
Re-Qualification Review The validation status of qualified equipment must be reviewed to determine whether it continues to operate in a qualified state. With the exception of those processes that are subject to regulatory requirements regarding time specific intervals for periodic re-qualification, the change control process is appropriate to determine re-qualification requirements to maintain
the validated state. As part of the Change Control process, a validation assessment will be completed for each change to determine and document any potential validation impact and any actions deemed appropriate to ensure the validation status is maintained including the possibility of requalification. IVT Validation Week - October, 2012
26
Documentation Strategies
IQ
OQ IOQ
27
Interactive Stuff
Participants develop an equipment qualification protocol
28
BONUS Material
Mold Validation Procedure Forms Production Equipment and Process validation Procedure GxP Assessment Procedure
29